Risk Level Determination (RLD) for the Construction General Permit (CGP)

54
December 2010 Risk Level Determination (RLD) for the Construction General Permit (CGP) December 7, 2010

description

Risk Level Determination (RLD) for the Construction General Permit (CGP). December 7, 2010. Agenda. Introductions. Meet the Presenters. Facilitator : Jeff Bold Presenter : Tim Sobelman Q&A Panel : Tim Sobelman Robert Schott Mike Marti. Agenda. - PowerPoint PPT Presentation

Transcript of Risk Level Determination (RLD) for the Construction General Permit (CGP)

Page 1: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010

Risk Level Determination (RLD) for theConstruction General Permit (CGP)

December 7, 2010

Page 2: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Agenda

2

Page 3: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Meet the Presenters

Facilitator: Jeff Bold

Presenter: Tim Sobelman

Q&A Panel: Tim Sobelman

Robert Schott

Mike Marti

3

Page 4: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Agenda

4

Page 5: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Communication During Webinar

Your phone is automatically muted.

Please submit your questions electronically on the Q/A portion of your screen.

Questions will be addressed after the presentation is completed.

5

Page 6: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Agenda

6

Page 7: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans CGP Guidance

Division of Environmental Analysis – Webinars, Water Quality Dispatch, etc.http://www.dot.ca.gov/hq/env/stormwater/cgp/index.htm

Division of Construction – CPD/CPB, SWPPP Preparation Manual, etc.http://www.dot.ca.gov/hq/construc/stormwater/stormwater1.htm

Division of Design – Risk Level Determination Guidance, CGP Cost Estimating,

Specifications, etc.– Risk Level Determination (RLD) Webinar– RUSLE2 Training (RL Determination module)

7

Page 8: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Risk Level Determination

Today’s presentation will:

1) Discuss what Risk Levels mean to a Caltrans Construction Sites2) Describe the site-specific data that is needed to conduct a RL

Determination 3) Discuss the programs/websites that are available to obtain the site

data4) Go over two Methods of conducting a RL Determination 5) Answer questions related to calculating a project Risk Level

8

Page 9: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans Project RLD Guidance

http://www.dot.ca.gov/hq/oppd/stormwtr/index.htm

Goals:- Determine appropriate Risk

Level for each site:- Accurate Slope Length and

Steepness values - Construction during dry seasons

could reduce sediment risk- GIS Map / Individual Method

9

Page 10: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Risk Level Determination Factors

Completed for pre-construction conditions Only two factors determine Risk Level:

– Sediment– Receiving Water

3 possible Risk Levels

10

Page 11: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Combined Risk Level

For each project sediment and receiving water risks are combined

Combined Risk Levels: 1 2 3 low medium high

11

Page 12: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

What does Risk Level 1 mean?

Level 1 SWPPP Requirements for a QSD/QSP Visual monitoring Annual reports

Combined Risk Levels: 1 2 3 low medium high

12

Page 13: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

What does Risk Level 2 mean?

Combined Risk Levels: 1 2 3 low medium high

Level 2 = Level 1 requirements plus: Rain Event Action Plan (REAP) Numeric Action Level (NAL)

– pH 6.5-8.5, – turbidity < 250 NTU

Storm water sampling during rain events

13

Page 14: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

What does Risk Level 3 mean?

Combined Risk Levels: 1 2 3 low medium high

Level 3 = Level 1 + Level 2 requirements plus: Numeric Effluent Limits (NEL)

- pH 6.0 – 9.0 - turbidity < 500 NTU

Receiving water sampling during rain eventsConduct bioassessment testing on sites > 30 acres

14

Page 15: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

RLD – Where to start…

http://www.swrcb.ca.gov/water_issues/programs/stormwater/constpermits.shtml

Appendix 1 - Risk Determination Worksheet (select ‘Excel’)

15

Page 16: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Open SWRCB Excel fileGIS Map Method

Use GIS Map Method to determine: Step 1) Sediment RiskStep 2) Receiving Water RiskStep 3) Combined Risk Level

16

GIS Method is used at each phase (PID, PAED, PS&E). Document in the Storm Water Data Report.

Page 17: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk Factors

Based on Revised Universal Soil Loss Equation (RUSLE) Soil loss (tons/acre/year) = R • K • L • S • C • P

R = rainfall erosivity (EPA website)K = soil erodibilityL = length of slope S = slopeC = coverP = practices

C and P are assumed to be constant; no data needed for risk calculation

17

Page 18: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Step 1 - Sediment Risk

1) Locate site2) Obtain KLS3) Calculate R4) Sediment Risk = R • KLS

18

Page 19: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Truckee Bypass

Project located adjacent to the Truckee River

39°20’23.44” N; 120°10’16.20” W 19

Page 20: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Rainfall Erosivity (R)

Enter site name, project duration

20

http://cfpub.epa.gov/npdes/stormwater/LEW/lewCalculator.cfm

Page 21: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Rainfall Erosivity (R)

Enter site location (latitude/longitude)

21

Page 22: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Rainfall Erosivity (R)

For a 13 month job:

R = 10.34

22

Page 23: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk - KLS GIS Map

1) Locate site2) Obtain KLS

23

Page 24: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk - KLS GIS Map

KLS = 1.6

Truckee Bypass Project

24

Page 25: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Calculate Sediment Risk

Sediment Risk = R • KLS

= 10.34 • 1.6

= 16.54

Low: <15 tons/acreMedium: ≥15 to <75 tons/acreHigh: ≥75 tons/acre

Medium Sediment Risk

25

Page 26: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk

Change from a 13 month project to a 12 month project

R declines from 10.34 to 9.03

= 9.03 • 1.6

= 14.45

Low: <15 tons/acreMedium: ≥15 to <75 tons/acreHigh: ≥75 tons/acre

LOW Sediment Risk

26

Page 27: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Step 2 - Receiving Water (RW) Risk

Locate watershed and identify receiving water body

TMDL and/or 303(d) listed for sediment?OR

Designated Beneficial Uses? • Spawn and• Cold and• Migratory

If No to both – Low RW riskIf Yes to either – High RW risk

27

Page 28: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Water Quality Planning Tool

http://www.owp.csus.edu/research/stormwater/tools/wqpt.htm

Locates site, watershed by Post-Miles

28

Page 29: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Water Quality Planning Tool

TMDL & 303(d)listed waterbodies

Receiving Water located in Truckee River Watershed

Truckee River TMDL listed forsediment

29

Page 30: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Water Quality Planning Tool – Truckee River

Spawn

Migratory

Cold

30

Page 31: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Receiving Water Risk Estimate – Truckee River

TMDL sediment – Yes Cold+Spawn+Migratory – YesReceiving Water = High Risk

31

Page 32: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Combined Risk Level

Sediment Risk = Low

Receiving Water Risk = High

Combined Risk = Level 2

32

Page 33: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk – Individual Method

Use when detailed analysis may produce more favorable RLD

Consider Individual Method at PS&E (unless detailed project information is available earlier).

Document in the Storm Water Data Report.

33

Page 34: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Individual vs GIS Map Methods

34

Page 35: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk – Individual Method

35

Page 36: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Individual Method - Sediment Risk Factor Worksheet

R Factor

K Factor

LS Factor

Sediment Risk

36

Page 37: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

How do we get the data?

R, K factors require latitude/longitude

Sources for latitude/longitude:1) Web Browser Post Mile Query Tool (Caltrans website)

2) Google Earth

3) Caltrans District 8 GIS website: http://sv08arcgis/cgp2009/

37

Page 38: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Soil Erodibility (K)

http://soils.USDA.gov

38

Page 39: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Soil Erodibility (K)

Find specific K factor for area of influence (AOI)

K = 0.24

39

Page 40: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Slope Length and Steepness (LS)

Example: weighted average for project area are:L = 50 feet, S = 50%

40

LS= 5.16

Page 41: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Sediment Risk – Individual Method

Sediment Risk was reduced from:

15.54 tons/acre (Med) (GIS MAP Method)

to

12.81 tons/acre (Low)(Individual Method)

41

Page 42: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Receiving Water Risk

Same as GIS Method

RW Risk = High

42

Page 43: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

RLD Truckee Bypass

43

Sediment Risk = Low(Individual Method)

Receiving Water Risk = High

Combined Risk Level 2

Page 44: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Alternative Rainfall Erosivity (R)

For a 5 year, 4 month job:

R = 49.74

44

Page 45: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Calculate Sediment Risk – GIS Map Method

Sediment Risk = R • KLS

= 49.74 x 1.6

= 79.58 (High Sediment Risk)

Low: <15 tons/acreMedium: ≥15 to <75 tons/acreHigh: ≥75 tons/acre

Risk Level 3

45

Page 46: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Calculate Sediment Risk – Individual Method

Sediment Risk = R • KLS

= 49.74 x 1.24

= 61.68 (Medium Sediment Risk)

Low: <15 tons/acreMedium: ≥15 to <75 tons/acreHigh: ≥75 tons/acre

Risk Level 2

46

Medium

Page 47: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans D8 GIS

District 8 has compiled a unique GIS http://sv08arcgis/cgp2009/ This GIS integrates many data sources to provide the user:

– Street and aerial photography location information– Sediment Risk – Latitude/Longitude (R), GIS map method (KLS),

individual method (K, R, topographic info)– Receiving Water Risk – draft SWRCB GIS

How to use D8 GIS described in Caltrans RLD Guidance

47

Page 48: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans District 8 GIS

On Caltrans website: http://sv08arcgis/cgp2009/

latitude and longitude

48

Page 49: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans District 8 GIS - Imagery

49

Page 50: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

K Factor - Caltrans District 8 GIS

K= 0.24

50

Page 51: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Caltrans District 8 GIS – Planning Watershed Boundaries

51

Page 52: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Summary

Which RLD method?– Start with GIS Map Method PID and PAED

• Simple, fast, conservative – Individual Method (optional) PS&E

• More detailed• Use when GIS method results in borderline

sediment risk

52

Page 53: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Where to go for more information?

This site contains: RLD Guidance RUSLE2 8-hour training course A recording of this presentation A copy of the Q&A Session

53

http://www.dot.ca.gov/hq/oppd/stormwtr/index.htm

Page 54: Risk Level Determination (RLD) for the Construction General Permit (CGP)

December 2010Webinar 1: Risk Level Determination

Agenda

54