Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a...

34
Chris Wilson – September 2008 Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources

Transcript of Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a...

Page 1: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Running Subsea Trees from a Jack-up MODU

Chris Wilson – Coogee Resources

Page 2: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Montara Development – Drilling Program

• Drill, Complete & Clean-up 2 new Subsea Development wells (Water Depth 82m)

• Re-enter 2 existing subsea wells, run a tree, complete and clean-up each well (Water Depth 77 to 82m)

• Drill and complete 3 platform wells (Water Depth 80m)

• Jack-up MODU with 400’ legs required

Page 3: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Subsea Trees

Tree• Vetco 13 5/8” 5000psi• Separate flow base• 4.3m(l) x 3.9m(w) x 2.6m(h)Flowbase• 3.9m(l) x 3.8m(w) x 5.1m (h)

– with guideposts installed

Page 4: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Two New Subsea Wells

• Wells needed to be close enough not to move the rig

• Not too close to inhibit ROV Access

• Performed 3D modelling with TMT to determine spacing

• 5m Centre to Centre• 1m Difference in

Elevation

Page 5: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Existing Subsea Wells

• Needed to have positioning tolerance capabilities

• Positioning on a “postage stamp” is time consuming & difficult with a jack- up

Page 6: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Montara Development Drilling Project Requirements

• 400’ Leg Jack-up New Generation Jack-up• Ability to drill two subsea wells at 5m centres Modified

conductor deck• Run subsea trees (preferably not picking-up off the

back of a boat) Make room under the cantilever• Be able to support the weight of the high pressure

riser and BOP’s outside of the existing conductor tensioner location Modified conductor deck

• Have positioning tolerance capability Modified conductor deck

Page 7: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

MODU – Seadrill’s West Atlas•

K-Fels Mod V Class B

Leg Length –

157m (517’) capable of drilling in 114m of water

Derrick Capacity –

1500 kips

BOP Pressure Rating – 15kpsi

Proven Rig design (Ensco 104, 106, 107, 108, Wilcraft & Atwood Beacon)

Page 8: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Rig Modifications to Handle Subsea Trees

Relocation of the Cement Unit to allow Subsea Trees & Flow Bases to be skidded aft

Page 9: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree Skidding System

Train Track Style•

Easy to Install

No welding required•

Tree Trolleys to have capability to test trees

Page 10: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Conductor Deck Modification Requirements

• Space to drill 2 subsea wells at 5m centre• Ability to hold weight of the high pressure riser,

BOP’s plus a safety factor (~200MT)• Provide positioning tolerance• Handle environmental loads• Able to run trees through (if required)

Page 11: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Concepts

Page 12: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Final Design

Page 13: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Installation of Conductor Deck Extension

Page 14: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Final Product – Conductor Deck Extension

Page 15: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Final Product - Spreader Beam Assembly

Page 16: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor

Page 17: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 18: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft

Page 19: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 20: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig

floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line

Page 21: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 22: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig

floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line

• Skid in cantilever – make-up tree running tool to tree

Page 23: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 24: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig

floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line

• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft

Page 25: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 26: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence

• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig

floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line

• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension

Page 27: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 28: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree / Flowbase Running Sequence• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig

floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line

• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension• Lower the box beam assembly into the conductor deck

extension• Land tree and nipple-up Surface wellhead & BOP’s

Page 29: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 30: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Page 31: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Conductor Deck Extension – Lessons

• Deck was time consuming to recover and store between wells

• Support slings time consuming to move when skidding cantilever

• Box beam assembly was cumbersome• Despite the lessons – the extension deck

satisfied a wide variety of expectations

Page 32: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Tree Skidding System - Lessons

End of the track interfered with cantilever beam

Tree Was not on centreline (handling Issues)

Tolerance was tight

Page 33: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Subsea Trees on Jack-ups - Conclusions

• Early access to rig during construction allowed for subsea tree running to be part of the rig design

• Conductor Deck Extension ~ 8 Months from concept to delivery & cost ~$750,000

• Drilling Contractors should recognize the ability of these new build jack-ups to run subsea trees especially with the increased water depth capability

Page 34: Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a Jack-up MODU Chris Wilson – Coogee Resources. Chris Wilson ... riser and BOP’s outside

Chris Wilson – September 2008

Subsea Trees from Jack-ups

ANY QUESTIONS