Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion...

9
Las Vegas Executives Association Presentation Risk-Based Models for Project Planning Edited per 1/15/08 Meeting David B. Ashley President University of Nevada, Las Vegas January 30, 2008 Risk Planning and Management for the Panama Canal Expansion Program Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily and Ricardo Ungo September 30, 2010 Construction Engineering Conference: Opportunity and Vision for Education, Practice, and Research Presentation Outline 1. Motivation for risk analysis on Canal Expansion 2. The project risk management approach 3 Lessons learned 3. Lessons learned Expansion Background ACP formally proposed project with public referendum in 2006 What was the construction market like in 2000-2006?

Transcript of Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion...

Page 1: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Risk Planning and Management for the Panama

Canal Expansion ProgramCanal Expansion Program

Keith MolenaarLuis F. Alarcón, David B. Ashley,

Angelique Sucre de Hanily and Ricardo Ungo

September 30, 2010Construction Engineering Conference:

Opportunity and Vision for Education, Practice, and Research

Presentation Outline

1. Motivation for risk analysis on Canal Expansion

2. The project risk management approach

3 Lessons learned 3. Lessons learned

Expansion Background

• ACP formally proposed projectwith public referendum in 2006

• What was the constructionmarket like in 2000-2006?

Page 2: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

History of Mega Projects

• Tren Urbano Rail, Puerto Rico1

– 1996 Estimated $1.25 billion

– 2002 Estimated $2.25 billion

• The Big Dig, Boston2

1985 E ti t d $2 5 billi– 1985 Estimated $2.5 billion

– 2002 Estimated $14.6 billion

• Flyvbjerg Study (2002)– 256 public project over 70 years

– 8 of 10 project had cost overruns

11 Federal Transit Administration Inspector General 2004Federal Transit Administration Inspector General 20042 2 National Academy of Sciences 2003National Academy of Sciences 2003

History of Mega Projects

• New cost estimating and cost management methods research

New Cost Estimating Methods

• 18 primary cost escalation factors

• 8 strategies to address cost8 strategies to address costescalation factors

• 30 implementation methods

• 90 tool applications

Page 3: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

New Cost Estimating Methods

• Risk StrategyIdentify risks, quantify their impact on cost their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed.

Canal Expansion – A risky project?

New Locks: Water-Saving Basins and Rolling Gates

Bottom- or side-filling?

Page 4: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Page 5: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Unrecognized Costs(Unknown/Unknowns)

t C

ost

Baseline

Contingency

Known but not Quantifiable Costs(Known/Unknowns)

Project Baseline Cost

Pro

jec

Project Development Process

Project Planand Concept

30%Design

100%Design

ConstructionCompletion

Conservative Estimate with allowance at any pointKnown and

Quantifiable Costs(Known/Knowns)

Financial Risk Model

Consultants Guidance

Input from Other Units

Risk Model Approach Multidisciplinary Team Approach

Program Development Office- Risk identification

- Coordination

Engineering - Design- Cost Estimate

Finance- Risk variables- Others

Page 6: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

More Detailed Analysis - 350 Risks

Risks identification AON, Value Management & ACP

More Detailed Analysis - 185 Risks

Workshop with ACP

Risk Model Approach Redefine Risks to be Modeled

pPersonnel

More Detailed Analysis - 40 Risks

Risks identification AON, Value Management & ACP

14 Key Risks forRisk Model

Factorsf Ri k

OrganizationRisks

Lack ofControls

InefficientPlanning

InefficientGeneral Referendum

Major Risk Factors for Risk Modeling

for Risk Modeling

ContractingProcess

GeneralInflation

ReferendumDelays

ExtremeBad Weather

Owner DrivenChanges

InsufficientRevenues

Inadequate Claims

Administration

Local LaborStrikes

Changes inDesign and Quantities

Lack of Skilled andLocal Labor

Material,Equipment and

Labor Cost Increases

Organizational risksOrganizational risks

Insufficient revenuesInsufficient revenues

MARKET

Risk Factor Categorization

Inflation Inflation

Poor claims administrationPoor claims administration

Material, equip. & labor cost increasesMaterial, equip. & labor cost increases

OVERRUNS

Lack of controlsLack of controls

Inefficient planningInefficient planning

Inefficient contractingInefficient contracting

Referendum delaysReferendum delays

Extreme bad weatherExtreme bad weather

Local labor strikesLocal labor strikes

Owner driven changesOwner driven changes

Changes in design & quantitiesChanges in design & quantities

Lack of skilled and local laborLack of skilled and local labor

DELAYS

Page 7: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Risk Model ResultsExample Total Cost

0.18

0.16

0.14

0.12

Distribution for Investment + Delay & Overrun

Total

Mean

Total costw / contingency

0.10

0.08

0.06

0.04

0.02

0.00

Risk Model ResultsExample Total Cost

0.16

0.14

0.12

0.10

Distribution for Commissioning Year

Total

Mean

Total costw / contingency

0.08

0.06

0.04

0.02

0.00

g y

Risk Model ResultsTornado Diagram

Factors with the greatest

Material X - Atlantic Locks

Event X

Material Y - Atlantic Locks

Productivity X - Access Channel

Delay Activity X

Material X - Pacific Locksthe greatest impact on total cost variation

Event Y

Material Z - Atlantic Locks

Event Y - Pacific Locks

Productivity x - Pacific Locks

Locks Delay Activity Y

Productivity Y - Pacific Locks

Locks Event Z

Material Z - Pacific Locks

Page 8: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Risk Mitigation Options

Risk ResolutionTotal Contingency

Contingency Management

Contingency

Lessons Learned

• Impact of project on country– Referendum– Communications

• Benefits of bottom-up contingency• Use of risk analysis and management• ACP’s willingness to innovate

Page 9: Risk Planning and Management for the Panama Canal ... · Management for the Panama Canal Expansion Program Keith Molenaar Luis F. Alarcón, David B. Ashley, Angelique Sucre de Hanily

Las Vegas Executives AssociationPresentation

Risk-Based Models for Project Planning

Edited per 1/15/08 Meeting

David B. AshleyPresident

University of Nevada, Las Vegas

January 30, 2008

Thank you!Thank you!