Rt 29 Solutions Hydraulic Planning Advisory Panel
May 25, 2017
![Page 2: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/2.jpg)
Rt 29 Solutions
2
Agenda Item 1: Introductions Hydraulic Planning Advisory Panel members Technical Team members
![Page 3: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/3.jpg)
Rt 29 Solutions
3
Agenda item 2: Public Interaction and Feedback Live Streaming May 11, 2017 Apr 27, 2017
• Live Stream Viewers: 14 16
![Page 4: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/4.jpg)
Rt 29 Solutions
4
Agenda item 2: Public Interaction and Feedback (continued) For the period May 9 - May 23, 2017 Inbox and Phone • Caller states that he/she owns property along Emmet Street in the vicinity
of the Route 29/Hydraulic intersection. Requested information about the project and would like to be added to the distribution list for future information about the project.
• Writer states that whatever solution is derived for Hydraulic it must be centered around moving people from one side of the intersection to the other. It is logical that this solution will be focused primarily on vehicular traffic, but alternatives should also be evaluated based on pedestrian and bicycle modes. The writer suggests the use of a rubric that could help to evaluate alternatives for several different criteria including multi-modal transportation. Writer provided an example rubric for consideration.
![Page 5: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/5.jpg)
Rt 29 Solutions
5
Agenda item 2: Public Interaction and Feedback (continued) For the period May 9 - May 23, 2017 Website input • None
![Page 6: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/6.jpg)
Rt 29 Solutions
6
Agenda item 3: Response to Panel Feedback Finalization of Vision Statement and Goals
• Agenda Item 4 Neighborhood Outreach Plan Update
• Agenda Item 6
![Page 7: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/7.jpg)
Rt 29 Solutions
7
Agenda item 4: Phase 1 Completed and Upcoming Tasks To be complete by:
PROJECT KICK-OFF MEETING MAR 9 ✓
INITIAL SITE RECONNASAINCE MAR 23✓
SITE RECONNAISSANCE MAR 31✓
DATA COLLECTION, RESEARCH AND MAP REVIEW APR 7 ✓
PROJECT BASE MAP DEVELOPMENT APR 7 ✓
REVIEW OF RELEVANT STUDIES APR 7 ✓
SITE INVENTORY AND ANALYSIS SUMMARY APR 7 ✓
BEGIN LAND USE PLAN DEVELOPMENT APR 7 ✓
CLIENT CHARETTE APR 11✓
![Page 8: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/8.jpg)
Rt 29 Solutions
8
Agenda item 4: Phase 1 Completed and Upcoming Tasks (continued) To be complete by:
PUBLIC MEETING # 1 APR 26 ✓
ALTERNATIVE LAND USE SCENARIOS MAY 15 ✓
INTERNAL TRANSPORTATION INPUTS MAY 15 ✓
EXTERNAL TRANSPORTATION INPUTS MAY 15 ✓
CONCEPT SCREENING JUN 23
EXTERNAL TRANSPORTATION INPUTS JUL 14
CORE AREA PLAN AUG 21
PUBLIC MEETING # 2 AUG 23
DRAFT SMALL AREA PLAN SEP 15
![Page 9: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/9.jpg)
Rt 29 Solutions
9
Agenda item 4: Phase 1 Completed and Upcoming Tasks (continued)
To be complete by:
FINAL SMALL AREA PLAN SEP 29
PROJECT ABSTRACT SEP 29
COUNTY PLANNING COMMISSION SEP (date tbd)
CITY PLANNING COMMISSION SEP (date tbd)
![Page 10: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/10.jpg)
Rt 29 Solutions
10
Agenda item 4: Phase 1 Study Progress and Work Underway Work completed since May 11 meeting
• Additional Land Use Concept Alternatives
• Final Vision Statement and goals
Work currently underway
• Additional Land Use Concept Alternatives
• Transportation inputs
![Page 11: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/11.jpg)
Rt 29 Solutions
11
As we plan let’s…
Choose a desired Outcome ……then develop Path
Develop Framework first ……then Land Use
Plan for Flexibility and Change… embrace the unknown
Find our “Ocean” ……create great places
Create Demand first ……then build
![Page 12: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/12.jpg)
Rt 29 Solutions
12
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
• Key Land Use Plan Elements
• Plan elements common to each concept:
– Reduced block size for better connectivity, walkability, and scale – Integrated multi-modal systems along public streets and greenways – Increase residential uses in core area – Expanded mixed-use residential sub-area and corridors – Develop updated street typology and improve quality of public realm
– Introduction of traffic calming where appropriate, including roundabouts
![Page 13: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/13.jpg)
Rt 29 Solutions
13
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
• Key Land Use Plan Elements
• Plan elements common to each concept (continued):
– Alternatives for grade separated options – Contemplates long-term redevelopment of large single-user parcels – Enhanced connectivity between core area and legacy residential
neighborhoods – Integration of green infrastructure within core area, significant public
gathering spaces – Explore transit opportunities including a potential transit hub
![Page 14: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/14.jpg)
Rt 29 Solutions
14
Agenda item 4: Phase 1 Study Progress and Work Underway External Transportation Inputs - Initial Thoughts: • Removing heaviest turning movements at 29 / Hydraulic for biggest
impact on intersection operations • Consider impact to parallel street network as result of limiting
movements at 29/Hydraulic • How will changes to parallel network impact decisions about land use,
especially residential uses? • Consider roundabouts to calm traffic and improve intersections on
secondary network
![Page 15: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/15.jpg)
Rt 29 Solutions
15
Agenda item 4: Phase 1 Study Progress and Work Underway (continued) Conceptual Framework Plans: Route 29 at Hydraulic Focus Area Framework Plans focus on block structure, circulation and key organizing principles (such as
public space). Land Use is a secondary supportive element.
• Framework Concept 1: Route 29 / Hydraulic Activity Center – Route 29 Over
• Framework Concept 2: Route 29 / Hydraulic Activity Center – Route 29 Under
• Framework Concept 3: Mid-Block Activity Center (29/Hydraulic at grade)
![Page 16: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/16.jpg)
Rt 29 Solutions
16
Agenda item 4: Phase 1 Study Progress and Work Underway (continued) Framework Plan Concept 1 – Hydraulic Activity Center: Route 29 Over
![Page 17: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/17.jpg)
Rt 29 Solutions
17
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Lower Level Plaza Concept
![Page 18: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/18.jpg)
Rt 29 Solutions
18
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Section: Lower Level Plaza at Hydraulic / 29
![Page 19: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/19.jpg)
Rt 29 Solutions
19
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Framework Plan Concept 2 – Hydraulic Activity Center: Route 29 Under
![Page 20: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/20.jpg)
Rt 29 Solutions
20
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
![Page 21: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/21.jpg)
Rt 29 Solutions
21
Agenda item 4: Phase 1 Study Progress and Work Underway (continued) Conceptual Framework Plans: Study Area Framework Plans focus on block structure and key organizing principles (such as public
space). Land Use is a secondary supportive element.
• Framework Concept 1: Route 29 / Hydraulic Activity Center – Route 29 Over
• Framework Concept 2: Route 29 / Hydraulic Activity Center – Route 29 Under
• Framework Concept 3: Mid-Block Activity Center
![Page 22: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/22.jpg)
Rt 29 Solutions
22
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Existing
Framework
![Page 23: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/23.jpg)
Rt 29 Solutions
23
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Overall Framework Plan #1
Plan #1
![Page 24: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/24.jpg)
Rt 29 Solutions
24
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Conceptual Land Use Plan #1
Plan #1
![Page 25: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/25.jpg)
Rt 29 Solutions
25
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Mixed-Use
Walkable
Sense of Place
![Page 26: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/26.jpg)
Rt 29 Solutions
26
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Overall Framework Plan #2
![Page 27: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/27.jpg)
Rt 29 Solutions
27
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Conceptual Land Use Plan #2
Plan #1
![Page 28: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/28.jpg)
Rt 29 Solutions
28
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Overall Framework Plan #3
![Page 29: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/29.jpg)
Rt 29 Solutions
29
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
“Park” Crossing
![Page 30: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/30.jpg)
Rt 29 Solutions
30
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
“Park” Crossings
![Page 31: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/31.jpg)
Rt 29 Solutions
31
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Conceptual Land Use Plan #3
Plan #1
![Page 32: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/32.jpg)
Rt 29 Solutions
32
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Stormwater
ra
![Page 33: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/33.jpg)
Rt 29 Solutions
33
Agenda item 4: Vision Statement: How are we doing?
![Page 34: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/34.jpg)
Rt 29 Solutions
34
Agenda item 4: Phase 1 Study Progress and Work Underway (continued)
Marietta, GA
ra
![Page 35: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/35.jpg)
Rt 29 Solutions
35
Agenda item 5: Pedestrian and Bicycle Recommendations
![Page 36: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/36.jpg)
Rt 29 Solutions
36
Agenda item 6: Neighborhood Outreach Plan Update Hold small, informal neighborhood meetings with interested neighborhoods
Meetings will be focused on listening to members of the community to shape desires into overall Hydraulic land-use and transportation plans
Keen focus on transportation and connectivity, including multi-modal transportation, potential "mini-charette" style
Update since last meeting: • Meeting held with stakeholder groups
• Three meetings scheduled so far
• Greenbrier - Location - Greenbrier Elementary, May 30th at 6:00 pm
• Senior Center - Location - Senior Center, June 6 at noon
• International Rescue Committee - Location - Church of Incarnation, Date and Time TBD
![Page 37: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/37.jpg)
Rt 29 Solutions
37
Agenda item 6: Neighborhood Outreach Plan (continued)
Charlottesville PC Informational Presentation FEB 14 ✓
HPAP 1 MAR 9 ✓
HPAP 2 MAR 23✓
HPAP 3 - First Charette APR 11 ✓
Meadows Neighborhood Meeting APR 12 ✓
Public Information Meeting APR 26 ✓
HPAP 4 APR 27 ✓
HPAP 5 MAY 11 ✓
Housing/Neighborhood/Business Leader Meeting MAY 15 ✓
Hold neighborhood meetings MAY 22 - June 22
![Page 38: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/38.jpg)
Rt 29 Solutions
38
Agenda item 6: Neighborhood Outreach Plan (continued)
HPAP 6 MAY 25 ✓
Greenbrier Neighborhood Meeting MAY 30
Senior Center Neighborhood Meeting JUN 6
HPAP 7 JUN 8
HPAP 8 JUN 22
Second Charette JUN 23
HPAP 9 AUG 10
Public Information Meeting # 2 AUG 23
Joint Planning Commission Work Session AUG 24 AM
HPAP 10 AUG 24 PM
![Page 39: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/39.jpg)
Rt 29 Solutions
39
Agenda item 6: Neighborhood Outreach Plan (continued)
Joint Planning Commission Draft Review SEP 12
HPAP 11 SEP 14
Draft Small Area Plan SEP 15
HPAP 12 SEP 28
![Page 40: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/40.jpg)
Rt 29 Solutions
40
Agenda item 7: Review of Upcoming Phase 1 Tasks To be complete by:
CONCEPT SCREENING JUN 23
EXTERNAL TRANSPORTATION INPUTS JUL 14
![Page 41: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/41.jpg)
Rt 29 Solutions
41
Agenda item 8: Open Discussion and Future Agenda Items
![Page 42: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/42.jpg)
Rt 29 Solutions
42
Agenda Item 9: New business and wrap up Agenda item 10: Adjourn
![Page 43: Rt 29 Solutions Hydraulic Planning Advisory Panel_… · information about the project. • Writer states that whatever solution is derived for Hydraulic it must be centered around](https://reader034.fdocuments.us/reader034/viewer/2022042200/5ea05d2496d16b365c64cf72/html5/thumbnails/43.jpg)
Rt 29 Solutions Hydraulic Planning Advisory Panel
May 25, 2017