River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report !...

22
River Crane Phosphorus Project – Stage 1 Stage 1 of Phosphorus Project has been made possible by funding from Thames Water, it has been delivered in conjunction with project partners; Friends of the River Crane Environment and Crane Valley Partnership with support from frog environmental.

Transcript of River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report !...

Page 1: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project – Stage 1  

Stage  1  of  Phosphorus  Project  has  been  made  possible  by  funding  from  Thames  Water,  it  has  been  delivered  in  conjunction  with  project  partners;  Friends  of  the  River  Crane  Environment  and  Crane  Valley  Partnership  with  support  from  frog  environmental.    

 

 

 

 

 

 

 

 

 

 

Page 2: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 2 Stage 1 Report  

 

 

   

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Project

Submitted to

Developed by

Project Manager

Project Number

Document Version

Date

RIVER CRANE PHOSPHORUS PROJECT – STAGE 1. V2

Crane Valley Partnership

FORCE & frog environmental ltd

Richard Haine

FE13-12-004

1.0

January 2014

Page 3: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 3 Stage 1 Report  

Acronyms  &  Abbreviations    

 

EA………..  Environment  Agency  

CSO………  Combined  Sewer  Overflow  

FORCE….  Friends  of  River  Crane  Environment  

HLF………  Heritage  Lottery  Fund  

LWT…….  London  Wildlife  Trust  

PPE……..  Personal  Protective  Equipment    

SAGIS…..  Source  Apportionment  Geographical  Information  System  

SRP………  Soluble  Reactive  Phosphorus  

STW……..  Sewage  Treatment  Works  

TW……….  Thames  Water  

WFD……..  Water  Framework  Directive  

ZSL……….  Zoological  Society  of  London  

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Page 4: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 4 Stage 1 Report  

 

 

Report  contents    

Executive  summary  of  key  findings    

1. Introduction……………………………………………………………………………………………………  3  

2. Stakeholder  analysis……………………………………………………………………………………….  6    

3. Data  review…………………………………………………………………………………………………….  7    

4. Sampling  Strategy…………………………………………………………………………………………..  11  

5. Data  Management………………………………………………………………………………………….    16  

6. Health  &  Safety  Management…………………………………………………………………………  18  

7. Communications…………………………………………………………………………………………….  19  

8. Project  Finance……………………………………………………………………………………………….  20  

Contents  of  tables  and  figures  

Table  1:  Timeline  and  key  milestones……………………………………………………………………    5  

Table  2:  Environment  Agency  sampling  points  and  regime……………………………………    8  

Figure  1:  Map  showing  hotspot  data  &  sampling  points………………………………………..    10  

Table  3:  Stage  2  constraints  and  mitigation…………………………………………………………..   13  

Appendices  

1. Stakeholder  engagement  spreadsheet  2. Environment  Agency  Soluble  Reactive  Phosphate  data  (plotted  to  line  graphs)  3. Combined  Sewage  Overflow  data  from  Thames  Water  4. SAGIS  data  (EA)  5. Cost  Centres  and  financial  summary  of  stage  2    6. Draft  flow  calculation  for  stage  2  site  assessment  (FORCE)  

   

Page 5: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 5 Stage 1 Report  

 Executive  summary  -­‐  key  findings    

• A  Citizen  Science  approach  to  the  Phosphorus  Project  is  both  practical  &  feasible  and  will  bring  an  increased  value  to  the  outcomes  of  the  project.    

 • Creating  a  well-­‐resourced  water  quality  monitoring  network  on  the  River  Crane  that  

combines  Citizen  Scientists,  Academia,  Volunteer  Groups,  and  Professional  Services,  key  Stakeholders  from  the  Private  Sector  and  the  Regulator  is  of  practical  benefit  to  meeting  targets  set  out  under  the  Water  Framework  Directive  (WFD).    

 • There  is  willingness  on  the  part  of  a  wide  range  of  stakeholders  covering  all  sectors  

to  devote  time  and  resources  to  the  success  of  the  project  (as  summarised  in  appendix  1).      

• Stage  2  of  the  project  cannot  be  delivered  without  the  support  of  the  private  sector  to  assist  with  coordination  and  delivery  during  the  first  12  months.    

 • Costs  in  the  first  12  months  of  the  project  (phase  two)  include  a  considerable  input  

to  develop  and  test  the  methodology  and  set  up  and  train  the  large  volunteer  and  academic  project  team.    The  annual  costs  of  ongoing  monitoring  have  not  been  calculated  as  yet,  but  are  likely  to  be  substantially  lower.  Long-­‐term  partnerships  and  funding  are  being  planned  that  will  ensure  the  longevity  of  the  project.      

• Data  review  has  shown  that  a  typical  phosphate  concentration  in  the  Crane,  from  Environment  Agency  (EA)  data,  is  between  0.3  and  0.5mg/l  and  that  a  major  historic  source  of  phosphate  loading  is  likely  to  be  from  the  River  Colne  via  the  DNR.    

 • Positive  Engagement  with  the  Zoological  Society  of  London  (ZSL)  and  third  sector  

organisations  such  as  Thames21  has  revealed  opportunities  to  share  resources  and  to  cross-­‐pollinate  and  promote  projects.    The  prospect  of  joint  Citizen  Scientist  training  days  and  sharing  of  sampling  points  on  the  River  Crane  is  also  a  practical  benefit.    This  should  lead  directly  to  resource  efficiencies  being  found  and  a  more  joined  up  approach  to  water  quality  investigation  on  the  River  Crane.    The  Phosphorus  Project  is  open  to  new  partnerships  being  formed  with  other  organisations  in  the  quest  for  delivering  value  and  efficiency  with  the  resources  available.      

         

   

Page 6: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 6 Stage 1 Report  

1.  Introduction      

Elevated  concentrations  of  the  nutrient  phosphorus  in  rivers  can  lead  to  excessive  growth  of  plants  and  algae.    This  in  turn  can  have  an  adverse  impact  on  water  quality  parameters  such  as  oxygen.    Increased  plant  and  algae  can  also  affect  the  habitat  of  the  river,  impacting  on  populations  of  water  animals  such  as  invertebrates  and  fish.      The  EA  has  set  out  standards  for  Soluble  Reactive  Phosphorus  (SRP)  under  the  Water  Framework  Directive  (WFD);  this  helps  manage  the  risk  of  adverse  ecological  impacts  caused  by  higher  concentrations.  Having  these  standards  can  help  indicate  the  likely  degree  to  which  phosphorus  concentrations  would  need  to  be  reduced  in  order  to  improve  ecological  quality.      This  study  proposes  the  development  of  a  well-­‐resourced  water  quality  investigation  network,  which  will  lead  to  a  higher  frequency  of  monitoring  on  the  Crane,  in  more  locations  and  show  more  accurately  where  efforts  should  be  directed  to  meet  environmental  objectives  as  set  out  under  the  WFD.  The  study  has  3  stages:        Stage  1:  data  review,  stakeholder  engagement,  feasibility  study    

Stage  2:  data  collection  and  review    

Stage  3:  planning  and  delivering  interventions    

   This  report  is  concerned  with  the  delivery  of  stage  1  and  the  planning  aspects  of  stage  2;  stage  3  will  be  referred  to  as  and  when  required  to  give  context  and  will  run  concurrently  with  stage  2.      This  stage  1  investigation  indicates  that  using  a  Citizen  Science  (CS)  approach  to  provide  an  increased  monitoring  system,  subject  to  providing  a  professional  technical  and  safety  framework,  is  feasible  and  will  add  value  to  the  project.    There  is  a  significant  level  of  interest  from  local  volunteer  groups  and  others  in  supporting  this  initiative  and  the  project  should  provide  a  level  of  investigation  and  assessment  that  would  not  be  possible  from  any  one  organisation.    The  addition  of  academic  involvement  as  well  as  MSc  projects  to  provide  targeted  investigations  on  the  River  Crane  should  further  increase  the  value  of  the  project  and  prospects  of  building  successful  long-­‐term  partnerships.    A  further  outcome  of  the  project  is  increasing  the  awareness  of  the  issues  of  water  quality  on  the  River  Crane  among  participants  and  the  local  community.    This  benefit  should  be  enhanced  through  working  alongside  the  “Only  Rain  in  Rivers”  campaign  headed  up  by  the  EA.  There  are  also  significant  potential  benefits  to  be  gained  from  combining  efforts  with  the  Zoological  Society  of  London’s  (ZSL)  Citizen  Science  project  for  River  Fly  monitoring.    It  is  anticipated  that  the  large  local  population,  with  a  high  level  of  engagement  in  the  Crane  

Page 7: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 7 Stage 1 Report  

corridor,  will  provide  a  fertile  ground  for  dissemination  of  outcomes  and  possible  local  actions.        It  should  be  noted  that  the  project  is  creating  a  framework  for  collecting  and  studying  phosphorus  loading  that  is  replicable  elsewhere,  the  outcomes  of  this  work  therefore  have  a  value  that  stretches  beyond  the  boundaries  of  the  catchment  and  have  great  potential  significance  for  achieving  improvements  as  set  out  under  the  WFD  both  on  the  Crane  and  elsewhere  in  the  country.      A  typical  phosphate  concentration  in  the  Crane,  from  EA  data,  is  between  0.3  and  0.5mg/l.    Phosphate  is  the  crucial  parameter  for  the  WFD  classification  of  the  Crane,  resulting  in  the  upper  and  middle  Crane  being  classed  as  of  moderate  ecological  potential  and  the  lower  Crane  being  classed  as  poor  potential.    Reducing  the  phosphate  concentration  in  the  river  is  considered  to  be  the  best  means  of  reaching  the  good  ecological  potential  target  under  the  WFD.      Concentration  data  are  of  value,  but  they  do  not  give  any  information  about  the  phosphorus  loading  in  the  river.    Measuring  the  flow  rate  as  well  as  the  concentration,  as  proposed  by  this  project,  allows  the  loading  to  be  calculated,  and  this  is  essential  information  for  investigating  the  sources  of  phosphorus.    An  average  flow  rate  in  the  lower  River  Crane  of  one  m3/s  therefore  translates  to  a  phosphorus  loading  of  the  order  of  50  kg  per  day.    One  of  the  key  objectives  of  this  project  is  to  improve  our  understanding  of  where  this  50  kg  of  phosphorus  is  sourced  from  and  how  it  may  best  be  reduced.        

2.1  The  key  deliverable  for  stage  1  are:  

i. Work  with  stakeholders  in  establishing  the  type  of  involvement  and  their  level  of  commitment  in  the  formation  of  a  water  quality  investigation  and  monitoring  network  on  the  River  Crane.      

ii. Undertake  the  necessary  research  and  provide  the  information  required  to  form  a  monitoring  strategy  for  stage  2  of  the  investigation  (collection  of  data  in  the  field).    

iii. Objectively  assess  the  feasibility  and  value  of  stage  2  given  the  anticipated  level  of  resource  and  data  already  available.      

 

2.2  Project  boundaries,  timeline  and  key  milestones      Following  approval  from  the  Crane  Valley  Partnership  (CVP),  the  Phosphorus  Project  is  to  take  a  catchment-­‐based  approach  rather  than  solely  focus  on  the  Lower  Crane.    Using  a  catchment-­‐based  approach  will  also  open  up  the  investigation  to  more  support  from  the  EA  as  well  as  provide  a  wider  catchment  for  academic  and  volunteer  support.  A  catchment-­‐based  approach  will  also  lend  the  project  to  replication  elsewhere.    

 

Page 8: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 8 Stage 1 Report  

Table  1.   Planned  timeline  and  key  milestones  in  project  formation  

Milestone   Planned  date  Completion  of  stage  1     January  31st  2014  Formation  and  submission  of  stage  2   January  31st  2014  Confirmation  of  stakeholder  resources     ongoing  Pilot  testing  data  collection  method   February  -­‐  March  Citizen  Science  Training  Day  with  Environment  Agency  

March  -­‐  April  2014  

Citizen  Scientists  to  commence  field  work     April  -­‐  May  2014  Stage  2  initial  monitoring  period   April  2014  to  March  2015    

It  is  anticipated  that  stage  2  of  this  project  will  co-­‐ordinate  several  different  lines  of  investigative  approach;  these  can  be  broken  down  as  follows:    

• CS  project,  with  CS  collecting  water  quality  data  and  collecting  other  observations  from  monitoring  points  that  are  pertinent  to  the  study.    There  are  plans  for  regular  sample  collection  as  well  as  more  focused  bursts  of  sampling  in  specific  areas  using  CS.    

• Academic  research  providing  more  detailed  insight  into  specific  relevant  areas  of  study.  

• Regulatory  and  professional  review  and  analysis  that  will  help  inform  decision  making  on  a  catchment  level  and  allow  the  value  of  actions/interventions  to  be  assessed.    

 

3.  Stakeholder  analysis  and  anticipated  level  of  commitment    

Appendix  1  contains  a  full  stakeholder  analysis  of  the  River  Crane  Phosphorus  Investigation.    The  table  also  outlines  the  role  that  each  stakeholder  has  played  thus  far  and  the  anticipated  or  confirmed  level  of  commitment  in  the  delivery  of  Stage  2.    The  pro  bono  value  of  this  commitment  has  also  been  calculated.    

In  summary,  a  wide  range  of  support  from  different  sectors  is  evident  with  key  stakeholders  displaying  a  good  level  of  commitment.    Due  to  the  short  timeframes  involved  not  all  stakeholders  engaged  have  been  able  to  confirm  their  level  of  commitment  to  this  project.    Key  stakeholders  such  as  Friends  of  River  Crane  Environment  (FORCE),  Thames  Water  (TW)  the  EA  and  ZSL  are  all  very  supportive  of  the  project.    Strong  interest  from  individual  volunteers  from  an  initial  communication  sent  in  December  also  shows  a  good  public  interest  with  locally  based  volunteers  wishing  to  undertake  data  collection  during  Stage  2.    

Positive  Engagement  with  ZSL,  Thames21  and  London  Wildlife  Trust  (LWT)  have  yielded  good  ideas  such  as  sharing  resources,  cross  pollination  and  promotion  of  projects.    Joint  training  days  and  sharing  of  sampling  points  on  the  River  Crane  should  lead  directly  to  resource  efficiencies  being  found  and  a  more  joined  up  approach  to  improving  water  quality  on  the  River  Crane  as  well  as  a  positive  public  perception  of  how  efforts  to  restore  the  River  Crane  are  coordinated.      

Page 9: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 9 Stage 1 Report  

4.  Data  review  

In  order  to  start  refining  a  sampling  strategy  for  the  phosphorus  project  it  has  been  important  to  collate  different  sources  of  data  from  sampling  already  being  undertaken  on  the  River  Crane.    

A  key  source  of  data  is  from  the  EA,  who  have  SRP  data  stretching  back  to  1978  up  until  the  present  day,  for  certain  sites.    Frog  environmental  have  taken  these  data  and  plotted  it  into  graphs  to  assist  with  trend  analysis.    These  graphs  can  be  found  in  Appendix  2.  

Other  sources  of  data  that  will  be  relevant  for  the  study  include  Source  Apportionment  Geographical  Information  System  (SAGIS)  data  from  the  EA  and  data  from  Heathrow  Airport  Ltd,  who  have  engaged  a  consulting  firm  to  collect  and  review  water  quality  data.    

These  data  will  be  reviewed  in  the  following  sections.  

 

4.1  Environment  Agency    

The  table  below  shows  the  EA  monitoring  regime  for  SRP  on  the  River  Crane.    All  of  these  raw  data  have  been  made  available  to  FORCE  and  frog  environmental.    Table  2  shows  that  8  sites  on  the  River  Crane  are  regularly  monitored  for  levels  of  SRP.    Active  sampling  sites  are  highlighted  in  green.  

Table  2.   Historic  and  present  SRP  monitoring  regime  on  the  River  Crane  by  the  Environment  Agency  (present  highlighted  in  green)  

Monitoring  location   Frequency    CRANE  AT  NORTHCOTE  ROAD,  ISLEWORTH    

1978  -­‐  present  (monthly  from  1987)  

CRANE  AT  THE  CAUSEWAY,  HOUNSLOW    

Occasional  samples  1986  –  1989,  Regular  samples  from  1990  –  1999  and  from  2001  –  2006.  

CRANE  BELOW  EASTERN  BALANCING  RESERVOIR  OUTLET,  HOUNSLOW    

4  samples  1993  –  1994,  Monthly  samples  2001  –  2007  and  2013  –  present.    

CRANE  ABOVE  EASTERN  BALANCING  RESERVOIR  OUTLET,  HOUNSLOW    

Monthly  from  Sept  2013  only.    

CRANE  ABOVE  DUKE  OF  NORTHUMBERLAND’S  RIVER    

Quarterly/intermittent  from  1978  –  1990,  Monthly  from  1990  –  2010,  Quarterly  from  2013.    

HEATHROW  AIRPORT  EASTERN  LAGOONS  AT  OUTLET  WEIR    

Quarterly  from  1978  –  1986,  Monthly  from  1987  –  present.    

HEATHROW  AIRPORT  EASTERN  LAGOONS  U/S  CAUSEWAY  

One  sample/yr  in  1979  and  1980.  Regular  samples  (but  not  as  often  as  monthly)  from  

Page 10: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 10 Stage 1 Report  

Monitoring  location   Frequency       1985  –  1999.  Monthly  from  2001  –  2006.  

 HEATHROW  AIRPORT  EASTERN  LAGOONS  U/S  CAUSEWAY    

One  sample/yr  in  1979  and  1980.  Intermittent  between  1985  –  1991.  One  sample  in  2006.    

YEADING  BROOK  AT  NORTH  HYDE  ROAD,  HAYES    

Regular  monthly  samples  from  1986  –  present  (except  for  1989).    

YEADING  BROOK  WEST  AT  THE  WESTERN  AVENUE,  HILLINGDON    

Quarterly  from  1978  –  1984,  Monthly  from  1985  –  1989,  1990  –  1993,  1995  –  2008  and  2013  –  present.    

YEADING  BROOK  EAST  ABOVE  PRIORS  FARM,  RUISLIP    

Quarterly  /  intermittent  from  1978  –  1989,  Monthly  from  1990  –  2008  and  2013  –  present.    

 

The  sampling  points  noted  in  Table  2  have  been  mapped  in  Figure  1.        

4.1.1  Commentary  

Graphical  representations  of  the  EA  data  have  been  produced  (Appendix  2).    Several  of  these  sampling  points,  notably  ‘Crane  at  Northcote  Rd’  and  ‘Crane  Above  Duke  of  Northumberland’s  River’  show  a  significant  drop  off  in  level  of  SRP  around  the  year  1999  as  follows:  

• From  1978  to  1998  –  a  background  level  of  between  0.5  to  1  mg/l  with  regular  spikes  up  to  3  and  5  mg/l  

• From  1998  to  present  –  a  background  level  of  between  0.3  and  0.5  mg/l  with  nothing  above  0.6  mg/l    

This  would  be  consistent  with  the  removal  of  a  major  point  source  from  the  system  at  that  time.    The  EA  has  indicated  that  a  new  phosphorus  stripping  plant  was  installed  at  Maple  Lodge  Sewage  Treatment  Works  (STW)  on  the  upper  Colne  in  1999  and  this  is  the  most  likely  cause  of  this  step  change.      

Assuming  that  this  is  the  cause  of  the  changed  levels,  the  impact  on  the  River  Crane  has  been  remarkable,  all  the  more  so  given  that  the  contribution  of  the  River  Colne  (via  the  Duke  of  Northumberland’s  River  [DNR])  to  the  total  River  Crane  flow  at  Isleworth  is  approximately  one  third  to  roughly  half  of  the  total  at  low  flow.    

 

 

Page 11: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 11 Stage 1 Report  

4.2  Polluting  outfalls  study  (TW  and  EA  study)  

Thames  Water,  working  with  the  EA,  undertook  a  walkover  of  the  River  Crane  for  the  purpose  of  identifying  polluting  outfalls.    On  site  observations  such  as  presence  or  lack  of  sewage  fungus  were  used  to  establish  if  the  outfall  is  likely  to  be  subject  to  a  significant  “missed  connection”  problem.    

Data  from  TW  has  been  mapped  in  Figure  1  below.  

These  data  indicate  that  around  half  of  the  130  outfalls  mapped  to  date  indicate  some  form  of  pollution,  as  identified  through  sewage  fungus  presence.    Note  that  the  mapping  does  not  as  yet  include  all  data  from  the  lower  River  Crane  or  lower  DNR  below  Mereway  Road  Weir.    

4.3  Thames  Water  data  on  Combined  Sewer  Overflow  discharges  into  the  Crane  Catchment    

Data  has  been  supplied  by  TW  concerning  Combined  Sewage  Overflows  (CSO)  in  the  Crane  Catchment.  This  data  is  replicated  in  appendix  3.      

 

Page 12: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 12 Stage 1 Report  

Fig.  1.  EA  sampling  points  for  SRP  in  the  Crane  Catchment,  hotspot  data  as  referenced  in  section  4.2  and  planned  monitoring  locations  referenced  in  5.1.2  

 

 

Page 13: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 13 Stage 1 Report  

4.4  SAGIS  data    

The  EA  provided  SAGIS  data  for  the  Crane  Catchment  this  week  (w/c  20th  January).    

An  initial  review  indicates  that  the  data  will  be  a  further  valuable  input  to  stage  2  of  the  Phosphorus  Project.    

SAGIS  data  supplied  by  the  EA  is  reproduced  in  appendix  4.    

 

4.5  Heathrow  Airport  Ltd  data  

Heathrow  Airport  Ltd  undertake  regular  monitoring  of  outfalls  and  balancing  ponds  linked  to  their  infrastructure.    Sampling  is  undertaken  at  the  start  of  the  month  at  the  following  points:    

• Within  the  Eastern  Balancing  Reservoir  (EBR)  • Outfall  of  EBR  • Upstream  of  outfall  to  EBR  • 200m  downstream  of  outfall  of  EBR  

Heathrow  undertake  a  schedule  of  analysis  aligned  with  testing  the  WFD  status  of  a  water  body,  one  parameter  of  which  is  SRP.  SRP  data  for  the  previous  12  months  (as  of  March  2014)  will  be  supplied  to  FORCE  to  assist  with  water  quality  investigation  on  the  River  Crane.        

Receiving  regular  SRP  data  from  Heathrow  as  and  when  samples  are  taken  has  been  agreed  in  principle  with  the  site  Environment  Manager.    

 

4.6  FORCE  water  quality  report  and  invertebrate  analysis  

Since  the  major  pollution  event  of  October  2011,  Friends  of  the  River  Crane  Environment  with  ZSL  have  been  producing  a  detailed  water  quality  report  for  the  River  Crane,  with  quarterly  updates.    This  report  includes  background  water  quality  data,  sample  data  from  their  own  kick  sample  invertebrate  analysis  and  qualitative  data  from  local  people  with  a  historic  knowledge  and  interest  in  the  River  Crane.    

The  report  is  available  via  the  FORCE  website  and  is  very  useful  for  understanding  the  background  and  recent  history  of  the  River  Crane.    

 

5.  Sampling  strategy  

To  execute  stage  2  efficiently,  data  collection  in  the  field  should  serve  to  complement  the  sampling  strategy  of  relevant  third  parties,  mainly  that  of  the  EA.    The  overall  aim  of  the  Phosphorus  Project  in  its  3  stages  is  to  be  able  to  plan  and  deliver  good  value  interventions  to  reduce  phosphorus  levels;  a  monitoring  network  set  up  on  the  River  Crane  as  part  of  

Page 14: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 14 Stage 1 Report  

stage  2  could  also  play  a  long-­‐term  role  in  assessing  the  effectiveness  of  interventions  designed  to  reduce  levels  of  phosphorus  during  stage  3.    

The  primary  source  of  field  data  collected  during  stage  2  will  be  from  Citizen  Scientists  who  will  adopt  sampling  points  and  collect  data  at  regular  intervals.    TW  has  agreed  in  principle  that  their  laboratories  can  be  used  for  the  analysis  of  SRP  to  the  United  Kingdom  Accredited  Standard  (UKAS).    

The  planned  involvement  of  academic  partners  will  provide  a  different  type  of  investigation  and  analysis,  designed  to  build  upon  and  enhance  the  project  outcomes.    We  envisage  that  targeted  academic  studies  would,  for  example  investigate  the  relative  loadings  of  various  outfalls  or  consider  the  role  of  sediment  on  the  dissolved  phosphorus  loading.    The  development  of  these  investigations  will  be  iterative  and  will  take  shape  during  stage  2.    Work  undertaken  so  far  indicates  locally  based  academic  partners  would  also  be  willing  to  play  a  key  long  term  role  in  assessing  the  effectiveness  of  interventions  undertaken  in  stage  3  of  Phosphorus  Project.    

The  data  collected  must  necessarily  be  reliable;  organisations  such  as  the  EA  and  TW  should  be  able  to  use  the  data  collected  within  stage  2  of  the  Phosphorus  Project  to  assist  in  decision-­‐making.    The  data  must  therefore  be  of  a  high  standard,  collected,  transported  and  analysed  using  approved  methodologies.    

The  following  sections  outline  key  elements  of  the  Citizen  Science  led  sampling  strategy.    

 

5.1  Citizen  Scientist  sampling  (planned)  

Fieldwork  for  Citizen  Scientists  should  be  designed  to  be  interesting  and  engaging;  a  level  of  empowerment  should  come  with  the  responsibilities  of  collecting  information  that  will  contribute  to  improved  water  quality  in  the  catchment.    Data  collection  has  been  designed  with  this  in  mind.    Citizen  Scientists  will  therefore  record  SRP  measurements  on  site  as  well  as  collecting  a  water  sample  for  analysis  at  a  UKAS  accredited  laboratory.    Should  the  Citizen  Scientist’s  data  record  a  breach  in  an  agreed  level  of  SRP,  they  will  report  a  pollution  incident  to  the  EA.  The  threshold  for  calling  in  an  incident  will  be  agreed  with  the  EA  prior  to  the  commencement  of  fieldwork  and  will  be  based  on  historical  local  data.    

As  well  as  collecting  a  water  sample  for  SRP  analysis  and  a  sample  for  laboratory  analysis,  it  is  also  anticipated  that  Citizen  Scientists  will  collect  the  following  data  from  each  visit  to  site:  

• Flow  (to  allow  volume  of  water  and  loading  of  P  to  be  calculated)  • Invasive  species  check    • Visual  and  olfactory  check  for  pollution    • Any  other  observations  of  note    

Whilst  the  central  outcome  of  the  Phosphorus  Project  is  to  collect  quantitative  data  to  allow  appropriate  interventions  to  be  planned,  there  is  an  equally  important  aspect  of  the  project  that  relates  to  an  increase  in  local  ownership,  knowledge  and  empowerment.    The  precise  

Page 15: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 15 Stage 1 Report  

outputs  of  these  factors  are  difficult  to  quantify  but  they  are  very  relevant  for  the  long-­‐term  stewardship  of  urban  rivers  such  as  the  Crane.    

CS  data  collection  could  be  coordinated  with  the  EA  schedule  and  Heathrow  Airport  for  data  collection  so  that  more  regular  snap  shots  of  phosphate  levels  are  attained.  This  is  likely  to  be  possible  for  the  Heathrow  Airport  data  (first  week  of  the  month)  than  the  EA  data,  which  is  scheduled  at  short  notice  and  not  always  carried  out  at  the  same  time  each  month.    

 

 

5.1.2.  Site  Assessment  and  Selection  

Site  selection  will  be  finalised  in  the  early  parts  of  stage  2  when  all  constraints  and  resources  are  finalised.    Final  site  selection  will  be  based  on  the  following  key  inputs:  

• Existing  monitoring  taking  place    • Safety  and  accessibility  for  Citizen  Scientists    • Location  of  polluting  outfalls  previously  assessed  • Availability  of  Citizen  Scientist  resource  to  visit  the  sampling  point  

As  part  of  site  selection,  the  following  should  be  assessed:  

• Site  survey  to  estimate  cross  section  so  that  the  flow  rate  of  water  can  be  calculated.  Appendix  5  contains  a  draft  preform.  The  EA  hydrometrics  team  are  collaborating  on  methodology  for  this  element  of  data  collection.    

• Assessment  of  any  site  specific  risks  e.g.  isolation,  cyclists,  traffic,  edge  protection  to  water,  slippery  or  unmade  ground.  

Figure  1  (Page  12)  includes  a  map  of  proposed  sampling  points  on  the  River  Crane.      

ZSL  Riverfly  monitoring,  Thames  21  River  Watch  and  other  organisations  are  also  planning  to  operate  sampling  points  on  the  River  Crane.    Sharing  sampling  sites  where  practical  to  do  so  will  increase  the  potential  for  resource  efficiency  and  aid  communication  between  organisations  involved  in  the  Crane.    

 

 

5.1.3  Constraints  to  delivery  of  stage  2  

Several  constraints  have  been  identified  that  have  the  potential  to  limit  both  the  execution  of  the  sampling  plan  and  validity  of  data  collected.    These  are  shown  in  Table  3  below.    

 

 

 

Page 16: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 16 Stage 1 Report  

Table  3.  Constraints  to  executing  Stage  2  of  Phosphorus  Project  

Constraint   Mitigation  Availability  of  volunteers  to  deliver  the  planned  sampling  programme.  

Project  promotion  and  execution  of  communication  plan  must  take  place  so  that  a  realistic  monitoring  proposal  can  be  finalised.    

Availability  of  existing  water  quality  data  from  third  parties  

Data  will  inform  site  selection.    Sampling  strategy  should  complement  existing  data  collection.    There  has  been  a  good  level  of  response  so  far  to  requests  for  data  from  the  EA.      

Agreed  methodology  for  sample  collection  must  meet  EA  criteria.  

EA  involvement  at  early  stage,  liaison  with  sampling  team  and  agreement  for  the  data  collection  methodology  

Laboratory  compliance     Samples  for  laboratory  analysis  must  be  kept  at  a  specified  temp  and  be  with  the  laboratory  within  agreed  timeframe.  Logistics  to  be  set  up  to  ensure  compliance  with  laboratory  testing.    There  have  been  very  positive  discussions  to  date  with  the  TW  laboratory  team  and  it  is  believed  that  the  TW  requirements  can  be  met  by  the  CS  team  

Volunteer  safety     Site  specific  H&S  plans  will  be  developed  for  each  sampling  site  in  the  early  part  of  stage  2  once  site  selection  is  finalised.  

Volunteer  turn  over   Good  communication  is  essential,  project  design  must  be  interesting,  not  laborious,  and  reserve  resources  to  service  sites  should  be  planned.    

Ability  to  collect  representative  sample     Methodology  to  be  agreed  with  EA,  with  site  specific  methods  to  address  any  ambiguity/bias  

Availability  of  capital  and  match  funding  for  stage  2  

A  well-­‐developed  plan  showing  detailed  resource  planning  and  advanced  stakeholder  engagement  will  be  more  likely  to  draw  funding.    One  application  for  match  funding  has  already  been  submitted  –  and  there  are  also  possible  match  funding  pots  with  our  academic  partners.    Volunteer  match  funding  resources  have  been  promised.    TW  has  indicated  the  availability  of  laboratory  resources.    

Availability  of  cost  effective  site  measurements  method.  

Viso-­‐colour  kits  identified  as  appropriate.    Two  kits  purchased  by  FORCE  and  pilot  tested  successfully  in  January  2014.    

Page 17: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 17 Stage 1 Report  

Constraint   Mitigation  Effective  coordination  of  volunteers  to  attend  site  at  the  same  time  

Good  communication  protocol  from  project  coordinator,  correct  volunteer  profiling  and  selection,  correct  expectation  set  with  volunteers  

 

5.1.4  Responsive  sampling  using  CS  (reactive)    

As  well  as  planned  collections,  stage  2  of  the  investigation  will  aim  to  mobilise  Citizen  Scientists  to  undertake  responsive  sampling.    This  may  be  in  response  to  unusual  conditions  such  as  very  low  or  high  flows  or  to  understand  the  response  to  pollution  incidents.    

A  nested  strategy  could  be  adopted  that  considers  different  sampling  resolutions.    As  data  collection  continues,  analysis  may  lead  to  certain  areas  being  highlighted  that  would  benefit  from  an  increased  sampling  resolution,  it  is  therefore  important  to  build  the  resources  and  capacity  for  responsive  sampling  into  the  planning  process.      

There  is  a  potential  tie-­‐in  with  the  EA  ‘Pollution  Assessment  Volunteer‘  scheme,  which  is  currently  under  development.  This  represents  a  potentially  powerful  tool  in  helping  to  quantify  the  ecological  response  to  discharges.    

5.1.5  Draft  methodology  for  water  sampling  CS    

As  previously  noted,  volunteers  will  collect  2  types  of  sample  during  a  site  visit.    The  first  sample  will  be  tested  on  site  using  a  Visocolour  kit  and  the  second  sample  will  be  stored  in  a  specified  container  for  UKAS  laboratory  analysis.      

A  site  visit  methodology  is  outlined  below:  

1. Arrive  at  site.  2. Wear  any  Personal  Protective  Equipment  as  per  the  risk  assessment.  3. Set  up  site  kit  to  ensure  that  no  obstruction  is  caused  or  trip  hazards.  4. Fill  out  details  on  laboratory  sample  container  (it  is  often  easier  to  do  this  before  at  

home!).    5. Fill  out  site  details  on  data  collection  sheet.    6. Measure  depth  (using  marker)  and  flow  velocity.  7. Collect  water  sample  and  bring  the  sample  to  a  safe  location  away  from  the  water’s  

edge  and  out  of  the  way  of  pedestrians  or  cyclists.      8. Undertake  field  SRP  test.  9. Record  the  result  using  colour-­‐metric  chart.    10. Discard  contents  of  bucket.  11. Repeat  steps  7,  8  &  9.    12. Retain  sample  and  fill  the  specified  container  to  be  sent  for  laboratory  analysis.  13. Ensure  lid  is  fully  sealed  and  container  is  labelled  correctly.  14. Package  in  bubble  wrap  and  place  in  cool  box.  15. Discard  remaining  water  into  surface  water  drain  or  directly  back  into  river.  16. Ensure  that  no  waste  is  left  on  site.      

Page 18: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 18 Stage 1 Report  

 

5.1.6  Training  offered  to  Citizen  Scientists  

The  EA  has  put  forward  the  involvement  of  its  sampling  team  to  assist  with  training  Citizen  Scientists  to  collect  samples.    As  a  key  stakeholder  in  the  project,  the  EA  will  play  an  important  role  in  helping  to  make  sure  that  samples  collected  are  representative  and  that  bias  is  eliminated  as  far  as  possible.  Data  must  be  usable  by  organisations  such  as  TW  and  the  EA  in  undertaking  further  investigations  or  planning  interventions  to  reduce  phosphorus  levels.  

Collaboration  with  ZSL  throughout  the  duration  of  stage  1  has  presented  good  opportunities  for  Citizen  Scientists  involved  with  the  Riverfly  Project    to  help  gather  important  information  that  will  feed  into  the  Phosphorus  Project.    Sharing  monitoring  points  and  providing  riverfly  Citizen  Scientists  with  monitoring  tools  designed  for  the  Phosphorus  Project  are  two  ways  that  the  projects  can  support  one  another.    There  is  good  potential  for  the  EA  Pollution  Assessment  Volunteer  scheme  (In  development)  to  be  another  common  thread  linking  the  two  projects.    

Following  initial  discussions  with  Thames  21,  there  will  be  opportunities  to  link  the  tidal  Thames  River  Watch  campaign  and  the  Phosphorus  Project,  both  in  terms  of  sharing  certain  monitoring  points  and  planning  joint  training  days  where  sampling  techniques,  monitoring  methodologies  and  data  management  will  be  covered.      

The  involvement  of  more  organisations  and  creating  links  with  their  projects  will  lead  to  a  joined  up  approach  on  the  River  Crane  and  provide  the  best  opportunities  for  delivering  positive  outcomes  as  efficiently  as  possible.    

 

5.2  Academic  studies    

Academic  studies  have  the  potential  to  bring  a  different  investigative  approach  to  the  Phosphorus  Project.    In  the  short  term  Kingston  University  and  St  Mary’s  University  are  involved  with  project  formation  and  working  with  frog  environmental  on  developing  research  briefs  to  be  carried  out  by  MSc  students.    These  projects  will  typically  involve  several  weeks  of  fieldwork  and  a  final  project  report,  the  planned  outcome  of  which  will  contribute  to  the  overall  understanding  on  phosphorus  in  the  River  Crane.    

Ideas  under  development  so  far  include:  

• Intensive  water  quality  monitoring  in  specific  areas,  thereby  creating  a  nested  sampling  strategy  to  fit  in  with  the  overall  water  quality  monitoring  approach.    

• Source  Apportionment  studies.  • Study  of  benthic  algae.  • Sediment  investigation  looking  at  the  nutrient  exchange  between  sediment  and  

water  body.  

The  possibility  of  drawing  in  European  funding  for  a  research  position  solely  focused  on  the  River  Crane  is  another  avenue  that  is  being  explored.    

Page 19: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 19 Stage 1 Report  

In  the  long  term,  partnerships  with  academic  institutions  will  form  a  useful  symbiotic  relationship  that  provides  resource  year  on  year  for  the  study  of  the  River  Crane  whilst  providing  educational  institutions  with  a  live  environment  on  their  doorstep  for  research.    Over  one  year  these  relationships  may  not  yield  a  great  return  but  over  ten  years  the  value  in  developing  partnerships  such  as  this  will  be  self-­‐evident.    The  Universities  named  in  the  stakeholder  plan  have  already  been  working  on  the  River  Crane  for  several  years  as  part  of  their  academic  modules  and  greatly  welcome  the  opportunity  to  be  more  actively  engaged  in  a  live  programme  of  work.      

 

 

5.3  Sediment  sampling  

Sediment  sampling  is  an  option  at  this  stage.    It  would  be  useful  to  build  a  picture  of  the  nutrient  sinks  and  sources  in  the  whole  river  system.  

Kingston  University  have  indicated  an  interest  in  leading  on  a  catchment  wide  sediment  investigation  with  a  view  to  establishing  the  potential  for  sediment  to  impact  on  WFD  status.  

 

6.  Data  Handling  

6.1  Data  Collection  

Citizen  Scientists  will  use  a  data  collection  sheet  to  record  the  following  information  each  time  they  sample:  

• Surveyor  name  (or  surveyor  number/  site  number)  • Time,  date,  sample  location    • Prevailing  conditions    • Flow  velocity    • Site  specific  observations  e.g.  Weed  coverage,  invasive  plants,  pollution    • Results  site  test  1    • Results  site  test  2  • Confirmation  of  sample  taken  for  lab  analysis  

The  data  sheet  should  also  contain:  

• A  check  list  of  all  materials/  equipment  required  for  sampling    • Information  on  what  to  do  if  pollution  is  observed  

 

6.2.  Data  Management  

There  are  two  main  streams  of  data  from  Citizen  Scientist  sampling  require  management;  data  collected  on  site  using  colour-­‐metric  testing  and  data  returned  from  the  lab.  

Page 20: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 20 Stage 1 Report  

• Site  data.  SRP  data  collected  on  site  could  be  texted  to  a  nominated  number  (PAYG  mobile  that  can  be  held  by  project  coordinator).    Data  sheets  can  be  collected  with  samples,  scanned,  or  the  information  transcribed  and  sent  by  email,  the  latter  likely  to  be  the  most  efficient  way.        

• Laboratory  data.  Data  from  the  laboratory  analysis  will  be  sent  to  the  nominated  project  coordinator  to  record  in  a  database    

To  help  obtain  an  overview  of  all  monitoring  for  SRP  being  undertaken  on  the  River  Crane,  a  table  could  be  produced  to  consolidate  data  from  the  EA,  FORCE  stage  2  and  Heathrow  Airport  Ltd.    The  table  would  be  updated  monthly  and  results  plotted  into  graphs  for  trend  analysis.    

 

6.3  Communication  of  data    

Communication  is  a  critical  aspect  of  the  Phosphorus  Project,  and  is  covered  in  section  8;  this  section  is  only  concerned  with  communication  of  results.    

The  results  collected  during  stage  2  will  be  freely  available  through  the  Crane  Valley  Partnership.    It  is  also  anticipated  that  a  page  could  be  made  available  for  results  of  Phosphorus  Project  on  the  Crane  Valley  Partnership  website.    

Discussions  have  taken  place  with  both  ZSL  &  Thames  21  regarding  use  of  an  existing  online  data  collection  tool  and  there  is  scope  for  a  development  of  this  during  stage  2.  

Certain  stakeholders  such  as  the  EA  and  TW  will  have  a  key  interest  in  the  data  produced  as  a  result  of  stage  2.    The  results  are  intended  to  help  guide  where  to  focus  resources  in  the  catchment.      

The  method  of  sharing  data  has  not  been  finalised.    However,  shared  cloud  space  is  seen  as  a  cost  effective  tool  that  allows  access  to  multiple  parties  without  an  associated  time  cost.  It  is  noted  though  that  not  all  organisations  have  access  to  free  cloud  space  e.g.  dropbox;  where  this  is  the  case,  other  methods  of  sharing  data  e.g.  via  email  update  will  be  used.      

Quarterly  meetings  involving  a  small  project  group  will  take  place,  minutes  and  actions  of  which  will  be  sent  to  all  stakeholders,  this  could  include  data.    

 

6.4  Interpretation  on  data  

Data  collected  in  the  field  is  only  as  useful  as  those  reviewing  it;  it  is  therefore  deemed  important  to  secure  a  commitment  from  specialists  within  both  TW  and  the  EA  to  support  the  date  review  and  enter  into  discussions  regarding  the  data  collected  at  regular  intervals.    

These  discussions  will  provide  a  natural  progression  to  stage  3,  i.e.  using  the  data  to  plan  and  deliver  interventions.    

Page 21: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 21 Stage 1 Report  

It  is  anticipated  that  a  project  review  with  key  stakeholders  will  take  place  two  to  four  times  per  year  during  stage  2.    If  deemed  of  value  by  the  partnership  this  could  take  the  form  of  a  project  steering  group,  linked  into  the  Crane  Valley  Partnership.        

 

7.  Health  &  Safety  management    

Health  &  Safety  (H&S)  is  a  critical  aspect  to  the  Phosphate  Project.    Putting  the  safety  of  Citizen  Scientists  or  any  staff  associated  with  the  project  at  risk  is  unacceptable.      

Each  monitoring  location  will  be  subject  to  a  simple  risk  assessment  designed  to  highlight  any  site-­‐specific  hazards  and  how  the  risk  of  these  hazards  causing  any  harm  will  be  mitigated.    As  noted  in  Table  3,  the  H&S  of  Citizen  Scientists  will  be  a  potential  constraint  for  site  selection.    

The  main  H&S  concerns  with  the  project  are  as  follows:  

• Slips,  trips  and  falls;  the  most  common  cause  of  accidents  in  a  place  of  work.  • Weils  disease  and  water  borne  contaminants.  • Lone  working;  sites  will  be  assessed  for  suitability  for  Citizen  Scientists  to  lone  work.  • Working  around  water.    

The  site-­‐specific  risk  assessments  will  dictate  the  type  of  Personal  Protective  Equipment  (PPE)  to  be  issued  to  all  volunteers  along  with  instructions  for  use.    In  some  cases  specialised  PPE  such  as  a  life  jacket  may  be  required,  although  a  hierarchy  of  risk  management  will  be  followed  that  will  manage  out  operational  risks  without  the  reliance  on  PPE.      

 

8.  Communications  

Good  communication  is  not  just  about  recruiting  volunteers  and  achieving  support  from  stakeholders;  good  communication  will  be  a  vital  ingredient  for  sample  collection,  data  exchange,  planned  and  reactive  sampling  co-­‐ordination  and  completing  the  loop  by  providing  feedback  to  the  Citizen  Scientists  on  the  results.    This  last  element  is  important  for  empowering  local  community  and  encouraging  continued  involvement  in  the  project.  

Providing  a  conduit  that  will  allow  Citizen  Scientists  to  provide  feedback  of  their  experience  of  the  project  will  also  be  important  for  creating  a  better  experience  for  Citizen  Scientists.    

There  are  important  communication  aspects  to  almost  every  part  of  the  Phosphorus  Project,  however  the  priority  for  stage  1  and  2  is  building  and  maintaining  a  database  of  Citizen  Scientists  and  interested  stakeholders  and  providing  regular  and  concise  communications  concerning  the  project,  a  task  that  bridges  stages  1  and  2.    

It  should  be  noted  that  participating  groups  have  good  contacts  with  the  local  media,  as  well  as  their  own  newsletters  and  contact  lists  that  will  help  raise  the  profile  of  the  project.    Any  communications  regarding  results  should  be  approved  by  project  partners  before  dissemination  to  ensure  that  messages  are  both  accurate  and  consistent.  

Page 22: River Crane Phosphorus Project – Stage 1 · River Crane Phosphorus Project 2 Stage 1 Report ! Project Submitted to Developed by Project Manager Richard Haine Project Number Document

River Crane Phosphorus Project 22 Stage 1 Report  

A  review  and  discussion  meeting  is  proposed  at  the  end  of  the  first  year  of  the  project  where  all  the  Citizen  Scientists  and  other  interested  parties  can  gather,  hear  the  draft  findings  of  the  project  and  contribute  their  views  and  experiences  to  the  debate.  

Communication  between  stakeholders  is  also  an  important  part  of  project  development.    This  is  particularly  important  for  projects  that  have  been  funded  by  TW  as  it  will  help  ensure  that  value  is  achieved  by  having  a  joined-­‐up  approach  to  water  quality.    

Ensuring  that  events  such  as  training  days  are  linked  with  the  various  projects  within  external  communications  will  ensure  a  clear  public  perception  of  all  of  the  various  projects  taking  place  on  the  River  Crane  and  give  Citizen  Scientists  an  opportunity  to  become  involved  in  more  than  one  project.      

 

9.  Financial    

9.1  Stage  2  resource  planning    

Appendix  5  ‘project  costs  centres’  captures  the  management  time  and  capital  overheads  for  stage  2  of  the  Phosphate  Project.    

The  purpose  of  the  table  is  to  itemise  and  estimate  the  capital  and  time  required  to  complete  stage  2  of  the  project.    

 

9.2  Match  funding    

An  estimate  of  the  match  funding  being  committed  to  the  project  is  included  in  Appendix  5.    Not  all  stakeholders  identified  in  Appendix  1  have  been  able  to  confirm  their  planned  time  commitment  to  the  project  as  yet;  where  this  is  the  case  an  estimate  has  been  made.  HLF  figures  will  be  used  to  quantify  real  costs.    

An  early  action  for  Stage  2  of  the  Phosphorus  Project  is  to  begin  planning  for  the  long-­‐term  sustainability  of  the  project  in  subsequent  years.    A  strategy  targeting  specific  funds  and  involving  key  stakeholders  will  be  developed  to  ensure  the  longevity  of  the  project.