    H2S Engineers In-House Training1 st December 6 th December 2 8

    ROLE OF H2S ENGINEERSON ARRIVAL AT THE

    FIELD LOCATION

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    2/9

    TOPICS COVERED UNDER THIS PRESENTATION:

    What are the activities that an H 2S Engineer is expected to carry outhe is at the location?

    The presentation aims to give a step by step check-list for an H2Sengineer to install and commission the H 2S Detection and Protectionsystem on the field.

    The areas that the H 2S Engineer need to keep focus on to avoid any

    delays in the installation and commissioning of the equipmentsonboard the rig.

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    3/9

    STEP BY STEP CHECKLIST FOR EFFECTIVEINTALLATION & COMMISSION OF H2S SYSTEM:

    The H 2S Engineer should undergo the Rig Induction Training andacquaint himself with the life boat muster stations, Station bills.

    Report to the Company Man and OIM about his arrival on thelocation.

    Acquaint himself with the drilling operations currently undergoingat the location and the zone where H 2S is expected to beencountered.

    Check whether the H 2S equipment (container) has arrived at the

    location. If not, what is its ETA.Get the POB List from the Radio Operator

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    4/9

    In the event of the H 2S container not being on location, the H 2SEngineer should use the time available to do the following things inadvance:

    1. Conduct the survey of the rig.2. Based on the survey of the rig, determine the placement of fixed point

    sensors, strobes and siren on the rig.

    3. Check with the Barge Engineer about the likely location of the container.

    4. Based on the location of the container, plan the installation by: Tracing the path of laying of cables to the JB and H.P Hoses from

    the CCU to the ADB. Placement of Cascade Racks on the rig in the absence CCU. Laying of the L.P. Hose from the ADB to the Manifolds, etc

    5. Prepare the Schematic diagram showing the rig layout and the placementof sensors, cascade racks, strobes & sirens, ADBs, manifolds, etc.

    6. On the basis of POB and the inventory of SCBAs, Work line units andEscape sets, determine the requirement of SCBAs, SABAs on the field andEscape sets required to be placed in the accommodation area.

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    5/9

    7. Get the approvals from the base office and schematics and placements andthen discuss with the Company man and OIM on placements etc.

    8. Discuss with the Company man on providing the H2S training PPT presentation while waiting on equipment.

    9. Look out for the bulk penetration routes, speak to the electrician on taking the power supply from emergency generator for GDS system and B. A.Compressor and possible source for Big blowers near Rig floor, main deckareas.

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    6/9

    Once the Container arrives at the location, the following needs to bechecked out:

    1. Look out for any physical damages to the container. If any, report to officewith pictures if possible.

    2. Verify the availability of all equipments in the container per the Inventoryavailable and fill the requisite ISO Form - H 2S Package Verification (Report for any discrepancies in the inventory)

    3. Important Note: Before installation commences, look out for the CalibrationGas Bottle in the container and check whether the Cal gas is available or whether the concentration of H 2S gas or the Quad Gas is still intact byverifying with a Portable detector. Also check whether the Cal gas has gotexpired.

    (In the event the Cal Gas is not sufficient for calibration, inform the baseoffice to arrange for the same till the time you carry out your installation.)

    4. Based on the schematic diagram prepared, place the equipments at the desiredlocation.

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    7/9

    Check List:

    1. Ensure that the cables and hoses laid do not cause obstruction for any rigactivity or access of pathways.

    2. The hoses and cables are not tied with other cables or equipment which arelikely to be removed by other service companies/ rig personnel.

    3. Look out whether there is a bulk head penetration for the cables and hoses to

    be passed at the desired location.

    4. In the case of RM block are available, check with the Rig Electrician if thesame can be utilized by us for our installation activities.

    5. Conduct the Air Quality Test of the Air in the Cylinders and Compressor air before filling the cylinders and prepare the Air Quality Report accordingly.

    6. Once all the SCBAs, SABAs, Escape Sets and Portable detectors aredistributed in the location, fill their corresponding ISO forms.

  • 8/11/2019 Roles and Responsibility of H2S Engineer

    8/9

    Check List:7. Once all the sensors are placed and commissioned at the desired location,

    calibrate the sensors and fill the corresponding the ISO form for Calibrationof Fixed Point sensors and Portable Detectors.

    8. Conduct the Cascade Leak test and lookout for any leakages near the fittingsof H.P. hoses.

    9. Check if all the pressure gauges are functioning properly.

    10. Test the Alarms and Strobe Lights for their functioning. ( Note At the time of testing of alarms and sensors, inform the Company Man, OIM, Barge Engineer to have everyone addressed that the alarm should be only treated as a test andno action is required by anyone.)

    11. If Bug Blower is part of the package, check for its functioning and fill the ISOform BUG BLOWER MAINTENANCE LOG .

    12. Once all the breathing apparatus are distributed and the sensors arecommissioned and calibrated, have the INSTALLATION ACCEPTANCEFORM signed by the Company Man and send the same to office.

  • 8/11/2019 Roles and Responsibility of H2S Engineer