S11.1 Closed Cooling Water
-
Upload
sofiane-halimi -
Category
Documents
-
view
217 -
download
0
Transcript of S11.1 Closed Cooling Water
-
7/28/2019 S11.1 Closed Cooling Water
1/8
GL1.Z COMPLEX - SONATRACH
PROCESS OPERATING MANUAL
CLOSED COOLING WATER
SECTION No 11.1~ REVISION No. 2
GL1.Z RENOVATION PROJECT
-
7/28/2019 S11.1 Closed Cooling Water
2/8
TABLE OF CONTENTS
1.0 GENERAL OVERVIEW...........................................................................................1
2.0 OPERATING PRINCIPLES....................................................................................1
2.1 Process Description...............................................................................................1
3.0 PREPARATION FOR START-UP...........................................................................2
3.1 Filling the System..................................................................................................2
4.0 NORMAL START-UP...............................................................................................2
5.0 NORMAL OPERATION...........................................................................................3
5.1 Normal Operating Parameters..............................................................................3
6.0 PROCESS CONTROL..............................................................................................3
7.0 NORMAL SHUTDOWN...........................................................................................4
8.0 PROTECTIVE SYSTEMS AND EMERGENCY SHUTDOWN.............................4
8.1 Primary Protection................................................................................................4
10.0 TROUBLESHOOTING..........................................................................................4
11.0 APPENDICES.........................................................................................................6
11.1 DCS Print-outs....................................................................................................6
11.2 Process Flow Diagrams - PFD's.........................................................................6
11.3 Process and Instrument Diagrams P&ID's......................................................6
11.4 Cause and Effect Charts......................................................................................6
-
7/28/2019 S11.1 Closed Cooling Water
3/8
Aug 2001 Page 5 of 5Rev 2SECTION 11.1
PROCESS OPERATING
MANUALCLOSED COOLING WATER
1.0 GENERAL OVERVIEW
The closed cooling water system is installed to provide the cooling system
for the Turbine Seal gland condensers, Turbine Ejectors, the Process
Boiler areas and the Mitsubishi 400 T/hour boiler auxiliary equipment.
The cooling water is distilled water with corrosion inhibitor added.
Alternatively, potable water can be used as a makeup supply.
2.0 OPERATING PRINCIPLES
2.1 Process Description
The closed cooling water systems are located in Units 200/400/600. Each
system supplies 2 Process units and may supply the Mitsubishi 400T/hour boilers via a common header. Normal operation has only one unit
supplying the Mitsubishi boiler. Two electric motor driven pumps are
supplied for each system. Normal operation has one in service with the
other in "Auto" standby. Water exits the discharge of pumps, X20-J-
370/371 and flows to "plate" exchangers, X20-E-334/335 where it is
cooled by seawater from the process seawater supply system. The closed
cooling water system supplies the following users:
Forced draft Fan turbines (Process boilers) 7X0-D301K1T, 7X0-
D302K1T, 7X0-D303K1T bearings and Lubrication oil coolers.
Seal cooling for BFW pump 7X0-J-349.
Oil cooling for BFW pumps and turbine 7X0-J-349/369
Sample coolers for 7X0-D301/302/303
Bearing cooling for X02-K01.30R-JT1
Bearing cooling for X01-J-503 MEA pump.
Bearing cooling for X04-J-07.95 C3 transfer pump.
Bearing cooling for X10-J-07.47 C3 return pump.
Bearing cooling for X10-J-07.37 C2 return pump.
Bearing cooling for X10-J-07.57 C4 recycle pump.
Bearing cooling for X10-J-07.61 C4 recycle pump.
Gland condenser X05-K01.20E
Ejector condenser X05-E-301
Ejector condenser X05-E-302
Gland condenser X05-K01.21E
Gland condenser X03-K01.10E
Gland condenser X02-K01.30E
Ejector condenser X03-E-313
Ejector condenser X02-E-319
Bearing cooling for X03-K-01.10R JT1
Bearing cooling for X03-K-01.10R JT3
-
7/28/2019 S11.1 Closed Cooling Water
4/8
Aug 2001 Page 5 of 5Rev 2SECTION 11.1
PROCESS OPERATING
MANUALCLOSED COOLING WATER
The cooling water returns back to the pump suction lines. On the
return header a Surge drum, (X20-G-338) is provided to maintain
stable flow to the pump suction. Potable water make-up is added viaLV-X20-01 as is necessary to maintain the proper water level in the
system.
3.0 PREPARATION FOR START-UP
3.1 Filling the System
This section describes the initial cleaning and filling of the Closed cooling
water circuit after a shutdown.
Fill X20-G-338 to 80% with potable water via LV-X20-01.
Remove the suction spools on both CCW pumps, (X20-J-
370/371).
Open the suction valves on both pumps and flush the piping until
clean. Reinstall the suction spools with temporary strainers in line.
Refill X20-G-338 to 80% with potable water.
Remove the inlet spools on X20-E-334/335 downstream of the
valves.
Ensure both pumps are primed. Start either pump, (discharge
closed) and slowly open the discharge valve to flush the piping to
the cooler inlet lines. Reinstall the inlets spools when the piping is
clean.
Refill X20-G-338 to 80%.
Disconnect the inlet/outlet piping to all CCW users and install
pipe spools. Flush the lines until clean using the system pumps.
Repeat this process until all the piping is clean in all trains.
Inventory the system with distilled water. Add the proper
corrosion inhibiting chemicals, (Nalco 8539) and circulate the
system.
4.0 NORMAL START-UP
It is assumed that the system has been filled with distilled water and the
necessary chemicals added.
Set LIC-X20-01, at 60% in Automatic.
Ensure the seawater is open to one of the seawater exchangers.
-
7/28/2019 S11.1 Closed Cooling Water
5/8
Aug 2001 Page 5 of 5Rev 2SECTION 11.1
PROCESS OPERATING
MANUALCLOSED COOLING WATER
Start one of the CCW pumps in the "HAND" position. Place the
stand-by pump in "AUTOMATIC".
Open the supply and return valves to each piece of equipment as is
necessary for start-up.
5.0 NORMAL OPERATION
5.1 Normal Operating Parameters
Normal operation of the closed cooling water circuit has a system
supplying Units 100/200, a system supplying Units 300/400, a system
supplying Units 500/600 and one of the units supplying the 4 Mitsubishi
boilers.
The system has one pump and one heat exchanger in service with the
other pump in Automatic standby, starting by PSLL-X2014. Normal
pump discharge pressure is 4.6 Bar. Design flow from the pump discharge
is 695 m3/hr with the exchanger outlet temperature of 30 C. The cooling
water flow to the 4 Mitsubishi boilers is 320 m3/hr and the flow to each
process unit being 187.8 m3/hr. The cooling water return header design
temperature is 35 C.
6.0 PROCESS CONTROL
The closed cooling water system supplies cooling water to the varioususers in the Process units and the Mitsubishi boilers. A surge drum X20-
G-338 is provided for the pump suction and to maintain a constant level
in the system. Level indication is provided locally on gage glasses, LG-
X20-02A/B. A level transmitter, LT-X20-01 is provided which sends a
signal to LIC-X20-01, which in turn acts upon LV-X20-01 to makeup
potable water into the system. LIC-X20-01 is normally set at 50% and has
High and Low alarm functions on the DCS.
Two circulation pumps, X20-J-370/371 are provided with local hand
switches (3 position) H-O-A. Normal operation is one pump in the Hand
position, the other in Auto standby. Pump running indication is provided
on the DCS by JI-X20-18/19. Pump discharge pressure is indicated
locally by PI-X20-15 (X20-J-370) and PI-X20-16 (X20-J-371). On the
common discharge header a pressure switch, (PSLL-X20-14) is provided
which sends a signal to PALL-X20-14 that automatically starts the
standby pump on low header pressure. Pressure transmitter PT-X20-13 is
provided with DCS indication on PI-X20-13. Temperature is indicated
locally on TI-X20-12.
The cooling water flows through one of the two exchangers X20-E-
334/335 where it is cooled by seawater. Local CCW outlet temperature is
provided on TI-X20-07/08. Provisions to measure the Seawater outlet
-
7/28/2019 S11.1 Closed Cooling Water
6/8
Aug 2001 Page 5 of 5Rev 2SECTION 11.1
PROCESS OPERATING
MANUALCLOSED COOLING WATER
temperature are installed on each exchanger TW-X20-09/10. A local
differential pressure indicator, PDI-X20-17 is installed to measure the
differential pressure across the seawater inlet strainers for plugging.Common CCW outlet temperature is monitored by TE-X20-11 with DCS
indication and alarm functions on TI-X20-11.
7.0 NORMAL SHUTDOWN
The closed cooling water system is similar to the seawater system, as
when equipment does not require CCW it can be isolated to the
equipment. To shutdown the entire system:
Isolate the valves from the Mitsubishi boiler supply and return
header.
Stop the pumps, X20-J-337/338. De-energize the electrical supply.
Isolate LV-X20-01, potable water make-up supply.
Isolate and drain the system as is required.
8.0 PROTECTIVE SYSTEMS AND EMERGENCY SHUTDOWN
8.1 Primary Protection
TSV-X20-06, X20-E-335 thermal relief set at 6 Bar.
TSV-X20-03, X20-E-334 thermal relief set at 6 Bar.
10.0 TROUBLESHOOTING
Effect Check List Immediate Action
Low level in X20-G-
338
Check the level on the
sight glass.
Check the operation ofLIC-X20-01
Ensure there is
distilled & potable
water available from
utilities.
High cooling water
temperature on TI-
X20-11
Verify the temperature
locally.
Check seawater inlet
strainer, PDI-X20-17
Adjust the seawater
flow.
Switch exchangers,
isolate and clean the
seawater inlet strainer.
Pump discharge
pressure low, PALL-X20-14
Verify the standby
pump has started.
Ensure the pump is in
Automatic.
-
7/28/2019 S11.1 Closed Cooling Water
7/8
-
7/28/2019 S11.1 Closed Cooling Water
8/8
Aug 2001 Page 5 of 5Rev 2SECTION 11.1
PROCESS OPERATING
MANUALCLOSED COOLING WATER
11.0 APPENDICES
11.1 DCS Print-outs
11.2 Process Flow Diagrams - PFD's
11.3 Process and Instrument Diagrams P&ID's
85-X00-24.1
85-X00-24.2
85-X00-24.3
85-X00-24.4
85-X00-26
11.4 Cause and Effect Charts