S pecial dition aper - jreast.co.jp pecial dition aper Platform air conditioner ... conditioner FAN...

4
29 JR EAST Technical Review-No.23 S pecial edition paper Platform air conditioner Platform air conditioner Air supply shaſt Exhaust shaſt Track area Exhaust fan for track Air supply fan for track Air supply fan for track Platform air conditioning Air curtain air conditioner Platform area Platform Exhaust on track Air curtain air conditioning Air supply to track Air conditioner Air conditioner FAN FAN Air supply shaſt Exhaust shaſt Track area Exhaust fan for track Reduced air volume Platform area Platform Exhaust on track Air curtain air conditioning Air supply to track Air conditioner FAN FAN Suspended Suspended Reduced Air curtain air conditioner Air conditioner Platform air conditioning Air conditioning systems for underground spaces have to be designed for conditions different from those of ordinary buildings, such as heat discharge from trains, train draft from tunnels, and heat radiation from walls. Heat discharge from trains and train draft from tunnels are loads that change by the second. At the time of construction of many of JR East’s underground stations, however, those were estimated by hours and the peak load calculated based on past research results to decide the capacity of refrigerating machines. Calculations also referred to wind tunnel test results using scaled-down models and estimations of the number of train passengers. As Tokyo Station for rapid service on the Yokosuka and Sobu lines (hereinafter, the “Tokyo Station Sobu underground area”) is an underground station nearing the time to replace its air conditioning system, we can acquire data on actual operation of the existing system and the thermal environment on the platform to reflect those in heat load calculation. Figuring out actual operation of the existing systems of Bakurocho, Shin-Nihombashi, and Shimbashi stations on the Yokosuka and Sobu lines for rapid service and the Tokyo Station Keiyo underground area that are adjacent to the Tokyo Station Sobu underground area as well, we have identified issues on the air conditioning system for underground stations. Air Conditioning Method of Tokyo Station Sobu Underground Area 2 For cooling underground stations, refrigerating machines and chillers of the system make cold water and unit type air conditioners (hereinafter, “air conditioners”) send out cool air. For ventilation, the system also includes air supply fans and exhaust fans. Fig. 1 is a diagram of the air conditioning method for the Tokyo Station Sobu underground platform. Here we will call this the usual mode. Conversely, the air conditioning method to reduce the load at the track from outside, which has been clarified in the simulation to be explained later, is called the improved mode (Fig. 2). Introduction 1 Issues of Air Conditioning System of Tokyo Station Sobu Underground Area 3 Air conditioning methods vary according to the time of construction of underground station air conditioning systems. e air conditioning system for the Tokyo Station Sobu underground platform was designed at a time when brakes that Research on Reduction of Air Conditioning Load in Large-scale Underground Stations Keywords: Underground station, Air conditioning equipment, Energy saving, Latent heat JR East has underground stations on the Yokosuka and Sobu lines (for rapid service), the Keiyo Line, and other lines, and those are provided with ventilators, smoke control systems, as well as cooling systems that remove heat from trains, lighting and human bodies. More than 30 years have passed since construction of many of those underground stations, so the heat load calculation conditions have changed and the calculation methodology has progressed from those at the time of construction. This research article will report on case studies of energy saving where the air conditioning load was reviewed based on the thermal environment and the cooling system operation status of an underground station using the Sobu Line underground area at Tokyo Station as a model. Thermal environment measurement of the underground stations for rapid service on the Yokosuka and Sobu lines and on the Keiyo line clarified that the humidity in those underground stations was high, requiring the removal of latent heat. * Mechatronics Technology Management Center, Facilities Depertment (previously at Environmental Engineering Research Laboratory) ** Environmental Engineering Research Laboratory, Research and Development Center of JR East Group Sogo Iyobe * Masafumi Sato ** Fig. 2 Tokyo Station Sobu Underground Platform Air Conditioning Method (Improved Mode) Fig. 1 Tokyo Station Sobu Underground Platform Air Conditioning Method (Usual Mode)

Transcript of S pecial dition aper - jreast.co.jp pecial dition aper Platform air conditioner ... conditioner FAN...

29JR EAST Technical Review-No.23

Special edition paper

Platformair conditioner

Platform airconditioner

Air

supp

ly sh

a�

Exha

ust s

ha�

Track area

Exhaust fanfor track

Air supply fanfor track

Air supply fanfor track

Platform airconditioning

Air curtainair conditioner

Platform area

PlatformExhaust on track

Air curtain airconditioning

Air supply to track

Airconditioner

Airconditioner

FAN

FAN

Air

supp

ly sh

a�

Exha

ust s

ha�

Track area

Exhaust fanfor track

Reduced air volume

Platform area

PlatformExhaust on track

Air curtain airconditioning

Air supply to track

Air conditioner

FAN

FAN

Suspended

Suspended

Reduced

Air curtain air conditioner

Air conditioner

Platform airconditioning

Air conditioning systems for underground spaces have to be designed for conditions different from those of ordinary buildings, such as heat discharge from trains, train draft from tunnels, and heat radiation from walls. Heat discharge from trains and train draft from tunnels are loads that change by the second. At the time of construction of many of JR East’s underground stations, however, those were estimated by hours and the peak load calculated based on past research results to decide the capacity of refrigerating machines. Calculations also referred to wind tunnel test results using scaled-down models and estimations of the number of train passengers.

As Tokyo Station for rapid service on the Yokosuka and Sobu lines (hereinafter, the “Tokyo Station Sobu underground area”) is an underground station nearing the time to replace its air conditioning system, we can acquire data on actual operation of the existing system and the thermal environment on the platform to reflect those in heat load calculation.

Figuring out actual operation of the existing systems of Bakurocho, Shin-Nihombashi, and Shimbashi stations on the Yokosuka and Sobu lines for rapid service and the Tokyo Station Keiyo underground area that are adjacent to the Tokyo Station Sobu underground area as well, we have identified issues on the air conditioning system for underground stations.

Air Conditioning Method of Tokyo Station Sobu Underground Area2

For cooling underground stations, refrigerating machines and chillers of the system make cold water and unit type air conditioners (hereinafter, “air conditioners”) send out cool air. For ventilation, the system also includes air supply fans and exhaust fans.

Fig. 1 is a diagram of the air conditioning method for the Tokyo Station Sobu underground platform. Here we will call this the usual mode.

Conversely, the air conditioning method to reduce the load at the track from outside, which has been clarified in the simulation to be explained later, is called the improved mode (Fig. 2).

Introduction1

Issues of Air Conditioning System of Tokyo Station Sobu Underground Area3

Air conditioning methods vary according to the time of construction of underground station air conditioning systems. The air conditioning system for the Tokyo Station Sobu underground platform was designed at a time when brakes that

Research on Reduction of Air Conditioning Load in Large-scale Underground Stations

•Keywords: Underground station, Air conditioning equipment, Energy saving, Latent heat

JR East has underground stations on the Yokosuka and Sobu lines (for rapid service), the Keiyo Line, and other lines, and those are provided with ventilators, smoke control systems, as well as cooling systems that remove heat from trains, lighting and human bodies. More than 30 years have passed since construction of many of those underground stations, so the heat load calculation conditions have changed and the calculation methodology has progressed from those at the time of construction.

This research article will report on case studies of energy saving where the air conditioning load was reviewed based on the thermal environment and the cooling system operation status of an underground station using the Sobu Line underground area at Tokyo Station as a model. Thermal environment measurement of the underground stations for rapid service on the Yokosuka and Sobu lines and on the Keiyo line clarified that the humidity in those underground stations was high, requiring the removal of latent heat.

*Mechatronics Technology Management Center, Facilities Depertment (previously at Environmental Engineering Research Laboratory)**Environmental Engineering Research Laboratory, Research and Development Center of JR East Group

Sogo Iyobe* Masafumi Sato**

Fig. 2 Tokyo Station Sobu Underground PlatformAir Conditioning Method (Improved Mode)

Fig. 1 Tokyo Station Sobu Underground PlatformAir Conditioning Method (Usual Mode)

30 JR EAST Technical Review-No.23

Special edition paper

Fig. 5 shows the measurement results for the thermal environment.

Fig. 5 is a scatter plot of the measurement results, with enthalpy of the platform air on the vertical axis and enthalpy of outside air on the horizontal axis.

The outside temperature and humidity calculation conditions of JR East for the hottest hours in summer in Tokyo is 34 ºC temperature and 57.8% relative humidity, thus the enthalpy is 81.6 kJ/kg.

When outside air enthalpy reached its peak (81.6 kJ/kg), the enthalpy of the platform air in the improved mode was lower that that in the usual mode, indicating that the thermal environment was improved. This is a thermal environment equivalent to the platform heat load calculation conditions of 28 ºC temperature, 60% relative humidity and 65.3 kJ/kg enthalpy.

4.2 Measurement of Heat Generated by Refrigerating Machines

In the same periods as the thermal environment was measured, we installed thermometers and flowmeters to the supply pipes to the platform and the concourse, measuring the amount of heat generated by the refrigerating machines. Fig. 6 shows the measurement result.

Fig. 6 shows the amount of heat generation on the vertical axis and the outside air enthalpy on the horizontal axis.

The amount of heat generation at the maximum outside air enthalpy in the heat load calculation conditions was 1,208 RT in the improved mode, a reduction of approx. 200 RT from the 1,415 RT in the usual mode.

convert braking force into heat was predominant.As the heat discharge from bogies by braking was large at that

time, it was estimated that the temperature at the track was higher than the outside temperature. An air conditioning method that takes in large volumes of outside air was thus adopted.

Today, however, the mainstream of braking is regenerative brakes that convert braking force into electricity. We thought that the air supplied from outside to on the track is in fact a burden to the system.

We thus carried out simulation of train heat discharge as shown in Fig. 3.

Fig. 3 clarifies that the heat discharge from series E217 rapid trains is approx. 58% less than the heat discharge from series 113 rapid trains that were dominant at the time of construction. It is also reveals that heat discharge from air conditioner outside units now exceeds heat discharge from bogies.

Conducting thermofluid analysis on the platform shows that there was little air curtain effect; we confirmed that outside air flowed in to the platform and cool air flowed out under the platform (Fig. 4).

Cooling is for the passengers on the platform, however we found that incoming outside air raises the temperature on the platform and cool air is wastefully allowed to escape.

Identifying State of Air Conditioning at Tokyo Station Sobu Underground Platform4

4.1 Measurement of Thermal Environment on PlatformWe carried out measurement of the thermal environment on the platform and the refrigerating machines in the usual mode and in the improved mode in the following separate periods.a) Usual mode: July 24 - August 1, 2010b) Improved mode: August 2 – 8, 2010

5050

120

▲58%▲58%▲58%▲58%

Shin-Nihombashi Tokyo Shimbashi Shin-Nihombashi Tokyo Shimbashi

Running speed

Curve resistanceheat

Air resistanceheat

Cooler heat

Human bodyheat

Controller heat

Motor heat

Bogie heat

Heat discharge for 2-minute stop at Tokyo Station

Under�oorexhaust heat

Under�oorexhaust heat

[Input data] · Train performance data · Train performance curve · Passenger load factor

Series 113 train (at time of construction) Series E217 train (now)

Originally outside air becomes exhaust

Little air curtain e�ect

Cool air �ows out

Outside air �ows in

Track area

Platform

Hea

t gen

erat

ed [R

T]

Enthalpy of outside air [kl/kg] (source: Japan Meteorological Agency)

Usual mode: 1,415 RTApprox. -200 RT

Improved mode: 1,208 RT

Hea

t loa

d calc

ulati

onco

nditi

on: 8

1.6

Usual modeImproved mode

Fig. 4 Analysis Results for Flow of Outside Air at Track to Platform

Fig. 3 Analysis Results for Heat Discharge from Trains

Fig. 6 Relation Between Heat Generated and Enthalpy of Outside Air

Enth

alpy

of p

latfo

rm ai

r [kl

/kg]

Enthalpy of outside air [kl/kg] (source: Japan Meteorological Agency)

Usual modeImproved mode

Heat load calculationcondition: 65.3

Usual mode: 68.4

Improved mode: 65.8

Hea

t loa

d calc

ulati

onco

nditi

on: 8

1.6

Fig. 5 Relation Between Enthalpy of Platform Air and Outside Air

31JR EAST Technical Review-No.23

Special edition paper

Proposal for Improvement of Air Conditioning of Tokyo Station Sobu Underground Platform5

In the previous section, we explained that reducing intake outside air on the track could improve the platform thermal environment and reduce the heat load as well. For further energy saving, we examined taking in return air to reduce the amount of outside air the air conditioner deals with.

Simply reducing the amount of outside air might push up CO2 and density of dust. Carrying out an empirical test by gradually reducing the amount of outside air, we found out that no problems would occur even when reducing the current value of 190 m3/h/m2 on the platform level to 20 m3/h/m2.

Renovation work is required to allow intake of air. We thus checked the load (Fig. 7).

Fig. 7 shows that the air conditioning load in the improvement proposal is expected to be approx. 1,100 RT, a reduction of the air conditoning heat load in the usual mode by approx. 670 RT (▲38%).

A 3,379 MWh (approx. 33%) reduction of power consumption was calculated to be possible if the improvement proposal is carried out (Table 1).

Identifying State of Air Conditioning of Underground Stations Other than Tokyo Station Sobu Underground Area

6

6.1 Air Conditioning Method of Other Underground StationsFig. 8 is a diagram of the air conditioning method of Bakurocho, Shin-Nihombashi, Shimbashi stations on the Yokosuka and Sobu lines for rapid service and of the Tokyo Station Keiyo underground area.

To Bakurocho and Shin-Nihombashi stations and the Tokyo Station Keiyo underground area, an air conditioning method completely using outside air is applied, while a method using return air is applied to Shimbashi Station. However, use of air conditioners of Shimbashi Station that take in return air have been suspended since 2010 as a part of electricity conservation measures, so the air conditioning method shown in Fig. 8 (a) is now applied to all those stations.

6.2 Measurement of Thermal EnvironmentTo measure humidity, we installed a hygrothermograph each to a point on the underground platform of each station in addition to the thermometers used to control platform cooling.

We measured the thermal environment on the platform of each station in the following periods separately in usual and improved modes.c) Period with cooling: August 23 – 29, 2010d) Period without cooling/heating: November 15 – 23, 2010

Currently cooling is controlled based on the platform temperature detected. We confirmed that the platform temperature in each station in the period with cooling was kept almost at 28 ºC.

Fig. 9 and 10 shows humidity measurement results of intermediate stations and a terminal station. An intermediate station in this article means a station where trains stop for a short time, and those include Shimbashi, Shin-Nihombashi, and Bakurocho Stations. A terminal station means a station where trains stay a long time, and those include the Tokyo Station Keiyo underground area. The vertical axis is the absolute humidity of the platform air and the horizontal axis is the absolute humidity of outside air. The dotted diagonal line indicates that the absolute humidity of the platform air and the outside air were equal to each other. The vertical dashed-dotted line is the peak of the outside air humidity in the heat load calculation conditions,

Table 1 Power Consumption to Be Reducedin Improvement Proposal

Power consumption [MWh]Reduction

rateUsual mode Improvement

proposal Reduction

Carrier motive energy 3,411 1,410 2,001 59%

Heat source 6,866 5,488 1,378 20%

Total 10,277 6,898 3,379 33%

▲ ▲

Air

cond

ition

ing l

oad

[RT

]

Review load

Air conditioning loadRefrigeratingmachine capacity

Cur

rent

refr

iger

atin

gm

achi

ne ca

paci

ty

Usu

al m

ode

(mea

sure

men

t)

Impr

ovem

ent p

ropo

sal

Change airconditioning method

Outside air ExhaustAirconditioner

Airconditioner

Exhaustfan

Exhaust

Cool air

Undergroundplatform

Undergroundplatform

Outside air ExhaustExhaust

fan

Exhaust

Cool air

(a) Bakurocho Station, Shin-Nihombashi Station,Tokyo Station Keiyo Underground Area

(b) Shimbashi Station

Return air

Fig. 8 Air Conditioning Methods for Underground Stations on the Sobu and Yokosuka Lines for Rapid Service and on the Keiyo Line

Fig. 7 Simulation Result of Air Conditioning Load of Refrigerating Machines

32 JR EAST Technical Review-No.23

Special edition paper

and the horizontal dashed-two dotted line is the humidity of the platform in the heat load calculation conditions.

Fig. 9 and 10 proved that the humidity in the intermediate stations was always higher than that of the outside air. They also proved that the humidity in the terminal station in the period with cooling was kept at the calculated absolute humidity, while the humidity in the period without cooling/heating was slightly higher than the outside air humidity.

6.3 Heat Generated by Refrigerating MachinesFor the amount of heat generated by the refrigerating machines, we used the data collected and stored by the existing monitoring system. Fig. 11 shows the capacity of the refrigerating machines and the peak load on the day in the measurement periods when the outside air temperature reached its highest (August 9, 2011).

The figure shows that the refrigerating machines of each underground station on the Sobu and Yokosuka lines for rapid service were operated with low loads with very small amount of heat generation compared to the current refrigerating machine capacity.

Considerations7

One of the reasons why the humidity in the intermediate stations was high and the amount of heat generation was low compared to the refrigerating machine capacity is assumed to be that latent heat was large due to evaporation of sump water in tunnels and the sensible heat ratio was low. In contrast, in the terminal station, sensible heat ratio is assumed to be higher than in the intermediate stations because sensible heat from outside units of train air conditioners became large while trains were in the station for a long time.

The existing refrigerating machines can deal with sensible heat, but they cannot sufficiently deal with latent heat. Therefore, the amount of heat generated by refrigerating machines is small compared to the refrigerating machine capacity in intermediate stations with low sensible heat ratio, while refrigerating machines operate with high load factor in terminal stations (Fig. 12).

Analyzing the load using the simulator, we also found deviation from the actually measured peak load as found in Fig. 11. This is assumed to be because the current simulator cannot accurately analyze latent heat conditions.

Conclusion8Since we were able to verify that energy saving could be achieved in the Tokyo Station Sobu underground area by modifying the air conditioning method used there, we have partly changed how the air conditioning system is operated since 2011 as an effort for electricity conservation. We are also planning renovation of air conditioners on the occasion of replacement of the equipment for the heat source.

In intermediate stations, the rate of latent heat is high, and existing refrigerating machines cannot deal with latent heat. In order to improve the thermal environment on the platform of intermediate stations, we need to study and develop a new air conditioning system.

The current simulation cannot accurately analyze latent heat conditions. We thus have to revise the heat analysis method to reflect analysis results in the heat load calculation approach at equipment replacement.

Plat

form

air a

bsol

ute h

umid

ity [k

g/kg

]

Shimbashi StationShin-Nihombashi StationBakurocho StationOutside air heat load calculation condition: 0.0189 kg/kgInside air heat load calculation condition: 0.142 kg/kg

Nov. 15 - 22(without cooling)

Outside air absolute humidity [kg/kg] (source: Japan Meteorological Agency)

Plat

form

air a

bsol

ute h

umid

ity [k

g/kg

]

Aug. 23 - 29(with cooling)

Nov. 15 - 22(without cooling)

Outside air absolute humidity [kg/kg] (source: Japan Meteorological Agency)

Tokyo Station Platforms #3 and 4Tokyo Station Platforms #1 and 2Outside air heat load calculation condition: 0.0189 kg/kgInside air heat load calculation condition: 0.142 kg/kg

Aug. 23 - 29(with cooling)

Ref

riger

atin

g mac

hine

capa

city

,A

mou

nt o

f hea

t gen

erat

ion

[RT

]

ShimbashiStation

Shin-NihombashiStation

BakurochoStation

Tokyo StationKeiyo underground area

Existing refrigerating machine capacityPeak heat generated

Heat a refrigeratingmachine can deal with

Heat a refrigeratingmachine cannot deal with

Intermediatestation

Terminalstation

Sensibleheat Latent heat

Sensible heat Latent heat

Heat a refrigeratingmachine can deal with

Heat a refrigeratingmachine cannot deal with

Total airconditioning load

Fig. 10 Correlation Between Absolute Humidity of Platform Air and Outside Air (Terminal Station)

Fig. 9 Correlation Between Absolute Humidity of Platform Air and Outside Air (Intermediate Station)

Fig. 12 Concept of Heat in Intermediate Stationsand Terminal Stations

Fig. 11 Refrigerating Machine Capacity and Heat Generated