S P E C I F I C A T I O N - F O RNAME OF WORK :-
CONSTRUCTION O MINOR BRIDGE & C. D. WORKS & GAT WALL ONADGAON GIRNARE - WAGHERE - HARSUL - OZARKHED ROAD SH-26 AT CH 40/000, 43/600 & 46/600 TALUKA TRIMBAKESHWAR, DIST. NASHIK
0.00
Note :- Reference given for specifications from standard specifications book, published by Government of Maharashtra P.W. & housing
department, Volume - I & Volume - I I, edition 1979 and 1981 respectively. The numbers are indicative and any other specifications from the
book of standard specifications will be entirely applicable & binding on the contractor. If so directed by the Engineer - Incharge. Items are
inclusive of all leads & lifts required for completion of the work satisfactorily.
SCHEDULE “ C “ Specifications as per StandardSpecifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
FOR BRIDGE WORK
1 Excavation for foundation including shoring and Spec.No. BR.3 Page No. 102 a ) The sizes of length, width and depth of excavation
strutting as necessary and disposing off shown on drawing are probable and may vary in
excavated stuff as directed in earth, soils of all actual execution. The contractor is not entitled to claim
types, sand, gravel, soft murum etc. (excluding extra payment for changes in sizes of excavation.
dewatering) inlcuidng all leads and lift complete. b ) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
binding on the contractor.
c ) Soft strata includes all types of soil, all types clay,
sand, soft murum, all types of hard murum,Boulders
which can be best removed by pick axe and /or with
shawel after loosening with pick axe or crow bar. It shall
also includes isolated boulders up to0.10cubicmeter
each, which do not need blasting and could be removedeach, which do not need blasting and could be removed
with pick axe, crow bar and shawel.
2 Excavation for foundation in hard murum including Spec.No. BR.3 Page No. 102 a ) The sizes of length, width and depth of excavation
shoring and strutting as necessary and disposing off shown on drawing are probable and may vary in
excavated stuff as directed (excluding dewatering) actual execution. The contractor is not entitled to claim
inlcuidng all leads and lift complete. extra payment for changes in sizes of excavation.
b ) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
binding on the contractor.
c ) Soft strata includes all types of soil, all types clay,
sand, soft murum, all types of hard murum,Boulders
which can be best removed by pick axe and /or with
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
shawel after loosening with pick axe or crow bar. It shall
also includes isolated boulders up to0.10cubicmeter
each, which do not need blasting and could be removed
with pick axe, crow bar and shawel.
3 Excavation for foundation in hard murum and Spec.No. BR.3 Page No. 102 a ) The sizes of length, width and depth of excavation
boulders including shoring and strutting as shown on drawing are probable and may vary inboulders including shoring and strutting as shown on drawing are probable and may vary in
necessary and disposing off excavated stuff as actual execution. The contractor is not entitled to claim
directed. (excluding dewatering.) inlcuidng all leads extra payment for changes in sizes of excavation.
and lift complete. b ) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
binding on the contractor.
c ) Soft strata includes all types of soil, all types clay,
sand, soft murum, all types of hard murum,Boulders
which can be best removed by pick axe and /or with
shawel after loosening with pick axe or crow bar. It shall
also includes isolated boulders up to0.10cubicmeter
each, which do not need blasting and could be removed
with pick axe, crow bar and shawel.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
4 Excavation for foundation in soft rock including Spec.No. BR.3 Page No. 102 a ) The sizes of length, width and depth of excavation
shoring and strutting as necessary and disposing off shown one drawing are probable and may vary in
excavated stuff as directed (excluding dewatering). actual execution. The contractor is not entitled to claim
inlcuidng all leads and lift complete. extra payment for changes in sizes of excavation.
b ) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
binding on the contractor.binding on the contractor.
c ) Soft strata includes all types of soil, all types clay,
sand, soft murum, all types of hard murum,Boulders
which can be best removed by pick axe and /or with
shawel after loosening with pick axe or crow bar. It shall
also includes isolated boulders up to0.10cubicmeter
each, which do not need blasting and could be removed
with pick axe, crow bar and shawel.
5 Excavation for foundation including shoring Spec.No. BR.3 Page No. 102 a ) The sizes of length, width and depth of excavation
and strutting as necessary and disposing off shown on drawing are probable and may vary in
excavated stuff as directed in hard rock actual execution. The contractor is not entitled to claim
inlcuidng all leads and lift complete. extra payment for changes in sizes of excavation.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
b ) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
binding on the contractor.
c ) Soft strata includes all types of soil, all types clay,
sand, soft murum, all types of hard murum,Boulders
which can be best removed and /or with shawel after
loosening with pick or crow bar. It shall also includesloosening with pick or crow bar. It shall also includes
isolated boulders up to0.10cubicmeter each, which do
not need blasting and could be removed with pick axe,
crow bar and shawel.
2) Hard strata includes soft rock and hard rock It shall
also include isolated boulders having mass above
0.10 cubic meter each, which do not need blasting and
could be removed with pick axe, crow bar and shawel.
6 Dewatering including diversion of stream, Spec.No. BR.4 Page No.103 to The mode of measurement will be in cubic meter,
providing coffe dam, bunds etc. as may be 105 based on the lnitial Water Level' approved by the
necessary for foundation and other parts of work Engineer in charge. The payment should be made
and bailing out and pumping out water during for the excavation done below the Initial Water
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
and after excavation as required. Level' approved by the Engineer in Charge in the
1) For Abutment case of lnitial water level' approved is above the
ground level, the quantity above the ground level
and upto the lnitial Water Level' is not applicable
for the payment.The above additional specific
ation is applicable for the payment Open
Foundation, Raft and Cutoff Wall.Foundation, Raft and Cutoff Wall.
7 Dewatering including diversion of stream, Spec.No. BR.4 Page No.103 to The mode of measurement will be in cubic meter,
providing coffe dam, bunds etc. as may be 105 based on the lnitial Water Level' approved by the
necessary for foundation and other parts of work Engineer in charge. The payment should be made
and bailing out and pumping out water during for the excavation done below the Initial Water
and after excavation as required. Level' approved by the Engineer in Charge in the
2) For Return case of lnitial water level' approved is above the
ground level, the quantity above the ground level
and upto the lnitial Water Level' is not applicable
for the payment.The above additional specific
ation is applicable for the payment Open
Foundation, Raft and Cutoff Wall.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
8 Dewatering including diversion of stream, Spec.No. BR.4 Page No.103 to The mode of measurement will be in cubic meter,
providing coffe dam, bunds etc. as may be 105 based on the lnitial Water Level' approved by the
necessary for foundation and other parts of work Engineer in charge. The payment should be made
and bailing out and pumping out water during for the excavation done below the Initial Water
and after excavation as required. Level' approved by the Engineer in Charge in the
3) For Return case of lnitial water level' approved is above the3) For Return case of lnitial water level' approved is above the
ground level, the quantity above the ground level
and upto the lnitial Water Level' is not applicable
for the payment.The above additional specific
ation is applicable for the payment Open
Foundation, Raft and Cutoff Wall.
9 Providing and laying in situ Mix-10 grade / 1:3:6 cement Spec.No. BR.5 Page No.105 1) The foundation shall be passed in writing by
concrete of trap metal in foundation including and IS 456 (2000)Executive Engineer before concreting is started.
necessary bailing out water compacting and curing. 2) Wooden centring and shuttering will not be allowed
(including form work, centering and excluding
dewatering by pump.) Newly laid concrete shall be
covered by gunny bags, plastic tarpaulin including all
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
leads and lift etc complete .(wooden centering,
shuttering will not be allowed)
10 Providing and laying Mix-15 gradecement concrete Spec.No. BR.27 Page No.127 A ) All materials are to be tested and design mix should
of trap metal for cast in situ piers,abutments,returns and IS 456 (2000)be obtained from Government or Government
wings, etc. including provision of " V " shaped false approved laboratory before starting of work and shall
joints to form suitable panels on the faces to approved get approved from Engineer in - charge.joints to form suitable panels on the faces to approved get approved from Engineer in - charge.
design with compacting by vibrating, covering B ) Grade of concrete shall be M-15 by design mix.
newly laid concrete by gunny bag, plastic or C ) Sampling and testing shalll comply with
tarpaulin & curing with all leads and lift etc complete. specification No. B-7 (3) Page No. 38 and relevent
(excluding finishing with cement plaster) including specifcation No. B-6 (12) Page No. 37 from standard
formwork and bailing out of water. (upto 4m height) specification
(Item includes provision of surface reinforcement but D ) The rate of item is based on cement content of 360
excluding cost of steel reinforcement) kilogram per cubic meter. For change of cement
content as per actual design mix. The rate of item will
be increased or decreased as per the conditions
mentioned B-7 / 4 Page No. 39 of clause
E )The testing charges will be borne by contractor.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
11 Providing and laying in situ cement concrete Mix-20 Spec.No. BR.29 Page No.129 A ) All materials are to be tested and design mix should
grade of trap metal for Reinforced cement concrete /IS 456 (2000) be obtained from Government or Government
caps over piers and abutments including necessary approved laboratory before starting or work and shall
scaffolding, formwork, compacting by vibrating, get approved from Engineer in - charge.
finishing,covering newly laid concrete by gunny bag, B ) Grade of concrete shall be M-20 by design mix.
plastic or tarpaulin and curing inlcuding all leads and C ) Sampling and testing shalll comply with
lift etc complete. (excluding reinforcement and specification No. B-7 (3) Page No. 38 and releventlift etc complete. (excluding reinforcement and specification No. B-7 (3) Page No. 38 and relevent
including centering). specifcation No. B-6 (12) Page No. 37 from standard
specification
D ) The rate of item is based on cement content of 360
kilogram per cubic meter. For change of cement
content as per actual design mix. The rate of item will
be increased or decreased as per the conditions
mentioned in the B-7 / 4 Page No. 39
E )The testing charges will be borne by contractor.
12 Providing and laying in situ Mix-25 grade cement Spec.No. BR.38 Page No.135 A ) All materials are to be tested and design mix should
concrete of trap/ granite/ quartzite/ gneiss metal for /IS 456 (2000) be obtained from Government or Government
Reinforced cement concrete Work including approved laboratory before starting of work and shall
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
ramming, vibrating finishing, covering newly laid get approved from Engineer in - charge.
concrete by gunny bags, plastic or tarpaulin and curing B ) Grade of concrete shall be M-25 by design mix.
complete in solid/deck slab, including all leads C ) Sampling and testing shalll comply with
and lift etc complete. (including formwork, centering, specification No. B-7 (3) Page No. 38 and relevent
finishing in cement plaster and excluding specifcation No. B-6 (12) Page No. 37 from standard
reinforcement) specification
D ) The rate of item is based on cement content of 412.50D ) The rate of item is based on cement content of 412.50
kilogram per cubic meter. For change of cement
content as per actual design mix. The rate of item will
be increased or decreased as per the conditions
mentioned B-7 / 4 Page No. 39 of clause
E )The testing charges will be borne by contractor.
13 Providing tar paper bearing of approved quality. ~~ ~~ The work shall be executed as per spcifications and
in proper size etc. complete. As directed by Engineer in charge.
14 Providing expansion joints with 25 milimetre thick Spec.No. BR. 43 Page No.138 to The work shall be executed as per spcifications and
bitumenous pad as per detailed drawings. 139 As directed by Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
15 Providing and laying in situ Mix-20 grade cement Spec.No. BR. 50 Page No.143 A ) All materials are to be tested and design mix should
concrete of trap metal for Reinforced cement be obtained from Government or Government
concrete work of ballast walls, kerbs, box returns etc. approved laboratory before starting or work and shall
including scaffolding, compaction, formwork finishing, get approved from Engineer in - charge.
covering newly laid concrete by gunny bag, plastic or B ) Grade of concrete shall be M-20 by design mix.
tarpaulin and curing including all leads and lift etc C ) Sampling and testing shalll comply with
complete. (excluding reinforcement) specification No. B-7 (3) Page No. 38 and releventcomplete. (excluding reinforcement) specification No. B-7 (3) Page No. 38 and relevent
specifcation No. B-6 (12) Page No. 37 from standard
specification
D ) The rate of item is based on cement content of 360
kilogram per cubic meter. For change of cement
content as per actual design mix. The rate of item will
be increased or decreased as per the conditions
mentioned in the B-7 / 4 Page No. 39
E )The testing charges will be borne by contractor.
16 Providing and laying in situ M-20 grade cement Spec.No. BR.47 Page No.140 A ) All materials are to be tested and design mix should
concrete of trap metal For wearing course /IS 456 (2000) be obtained from Government or Government
75millimetre thick. including compacting. finishing, approved laboratory before starting or work and shall
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
covering newly laid concrete by gunny bag, plastic or get approved from Engineer in - charge.
tarpaulin, curing and filling in joints with bitumen B ) Grade of concrete shall be M-20 by design mix.
inlcuidng all leads and lift etc complete. C ) Sampling and testing shalll comply with
specification No. B-7 (3) Page No. 38 and relevent
specifcation No. B-6 (12) Page No. 37 from standard
specification
D ) The rate of item is based on cement content of 360D ) The rate of item is based on cement content of 360
kilogram per cubic meter. For change of cement
content as per actual design mix. The rate of item will
be increased or decreased as per the conditions
mentioned in the B-7 / 4 Page No. 39
E )The testing charges will be borne by contractor.
17 Providing and fixing in position Thermo Spec.No. BR.28 Page No.129 The Thermo Mechanically Treated steel bars
Mechanically Treated ( TMT ) bar reinforcementof Spec.No. BR.35 Page No.134 should be utilised instead of Mild steel bars.
various diameters for Reinforced cement Spec.No. BR.49 Page No.143 a) The work shall be executed as per spcifications and
concrete work as pe detailed designs, drawings and IS 1786:1985as directed by Engineer in charge.
and schedules inclduing cutting bending, b) Only approved material shall be allowed for this item
hooking the bars, binding with wires or tack c) Steel shall be brought from other plant
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
welding and supporting as required with all
leads and lifts etc complete as directed by
Engineer in char ( TMT Steel shall be from other
plant only )
18 Providing Reinforced cement concrete parapet with Spec.No.: BR.51(a) Page No.144/IS The work shall be executed as per spcifications and
M.15 cement concrete of trap/ granite/ quartzite/ 456 (2000) As directed by Engineer in charge.M.15 cement concrete of trap/ granite/ quartzite/ 456 (2000) As directed by Engineer in charge.
gneiss metal with cast in situ/precast panels as per
the detailed drawing including reinforcement,
scaffolding, centering, formwork, compacting, finishing
and curing with all leads and lift etc. complete.
19 Providing trap rubble filling behind the abutment, Spec.No. BR.57 Page No.151 1 ) As directed by Engineer - in - charge.
returns or wings.
20 Providing selected hard murum filling including Spec.No.CD.14 Page No.167 The work shall be executed as per spcifications and
laying in layers of 15 centimetre to 20 centimetre As directed by Engineer in charge.
watering and compacting including all leads and
lifts complete.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
21 Providing 90centimetre thick flexible stone mat as ~~ ~~ 1 ) As directed by Engineer - in - charge.
per standard drawing including supplying all materials
at work site spreading and compaction complete as
directed by Engineer in charge.
22 Providing and fixing Asbestos cement , Un-plasticised ~~ ~~ The work shall be executed as per spcifications and22 Providing and fixing Asbestos cement , Un-plasticised ~~ ~~ The work shall be executed as per spcifications and
Poly Vinyl Chloride pipes of 100 millimetre diameter As directed by Engineer in charge.
and of required length for providing weep holes in
Abutments, Riding returns, Returns, including
necessary inverted filter etc. complete.
23 Providing galvanised iron 100mm diameter Spec.No. : BR.55 Page No. 149 The work shall be executed as per spcifications and
water spouts as per approved drawings. As directed by Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
FOR C. D. WORK
24 Excavation for foundation in earth, soil of all Spec.No.Bd.A. 1 Page No.259 a ) The sizes of length, width and depth of
types, sand, gravel and soft murum,including excavation show on drawing are probale and may
removing the excavated material up to a vary in actual execution. The contractor is
distance of 50metre beyond construction area & not entitled to claim extra payment for changes in
stacking and spreading as directed, sizes of excavation. stacking and spreading as directed, sizes of excavation.
dewatering, preparing the bed for the b ) The decision regarding the classification of
foundation and necessary back filling, strata given by Executive Engineer shall be final &
ramming, watering including shoring and will be binding on the contractor.
strutting including all leads and lift etc. complete. c) Soft strata includes all types of soil, all types clay
sand, soft murum, all types of hard murum,
Boulders and soft rock which can be best
removed by pick axe and / or with shawel after loosening
with pick axe are or crow bar. It shall also include isolated
boulders up to 0.10cubicmeter each, which do not need
blasting and could be removed with pick axe, crow bar
and shawel.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
25 Excavation for foundation in hard murum Spec.No.Bd.A. 2 Page No.259 a ) The sizes of length, width and depth of
including removing the excavated materials excavation show on drawing are probale and may
upto distance of 50 metres beyond vary in actual execution. The contractor is
construction area and stacking and spreading not entitled to claim extra payment for changes in
as directed, dewatering, preparing the bed for sizes of excavation.
the foundation and necessary back filling, b ) The decision regarding the classification ofthe foundation and necessary back filling, b ) The decision regarding the classification of
ramming, watering including shoring and strata given by Executive Engineer shall be final &
strutting including all leads and lift etc. complete. will be binding on the contractor.
c) Soft strata includes all types of soil, all types clay
sand, soft murum, all types of hard murum,
Boulders and soft rock which can be best
removed by pick axe and / or with shawel after loosening
with pick axe are or crow bar. It shall also include isolated
boulders up to 0.10cubicmeter each, which do not need
blasting and could be removed with pick axe, crow bar
and shawel.
mentioned in the wording of item.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
26 Providing and laying in situ cement concrete of Spec.No CD.3 Page No. 160 A ) The foundation shall be passed in writing by
1:4:8 with trap metal in foundation including /IS 456 (2000) Executive Eingineer before concreting is started.
necessary compacting, covering newly laid B ) The bed of the foundation trenches shall be
concrete by gunny bag, plastic or tarpaulin and cleaned. All loose material is to be well wetted if dry to
curing etc. complete. including form work. prevent absorption of water from the green concrete.
Including all leads and lifts etc. complete. C ) Proportion of ingradient materials shall be asIncluding all leads and lifts etc. complete. C ) Proportion of ingradient materials shall be as
mentioned in the wording of item.
27 Providing cement concrete M-15 grade for head Spec.No.CD.8 160/IS 456 (2000)The work shall be executed as per spcifications and
walls, abutments, piers, return, wings, with or As directed by Engineer in charge.
without circular or other shaped opening for
waterway including necessary scaffolding,
formwork, compaction, finishing, covering newly
laid concrete by gunny bag,plastic or tarpaulin and
curing with all leads and lifts etc. complete.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
28 Providing and laying in situ cement concrete of Spec.No CD.3 Page No. 160 A ) The foundation shall be passed in writing by
1:3:6 with trap metal in foundation including /IS 456 (2000) Executive Eingineer before concreting is started.
necessary compacting, covering newly laid B ) The bed of the foundation trenches shall be
concrete by gunny bag, plastic or tarpaulin and cleaned. All loose material is to be well wetted if dry to
curing etc. complete. including form work. prevent absorption of water from the green concrete.
Including all leads and lifts etc. complete. C ) Proportion of ingradient materials shall be asIncluding all leads and lifts etc. complete. C ) Proportion of ingradient materials shall be as
mentioned in the wording of item.
29 Providing and laying cement concrete pipe of I.S. Spec.No CD.7 Page No. 162 The work shall be executed as per spcifications and
N.P.-2 Class of 900 mm diameter in proper as directed by Engineer in charge.
line, level and slope including providing, fixing ii) The tested pipe with ISI mark shall be used and
collars or spigot and socket joint by rubber ring proof shall be produced for the same.
and in cement mortar 1:2 with all leads and lifts
etc. complete.
N.P.-2 Class of 900millimetre diameter
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
30 Providing and casting in situ cement concrete Spec.No.Bd.E.3 Page No. 288 / A ) All materials are to be tested and design mix
1:2:4 of trap metal, for coping to plinth or IS 456:2000 should be obtained from Government or
parapet moulded or chamfered as per drawing or Government approved laboratory before starting of
as directed including centering,form work, com work as directed by Engineer - in charge.
pacting, covering newly laid concrete by gunny B ) Grade of concrete shall be M-15 by design mix.
bag, plastic or tarpaulin, roughening them if C )Sampling and testing shall comply with
special finish is to be provided and curing and specification No B-7 ( 3 ) /Page No. 38 and releventspecial finish is to be provided and curing and specification No B-7 ( 3 ) /Page No. 38 and relevent
finishing if required with all leads and lifts etc. specification No. B - 6 ( 12 ) Page No. 37 from
complete. (The cement mortar 1:3 plaster is standard specifications.
considered for rendering uneven and honey D ) The rate of item is based on cement content of
combed surface only. Wooden planks/shuttering 305 kilogram per cubic meter. For change of
will not be allowed) cement content as per actual design mix. The rate
of item will be increased or decreased as per the
conditions mentioned in the B - 7 - 4 Page No. 39 of
P.W.D. Government of Maharashtra.
F ) The cement mortar 1:3 plaster is considered for
rendering uneven and honeycombed surface only.
G ) Wooden plnks shuttering will not be allowed,
Only steel or plywood shuttering shall be used.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
31 Providing and laying in situ Mix-15 cement concrete of Spec.No. BR.47 Page No.140 The work shall be executed as per spcifications and
trap metal including compacting, finishing, curing and IS456(1978) As directed by Engineer in charge.
filling in joints with bitumen complete etc. for approach BR 47D
slab (excluding reinforcement.)
FOR ROAD WORKFOR ROAD WORK
32 Excavation for road way in by mechanical Spec.No. Rd.2 Page No.180 a) The work shall be executed as per specifications and
means earth soil of all sorts sand, gravel, soft As directed by Engineer in charge.
murum and hard murum, hard murum with b) Instruction regarding widening and strenthning of
boulders including dressing section to the road and maintaing crust thickness register issued
required grade, camber and side slopes and vide Govt. Circular No. RMR-2005/CR 201(1) /Road-1
conveying the excavated materials with all dt. 2.1.06 and Circular No. RMR-2005/C.R. 201 (2) /
lifts and spreading for embankment or Road-1 dt. 2.1.06 shall be strictly followed.
stacking etc. as directed by Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
33 Excavation for catch/side water gutter/jungle gutter Spec.No Rd. 9 Page No. 187 1 ) Soft strata includes all types of soil, all types clay,
in all sorts of soils strata to the specified section sand, soft murum, all types of hard murum,Boulders
including stacking the excavated stuff in a regular bund which can be best removed by pick axe & /or with shawel
and disposing of unsuitable or excess stuff beyond 50 crow bar. It shall also includes isolated boulders up
m. from place of excavation as directed by Engineer in to 0.10cubicmeter each, which do not need blasting
charge by Mechanical and sectioning manually for road and could be removed with shawel / crow bar of the
side gutter excavator machineside gutter excavator machine
a) In Sort of Soil ( By Mechanical ) 2) Hard strata includes soft rock and hard rock It shall
also include isolated boulders having mass above
0.10 cubic meter each, which do not need blasting and
could be removed with pick axe, crow bar
3) The decision regarding the classification of strata
given by Executive Engineer shall be final and will be
binding on the contractor.
4) The unit for mode of measurement will be one
cubic meter basis instead of one running metre length
as mentioned in the standard specification book.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
34 Providing earth work for embankment with Spec.No. Rd.13 Page No.194 The work shall be executed as per spcifications and
approved materials obtained from excavation As directed by Engineer in charge.
by mechanical means from Departmental
land or other sources including all lifts and , laying in
layers of 20 centimetre to 30 centimetre thickness
breaking clods dressing to the required lines,
curves,grades and sections and compacting withcurves,grades and sections and compacting with
power roller all leds and lift etc complete.
as directed by Engineer in charge
35 Supplying 60millimetre trap stone metal by Spec.No. Rd. 19 Page No.197 1)The materals shall be got tested from the approved
breaking boulders (hand broken) of required size laboratory before use, at the cost of contractor. He
by bringing the boulders at the road side, breaking must preserve the forest conservation act. 1980. He is
them to required gradation including conveying fully wholely and solely responsible for violance of
boulders and stacking broken metal including all leads forest conservation act. 1980. The rates shown in
and lift etc. complete. schedule ‘ B ‘ will be deemed to have included all
leads lifts, royalty chargs octroi duty, sale tax etc. if the
Government quarries are not available, it will be the
responsibility of the contractor to obtain the material
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
from the private quarry at his own cost, for which the
contractor should obtain the permission of the owner
and the competenet authority at his own cost and no
extra lead charges will be given to the contractor.
2) The Contractor should submit the receipt of payment
of royalty charges of the material used, if such receipt is
not produced by the contractor the royalty charges willnot produced by the contractor the royalty charges will
be deducted from the bill of work done by the contractor.
3) During execution rubble from quarry site should be
brouhgt to road side and stacked. The rubble for one
stack should be broken first and broken metal should
be got approved from Engineer in charge.
4) The broken metal should be collected as per
requirement by the side of road & properly stacked &
got approved from Engineer in charge before spreading
5) The stacking of metal should be so done that it do
not cause hinderence to existing traffic.
6) As directed by Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
36 Supplying 40millimetre trap stone metal by Spec.No. Rd. 19 Page No.197 1)The materals shall be got tested from the approved
breaking boulders (hand broken) of required size laboratory before use, at the cost of contractor. He
by bringing the boulders at the road side, breaking must preserve the forest conservation act. 1980. He is
them to required gradation including conveying fully wholely and solely responsible for violance of
boulders and stacking broken metal including all leads forest conservation act. 1980. The rates shown in
and lift etc. complete. schedule ‘ B ‘ will be deemed to have included all
leads lifts, royalty chargs octroi duty, sale tax etc. if theleads lifts, royalty chargs octroi duty, sale tax etc. if the
Government quarries are not available, it will be the
responsibility of the contractor to obtain the material
from the private quarry at his own cost, for which the
contractor should obtain the permission of the owner
and the competenet authority at his own cost and no
extra lead charges will be given to the contractor.
2) The Contractor should submit the receipt of payment
of royalty charges of the material used, if such receipt is
not produced by the contractor the royalty charges will
be deducted from the bill of work done by the contractor.
3) During execution rubble from quarry site should be
brouhgt to road side and stacked. The rubble for one
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
stack should be broken first and broken metal should
be got approved from Engineer in charge.
4) The broken metal should be collected as per
requirement by the side of road & properly stacked &
got approved from Engineer in charge before spreading
5) The stacking of metal should be so done that it do
not cause hinderence to existing traffic.not cause hinderence to existing traffic.
6) As directed by Engineer in charge.
37 Supplying hard murum at the road side, Spec.No. Rd. 23 Page No.202 1) The materials shall be got tested from the approved
including conveying and stacking incuding all laboratory before use, at the cost of contractor. He
leads and lift etc. complete. must preserve the forest conservation act. 1980. He is
fully wholely and solely responsible for violance of
forest conservation act. 1980. The rates shown in
schedule ‘ B ‘ will be deemed to have included all
leads lifts, royalty charges octroi duty, state Government
quarries are not available, it will be the responsibility of
the contractor to obtain the material from the private
quarry at his own cost, for which the contractor should
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
obtain the permission competenet authority at his own
cost and no extra lead charges will be giver to the
contractor.
2) The Contractor should submit the receipt of payment
of royalty charges of the material used, if such receipt is
not produced by the contractor the royalty charges will
be deducted from the bill of work done by the contractor.be deducted from the bill of work done by the contractor.
3) The murum should be collected as per requirement by
the side of road & propoerly stacked & got approved from
Engineer in charge before spreading.
4) The stacking of murum should be so done that it do
not cause hinderence to existing traffic.
38 Supplying soft murum at the road side, including Spec.No. Rd. 24 Page No.203 1) The materals shall be got tested from the approved
conveying and stacking inlcuding all leads and lift laboratory before use, at the cost of contractor. He
complete. must preserve the forest conservation act. 1980. He is
fully wholely and solely responsible for violance of
forest conservation act. 1980. The rates shown in
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
schedule ‘ B ‘ will be deemed to have included all
leads lifts, royalty charges octroi duty, state Government
quarries are not available, it will be the responsibility of
the contractor to obtain the material from the private
quarry at his own cost, for which the contractor should
obtain the permission competenet authority at his ownobtain the permission competenet authority at his own
cost and no extra lead charges will be giver to the
contractor.
2) The Contractor should submit the receipt of payment
of royalty charges of the material used, if such receipt is
not produced by the contractor the royalty charges will
be deducted from the bill of work done by the contractor.
3) The murum should be collected as per requirement by
the side of road & propoerly stacked & got approved from
Engineer in charge before spreading.
4) The stacking of murum should be so done that it do
not cause hinderence to existing traffic.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
39 Spreading 60 millimetre metal including Spec.No. Rd. 29 Page No.205 Prior to spreading of material, permission for
sectioning incuding all leads and lift complete. spreading should be obtained from theEngineer
in-charge.
40 Spreading 40 millimetre metal including Spec.No. Rd. 34 Page No.208 Prior to spreading of material, permission for
sectioning and incuding all leads and lift complete. spreading should be obtained from theEngineersectioning and incuding all leads and lift complete. spreading should be obtained from theEngineer
in-charge.
41 Spreading sand / soft murum/ hard murum over Spec.No. Rd.28, Page No.206 to Prior to spreading of material, permission for
rubble soling / Water Bound Macadam surface 31,36,37,39 210 spreading should be obtained from theEngineer
incuding all leads and lift complete. in-charge.
42 Compacting the sub grade / gravel oversize Spec.No. Rd. 32 Page No.206 The unit for mode of measurement will be one square
metal (200millimetre loose) layers 2.00 metre to Relevant Part metre of surface area instead of one kilometre
7.00 metre wide with power roller including of MOST - 2001 length as mentioned in the standard specification
necessary, labour, materials and artificial watering Clause No. 401 book. For compaction only power roller of 10 to 12
complete. Metric Tonne capacity roller of required Specification
shall be used as diected by the Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
43 Compacting the subgrade / gravel/size metal (100 Spec.No. Rd. 35 Page No.209 The unit for mode of measurement will be one square
millimetre loose) 2.00 to 7.00metre width with metre of surface area instead of one kilometre
power roller including necessary,labour, materials length as mentioned in the standard specification
and artificial watering complete. book. For compaction only power roller of 10 to 12
Metric Tonne capacity roller of required Specification
shall be used as diected by the Engineer in charge.shall be used as diected by the Engineer in charge.
44 Compacting the hard murum side widths (up to Spec.No Rd. 40 Page No. 211 The unit for mode of measurement will be one square
200 millimetre) with power roller including artificial metre of surface area instead of one kilometre
watering complete. length as mentioned in the standard specification
book. For compaction only power roller of 10 to 12
Metric Tonne capacity roller of required Specification
shall be used as diected by the Engineer in charge.
45 Providing and laying 75 millimetre thick Spec No. : MOST 2001 Cl. No. 5061) Bitumen of I. S. grade of 60/70 penetration
compacted Bitumen Bound Macadam Page No. 160 shall be used.
with 60/70 grade (VG-30) bitumen over Govt. of Maharashtra P.W.D. Circular2) For controlling traffic, construction and
existing Water Bound Macadam surface No Misc/2001/P.C.-2/PLN . maintenance of deversion, no extra payment
including picking the road metalled surface, Mantralaya Mumbai 24/01/2001 shall be made for this
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
thoroughly cleaning the Water Bound 3)The work shall be caried in day time only and
Macadam surface by using mechanical in dry weather condition.
broom or approved equipment, spreading 40 4) 8.00 to 10.00 tonne power roller for
millimetre size metal (Hand broken by compaction will be only allowed as approved by
bringing blasted rubble on site of work) at Engineer-in-charge.
the rate of 0.09 Cubic Metre per one Square 5) Bitumen shall be heated temp.of177 degrees
Metre compacting metal with roller and to 191 degrees Centigrade.Metre compacting metal with roller and to 191 degrees Centigrade.
bitumen is then spread at the rate of 2 6) All quality control test shall be carried out as
kilogram per square metre.,., spreading 12 per M.O.S.T. Clause No.900 & testing charges
millimetre metal at the rate of 0.018 Cubic should be bomed by contractor.
Metre per one Square Metre The surface 7) The representative of contractor should sign
shall be lightly rolled so that metal pieces get the register showing account of asphalt daily in
embeded in the bitumen layer and rolling token of his acceptance.
shall continue until entire surface is 8) The contractor should submit the receipt of
throughly compacted etc. complete. (With payment of royalty charges of the material used, if such
Static Roller) (including diversion road) receipt is not produced by the contractor the royalty
Spec. No.: As directed by Engineer-in-charge. charges will be deducted from the bill of work done
by the contractor.
9) The spraying of bitumen shall be done by using
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
mechanical sprayers with gun of bitumen attached to the
bouzer
10) Item Shall be executed as per instructions and as
directed by Engineer - in - Charge
11) The 40 mm metal shall be hand broken and it shall
be broken from blasted rubble brought at site.
46 Providing 20 millimetre thick open graded Spec No. MOST 2000 Cl. No. 511 1)The work shall be caried in day time only and
premix bituminous carpet, by using 60/70 Clause No. 509 Page No. 192 in dry weather condition.
grade (VG-30) bitumen including supplying to 195 2) Bitumen of I. S. grade of 60/70 penetration
all material, preparing and cleaning the for premix carpet and tack coat should be used.
base, heating bitumen, applying tack coat at 3) For controlling traffic, construction and
0.3 kilogram per one square metres laying mainterance of deversion, no extra payment
carpet and compacting without seal coat on shall be made for this
Black Topping surface Hot Mix Hot laid with 4) The representative of contractor should sign
paver finisher with all leads and lift complete. the register showing account of asphalt daily in
token of his acceptance.
5) 8.00 to 10.00 tonne roller for compaction will
be only allowed as approved by Engineer-in-charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
6) All quality control test shall be carried out as
per M.O.S.T. Clause No.900 and testing charges
should be borned by contractor.
7) To ensure the desired compaction of the material to
achieve the minimum density of 2250 kg per cubic metre
the contractor should produce the weight receipt
of every load of the premix material of the open gradedof every load of the premix material of the open graded
carpet at the site before laying the material and
accordingly the laying and compaction of the material
should be done.
8) The contractor should sbumit the receipt of
payment of royalty charges of the material used, if such
receipt is not produced by the contractor the royalty
charges will be deducted from the bill of work done
by the contractor.
9) Item Shall be executed as per instructions and as
directed by Engineer - in - Charge
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
47 Providing bituminous liquid seal coat (Type MOST 2001 201 to 204 1)The work shall be caried in day time only and
A) to black top surface, with 80/100 grade Cl.No.513 in dry weather condition.
(VG-10) bitumen including supplying all 2) Bitumen of I. S. grade of 80/100 penetration
materials including all leads, preparing for premix carpet and tack coat should be used.
existing road surface, heating and applying 3) For controlling traffic, construction and
bitumen, spreading chips and rolling complete maintenance of deversion, no extra paymentbitumen, spreading chips and rolling complete maintenance of deversion, no extra payment
(by using bulk asphalt) MOST 1995 Cl. No. shall be made for this
513 Spec.No. : M.O.S.T. 2000 Cl. No. 513 4) The representative of contractor should sign
the register showing account of asphalt daily in
token of his acceptance.
5) 8.00 to 10.00 tonne roller for compaction will
be only allowed as approved by Engineer-in-charge.
6) Bitumen shall be heated temp.of 177 degrees
to 191 degrees Centigrade.
7) All quality control test shall be carried out as
per M.O.S.T. Clause No.900 & testing charges
should be bomed by contractor.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
8) The contractor should submit the receipt of
payment of royalty charges of the material used, if such
receipt is not produced by the contractor the royalty
charges will be deducted from the bill of work done
by the contractor.
9) The spraying of bitumen shall be done by using9) The spraying of bitumen shall be done by using
mechanical sprayers with gun of bitumen attached to
the bouzer.
10) Item Shall be executed as per instructions and as
directed by Engineer - in - Charge
48 Providing dry rubble stone pitching 23centimetre. Spec.No. : Rd.73 Page No. 246 The work shall be executed as directed by Engineer in
(about 9") thick including packing with quarry charge.
spalls and hard murum etc. complete
As directed by Engineer in charge.
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
49 Royalty Charges as per Revenue and Forest ~~ ~~ The payment shall be done by producing orignal recept
Department's notification dated 11/02/2010 as of royalty charges of this work.
Maharashtra Minor Mineral Extraction Rules,
2010 and as per insruction in general notes on
CSR 2011-2012 in P.W. Sanctioned schedule
of rates for District Nashik for the yearof rates for District Nashik for the year
2011-2012 for items of lime stone, lime
shell,stones, rubble, stone dust, shingles,
gravel, murum, kankar and ordinary sand,
ordinary clay, ordinary earth (to be used for
embankment and filling), slate and shell etc. General Additional Specification For All Items :-1 ) For all above items all the materials shall be
got tested from the approved laboratory before
use at the cost of Contractor. He must preserve
the Forest Conservation Act. 1980. He is fully
wholy and solely responsible for violance of
Forest Conservation Act. 1980. The rates shown
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
in Schedule 'B' will be deemed to have including
all leads, lifts, royalty charges octroi duty, sale
tax etc. If the Government quarries are not
available the material from the private quarry his
own cost, for which the contractor should obtain
the premission of the owner and the competenetthe premission of the owner and the competenet
autharity at his own cost and no extra lead charges
will be given to the contractor.
2 ) The percentage of rates quated in the tender
shall be including all taxes, lavies, tolles, octri,
excise, turnover tax, tax as per works contract
act of Government of Maharastra etc.
No Extra payment on this behalf will begiven to
the contractor.
In addition to the above. All above items shall be
exuted according to the
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik
S P E C I F I C A T I O N - F O RSCHEDULE “ C “
Specifications as per Standard
specification book Published by
Sr Description of Items Govemment of Maharashtra Additional specification if any
No Volume I & II 1979 & 1981 Edition
Specification No Page No.
1 ) Standard specification book published by
Government of Maharastra Volume I & II, 1979 & 1981
Edition.
2 ) M.O.S.T. Edition 2000, IS. 456 - 2000 and all other
standard specifications and relevent I.S. codes and B I
S codes wherever applicable and as directed byS codes wherever applicable and as directed by
Engineer in Charge.
Sub Divisional Engineer Executive Engineer
P. W. Sub Division, No.1 Trimbakeshwar P. W. Division, ( North ) Nashik
Sign. of contractor No. of corrections Executive Engineer .
P. W. Division, ( North ) Nashik