Route 2020 Metro Dubai Construction Details

121
Metro Route 2020 Dubai Construction $2.9bn Included Route, Programme Graphic Tunnelling, Stations & Viaduct Details Lengths Viaduct 10.5 km Tunnel 4 km Stations Underground 2 Nr. Elevated 5 Nr. Capacity 46,000 passengers per hour. Maximum wait time will be 100 seconds and there will be 15 trains Tunnels & Underground Stations Viaduct 3D image to show Sequence, Method & Plant. David H Moloney 21 st July 2016 David H Moloney Project Execution Plan. Details how the Metro will be constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly

Transcript of Route 2020 Metro Dubai Construction Details

Page 1: Route 2020 Metro Dubai   Construction Details

Metro Route 2020 Dubai – Construction $2.9bn

IncludedRoute, Programme GraphicTunnelling, Stations & ViaductDetailsLengths

Viaduct 10.5 kmTunnel 4 km

StationsUnderground 2 Nr.Elevated 5 Nr.

Capacity 46,000 passengers per hour.Maximum wait time will be 100 seconds and there will be 15 trains

Tunnels & Underground Stations

Viaduct

3D image to show Sequence, Method & Plant.

David H Moloney

21st July 2016

ⓒ David H Moloney

Project Execution Plan. Details how the Metro will be

constructed, and how the progress, safety and quality will be

monitored and controlled. Also the measures to ensure that

the site is environmentally friendly

Page 2: Route 2020 Metro Dubai   Construction Details

ContentsWork Categories as per CESMM

Page 3: Route 2020 Metro Dubai   Construction Details

Introduction

Page 4: Route 2020 Metro Dubai   Construction Details

Metro Route 2020

Red Line Green Line

Route

ⓒ David H Moloney

Page 5: Route 2020 Metro Dubai   Construction Details

Route Animation

GreenCommunity

DubaiInvestmentPark

Jebel Ali Port

Palm Jebel Ali u/c

Ibn Battuta Mall

Harbour &Tower Station

Tunnel

ⓒ David H Moloney

Page 6: Route 2020 Metro Dubai   Construction Details

Programme Time ChainageThe chart has two axis: one for time and the other for location

A legend explains meaning of the colours, symbols and line types

Page 7: Route 2020 Metro Dubai   Construction Details

Programme Visualisation

Tunnel

Viaduct

Viaduct

ⓒ David H Moloney

Schematic longitudinal Profile

Page 8: Route 2020 Metro Dubai   Construction Details

Principal Quantities

Schematic Longitudinal Section ⓒ David H Moloney

Page 9: Route 2020 Metro Dubai   Construction Details

Cost Comparisons of various Metro Projects

Dubai Route 2020UAE (To Start)

Red Line North DohaQatar (In Progress)

Red Line South DohaQatar( In Progress)

Metro NorthDublin

(Proposed)

Dart UndergroundDublin (Proposed)

Overall Cost €2,450 million €1,803 million €1,500 million €2,400 million

Cost per km €158 million /k m €140 million / km €108 million / km €134 million / km

Overall Length 15.5 km 13 km 14m 18 km 5 km

Tunnel 4 kmSingle Tunnel

11.6 km Twin Tunnels

14 kmTwin Tunnels

7.5 km Twin Tunnels

5 km Twin Tunnel

Cut & Cover 0 2.7 km 0

Elevated 10.5 km 2.2 km 0

Road Level 0 5.5 0

Stations 7 Nr. 7 Nr. 5 Nr. 14 Nr. 3 Nr.

Capacity 13,000 Passengers per hour

19,800 Passengers per hour

?

ⓒ David H Moloney

Page 10: Route 2020 Metro Dubai   Construction Details

Advantages of Light Rail Systems Benefits of Metro to commuters

1. Time saving for commuters 4. Reduction in accident

2. Reliable and safe journey 5. Reduced fuel consumption

3. Reduction in atmospheric pollution 6. Reduced traffic congestion

Page 11: Route 2020 Metro Dubai   Construction Details

Contractor’s General Items

Page 12: Route 2020 Metro Dubai   Construction Details

Contractor’s Temporary Site Facilities

ⓒ David H Moloney

Page 13: Route 2020 Metro Dubai   Construction Details

Quarry & Aggregate Production

ⓒ David H Moloney

Brief Description

Rock is blasted free from the quarry

face and fragmented so it will fit into

the primary crusher. Any oversized

rock is broken with a excavator and

hydraulic Rockbreaker.

At the Crushing and screening yard

the fragmented rock is crushed and

screened into various size ranges.

Page 14: Route 2020 Metro Dubai   Construction Details

Concrete Batching Plant David H Moloney

Concrete batching plant comprises -concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Page 15: Route 2020 Metro Dubai   Construction Details

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Page 16: Route 2020 Metro Dubai   Construction Details

Site Hoarding examples

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 17: Route 2020 Metro Dubai   Construction Details

Weighbridge & Sheeting Access

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 18: Route 2020 Metro Dubai   Construction Details

Wheel Wash Drive-through

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 19: Route 2020 Metro Dubai   Construction Details

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or drainage of

groundwater and or surface / rain water usually by

pumping to keep the works dry.

Page 20: Route 2020 Metro Dubai   Construction Details

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 21: Route 2020 Metro Dubai   Construction Details

Dewatering by Wellpoints

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 22: Route 2020 Metro Dubai   Construction Details

Dust Suppression

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 23: Route 2020 Metro Dubai   Construction Details

Traffic Management

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Traffic management plans are necessary when working on or beside roads

Page 24: Route 2020 Metro Dubai   Construction Details

Traffic Management – Work on Median

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 25: Route 2020 Metro Dubai   Construction Details

Temporary Electricity Supply & Tower Lights

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 26: Route 2020 Metro Dubai   Construction Details

Welfare Facilities

ⓒ David H Moloney

Ge

ne

ral It

em

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Page 27: Route 2020 Metro Dubai   Construction Details

HSE

Page 28: Route 2020 Metro Dubai   Construction Details

Existing Underground Utilities

ⓒ David H Moloney

Ea

rth

wo

rks

Brief Description

Before digging

establish the location

and route of

underground utilities.

Locator to find Utilities

Spray Paint to mark pavement

Page 29: Route 2020 Metro Dubai   Construction Details

Existing Underground Utilities & Overhead Cables - Safety Measures

ⓒ David H Moloney

Ea

rth

wo

rks

Page 30: Route 2020 Metro Dubai   Construction Details

Trench - Safety Measures H

ealth,

Safe

ty &

Envir

onm

ent

Page 31: Route 2020 Metro Dubai   Construction Details

Trench - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Envir

onm

ent

Page 32: Route 2020 Metro Dubai   Construction Details

Safety Precautions

Page 33: Route 2020 Metro Dubai   Construction Details

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Page 34: Route 2020 Metro Dubai   Construction Details

Segregation of Waste H

ealth,

Safe

ty &

Envir

onm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Page 35: Route 2020 Metro Dubai   Construction Details

Water Pollution PreventionG

en

era

l It

em

s

Page 36: Route 2020 Metro Dubai   Construction Details

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Page 37: Route 2020 Metro Dubai   Construction Details

Emergency Phone Numbers & Response

Page 38: Route 2020 Metro Dubai   Construction Details

Geotechnical

Page 39: Route 2020 Metro Dubai   Construction Details

Diaphragm Wall Construction - Sequence, Plant & Methods

Diaphragm Wall Grab

ⓒ David H Moloney

Brief Description

Shown is the Sequence,

methods and plant to construct a

diaphragm slurry underground

wall.

Page 40: Route 2020 Metro Dubai   Construction Details

Diaphragm Wall Construction - Sequence, Plant & Methods

ⓒ David H Moloney

Page 41: Route 2020 Metro Dubai   Construction Details

Earthworks

Page 42: Route 2020 Metro Dubai   Construction Details

Tunnels & Underground Stations

3D image to show Sequence, Method & Plant.

David H Moloney

ⓒ David H Moloney

Page 43: Route 2020 Metro Dubai   Construction Details

Underground Station Excavation

Page 44: Route 2020 Metro Dubai   Construction Details

Underground Station Construction

Page 45: Route 2020 Metro Dubai   Construction Details

Rock - Excavability

The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.

ⓒ David H Moloney

Page 46: Route 2020 Metro Dubai   Construction Details

Concrete

Page 47: Route 2020 Metro Dubai   Construction Details

Concrete Full Scale Trial Castings of Pier

ⓒ David H Moloney

Brief Description

The full-scale trial casting(s) shall

demonstrate/document that all

requirements to the concrete and the

execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Co

ncre

te

BIM 3D Model Shutter Fibreglass

Page 48: Route 2020 Metro Dubai   Construction Details

Concrete Full Scale Trial Castings of Bridge Deck

Brief Description

The full-scale trial casting(s) shall

demonstrate/document that all

requirements to the concrete and the

execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Co

ncre

te

Fresh Concrete Properties Tests

Air Content, Consistence, Density, Initial and Final Setting Time, Temperature

and Bleeding

Chloride Ion Content

Hardening and Hardened Concrete Properties Tests:

Density and Compressive Strength for 1, 3, 7, 14 and 28 Days

Concrete Core Compressive Strength

Tensile Splitting Strength

Modulus of Elasticity

Heat Development

Chloride Migration Coefficient (28 Days)

Reinforcement Cover Measurement Survey

Page 49: Route 2020 Metro Dubai   Construction Details

Trial for Waterproofing to Bridge Deck

ⓒ David H Moloney

Brief Description

. The trial for the deck waterproofing

shall demonstrate/document that all

requirements to the waterproofing and

the execution of the work are fulfilled

simultaneously using the actual

methods and performed by personnel as

for the future production.

Co

ncre

te

Page 50: Route 2020 Metro Dubai   Construction Details

Trial for Waterproofing to Bridge Deck - TestsC

on

cre

te

Page 51: Route 2020 Metro Dubai   Construction Details

Vibrating Concrete

ⓒ David H Moloney

Co

ncre

te

Page 52: Route 2020 Metro Dubai   Construction Details

Tunnel Wall Segments Casting

Clean Mould

Lift Precast Segment out of mould

after 18 hours.

Reinforcement

fabricate

Reinforcement

into Mould

Concreting

Segment Storage

Cycle Time 24 hrs

ⓒ David H Moloney

Page 53: Route 2020 Metro Dubai   Construction Details

Tunnel Precast Segments

Page 54: Route 2020 Metro Dubai   Construction Details

Precast Yard for Tunnel Segments

Page 55: Route 2020 Metro Dubai   Construction Details

Viaduct Construction David H Moloney

ⓒ David H Moloney

Page 56: Route 2020 Metro Dubai   Construction Details

Viaduct Construction David H Moloney

ⓒ David H Moloney

Page 57: Route 2020 Metro Dubai   Construction Details

Viaduct Construction David H Moloney

ⓒ David H Moloney

Page 58: Route 2020 Metro Dubai   Construction Details

Viaduct Segments Casting David H Moloney

Casting Method

The concrete segments are manufactured

using the short-line, match-casting method.

Match-casting is when sequential segments are poured against the previous cast segment, this ensures that the segments will fit perfectly on site.

ⓒ David H Moloney

Page 59: Route 2020 Metro Dubai   Construction Details

Viaduct Segments – Short-line, Match Casting Method David H Moloney

Page 60: Route 2020 Metro Dubai   Construction Details

Precast Yard for Viaduct Segments

Page 61: Route 2020 Metro Dubai   Construction Details

Viaduct Segments Launching

ⓒ David H Moloney

Page 62: Route 2020 Metro Dubai   Construction Details

Bridge Construction Sequence David H Moloney

Page 63: Route 2020 Metro Dubai   Construction Details

Bridge Construction Sequence David H Moloney

Piling Surcharge Abutments

Remove Surcharge AbutmentsDeck centre

Post-tensioning Fascia & Waterproof deckComplete Bridge

PiersOverview

Deck Ends

Images with Schematic 3D view, Photos & Timeline

ⓒ David H Moloney

Page 64: Route 2020 Metro Dubai   Construction Details

Post-tensioning Bridge Deck David H Moloney

Page 65: Route 2020 Metro Dubai   Construction Details

Falsework & Shuttering for Insitu Ramp David H Moloney

Page 66: Route 2020 Metro Dubai   Construction Details

Large Floor Concrete Pour

Page 67: Route 2020 Metro Dubai   Construction Details

Reinforced Wall Construction SequenceDavid H Moloney

ⓒ David H Moloney

Page 68: Route 2020 Metro Dubai   Construction Details

Reinforced Structure Construction Sequence David H Moloney

ⓒ David H Moloney

Page 69: Route 2020 Metro Dubai   Construction Details

Going Underground

ⓒ David H Moloney

Page 70: Route 2020 Metro Dubai   Construction Details

Cut & Cover Tunnel Construction

Sequence -Traffic and utilities are diverted, excavate trench, construct & backfill to bury.

To prevent the faces of the excavation from collapsing, different measures are used –

batter the faces, diaphragm walls, secant piles or a combination of soil nailing and

shotcreting.

Page 71: Route 2020 Metro Dubai   Construction Details

Ramp Construction

Sequence -Traffic and utilities are diverted, excavate, construct and backfill to sides.

To prevent the faces of the excavation from collapsing, different measures are used – batter

faces, diaphragm walls, secant piles or a combination of soil nailing and shotcreting.

ⓒ David H Moloney

Page 72: Route 2020 Metro Dubai   Construction Details

Structural Steel

Page 73: Route 2020 Metro Dubai   Construction Details

Elevated Stations

Page 74: Route 2020 Metro Dubai   Construction Details

Elevated Stations

Page 75: Route 2020 Metro Dubai   Construction Details

Elevated Stations

ⓒ David H Moloney

Page 76: Route 2020 Metro Dubai   Construction Details

Elevated Stations

ⓒ David H Moloney

Page 77: Route 2020 Metro Dubai   Construction Details

Inside Stations

ⓒ David H Moloney

Page 78: Route 2020 Metro Dubai   Construction Details

Passenger Bridge

Page 79: Route 2020 Metro Dubai   Construction Details

Roof Covering

Page 80: Route 2020 Metro Dubai   Construction Details

Roof Covering

Page 81: Route 2020 Metro Dubai   Construction Details

Roof Covering

Page 82: Route 2020 Metro Dubai   Construction Details

View of Metro from Burg Khalifa

ⓒ David H Moloney

Page 83: Route 2020 Metro Dubai   Construction Details

Piling

Page 84: Route 2020 Metro Dubai   Construction Details

Piling Construction - Plant & Methods

Brief Description

Piling Plant, Equipment and Material;

Crawler Crane, Piling Hammer, Temporary Casing,

Piling Rig, Concrete Pump, Concrete Mixer Trucks,

Tremie Pipe and Reinforcement Cage

Pili

ng

Page 85: Route 2020 Metro Dubai   Construction Details

Piling Construction - Plant, Methods & SequenceP

ilin

g

Page 86: Route 2020 Metro Dubai   Construction Details

Piling Construction - Plant & MethodsP

ilin

g

Page 87: Route 2020 Metro Dubai   Construction Details

Piling Construction - Vertical PilesP

ilin

g

Page 88: Route 2020 Metro Dubai   Construction Details

Pile Load Test

ⓒ David H Moloney

Pili

ng

Brief Description

A jack is used to load the pile in steps and

gauges measure any settlement.

Page 89: Route 2020 Metro Dubai   Construction Details

Secant Pile Construction - Sequence, Plant & Methods

3D image to show Sequence, Method & Plant.

For construction details see my YouTube Channel

ⓒ David H Moloney

Brief Description

Shown is the Sequence,

methods and plant to construct a

secant pile underground wall.

Page 90: Route 2020 Metro Dubai   Construction Details

Secant Pile Construction - Sequence, Plant & Methods

Page 91: Route 2020 Metro Dubai   Construction Details

Sheet Pile Shaft Temporary to Support Excavation

Drive Sheet Piles Excavate & install bracing

Construct Concrete Structure Backfill, remove bracing & sheet piles

ⓒ David H Moloney

Page 92: Route 2020 Metro Dubai   Construction Details

Sheet Pile Shaft Temporary to Support Excavation

ⓒ David H Moloney

Page 93: Route 2020 Metro Dubai   Construction Details

Roads & Paving

Page 94: Route 2020 Metro Dubai   Construction Details

Asphalt Batching YardR

oa

ds &

Pa

vin

gs

Page 95: Route 2020 Metro Dubai   Construction Details

Road Construction Sequence Animation

Page 96: Route 2020 Metro Dubai   Construction Details

Railway

Page 97: Route 2020 Metro Dubai   Construction Details

Tunnel Fit-out Rail, Electricals, Ventilation

Page 98: Route 2020 Metro Dubai   Construction Details

Tunnel Fit-out

Install Sleepers & Rails

Concrete Batching Train for Floor Slab

Drilling Machine for Utilities Brackets

Page 99: Route 2020 Metro Dubai   Construction Details

Commissioning, Testing, Handover & Opening

Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.

ⓒ David H Moloney

Page 100: Route 2020 Metro Dubai   Construction Details

Commissioning, Testing, Handover & Opening

Purpose to test and ensure that everything (e.g. trains, escalators, lifts, ticket barriers) works as it should.

ⓒ David H Moloney

Page 101: Route 2020 Metro Dubai   Construction Details

Tunnel

Page 102: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

Page 103: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

HERRENKNECHY AG

Page 104: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

Page 105: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

Page 106: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

Cutting Head rotates to Dig

Excavated material removed by conveyor belt

Lifting muck to surface with skip

Placing Concrete Segments

Page 107: Route 2020 Metro Dubai   Construction Details

Tunnel Boring Machine (TBM)

Cutting Head rotates

7 nr. Precast segments form rings that line the tunnel Excavated material removed

by conveyor belt

ⓒ David H Moloney

Page 108: Route 2020 Metro Dubai   Construction Details

Miscellaneous Works

Page 109: Route 2020 Metro Dubai   Construction Details

Fencing

ⓒ David H Moloney

Sequence of Construction

Clear Scrub & Grade ground

Fix Corner & Strainer Posts

Fix Intermediate Posts

Fix Line Wire, Chain-link & Razer wire

Concrete ground beam

Page 110: Route 2020 Metro Dubai   Construction Details

Administrative

Page 111: Route 2020 Metro Dubai   Construction Details

Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current

progress and historical trends

Page 112: Route 2020 Metro Dubai   Construction Details

Histogram Charts for Resources & Outputs

Concrete, Manpower, TBM,

Manpower per Discipline Concrete per Location

Numbers for each month of the Project Quantity for each month of the Project

ⓒ David H Moloney

Page 113: Route 2020 Metro Dubai   Construction Details

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 114: Route 2020 Metro Dubai   Construction Details

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 115: Route 2020 Metro Dubai   Construction Details

Quality Assurance

Page 116: Route 2020 Metro Dubai   Construction Details

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Page 117: Route 2020 Metro Dubai   Construction Details

Setting out & Surveying

Page 118: Route 2020 Metro Dubai   Construction Details

Setting out & Surveying

Page 119: Route 2020 Metro Dubai   Construction Details

Setting out & Surveying

Page 120: Route 2020 Metro Dubai   Construction Details

Pavement Art

Page 121: Route 2020 Metro Dubai   Construction Details

Production by David H Moloney

See my YouTube channel for further details

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

ⓒ David H Moloney