Risk management presentation 2

download Risk management presentation 2

of 24

Transcript of Risk management presentation 2

  • 7/25/2019 Risk management presentation 2

    1/24

  • 7/25/2019 Risk management presentation 2

    2/24

    RISK MANAGEMENT IN

    CONSTRUCTION

    MBA 3 SEMESTER

    LECTURES 24 AUG 15 & 25 AUG 15

  • 7/25/2019 Risk management presentation 2

    3/24

    APPROACHES TO RISK IDENTIFICATIO

    TOP DOWN

    BOTTOM UP

  • 7/25/2019 Risk management presentation 2

    4/24

    RISK MANAGEMENT-STEPS?

  • 7/25/2019 Risk management presentation 2

    5/24

    WHAT DOES RISK MANAGEME

    INVOLVE?

    IDENTIFICATIONANALYSIS/ASSESSMENT-

    PRIORITIZATION OF RISKS

    ACTION PLANMONITORING &

    CONTROL

  • 7/25/2019 Risk management presentation 2

    6/24

    WHAT DOES RISK IDENTIFICATION INVOL

    1. PROCESS (??) OF DETERMINING:

    WHICH RISKS MAY AFFECT PROJECTOBJECTIVES?

    WHAT THEIR CHARACTERISTICS COULD

    2. KEY BENEFIT:?DOCUMENTATION OF EXISTING RISKS PROVIDES KNOWLEDGE AND ABILITY TO ANT

    EVENTS/FUTURE RISKS.

  • 7/25/2019 Risk management presentation 2

    7/24

    ITERATIVE PROCESS ??

    NEW RISKS MAY EVOLVE DURINGPROJECT LIFE CYCLE.

    FREQUENCY & DURATION VARWITH SITUATION.

  • 7/25/2019 Risk management presentation 2

    8/24

  • 7/25/2019 Risk management presentation 2

    9/24

    KEY PARTICIPANTS-RISK IDENTIFICATION ACTIVITI

    PROJECT MANAGER

    PROJECT TEAM MEMBERS

    RISK MANAGEMENT STAFF (IF ASSIGNED)

    CUSTOMERS

    SUBJECT MATTER EXPERTS (EXTERNAL & INTERN

    END USERS

    OTHER PROJECT MANAGERS

    OTHER STAKEHOLDERS

    RISK MANAGEMENT EXPERTS

  • 7/25/2019 Risk management presentation 2

    10/24

    1. TOP DOWN APPROACH-Con

    OUTPUT OF OTHER PROCESSESBE REVIEWED TO IDENTIFYPOSSIBLE RISKS ACROSS THE

    PROJECT PROVIDES RAPID START TO THASSESSMENT.

  • 7/25/2019 Risk management presentation 2

    11/24

    1. TOP DOWN APPROACH

    STARTS WITH AN OVERALL VIEOF PROGRAMME.

    REQUIRES UNDERSTANDING OPROJECTS MISSION, SCOPE ANOBJECTIVES OF OWNER, SPONAND/OR STAKEHOLDERS.

  • 7/25/2019 Risk management presentation 2

    12/24

    IMPLICATIONS-TOP DOWN APPROACH

    ALL DIRECTIONS COME FROM THE TOP & PROJECT OBJECTIESTABLISHED BY THE TOP MANAGEMENT.

    TOP MANAGERS PROVIDE RISK GUIDELINES, INFORMATIONAND FUND PROCESSES.

    ALL OF THE PROJECT MANAGERS EXPECTATIONS ARE CLEACOMMUNICATED TO EACH PROJECT PARTICIPANT.

    FOLLOWING THIS APPROACH, AMBIGUITY OPENS THE DOO

    POTENTIAL FAILURE-OFTEN RESULTS IN REDUCEDPRODUCTIVITY AND CAUSES BOTTLENECKS.

    THERE WAS NO EFFECTIVE COLLABORATION BETWEEN THEMEMBERS. THEY WERE NOT MORALLY MOTIVATED TO DO JOBS

  • 7/25/2019 Risk management presentation 2

    13/24

    2. BOTTOM UP APPROACH

    SYSTEMATIC AND COMPREHENSIVE

    CONSIDERATION OF PROJECT MANAGEMAND TECHNICAL DELIVERABLES.

    EXAMINES THE PROJECT REQUIREMENTSPLANS, SPECIFICATIONS, RESOURCES,

    CONTRACTS, CONTRACTOR, SUB CONTRACHARACTERISTICS AND PROJECT INTERFAAND INTERACTIONS TO IDENTIFY RISKS.

  • 7/25/2019 Risk management presentation 2

    14/24

    IMPLICATIONS OF BOTTOM UP APPROACH

    TEAM MEMBERS INVITED TO PARTICIPATE IN EVERY

    OF RISK IDENTIFICATION PROCESS.

    THE DECISION ON A COURSE OF ACTION IS TAKEN BWHOLE TEAM.

    IT ALLOWS MANAGERS TO COMMUNICATE GOALS AVALUE, E.G. THROUGH MILESTONE PLANNING.

    TEAM MEMBERS ENCOURAGED TO DEVELOP PERSODO LISTS WITH STEPS NECESSARY TO REACH MILESTON THEIR OWN.

  • 7/25/2019 Risk management presentation 2

    15/24

    IMPLICATIONS OF BOTTOM UP APPROAC

    THECHOICE OF METHODS

    & WAYS TO PERFORM THEIR TAS

    TO THE TEAM.

    ADVANTAGE OF THIS APPROACH- EMPOWERS TEAM MEMB

    THINK MORE CREATIVELY.

    THE TEAM MEMBERS MOTIVATION TO WORK AND MAKE

    MANAGEMENT OF PROJECT A SUCCESS IS DOUBLED. THE PLANNING PROCESS IS FACILITATED BY A NUMBER OF

    WHICH MAKES IT FLOW SIGNIFICANTLY FASTER

  • 7/25/2019 Risk management presentation 2

    16/24

  • 7/25/2019 Risk management presentation 2

    17/24

    THE BEST WAY IS TO FIND

    A BALANCE BETWEEN THE TWOOPPOSITE APPROACHES AND TATHE BEST PRACTICES FROM BOT

    THEM

  • 7/25/2019 Risk management presentation 2

    18/24

    COMMON FORM OF RISKS

    ABSENCE OF LABOUR/STAFF

    SUDDEN RESIGNATION OF KEY STAFF

    STAFF DIVERTED BY ORGANISATION

    ADDITIONAL STAFF/SKILLS NOT AVAILABLE

    TRAINING NOT EFFECTIVE

    INITIAL SPECS OR DRAWINGS INCOMPLETE/POORLY DRAFT

    WORK ON CHANGE ORDERS MULTIPLY DUE TO PROBLEMS

    ENHANCEMENT OF WORK TAKES LONGER THAN EXPECTED

  • 7/25/2019 Risk management presentation 2

    19/24

    CLASSIFICATION OF RISKS FINTECO EX

    FINANCIAL

    TECHNICAL

    COMMERCIAL

    EXECUTION

    CONTRACTUAL OR LEGAL

  • 7/25/2019 Risk management presentation 2

    20/24

    FINANCIAL RISK

    FINANCIAL EXPOSURE-EG. LARGE CAPITAINVESTMENT REQUIRED TO DEVELOPPROJECT

    WITHOUT CONTRACTED BUYER PRIOR TO

    CONSTRUCTION-MAJOR FINANCIAL RISKHOPE OF SELLING OFFICE SPACE OR BUILDAFTER IT IS COMPLETED

  • 7/25/2019 Risk management presentation 2

    21/24

    TECHNICAL RISK

    MAXIMUM RISK-UNIQUE TECHNICAL

    ELEMENTS OR UNPROVEN TECHNILOGYMINIMUM RISK- IF ONLY MODIFICATION

    ALREADY DEVELOPED DESIGN

    LEVEL OF TECHNICAL RISK DIRECTLYPROPORTIONAL TO UNDERPERFORMANCMEETING SPECIFIED REQUIREMENTS

  • 7/25/2019 Risk management presentation 2

    22/24

    COMMERCIAL RISKS

    PROJECTS DEVELOPED FOR COMMERCIAL

    PURPOSE-EG. RECEIVING REVENUES-DEGCOMMERCIAL SUCCESS IS UNKNOWN ONINTRODUCED IN MARKET

    UNCERTAINTY, COMPANIES WILLINGLY AC

    AS IT IS VIRTUALLY IMPOSSIBLE TO PREDICUSTOMER ACCEPTANCE/DEMAND OF NSERVICE/PRODUCT

  • 7/25/2019 Risk management presentation 2

    23/24

    EXECUTION RISK

    GEOGRAPHICAL OR PHYSICAL CONDITIONS/UNKNOWNS

    POORLY TRAINED OR INSUFFICIENT PROJECT TEAM PERSO

    UNCERTAINTY OF SUFFICIENT LOCAL MATERIALS OR OPPO(ABUNDANCE OF )-AN OPPORTUNITY!!

    UNCERTAINTY ABOUT AVAILABILITY/BREAKDOWN OF CRIT

    PLANT OR EQUIPMENT UNCERTAIN WEATHER/ADVERSE CLIMATE OR ENVIRONME

    ADVERSE TRAFFIC CONDITIONS/LAW & ORDER

  • 7/25/2019 Risk management presentation 2

    24/24

    CONTRACTUAL/LEGAL RISKS

    SUCH RISKS CONSISTENT WITH STRICT TEAND CONDITIONS DRAWN UP IN ADVAN

    LIQUIDATED DAMAGES/FIXED COST TYPECONTRACTUAL CONDITIONS/STRUCTURE

    SIGNIFICANT RISKS FOR CONTRACTORSUNCERTAINTY OF HANDING OVER

    LAND/ENVIRONMENTAL CLEARANCES