Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a...
Transcript of Running Subsea Trees from a Jack-up MODU Chris Wilson ...€¦ · Running Subsea Trees from a...
Chris Wilson – September 2008
Running Subsea Trees from a Jack-up MODU
Chris Wilson – Coogee Resources
Chris Wilson – September 2008
Montara Development – Drilling Program
• Drill, Complete & Clean-up 2 new Subsea Development wells (Water Depth 82m)
• Re-enter 2 existing subsea wells, run a tree, complete and clean-up each well (Water Depth 77 to 82m)
• Drill and complete 3 platform wells (Water Depth 80m)
• Jack-up MODU with 400’ legs required
Chris Wilson – September 2008
Subsea Trees
Tree• Vetco 13 5/8” 5000psi• Separate flow base• 4.3m(l) x 3.9m(w) x 2.6m(h)Flowbase• 3.9m(l) x 3.8m(w) x 5.1m (h)
– with guideposts installed
Chris Wilson – September 2008
Two New Subsea Wells
• Wells needed to be close enough not to move the rig
• Not too close to inhibit ROV Access
• Performed 3D modelling with TMT to determine spacing
• 5m Centre to Centre• 1m Difference in
Elevation
Chris Wilson – September 2008
Existing Subsea Wells
• Needed to have positioning tolerance capabilities
• Positioning on a “postage stamp” is time consuming & difficult with a jack- up
Chris Wilson – September 2008
Montara Development Drilling Project Requirements
• 400’ Leg Jack-up New Generation Jack-up• Ability to drill two subsea wells at 5m centres Modified
conductor deck• Run subsea trees (preferably not picking-up off the
back of a boat) Make room under the cantilever• Be able to support the weight of the high pressure
riser and BOP’s outside of the existing conductor tensioner location Modified conductor deck
• Have positioning tolerance capability Modified conductor deck
Chris Wilson – September 2008
MODU – Seadrill’s West Atlas•
K-Fels Mod V Class B
•
Leg Length –
157m (517’) capable of drilling in 114m of water
•
Derrick Capacity –
1500 kips
•
BOP Pressure Rating – 15kpsi
•
Proven Rig design (Ensco 104, 106, 107, 108, Wilcraft & Atwood Beacon)
Chris Wilson – September 2008
Rig Modifications to Handle Subsea Trees
•
Relocation of the Cement Unit to allow Subsea Trees & Flow Bases to be skidded aft
Chris Wilson – September 2008
Tree Skidding System
•
Train Track Style•
Easy to Install
•
No welding required•
Tree Trolleys to have capability to test trees
Chris Wilson – September 2008
Conductor Deck Modification Requirements
• Space to drill 2 subsea wells at 5m centre• Ability to hold weight of the high pressure riser,
BOP’s plus a safety factor (~200MT)• Provide positioning tolerance• Handle environmental loads• Able to run trees through (if required)
Chris Wilson – September 2008
Concepts
Chris Wilson – September 2008
Final Design
Chris Wilson – September 2008
Installation of Conductor Deck Extension
Chris Wilson – September 2008
Final Product – Conductor Deck Extension
Chris Wilson – September 2008
Final Product - Spreader Beam Assembly
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence
• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension
Chris Wilson – September 2008
Chris Wilson – September 2008
Tree / Flowbase Running Sequence• Recover box beam assembly to under rig floor• Place tree onto skid trolley and skid it aft• Skid in cantilever – when gap between cantilever & rig
floor is over the tree – use a crane to lift tree off the skid trolley and onto beams on the rig centre line
• Skid in cantilever – make-up tree running tool to tree• Lift tree off main deck and skid aft• Run tree through the conductor deck extension• Lower the box beam assembly into the conductor deck
extension• Land tree and nipple-up Surface wellhead & BOP’s
Chris Wilson – September 2008
Chris Wilson – September 2008
Chris Wilson – September 2008
Conductor Deck Extension – Lessons
• Deck was time consuming to recover and store between wells
• Support slings time consuming to move when skidding cantilever
• Box beam assembly was cumbersome• Despite the lessons – the extension deck
satisfied a wide variety of expectations
Chris Wilson – September 2008
Tree Skidding System - Lessons
•
End of the track interfered with cantilever beam
•
Tree Was not on centreline (handling Issues)
•
Tolerance was tight
Chris Wilson – September 2008
Subsea Trees on Jack-ups - Conclusions
• Early access to rig during construction allowed for subsea tree running to be part of the rig design
• Conductor Deck Extension ~ 8 Months from concept to delivery & cost ~$750,000
• Drilling Contractors should recognize the ability of these new build jack-ups to run subsea trees especially with the increased water depth capability
Chris Wilson – September 2008
Subsea Trees from Jack-ups
ANY QUESTIONS