CSA Program Guide on Premise Solutions (July 2013)(English)_1
Rt. 29 Solutions Project Delivery Advisory...
Transcript of Rt. 29 Solutions Project Delivery Advisory...
![Page 1: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/1.jpg)
Rt. 29 Solutions Project Delivery Advisory Panel
October 1, 2015
![Page 2: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/2.jpg)
Route 29 Solutions
2
Agenda item 1: Introductions
Project Delivery Advisory Panel
Technical Team
![Page 3: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/3.jpg)
Route 29 Solutions
3
Agenda item 2: Interaction and Feedback
Live Streaming Sep 17, 2015 Sep 25, 2014
• Unique Viewers: 36 31
• Streams: 280 123
• Average Minutes per stream: 8 31
![Page 4: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/4.jpg)
Route 29 Solutions
Agenda item 2: Interaction and Feedback
• 9 emailed comments to route29solutions.org inbox, Sep 15 - Sep 29 • 4 new Provide Input postings and responses on route29solutions.org,
Sep 15 - Sep 29 • No calls to Design-Build project hotline, Sep 15 - Sep 29 (844-220-5540)
Emailed Comments:
• 1 asked for additional information about Rio East closure • 1 asked whether VDOT sent representatives to talk to businesses • 1 said poor planning on “29 Norther” does not consider schools • 1 indicated that signal timing is too sensitive at Polo Grounds, Gander Drive,
and District Avenue (a 2nd comment also mentioned the Gander signal) • 1 asked why the projects are not included on 511VA • 3 expressed concerns about the u-turn at Rt 29 SB and Rio • 1 suggested a roundabout at Berkmar and Hilton Heights
4
![Page 5: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/5.jpg)
Route 29 Solutions
Agenda item 2: Interaction and Feedback (continued)
• 1 thought Rt. 29 was closed with a Hillsdale detour, but surprised that Rt. 29 was open at 5:15. Also indicated Proffit Road bridge is damaged, and asked questions about speed limits on Carrsbrook and Markwood.
• 1 repeat comment says the Rio GSI project is not necessary. • 1 believes there should be 3 through lanes at the Rio underpass. • 1 asked that deactivated signals be covered.
5
![Page 6: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/6.jpg)
Route 29 Solutions
6
Agenda item 3: Report on PDAP Feedback from September 17 PDAP meeting
Update regarding Business Assistance Subcommittee
• Chip Boyles
Berkmar - number of lanes
• Expect to have resolution no later than Nov 12 PDAP meeting
Placement of Rio GSI time lapse camera
• Was not installed last week. Will be installed before the Oct 15 PDAP meeting.
Construction presentation, piling, retaining walls, abutments
• To be covered today in agenda item 8
![Page 7: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/7.jpg)
Route 29 Solutions
7
Agenda item 4: Panel Feedback and Suggestions for Future Agenda Items
Open Discussion
![Page 8: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/8.jpg)
Route 29 Solutions
Agenda item 5: Design-Build Plan Submission Schedule
8
Route 29 Solutions Design ReviewsScheduled submission dates (s)Actual submission dates ✓
2015
Mar April May June July Aug Sept Oct Nov Dec
Rio Road Intersection Mar 630% ✓
Apr 1730% (s)
May 2760% ✓
Jun 2460% (s)
Jul 17100% ✓
Aug 7Final (s)
Route 29 Widening Mar 3130% ✓
Apr 830% (s)
Jun 1160% ✓
Sep 60%(s)Sep 11 100% ✓
Dec 2Final (s)
Berkmar Extended Aug 760% ✓
Sep 3 60% (s)
Dec 31Final (s)
Rio Enhanced Landscaping Oct 1 - DraftOct 29 - Final
Rio Pedestrian Lighting Local Lanes
Oct 29 - revisedDraft
Nov 12Final
![Page 9: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/9.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates
Rt. 250 / 29 Interchange Work this week • Continue grading operations in Rte. 29 median
• Continue curb installation along Rte. 29 median
• Begin sidewalk replacement at Rte. 29 and Angus Road intersection
• Complete construction of the retaining wall at Best Buy
• Continue SWMB excavation
• Complete installation of conduit along Rte. 29 for lighting and signals
• Continue construction of retaining wall along Rte. 250
• Continue sanitary sewer relocation along Rte. 250
• Begin installation of storm drain structures along the Barracks Road ramp9
![Page 10: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/10.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 250 / 29 Interchange (continued)
Significant lane closures this week
• Route 29 inside lane closures to construct curb and gutter
• Route 29 SB lane shoulder closures to construct sidewalk
• Ramp closure and detour in place at night
10
![Page 11: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/11.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 250 / 29 Interchange (continued)
Work next two weeks • Begin backfill of the retaining wall at Best Buy
• Complete sidewalk replacement at Rte. 29 and Angus Road intersection
• Continue construction of MSE wall along Rte. 250
• Complete SWM basin excavation
• Complete sanitary sewer relocation along Rte. 250
• Complete curb installation along Rte. 29 median
• Complete installation of storm drain structures along Barracks Road ramp11
![Page 12: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/12.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 250 / 29 Interchange (continued)
Anticipated significant upcoming lane closures
• Route 29 inside lane closures to construct curb and gutter
• Route 29 SB lane shoulder closures to construct sidewalk
• Ramp closure and detour in place at night
12
![Page 13: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/13.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Woodbrook - Berkmar Signal
Work this week
• Cut and install loop detectors
• Pull wire for signals
• Install cabinet and UPS
Significant lane closures this week
• None
13
![Page 14: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/14.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Woodbrook - Berkmar Signal (continued)
Work next two weeks
• Assemble signal heads
• Install mast arms
• Activate signals
• Perform changeover of signals
Anticipated significant upcoming lane closures
• Periodic traffic stops to install mast arms 14
![Page 15: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/15.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection
Work this week
• Storm drain and BMP installation
• Continue 18” water main relocations
• Valve installations with service shutdown (coordinated by ACSA)
• Continue 24” water main relocations
• Valve installations with service shutdown (coordinated by ACSA)
• Sawcutting operations along Route 29 at Rio intersection
15
![Page 16: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/16.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection (continued)
Work this week (continued)
• Begin gas main relocation in NE quadrant
• Complete existing signal equipment removal
• Set attenuator and barrier wall at SunTrust
• Demo existing retaining wall at SunTrust
• Begin RW3 wall at SunTrust
16
![Page 17: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/17.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection (continued)
Significant lane closures this week (nighttime)
• Rio crossover restricting thru movements and left turn movements
• Rte. 29 double or triple lane closures northbound and southbound
• Rio East westbound closure
17
![Page 18: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/18.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection (continued)
Work next two weeks
• Waterline trench asphalt patching
• Begin milling and pre-excavation for bridge cap
• Demo existing retaining wall at SunTrust
• Continue RW3 wall at SunTrust
• Storm drain and BMP installation
• Continue 18” water main relocations
• Valve installations with service shutdown (coordinated by ACSA)18
![Page 19: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/19.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection (continued)
Work next two weeks (continued)
• Continue 24” water main relocations
• Valve installations with service shutdown (coordinated by ACSA)
• Gas main relocation in NE quadrant
• Milling and pre-excavation for bridge cap
• Begin construction of retaining wall in NE quadrant
• Begin pile installation in Rte 29/Rio Road intersection
19
![Page 20: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/20.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rio Grade-Separated Intersection (continued)
Anticipated significant upcoming lane closures (nighttime)
• Rio crossover restricting thru movements and left turn movements
• Rte. 29 double or triple lane closures northbound and southbound
• Rio East westbound closure
20
![Page 21: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/21.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 29 Widening
Work this week
• Complete median clearing
• Continue installation of erosion and sediment controls
• Continue SBL left widening
Significant lane closures this week (nighttime)
• Route 29 inside lane closure NB and SB
• Periodic traffic stops to safely remove trees
21
![Page 22: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/22.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 29 Widening (continued)
Work next two weeks
• Continue installation of erosion and sediment controls
• Complete SBL left widening
• Perform traffic shift in SBL (minor shift, similar to NBL)
• Install SBL barrier wall
• Place fill in median
22
![Page 23: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/23.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Rt. 29 Widening (continued)
Anticipated significant upcoming lane closures (nighttime)
• Route 29 inside lane closure NB and SB
• Periodic traffic stops to safely remove trees
23
![Page 24: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/24.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Berkmar Extended
Work this week
• Archaeological exploration
• Clear alignment south of River
• Erosion control installation
• ROW offers
Significant lane closures this week (nighttime)
• None
24
![Page 25: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/25.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Berkmar Extended (continued)
Work next two weeks • Archaeological exploration
• Erosion control installation
• ROW offers
Anticipated significant upcoming lane closures (nighttime)
• None
25
![Page 26: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/26.jpg)
Route 29 Solutions
Agenda item 6: Rt. 29 Solutions Project Updates (continued)
Hillsdale Extended
Work this week • Response to comments on Plans will be submitted to VDOT for review • Response to comments on signal analysis addendum 9/10 will be
submitted for VDOT review • Response to comments on Floodplain Development Permit and SWM
MOA will be submitted for County review • Environmental Reevaluation being finalized for VDOT review
Upcoming work • Meet with VDOT to discuss signal analysis and plan comments • Revise ROW limits re: VDOT comments; deliver plans Oct 2015 • 4+ ROW proposals/appraisals in September and October
26
![Page 27: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/27.jpg)
Route 29 Solutions
Agenda item 7: Hillsdale - Greenbrier Traffic Signal
From the VDOT Supplement to the MUTCD:
• An engineering study of traffic conditions, pedestrian characteristics, and physical characteristics of the location shall be performed to determine whether installation of a traffic control signal is justified at a particular location.
• In order for a traffic signal to be justified, evidence of the need for right of way assignment beyond that which could be provided by a stop sign shall be demonstrated. Examples of such a need include: excessive delay, congestion, unfavorable approach conditions, or surrounding conditions that cause driver confusion.
27
![Page 28: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/28.jpg)
Route 29 Solutions
Agenda item 7: Hillsdale - Greenbrier Traffic Signal (continued)
The recently revised traffic signal analysis does not justify the installation of a traffic signal at this time.
VDOT agrees to install signal infrastructure as part of the Hillsdale project. Signal infrastructure includes underground components such as conduit, junction boxes, and pole foundations that would be required for a signal in the future.
The city and VDOT are meeting next week to discuss the signal analysis. If new information indicates that a signal is justified, the signal poles, mast arms and signal heads can be added to the Hillsdale contract. Or, a signal can be added in the future when sufficient warrants are met.
28
![Page 29: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/29.jpg)
Route 29 Solutions
29
Agenda item 8: Constructing retaining walls and abutments
General Steps of Construction Sequence 1. Auger Hole 2. Set Steel Casing 3. Set Pile 4. Drive Pile (abutment only) 5. Pour Concrete 6. Construct Abutment (bridge substructure) 7. Install Tie-backs (retaining wall only) 8. Begin Excavation (summer 2016) 9. Install Lagging 10. Set Bridge Beams 11. Pour Fascia Wall 12. Strip Forms 13. Stain Wall
![Page 30: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/30.jpg)
Terminology
30
H-Pile Nelson Studs
![Page 31: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/31.jpg)
Terminology
31
Lagging Tie-Back
![Page 32: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/32.jpg)
Equipment
32
Drill Rig/Auger
Diesel Hammer
![Page 33: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/33.jpg)
Pile Layout
33
Pile Orientation (View from top)
![Page 34: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/34.jpg)
Pile Layout Showing Trench
34
Pile Orientation (View from side)
![Page 35: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/35.jpg)
Augering - Pile Installation - Plating
35
Auger Hole Install Pile Install Plate
![Page 36: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/36.jpg)
Abutment Construction
36
Construction Of Abutment Prior To Summer 2016
![Page 37: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/37.jpg)
Tie-Back Installation
37
Tie-Backs Installed Before Excavation Is Performed
![Page 38: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/38.jpg)
Lagging Installation
38
Lagging Installed As Excavation Is Performed
![Page 39: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/39.jpg)
Fascia Wall Installation
39
Concrete Wall Installed Utilizing Nelson Studs
![Page 40: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/40.jpg)
Form Liners
40
Utilization of form liners for wall aesthetic treatment
![Page 41: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/41.jpg)
Route 29 Solutions
Agenda item 9: TODS Program and Plan Layout
https://www.google.com/maps/d/edit?mid=zklL9WNXAgek.kozclJ4v-uW0
41
![Page 42: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/42.jpg)
10/1/201542
US 29 Rio Road Project TODS Plan
Phase 1 continues to May 23, 2016.
Phase 2 is the 103 days where the crossovers will be closed.
Final Phase is the period after September 2, 2016.
Customers will not be charged application or annual fees until October 1, 2017. Invoices will be sent out in August of 2017.
Applications must be submitted no later than October 7, 2015 for each business wishing to participate in the construction program.
Following are examples of the overall signing plan under the TODS Program. Not all qualifying businesses are included in the following examples.
![Page 43: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/43.jpg)
US 29 Rio Road Project TODS Plan
10/1/201543
Area 1
Area 2
Area 3
Area 4
Stars are businesses within the construction zone
Circles are businesses outside the construction zone
Red represents the businesses that have not yet applied
Green represents businesses that have applied
Blue represents businesses that are currently participating in the TODS Program
Purple signs are existing signs
Yellow squares are proposed new signs
Area 5
![Page 44: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/44.jpg)
US 29 Rio Road Project TODS PlanSign #7 US 29 SB Left at Rio Rd - will become Follow Detour in Phase 2
10/1/201544
Phase 2
Final
Phase 1
Kirt’s Ice Cream and Little Caesars have applied. Carving Board, and Taste of China have not applied.
Area 1
The Food symbol may be added to the individual Food business’ panel.
This sign will be located prior to Woodbrook Dr
![Page 45: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/45.jpg)
US 29 Rio Road Project TODS PlanSign #26 Hillsdale Dr EB Left at Rio Rd – Detour for Phase 2
10/1/201545
Phase 2
FinalNo Sign
Phase 1No Sign
TODS Trailblazer for Albemarle Square businesses only installed during the 103 Days of Phase 2.
Detour signs will be installed as part of the project on US 29 at Branchlands BLVD, and at Branchlands Blvd and Hillsdale Dr. This sign will be installed at Hillsdale at Rio Rd to direct motorist back towards the Albemarle Square businesses.
Area 5
![Page 46: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/46.jpg)
US 29 Rio Road Project TODS PlanSign #12 US 29 SB Left at Fashion Square Dr
10/1/201546
Phase 2
Final
Phase 1
Jimmy John’s is currently participating. Red Lobster has applied. Fashion Square and Red Robin have not applied.
Area 2
The Food symbol may be added to the individual Food business’ panel.
This sign will be located prior to Woodbrook Dr
![Page 47: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/47.jpg)
US 29 Rio Road Project TODS PlanSign #13 US 29 NB Straight Ahead
10/1/201547
Phase 2
Final
Phase 1
Albemarle Square has applied. Chopstick Express, Vocelli Pizza, and Kohr Brothers have not applied.
Area 4
The Food symbol may be added to the individual Food business’ panel.
This sign will be located prior to Branchlands Blvd
![Page 48: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/48.jpg)
US 29 Rio Road Project TODS PlanSign #16 US 29 NB Right at Fashion Square Dr
10/1/201548
Phase 2
Final
Phase 1
Fashion Square, Red Robin, and Red Lobster have not applied.
Area 4
The Food symbol may be added to the individual Food business’ panel.
This sign will be located just past Branchlands Blvd
![Page 49: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/49.jpg)
US 29 Rio Road Project TODS PlanSign #17 US 29 NB Left at Berkmar Dr – Will become a Straight Ahead
10/1/201549
Phase 2
All have applied.
Final
Phase 1
Area 4
The Food symbol may be added to the individual Food business’ panel.
This sign will be located just past Branchlands Blvd
![Page 50: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/50.jpg)
US 29 Rio Road Project TODS PlanSign #20 Berkmar Dr NB Right at Rio Rd
10/1/201550
Phase 2
FinalNo Sign
Phase 1
TODS Trailblazer for Hardee’s, Wendy’s, and Hess.
Area 2
![Page 51: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/51.jpg)
US 29 Rio Road Project TODS PlanSign #21 Rio Rd EB Right onto US 29
10/1/201551
Phase 2
TODS trailblazer for Hardee’s, Wendy’s, and Hess.
FinalNo Sign
Phase 1
Area 2
![Page 52: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/52.jpg)
9/28/201552
• All locations will be confirmed in the field before October 8.
• The mileages may change depending on the final location of the signs.
• The locations may change depending on the final number of businesses that apply.
US 29 Rio Road Project TODS Plan
![Page 53: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/53.jpg)
Route 29 Solutions
Agenda item 10: Placemaking: Albemarle County Update
Lee Catlin
53
![Page 54: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/54.jpg)
Route 29 Solutions
Agenda item 11: October 15 visit to NWRO: Directions
VDOT Staunton District Office 811 Commerce Road Staunton, VA 24401 (540) 332-9075
• I-64 west to I-81 North • North on I-81 to exit 225. • Left at the off-ramp onto Route 262-South. • At the first stop light (about a mile up the road) turn left on to Route 11. • Stay on Route 11 about 1/4 mile to the fork in the road. • Take the left leg on the fork – Commerce Road. • The VDOT Staunton District office is about a mile on the left. On the right side of the
road will be a blue sign directly across from the entrance. • Park in the visitor’s lot in front of the building. • Go up the stairs to the main entrance – the receptionist can assist you upon your arrival.
Safety Message: The entrance drive to the district office has an un-gated railroad crossing. Trains pass through multiple times a day. Please ensure you check the railroad crossing before proceeding into district parking lot.
54
![Page 55: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/55.jpg)
Route 29 Solutions
Agenda item 12: New Business and Wrap Up
55
![Page 56: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/56.jpg)
Route 29 Solutions
Agenda item 13: Adjourn
56
![Page 57: Rt. 29 Solutions Project Delivery Advisory Panelroute29solutions.org/documents/pdap_presentation_oct._1.pdf · Oct 29 - revised Draft Nov 12 Final. Route 29 Solutions Agenda item](https://reader036.fdocuments.us/reader036/viewer/2022071018/5fd227fdc33c054dd050aa26/html5/thumbnails/57.jpg)
Rt. 29 Solutions Project Delivery Advisory Panel
October 1, 2015