IRAP: Eliminating High Risk Roads Speaker: Rob McInerney Economy: Australia.
Roads Australia Inland Rail presentation - Amazon S3 · ROADS AUSTRALIA 11 SEPTEMBER 2018 RICHARD...
Transcript of Roads Australia Inland Rail presentation - Amazon S3 · ROADS AUSTRALIA 11 SEPTEMBER 2018 RICHARD...
INLAND RAILROADS AUSTRALIA11 SEPTEMBER 2018
RICHARD WANKMULLER CHIEF EXECUTIVE OFFICER INLAND RAIL
1
HOW WE’RE CONNECTING AUSTRALIA
WITH SUPPORT FROM GOVERNMENT
$9.3bncommitmentIN PARTNERSHIP WITH THE PRIVATE SECTOR
HAND-IN-HAND WITH THE COMMUNITY
ENGAGEMENTLOCAL
SUPPORTJOBS INDUSTRYNETWORK
2
3
▪ Generate $16Billion in additional economic benefits
▪ Protect a significant dividend
▪ Create 16,000 jobs
▪ Make the nation safer and more efficient by removing +200,000 trucks from the road
▪ Provide the backbone for a world-class supply chain
WHY IS THE GOVERNMENT INVESTING $9.3BILLION?
4
MEETING THE FREIGHT CHALLENGE
Inland Rail is about more than modal shift. Inland Rail will also grow total freight capacity.
BRISBANE TO MELBOURNE, ADELAIDE AND PERTH CORRIDORS
5
MEETING THE FREIGHT CHALLENGEWITHOUT INLAND RAIL
2015
RAIL3.7 mt
ROAD6.3 mt
2030
RAIL7.0 mt
2050
ROAD9.7 mtROAD
4.7mt
RAIL2 mt
6
MEETING THE FREIGHT CHALLENGEWITH INLAND RAIL
2015 2030
RAIL5.7 mt
ROAD4.8 mt
2050
ROAD6.8 mt
ROAD4.7mt
RAIL2.0 mt
RAIL11.1 mt
SAFER, LESS CONGESTED ROADS200,000 FEWER TRUCKS =
Commodities andVolumes by rail line
CONNECTION OPENS UP OPPORTUNITIES FOR REGIONAL AUSTRALIA
7
RAIL NETWORKINTERFACE
9
DIRECT INVESTMENT
Stimulating private sector investment in ancillary developments that support regional economies
INDIRECT INVESTMENT
• Intermodal/Terminals• New Business
Ventures- Quarries
- Water Supply
- Precast Concrete
- …,
• Workforce training and development
PPP
PARTNERSHIP WITH PRIVATE SECTOR
10
Cut to Fill -
11,700,000m3 cut
to 10,400,000m3
fill Formation
(capping) layer –
194,327m3
131 culverts of
various sizes
51 bridges
totalling 3.94km
in length
11 viaducts totalling
8.07km in length
6 road over
rail grade
separations
Active – 10
Passive – 11
8.51km in
length
PPP – INNOVATION WHERE IT MATTERS THE MOST
133.6km of new dual gauge
track, 11 passing loops to
cater for 1.8km trains
Local road realignment
4.7km
New road access 7.3km
HAND-IN-HAND WITH THE COMMUNITY
12
2016/2017ARTC asked to complete project concept assessment reports
MAY 2016Infrastructure Australia recommends Inland Rail as a Priority Project
2006Government’s North-South Rail Corridor Study Go West, not East
2010Government’s Melbourne – Brisbane Inland Rail Alignment Study Find a
flat straight pathEARLY 2013Australian Government announces $300m for Inland Rail preconstruction activities 2014
Inland Rail Implementation Group formed by the Government and chaired by Hon. John Anderson
MAY 2017Australian Governmentselects ARTC to deliver Inland Rail. Commits $8.4bn in equity to ARTC for Inland Rail
NOVEMBER 2017Concept assessments complete and study areas identified
AUGUST 2015Inland Rail Implementation Group report released with Inland Rail program Business Case – Endorsement of the ‘Base Case’ alignment along all 17,00km
▪ 2016 – 30 June 2018 – more than 2,100 landowner meetings
▪ Valuable input into shaping greenfield project study areas
▪ Helping inform our engineering
▪ Designs within study areas
13
HAND-IN-HAND WITH THE COMMUNITY
Requirements differ across states but all invite extensive community involvement during the approvals process.
Our focus from now to 2021 is to hear from the community about impacts and develop mitigation actions in the approved study areas.
MINISTER FOR PLANNING
NSW
COORDINATOR-GENERAL
QLD
MINISTER FOR PLANNING
VIC
HAND-IN-HAND WITH THE COMMUNITY
14
Delivering on the commitment
ENGAGING ACROSS THE WHOLE PROJECT LIFE CYCLE
Community Consultative Committees
▪ Inform accurately▪ Listen and hear concerns and ideas▪ Ongoing exchanges of information▪ Maximise the benefits
FAST
Straight and flat
NOW33hrs
BENEFICIAL30%
CONNECTED
FUTURE
24<MELBOURNE
TO BRISBANE
16,000 JOBS
BILLION$16
COST REDUCTION
COMPARED TO TRUCKS
RELIABLE98%
KEY OUTCOMES
IN ADDITIONAL ECONOMIC BENEFITS
15
16
SOME RECENT HIGHLIGHTSAll 13 Inland Rail projects have completed the Concept Assessment stage
$250m worth of contracts already awarded $600m in contracts underwayover $1Billion by late next year
Environmental approvals granted in early September for construction work to begin on P2N
Progressing the Public Private Partnership (PPP),Industry briefings ongoing during October and November 2018
200,000 concrete sleepers under fabrication are being mobilised
INLink appointed as first preferred construction contractor in July
Continuous study area from Melbourne to Brisbane
1105 Land Access Agreements in place, 95% success rate
2,100 attended Industry Briefings (2017/18)
14,000 tonnes of steel rail being delivered for Parkes to Narromine project
WHAT YOU WILL SEE 2018/19
17
3 4 5Finalise the plan
1Continue on our commitment• Meeting with all
Landowners along the alignment
2Get more construction going
Commence large-scale construction
Get the Public Private Partnership going via EOI
• more than 1,500 meetings planned between now and June 2019