RRB Plenary Meeting , CERN 22 October 2007

15
RRB Plenary Meeting, CERN 22 October 2007 LHC Status Report Lyn Evans

description

Lyn Evans. LHC Status Report. RRB Plenary Meeting , CERN 22 October 2007. Q1.R8. Q3-Q2.8L interconnect after in situ repair. Descent of the last magnet, 26 April 2007. 30’000 km underground at 2 km/h!. Magnet interconnections. Cooldown of Sector 7-8. - PowerPoint PPT Presentation

Transcript of RRB Plenary Meeting , CERN 22 October 2007

Page 1: RRB Plenary Meeting , CERN 22 October 2007

RRB Plenary Meeting, CERN 22 October 2007

LHC Status Report Lyn Evans

Page 2: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 2

Q1.R8

Page 3: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 3

Q3-Q2.8L interconnect after in situ repair

Page 4: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 4

Descent of the last magnet, 26 April 2007

30’000 km underground at 2 km/h!

Page 5: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 5

Magnet interconnections

Page 6: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 6

Cooldown of Sector 7-8

From RT to 80K precooling with LN2. 1200 tons of LN2 (64 trucks of 20 tons). Three weeks for the first sector.

From 80K to 4.5K. Cooldown with refrigerator. Three weeks for the first sector. 4700 tons of material to be cooled.

From 4.5K to 1.9K. Cold compressors at 15 mbar. Four days for the first sector.

Page 7: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 7

Sector 7-8 cooldown

Page 8: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 8

Courtesy F.Bordry

Page 9: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 9

Tracking between the three main circuits of sector 78

Courtesy F.Bordry

2ppm

Page 10: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 10

Cooldown until Saturday 14-7-7 - Cooldown speed

Avg. Cold Mass Temperature

140

160

180

200

220

240

260

280

300

7/5/076:00

7/6/076:00

7/7/076:00

7/8/076:00

7/9/076:00

7/10/076:00

7/11/076:00

7/12/076:00

7/13/076:00

7/14/076:00

7/15/076:00

7/16/076:00

7/17/076:00

7/18/076:00

7/19/076:00

Date

T c

m [

K]

planned [K] measured [K] data S7-8 [K]

Page 11: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 11

Sector 4-5 cooldown

Page 12: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 12

RF cavities

Page 13: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 13

Two 300 kW klystrons with circulators and loads

Page 14: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 14

Updated General Schedule – 08.10.07

Pressure test Cool-down Powering tests

Sector 12 wk. 49 (2007) wk. 07 (2008) wk. 12 (2008) wk. 13 (2008) wk. 25 (2008)

Sector 23 wk. 44 (2007) wk. 05 (2007) wk. 10 (2008) wk. 11 (2008) wk. 22 (2008)

Sector 34 Done wk. 11(2008) wk. 16 (2008) wk. 17 (2008) wk. 25 (2008)

Sector 45 DoneStarted wk. 46 (2007) wk. 47 (2007) wk. 03 (2008)

wk. 16 (2008) wk. 19 (2008) wk. 20 (2008) wk. 26 (2008)

Sector 56 Done wk. 46 (2007) wk. 07 (2008) wk. 08 (2008) wk. 19 (2008)

Sector 67 Done wk. 48 (2007) wk. 08 (2008) wk. 09 (2008) wk. 17 (2008)

Sector 78Done Done Done Done Done

Done wk. 48 (2007) wk. 04 (2007) wk. 05 (2007) wk. 16 (2008)

Sector 81 Done wk. 50 (2007) wk. 06 (2008) wk. 07 (2008) wk. 19 (2008)

Page 15: RRB Plenary Meeting , CERN 22 October 2007

L. Evans – EDMS Document 874936 15

Updated General Schedule – 08.10.07

.

.

2007

2008

2007

2008

12 23 34 45 56 67 78 81

Machine Checkout

Beam Commissioning to 7 TeV

Consolidation

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

1011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

5051520102030405

0706

08091011121314151617

1918

2021222324252627

2928

3031323334353637

3938

4041424344454647

4948

505152

Interconnection of the continuous cryostat

Leak tests of the last sub-sectors

Inner Triplets repairs & interconnections

Global pressure test &Consolidation

Flushing

Cool-down

Warm up

Powering Tests

Global pressure test &Consolidation

Cool-down

Powering Tests

General schedule Baseline rev. 4.0