S. Morgan Creek to China Grove 8” Basic scope of work: Total Line Length is approx. 12.98 Mi. (68512ft) 20% of Route will include Rock Ditch, Rock Shield, and Padding. 40% of Route will Require Double ditching by landowners. String pipe directly off Truck. Excavation for new pipeline (Clearing ROW, proper disposal of brush and debri) Welding, jeeping, recoating pipe after welding Install Launch and Receiver Traps Install Valves, Checks, at begin point and ending point. Backfill with approved soil and apply Rock shield if necessary. Final tie in Contractor will be responsible for Transfer of pipe from the supplier to the job location (as well as string pipe along the ROW) Contractor will be responsible for installing 3 Above Ground Block Valves (Plains Pipeline will provide Valves and piping to install these valves) Contractor will be responsible for all machinery needed to install all piping, valving, and other

description

Pipeline Scope of Work

Transcript of S. Morgan to China Grove Scope

Page 1: S. Morgan to China Grove Scope

S. Morgan Creek to China Grove 8”

Basic scope of work:

Total Line Length is approx. 12.98 Mi. (68512ft)

20% of Route will include Rock Ditch, Rock Shield, and Padding.

40% of Route will Require Double ditching by landowners.

String pipe directly off Truck.

Excavation for new pipeline (Clearing ROW, proper disposal of brush and debri)

Welding, jeeping, recoating pipe after welding

Install Launch and Receiver Traps

Install Valves, Checks, at begin point and ending point.

Backfill with approved soil and apply Rock shield if necessary.

Final tie in

Contractor will be responsible for Transfer of pipe from the supplier to the job location (as well as string pipe along the ROW)

Contractor will be responsible for installing 3 Above Ground Block Valves (Plains Pipeline will provide Valves and piping to install these valves)

Contractor will be responsible for all machinery needed to install all piping, valving, and other lifting deemed necessary to complete the installation from start to finish.

Additional information for S. Morgan to China Grove 8” line.

Project consists of 1-68,512ft segment, beginning with Launch scraper trap leaving S. Morgan Creek Junction and a Receive scraper trap ending at China

Grove Station.

This line is for Crude oil. 68,512ft of .250 wall, FBE Coated pipe.

Page 2: S. Morgan to China Grove Scope

Contractor will need to facilitate any machinery to cross foreign lines. Plains Pipeline will provide 8” scraper traps. Plains Pipeline will provide all materials and requirements for tie in of

scraper traps, (launch and receive) Hydro-testing will be required prior to the completion of this project. Contractor will make the final tie-ins to the stations, beginning and ending. Terrain is Light/Medium rolling hills with some rock excavation. Plains Pipeline will provide All Valve Materials, Rock Shield, and Pipe

Coating. There will be two Navigable Water ways to cross. (Morgan Creek &

Colorado River) Morgan Creek Crossing will be an open ditch Colorado River Crossing will be Slick Bore FM 1229, FM 1808, and HWY 208 will also be slick bore