Risk Management in Ppp Projects

download Risk Management in Ppp Projects

of 28

Transcript of Risk Management in Ppp Projects

  • 8/23/2019 Risk Management in Ppp Projects

    1/28

    1J

    Risk Management in PPP ProjectsMormugao, 21st September, 2007

  • 8/23/2019 Risk Management in Ppp Projects

    2/28

    2J

    Agenda Overview of Risks in PPP Contracts

    Types of risk

    Mitigation strategies

    Case Studies

    Mumbai Pune Express way

    Mundra Port

    Mumbai Metro

    Conclusions

  • 8/23/2019 Risk Management in Ppp Projects

    3/28

    3J

    Sources of RiskGovernment

    Target Market

    Devel

    opers

    Risks in a typical

    PPP project

    Demand

    Legal & Regulatory

    Framework

    Contracts

    Construction

    O & M

  • 8/23/2019 Risk Management in Ppp Projects

    4/28

    4J

    Risks in PPP ProjectsPolitical

    Force Majeure

    Risk

    Market Risk

    Regulatory

    Operational &

    Maintenance

    Financial Risk

    Cost OverrunRisk

    Land Acquisition

    Risk

    Commercial

    Technology Risk Construction

    Risk

    RISKS

    RISKS

  • 8/23/2019 Risk Management in Ppp Projects

    5/28

    5J

    Risk Categories, Phase of Dominance and Allocation

    - Social risk

    - Nationalization or revocation

    - Events of warsInstitution/Private partyThroughout Project Cycle

    Political & social risk

    Institution/Private partyConstruction/Operations PeriodEnvironmental risk

    Institution/Private partyThroughout Project CycleForce Majeure

    Private partyThroughout Project CycleInsolvency and outside creditor risk

    Private partyOperations PeriodTermination risk

    - Inflation risk

    - Tax rate change risk

    - Foreign exchange exposure risk

    - Interest rate riskPrivate partyOperations Period

    Financial risk

    Private partyOperations PeriodOperations & maintenance risk

    Private partyOperations PeriodCommercial risk

    Institution/Private partyOperations PeriodRegulatory & administrative risk

    Private partyConstruction/Operations PeriodTechnology riskPrivate partyConstruction PeriodProject cost risk/Cost over-runs

    Private partyConstruction PeriodProject completion risk

    - Planning risk

    - Design risk Private partyProject Development

    Delays in project developmentInstitution/Private partyProject DevelopmentLand acquisition

    Allocation of riskPhase of dominanceRisk Categories

  • 8/23/2019 Risk Management in Ppp Projects

    6/28

    6J

    Risk Mitigation StepsDetermineSeverity of

    Risk

    AllocateRisk

    Mitigate theRisk

    IdentifyRisk

    Price theRisk

    Identifying

    the eventsor Actions

    which

    Effects the

    Viability of

    the Project

    In Case the

    Event occurthe effect of

    the same on

    the cost /

    time of the

    project

    Identifying

    and

    allocatingthe risk to

    the party

    who can

    manage it

    best

    Steps /

    actionswhich can

    be taking to

    reduce the

    chances of

    the eventoccurring

    Cost ofaddressing

    the risk have

    to be

    determined

  • 8/23/2019 Risk Management in Ppp Projects

    7/28

    7J

    Management of Risks What ?

    Time and Cost Overruns or shortfall in performance parameter of

    the competed project

    Why? High capital intensity and a relatively long construction period

    How to Mitigate? Engineering, procurement, and construction contracts to an

    experienced and reputed firm

    Provisions for liquidated damages in the contract(s)

    Construction Risk

  • 8/23/2019 Risk Management in Ppp Projects

    8/28

    8J

    Management of Risks What ?

    Technical performance of the project during its operational phase

    can fall below the levels projected by investors

    Why? Technology is untried or is changing rapidly or inability of the

    operator to manage such big and complex project i.e. Metro

    How to Mitigate?

    Entrusting operation to experienced operations and maintenance

    contractors

    Provisions for liquidated damages in the contact(s)

    Insurance against Force Majeure risks

    Operations Risk

  • 8/23/2019 Risk Management in Ppp Projects

    9/28

    9J

    Management of Risks What ?

    Possibility that market conditions assumed in determining the

    viability of the project are not realized. Non fulfillment of demand

    projections is an obvious example

    Why?

    Uncertainty in the forecast of the demand projections

    How to Mitigate?

    Investors enter into a contract with the monopoly purchaser to

    guarantee a minimum level of purchase.

    Market/Demand Risk

  • 8/23/2019 Risk Management in Ppp Projects

    10/28

    10J

    Management of Risks What ?

    Interest rates can vary during the life of the project (construction

    and payback period)

    Why? High capital intensity (large impact) and long payback periods

    (Risk spread over a long time). Interest cost is a large component of

    the total project cost

    How to Mitigate?

    Pass it on to consumers, as, for example, in arrangements in which

    the impact of interest rate variations on unit costs are treated as apass-through into the tariff

    Using hedging instruments

    Interest Rate Risk

  • 8/23/2019 Risk Management in Ppp Projects

    11/28

    11J

    Management of Risks What ?

    Risk of not being paid for services delivered

    Why?

    Financial condition of public sector utilities in developing countries

    is often very weak. These utilities are often the monopoly / large

    buyer for example power and water

    How to Mitigate?

    Long term solution is to improve the financial condition of the

    utilities by improvement in efficiencies or privatization

    Short term, guarantee and counter guarantee by state and centralgovernment

    Set up an escrow arrangement

    Payment Risk

  • 8/23/2019 Risk Management in Ppp Projects

    12/28

    12J

    Management of Risks What ?

    Any disruption in construction or operation of a project due to

    regulatory changes

    Why? Infrastructure projects have to interface with various regulatory

    authorities throughout the life of the project, making them

    especially vulnerable to regulatory action

    How to Mitigate?

    By establishing strong and independent regulatory authorities that

    operate with maximum transparency of procedures within a legalframework that provides investors with credible recourse against

    arbitrary action

    Regulatory Risk

  • 8/23/2019 Risk Management in Ppp Projects

    13/28

    13J

    Management of Risks What ?

    Any disruption in construction or operation of a project due to

    political decisions

    Why? Infrastructure projects have high visibility, and there is always a

    strong ele-ment of public interest. This makes them vul-nerable to

    political action that can interrupt or upset settled commercial

    terms; in extreme cases it can even lead to cancellation of licenses

    or nationalization.

    How to Mitigate? Partially mitigated through political risk insurance offered by

    multilateral organizations, such as the Multilateral Investment

    Guarantee Agency, or bilateral investment protection agreements.

    Political Risk

  • 8/23/2019 Risk Management in Ppp Projects

    14/28

    14J

    Typical Risk Allocation in India

    NoNoNoNoNoYesSub-

    ContractorEPC Contractor

    YesNoNoNoNoNoAwarding

    AgencyGovernment

    NoYesNoNoNoNoLenderLenders

    YesYesYesYesYesNoPromoterEquity Holders,

    Developer

    RegulatoryRisk

    Interest

    RateRiskMarketRiskRevenueRiskOperationRiskConstructionRiskRoleRiskParticipants

    Developer carries all type of risk in India unlike UK and

    other Latin American Countries where governmentguarantee minimum revenue and share the same also in

    case that exceeds threshold limit

  • 8/23/2019 Risk Management in Ppp Projects

    15/28

    15J

    Management of Risks

    HighHighProjectSpecific

    LowLowMediumPower

    MediumLowProject

    Specific

    HighHighHighAirport

    LowLowProjectSpecificMediumMediumHighPort

    MediumMediumProject

    Specific

    Project

    Specific

    LowHighRoad

    Regulatory

    Risk

    Payment

    Risk

    Interest

    Rate Risk

    Market

    Risk

    Operation

    Risk

    Construction

    Risk

    Type of

    Project

    Market Risk versus Payment Risk

  • 8/23/2019 Risk Management in Ppp Projects

    16/28

    16J

    Agenda Overview of Risks in PPP Contracts

    Types of risk

    Mitigation strategies

    Case Studies

    Mumbai Pune Express way

    Mundra Port

    Mumbai Metro

    Conclusions

  • 8/23/2019 Risk Management in Ppp Projects

    17/28

    17J

    Mumbai Pune Expressway Total Project Cost

    Rs 2136 crores

    Initial estimate

    Rs 1600 crores

    Time taken

    3 years

    Physical land acquired

    1030 ha

    Contractors appointed:

    IJM / SCL Joint Venture

    Hindustan Construction Co. Mumbai

    Larsen and Toubro Ltd. Mumbai

    V.M. Jog Engineering Ltd. Pune

    Konkan Railway Corporation Ltd

    Operation & Maintenance:

    Ideal Road Builders (IRB)

  • 8/23/2019 Risk Management in Ppp Projects

    18/28

    18J

    Mumbai Pune Expressway

    Risks borne by MSRDC

    Land acquisition

    Specific project clearances Political

    Non-insurable Force Majeure

    Water & Power Availability at

    source Project completion

    Risks borne by Private party

    Design

    Construction Operation & Maintenance

    Project cost

    Financing

    Revenue

    Technology

    Insurable Force Majeure

    Risk Allocation

  • 8/23/2019 Risk Management in Ppp Projects

    19/28

    19J

    Mumbai Pune ExpresswayRisk mitigation by MSRDC

    Different consultants appointed for

    the purpose of detailed engineering

    and for construction supervision ofworks

    Land acquisition and clearances for

    tree felling, forest clearing etc.

    obtained beforehand

    Environmental impact assessment

    carried out by external agencies

    Strong political will

    Providing power through 8 MSEB

    substations Removing/diverting utility service

    lines (power, telephone, water &

    sewer) coming in alignment

    Risk mitigation by Private party

    Pre-approved designs for the

    respective road segments Financial SOPs from GoM (Tax,

    imports etc.)

    Contractual and legal shield

    Employing state-of-the-art

    technology for carrying out theconstruction work

    Subcontractors working under tight

    clauses

    Absorption of certain costescalations by MSRDC

  • 8/23/2019 Risk Management in Ppp Projects

    20/28

    20J

    Mumbai Pune Expressway Total Project cost

    Rs 2151 crores

    Multi-terminal greenfield portdeveloped through PPP by the state of

    Gujarat

    Commenced operations in 1999

    Traffic is at 8 MMTA

    Was one of the first ports to securerail connectivity by putting up the

    investment for it through PPP (Rs 136crores)

    Private party

    Gujarat Adani Port Ltd. (GAPL) and P&O

  • 8/23/2019 Risk Management in Ppp Projects

    21/28

    21J

    Mumbai Pune Expressway

    Risks borne by GoG/GMB

    Revenue

    Regulatory & administrative Political & social

    Creditor

    Environmental

    Risks borne by Private party

    Design & Construction

    Operation & Maintenance Subcontractor

    Financing

    Revenue

    Financial

    Technology

    Environmental

    Connectivity Rail, Road

    Risk Allocation

  • 8/23/2019 Risk Management in Ppp Projects

    22/28

    22J

    Mumbai Pune ExpresswayRisk mitigation by GoG/GMB

    Traffic risk sharing

    Required clearances obtained

    beforehand

    Transparent and clear-cut

    BOOT policy in place

    Sustained political support to the

    non-major port development

    cause

    Various bodies constituted for

    reviewing and monitoring the

    PPP process

    Risk mitigation by Private party

    30 years Concession agreement

    with GMB Future development rights and

    sub-concession contracts

    Tariff set by P&O (independent

    of TAMP) Developed own rail connectivity

    Heavy machinery & equipments

    taken on lease basis

    GAPL sold stake to P&O ports

  • 8/23/2019 Risk Management in Ppp Projects

    23/28

    23J

    Mumbai Metro Total Project cost

    Rs 2356 crores

    First phase

    2006-11

    Commencement of Operations

    2009-10

    Mass transit corridor from Andheri to

    Ghatkopar

    First MRTS project in India beingimplemented on Public PrivatePartnership (PPP) format

    DMRC (Delhi Metro Rail Corporation)prepared the master plan for Mumbaimetro

    Private party

    Reliance Energy Ltd

  • 8/23/2019 Risk Management in Ppp Projects

    24/28

    24J

    Mumbai Metro

    Risks borne by MMRDA

    Land acquisition

    Force Majeure Environmental

    Political & social

    Risks borne by Private party

    Design & Construction

    Operation & Maintenance Subcontractor

    Financing

    Revenue

    Financial

    Technology

    Project completion

    Environmental

    Risk Allocation

  • 8/23/2019 Risk Management in Ppp Projects

    25/28

    25J

    Mumbai MetroRisk mitigation by MMRDA

    Detailed feasibility study carried

    out by TEWET in associationwith DE-Consult & TCS, during

    1997-2000

    Plan updated by MMRDA in

    2004

    Clearances obtained

    beforehand

    Deep political backing by GoM

    Risk mitigation by Private party

    35 years Concession agreement

    with MMRDA Contractual & legal shield

    Capital contribution of Rs 650

    crores with a 70:30 debt-equity

    ratio Independent parties assigned

    the review and monitoring job

    Technical consultants appointed

    for planning & reviewing theengineering & construction

    phase

    Insurance coverage for certain

    Force Majeure

  • 8/23/2019 Risk Management in Ppp Projects

    26/28

    26J

    Agenda Overview of Risks in PPP Contracts

    Types of risk

    Mitigation strategies

    Case Studies

    Mumbai Pune Express way

    Mundra Port

    Mumbai Metro

    Conclusions

  • 8/23/2019 Risk Management in Ppp Projects

    27/28

    27J

    Conclusions PPP Projects are complex projects that require effective

    attention to risk and their mitigation

    Risks are inherently related to returns and theservice/expertise which yields those returns

    This gives a good perspective on who is best placed to bear the risk

    Objectives of the government in taking up a ppp project is essential todecide who bears a particular risk

    PPPs in Western India

    Very active as compared to other parts of the country and ever increasingactivity

    Activity is mainly confined to transportation sector

    However some landmark projects have failed because risks were notproperly identified

    Some General Principles in Risk Management

    Thoroughness in identification of risks

    Lessons from similar projects

    Should be borne by party best placed to bear it

    Quantification of financial impact to the extent possible

    Thoroughness of documentation

  • 8/23/2019 Risk Management in Ppp Projects

    28/28

    28J

    Thank You!