Creating the PPP Enabling Environment
The PPP Cell Uttarakhand
Innovative Financing Modalities for Infrastructure Development in India
Sumit Barua, PPP Cell Uttarakhand
Sept 30, 2011
Asian Development Bank, Manila
THE GOITHE GOI--ADB PPP INITIATIVE,ADB PPP INITIATIVE,MainstreamingMainstreamingMainstreamingMainstreamingMainstreamingMainstreamingMainstreamingMainstreaming PPPsPPPsPPPsPPPsPPPsPPPsPPPsPPPs in Indiain Indiain Indiain Indiain Indiain Indiain Indiain India
PPP CellsPPP Cells A Critical SupportA Critical Support
forfor
The views expressed in these presentations are the views of the author and do not necessarily reflect the views or policies of the Asian Development Bank(ADB), or its Board of Directors or the governments they represent. ADB does not guarantee the source, originality, accuracy, completeness or reliability of
any statement, information, data, finding, interpretation, advice, opinion, or view presented, nor does it make any representation concerning the same.
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
2/10
PPP Cell Uttarakhand
PPP Cell Uttarakhand
Policy & Guidelines for PPPs at a State Level
Policy & Guidelines for PPPs at a State Level
Origination
Origination
Structuring
Structuring
Bid Process Mgt
Bid Process Mgt
The Role of PPP Cells - Manifold
Capacity Building of Officials in State
Capacity Building of Officials in State
Management Information Systems
Management Information Systems
Project Pipeline Development
Project Pipeline Development
Assistance for VGF. IIPDF. Projects of state
Assistance for VGF. IIPDF. Projects of state
PPP Facilities Development & Management
PPP Facilities Development & Management
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
3/10
1 Existing Rule addressed only Procurement and not the entire PPP Process
2 Sensitization and need for Policy. PPP Policy/ UIPDF/VGF were prepared
3 Preparation of RFP/RFQ/DCA based on Model documents and also customization
4 Systemization of Approval Process like EFC and Standardized Cabinet Notes
5 Created PPP Cell as a legal entity under the State Government. Professionals
inducted to ensure Continuity of PPP momentum the State.
Institutionalization and Policies/Guidelines/Rules
Empanelment of
Transaction Advisors
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
4/10
1 Prepared Training Modules
2 Facilitated State Participation in I-Cap Program Master Trainers Prepared
3 Ten(10) Training Programs Conducted and 275 Officials Trained (2010 & 2011)
4 Identified Training need for Middle Level Officials
5 Targeting Village Level, Urban Local Bodies Officials and Elected Members
Capacity Building
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
5/10
1 PPP Web site developed and maintained
2 Continuous data collection , Monthly Reports and Periodic Review by CS in place
3 Knowledge repository created
4 PPP Handbook and report on PPP in Health Sector prepared
5 Data Compiled for building future Project models with highest accuracy
6 Social Media Presence Facebook, Twitter, LinkedIn resulting increase in
responses to our project announcement
MIS, Project Monitoring and Knowledge Repository
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
6/10
Under Bidding ,
20
Pipeline, 48
Bid Completed,
22
1 Undertook Project Development activities including financial & risk analysis
2 Preparation of Bid Documents - RFQ/RFP/DCA.
3 Sector Specific Tech Qualification norms. Quantitative, Objective and Transparent
Scoring Method.
4 Bid process Management and Closure
5 PSC and VfM model for selection of PPP Projects and rationale
6 Appraisal of Reports/Bid Documents of TA s
7 90 Projects Developed Twenty Two (22) bids closed, Twenty (20) under bid
Project Pipeline Development: Overall
Projects Undertaken by PPP Cell 2008 - 2011
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
7/10
Snapshot: Social Sector Projects
HealthHealth
Thirteen(13) Projects Developed Seven (7) bids Closed, Five (5) Operational3
1 Projects addressing Health Delivery at Remote Location implemented
2 Grant based Projects under regulated user charges developed with positive VfM
4 Seven(7) education projects developed for building residential schools under bid
Sample Projects:
Nephrology Centers (two Locations) awarded
Mobile Health Vans (two projects) awarded
Cardiac Centre awarded
Ayurvedic and Wellness Centre - Awarded SWM in Dehradun awarded
SWM in Nainital - awarded
SWM Hardwar Bidding Complete (to be awarded soon)
Sample Projects:
Nephrology Centers (two Locations) awarded
Mobile Health Vans (two projects) awarded
Cardiac Centre awarded
Ayurvedic and Wellness Centre - Awarded
SWM in Dehradun awarded
SWM in Nainital - awarded
SWM Hardwar Bidding Complete (to be awarded soon)
Solid WasteSolid Waste
ManagementManagement
A Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at UttarakhandA Special Focus on Social Sectors at Uttarakhand
EducationEducation
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
8/10
Projects Developed / AwardedProjects Developed / Awarded
S No Project Status
1 MRI Machine , Dehradun Operational
2 Nephrology Centre, Dehradun Operational
3 Nephrology Centre, Haldwani Operational
4 Thirteen (13) Mobile Hospital Vans (MHVs) - One in eachdistrict
Operational
Thirteen (13) Mobile Medical Unit under NRHM Operational
6 Cardiac Centre, Dehradun Awarded/ Under Const
7 AYUSH Gram, Nainital Awarded/ Under Const
8 108 Emergency Response Services Operational
9 Diagnostic Centre Offering Services in Radiology, Pathologyand Non-Invasive Cardiology
Under Bidding
10 Diagnostic Centre Offering Services in Radiology, Pathologyand Non-Invasive Cardiology
Under Bidding
11 Oncology Centre Under approval
12 Community Health Centers - Sixteen (16) Under Bidding
12 Projects in Pipeline 8 awarded
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
9/10
Description Unit Dehradun Nainital Haridwar
Waste Generation MT/Day 235 38 213
Area Covered Sq Km 67.10 11.73 12.17
Population Million 1.0 0.04 0.79Compost Plant MT/Day 150 24 85
Land Fill MT/Day 50 8.50 40
SWM Projects Awarded: Fact-sheet
Project Cost Rs Crores 23.74 8.00 16.25
PV of Grant Rs Crores 24.89 5.49 19.62
Central Govt Share 80% 80% 80%
State Govt Share 20% 20% 20%
Concessionaire SPML A2Z KRL
Total Responses 8 5 8
Technically Qualified 6 4 6
Financial Proposals 6 4 4
-
8/3/2019 S1_110929 PPP Presn_Sumit Barua
10/10
Thank YouThank You