Runoff Hydrographs - Texas A&M...
Transcript of Runoff Hydrographs - Texas A&M...
Runoff Hydrographs
The Unit Hydrograph Approach
Announcements
HW#6 assigned
Storm Water Hydrographs
Graphically represent runoff rates vs. time
Peak runoff rates
Volume of runoff
Measured hydrographs are best
But not often available
Methods are available to develop a “synthetic”
hydrograph
Use a unit hydrograph (UHG)
Unit Hydrograph
Widely used method of empirical storm flow analysis
Def: Basin outflow resulting from 1 unit (in./mm/cm/etc) of direct runoff generated uniformly over the drainage area at a uniform rainfall rate during a specified period of rainfall intensity.
Unit Hydrographs
Assumptions: rainfall intensity is not considered linear relationship between stormwater runoff and
rainfall UHG is independent of antecedent conditions uniform rainfall distribution
Unit Hydrographs
Derived from observed records extensive data requirements
streamflow and rainfall record pairs
generally not used for small catchments
UHG represent direct surface runoff
baseflow (ground water) must be removed
For small catchments ==> synthetic UHG models
models give ==> tp (time to peak), qp(peak
flow rate and mathematical shape of curve
Duration of the Unit Hydrograph
Unit hydrograph have a duration that is the
same as the duration of the rainfall excess that
produced it
Conceptually it is possible to have an infinite # of
hydrographs corresponding to different durations.
Practically, unit hydrographs are limited to
rainfall excesses up to 25% different than the
duration of the unit hydrograph.
How is the unit hydrograph used? For a unit hydrograph of
duration, D, the volume underneath the hydrograph is always 1, produced by 1 unit of excess rainfall.
A hydrograph for a block of rainfall excess of any depth is obtained by multiplying the ordinates of the unit hydrograph by the depth of the rainfall excess block.
The result are the ordinates of the runoff hydrograph.
Unit Hydrograph Development
Approximate hydrograph using a triangle
Need to find: Time to peak (tp)
Time lag (tl)
Time of the base (tb)
Peak flow (qp)
Lag time, tL
5.0
7.08.0
LY1900
)1S(Lt
SCS Equation to calculate
time lagL = hydraulic length of
watershed (feet)
S = curve number parameter
(inches)
Y = average land slope of
the watershed (%)
tl = time lag (hours)
Eq. 1
Unit Hydrograph Development
Equation to calculate time to peak tp = tl + D/2, ( Eq. 2), where:
tl = time lag
D = time increment of rainfall excess
SCS Equation to calculate peak flow (qp) qp = 484A / tp , (Eq. 3), where:
A = watershed area in mi2
tp = time to peak in hours
qp = peak flow in cfs per inch of runoff***
SCS Equation for time of base (tb) tb = 2.67tp (Eq. 4)
Example 5.10 in Text
Given:
1-hr storm = 2.5 in. P = 2.5 in.
500 ac watershed = 21,780,000 ft2
Land use = commercial – business
Watershed soil HSG = D
Average watershed slope = 1%
Hydraulic length of watershed = 6,000 ft
Required:
Find the storm hydrograph Use the triangular unit hydrograph method
Example 5.10 in Text
Solution: HSG = D / Commercial T. 5.1 CN = 95
S = 0.53 in. S = (1000 / CN) - 10
Assume AMC = II Q = 1.96 in. of runoff Using the SCS CN method Q = (P - 0.2S)2 / (P + 0.8S)
Step #1 Find points to develop the unit hydrograph
tl = 0.75 hr (45 min) Use Eq. 1
tp = 1.25 hr (75 min) Use Eq. 2
tb = 3.33 hr (200 min) Use Eq. 4
qp = 302 cfs / 1 in. of runoff Use Eq. 3
Plot unit hydrograph
Check area under the triangle 1 in.
T(min)
Q (cfs)
Surface runoff depth = 1,815,000 ft3 / 21,780,000 ft2 =
0.0833 ft = 1.0 in. ok
600
100
300
150 tb = 200
tp = 75
50
200
400
qp = 302.5 cfs
Volume under triangle = 1/2bh
= ½(200 min x 60 sec/min)302.5 ft3/sec = 1,815,000 ft3
Watershed area (A) = 21,780,000 ft2
Example 5.10 in Text
Step #2
qp 2.5” rain = 302.5 cfs x 1.96 in. of SRO
- SRO = 1.96 in. from the SCS CN Method
qp 2.5” rain = 592.9 cfs
Plot storm hydrograph
Check area under the triangle 1.96 in.
T(min)
Q (cfs)
Surface runoff depth = 1.96 in. ok600
100
300
150 tb = 200tp = 7550
200
400
qp = 592.9 cfs
Volume under triangle = 3,557,400 ft3
3,557,400 ft3 / 21,780,000 ft2 = 0.163 ft = 1.96 in.
Example 5.11 in Text
Given: Same as Example 5.10 but this time more detailed rainfall
information 1-hr storm = 2.5 in.
0 – 15 min = 0.5 in. 15 – 30 min = 1.0 in. 30 – 45 min = 0.75 in. 45 – 60 min = 0.25 in.
500 ac watershed Land use = commercial – business Watershed soil HSG = D Average watershed slope = 1% Hydraulic length of watershed = 6,000 ft
Required: Find the storm hydrograph
Example 5.11 in Text
Solution: HSG = D / Commercial T. 5.1 CN = 95
S = 0.53 in. (same as Ex. 5.10, S = (1000 / CN) - 10)
Assume AMC = II Q = 1.96 in. of runoff (same as Ex. 5.10, Q = (P - 0.2S)2 / (P + 0.8S)
Find points to develop the unit hydrograph tL = 0.75 hr (45 min)
(same as Ex. 5.10, tL = [L0.8(S + 1)0.7] / [1900 x Y0.5]
New since D = 15 min. tp = tL + D/2 = 0.88 hr (52.5 min)
New since tp = 52.5 min qp = 484(A)/tp = 432 cfs / 1 in. of runoff
Example 5.11 in Text
0 – 15 min P = 0.5 in. (given)
Q1 = [0.5 – 0.2(.53))]2 / [0.5 + 0.8(.53)]
Q1 = 0.17 in. of runoff
qp1 = 432 cfs / 1” of SRO x 0.17” = 73.44 cfs
tp1 = tL + D/2 = 45 + 15/2 = 52.5 min
tb1 = 2.67(tp) = 2.67(52.5) = 140.2 min
Example 5.11 in Text
0 – 30 min P = 0.5 + 1.0 = 1.5 in.
Q1 + Q2 = [1.5 – 0.2(.53))]2 / [1.5 + 0.8(.53)]
Q1 + Q2 = 1.01 in. of runoff
Q2 = 1.01 in. - Q1
Q2 = 1.01 – 0.17 = 0.84 in. of runoff
qp2 = 432 cfs / 1” of SRO x 0.84” = 362.88 cfs
tp2 = 52.5 + 15 = 67.5 min Shift on the x-axis by 15 min
tb2 = 140.2 + 15 = 155.2 min Shift on the x-axis by 15 min
Example 5.11 in Text
0 – 45 min P = 0.5 + 1.0 + 0.75 = 2.25 in.
Q1 + Q2 + Q3 = [2.25 – 0.2(.53))]2 / [2.25 + 0.8(.53)]
Q1 + Q2 + Q3 = 1.72 in. of runoff
Q3 = 1.72 in. - Q1 - Q2
Q3 = 1.72 – 0.17 – 0.84 = 0.71 in. of runoff
qp3 = 432 cfs / 1” of SRO x 0.71” = 306.7 cfs
tp3 = 52.5 + 15 + 15 = 82.5 min
Shift on the x-axis by 30 min
tb3 = 140.2 + 15 + 15 = 170.2 min
Shift on the x-axis by 30 min
Example 5.11 in Text
0 – 60 min P = 0.5 + 1.0 + 0.75 + 0.25 = 2.50 in. Q1 + Q2 + Q3 + Q4 = [2.5 – 0.2(.53))]2 / [2.5 +
0.8(.53)]
Q1 + Q2 + Q3 + Q4 = 1.96 in. of runoff
Q4 = 1.96 in. - Q1 - Q2 - Q3
Q4 = 1.96 – 0.17 – 0.84 - 0.71 = 0.24 in. of runoff
qp4 = 432 cfs / 1” of SRO x 0.24” = 103.6 cfs
tp4 = 52.5 + 15 + 15 + 15 = 97.5 min Shift on the x-axis by 45 min
tb4 = 140.2 + 15 + 15 + 15 = 185.2 min Shift on the x-axis by 45 min
Y = -mx + b
Y = mx + b
Incremental Hydrograph #1
0
100
200
300
400
0 50 100 150 200
Time (min)
Q (
cfs
)
(140.2, 0.0)
(52.5, 73.4)
Y = mX + b m = (73.4 – 0) / (52.5 – 140.2) m = - 0.837
Y = -0.837X + b b = Y + 0.837X = 73.4 + 0.837(52.5) b = 117.343
Y = - 0.837X + 117.343