Route 47 Missouri River Bridge
description
Transcript of Route 47 Missouri River Bridge
![Page 1: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/1.jpg)
Route 47 Missouri River Bridge
Bridgescape, LLC
![Page 2: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/2.jpg)
Bridge Typical Section
![Page 3: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/3.jpg)
• Distinctive appearance so that bridge remains a symbol
• Stay within budget: “German Simple”
• Recognize views to bridge from downtown/riverfront
• Maintain views to downtown from the bridge
• Keep design subtle; historic feel with minimal detailing
• Light pedestrian/ bicycle trail but not entire roadway;
• Lighting should enhance structure, not draw attention to itself.
Committee Design Goals (4/18/2013)
![Page 4: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/4.jpg)
Previous Committee Selections:
• Variable Depth Girders ** ** MoDOT Funded
• Pier Shape – Gothic Pier **• One (1) Overlook Located at Pier 7 **• Railing – 27” Concrete Wall with Vertical Railing Element
• Girder Lighting – Girder Wash Fade
• Pier Lighting
• Overhead Pier Element – Curved Truss w/ Sun Shade
• Low Level Trail Lighting
![Page 5: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/5.jpg)
Previous Committee Prioritization:
Enhancement Priority
Decorative Railing 1
Girder Lighting 2
Pier Lighting 3
Overhead Element 4
Trail Lighting 5
![Page 6: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/6.jpg)
View from Washington Riverfront Park
![Page 7: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/7.jpg)
View from Washington Riverfront Park
![Page 8: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/8.jpg)
Aerial View of Overlook
![Page 9: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/9.jpg)
Aerial View of Overlook
![Page 10: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/10.jpg)
View from Pedestrian/ Bicycle Trail
![Page 11: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/11.jpg)
View from Pedestrian/ Bicycle Trail
![Page 12: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/12.jpg)
View from Northbound Traffic Lane
![Page 13: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/13.jpg)
View From Northbound Traffic Lane
![Page 14: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/14.jpg)
View from South Approach of Existing Bridge
![Page 15: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/15.jpg)
View from South Approach of Existing Bridge
![Page 16: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/16.jpg)
View from South Approach of Existing Bridge (w/ East Face Girder Lighting )
![Page 17: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/17.jpg)
View from Trail Below Bridge
![Page 18: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/18.jpg)
View from Trail Below Bridge
![Page 19: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/19.jpg)
Preferred Enhancement Package Decorative Rail + Girder Lighting + Pier Lighting + Overhead Element + Trail Lighting
Prioritization Enhancement Estimated Cost (4) Estimated Cost (4A)
1 Decorative Railing (Addition to MoDOT Credit) $120,000 $120,000
2 Girder Lighting – Fade (west face only) $587,000
Girder Lighting – Fade(east and west face) $1,133,000
3 Pier Lighting $172,000 $172,0004 Overhead Element (w/ lighting) $225,000 $225,0005 Trail Lighting (full length) $137,000 $137,000
SUBTOTAL $1,241,000 $1,787,0003% Inflation for 3 years (9.27%) $115,000 $166,000
TOTAL $1,355,000 $1,953,000
![Page 20: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/20.jpg)
Preferred Enhancement Package $1,355,000Decorative Rail + Girder Lighting + Pier Lighting + Overhead Element + Trail Lighting (west face only)
![Page 21: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/21.jpg)
Preferred Enhancement Package $1,355,000Decorative Rail + Girder Lighting + Pier Lighting (west face only)+ Overhead Element + Trail Lighting
![Page 22: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/22.jpg)
Preferred Enhancement Package $1,953,000Decorative Rail + Girder Lighting + Pier Lighting + Overhead Element + Trail Lighting (east & west face)
![Page 23: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/23.jpg)
Project Schedule
• Final Enhancement Commitment August 16, 2013
• Public Hearing (Right-of-Way) October 2013
• Final Enhancement Funds Secured August 2014
• Open Construction Bids September 2016
• New Bridge Open to TrafficFall 2018
• Project Complete Summer 2019
![Page 24: Route 47 Missouri River Bridge](https://reader036.fdocuments.us/reader036/viewer/2022062323/56816207550346895dd22f93/html5/thumbnails/24.jpg)
Thank You for your Participation