Risk Assessment for Cable Laying
-
Upload
vinod-kumar -
Category
Documents
-
view
1.204 -
download
6
Transcript of Risk Assessment for Cable Laying
TASK DESCRIPTION EXACAVATION FOR CABLE LAYING DATE 06/06/2012
PROJECT LOCATION TRANSCO LDC REF NO TRA 03
S.No Activity Hazards Involved Consequences Probaility Risk Rating
Control Measures Residualrisk
ReasponsiblePerson
1 ExacavationFor Cable Trench by Hand Tools
- Damage Underground
facilities
- Excavation close to
electrical poles
- Trips, slips falling to the excavation
- Dust, Heat, noise and vibration
Environment / Property Damage
Property Damage
Property, and Personnel
Injury to personnel
M
M
M
M
H
H
M
M
- Trial pits made to establish services lines
- Cable detector-
- Use of updated underground facility layout Mark cable / piping routes
- Use of Hand Tools
Trial pits made to establish services lines
Proper access/egress to be provided(Ladder/Stair)
Proper PPE to be used (safety goggles, dust mask, car plug)
L
L
L
L
Supervisor
Supervisor
Supervisor
Supervisor
TASK DESCRIPTION EXACAVATION FOR CABLE LAYING DATE 06/06/2012
PROJECT LOCATION TRANSCO LDC REF NO TRA 03
S.No Activity Hazards Involved Consequences Probaility Risk Rating
Control Measures Residualrisk
ReasponsiblePerson
2 Cable Installation - Unauthorised work.Electrocution, fire.
- Electric shock. Fire.
Electric shockfrom livecircuit,shorting sparkswrongconnections,wrong item.
Electric shock. Property damage. Damage to test equipment
Environment / Property Damage
Property Damage
Property, and Personnel, depth
Injury to personnelProperty, and Personnel, death
M
M
M
M
H
H
M
M
Use proper Personal Protective Equipment when using electric power tools e.g face shields, rubber soled shoes
Always switch off power and pull out the plug before changing parts on the tool or making some adjustments.
Check with voltmeter that power is off.Switch off power on earth leakage.
Encourage electric hazard spotting among employees such as cracked plug etc and get them to report fault for remedial action.
L
L
L
L
Supervisor
Supervisor
Supervisor
Supervisor
TASK DESCRIPTION EXACAVATION FOR CABLE LAYING DATE 06/06/2012
PROJECT LOCATION TRANSCO LDC REF NO TRA 03
S.No Activity Hazards Involved Consequences Probaility Risk Rating
Control Measures Residualrisk
ReasponsiblePerson
3 Backfilling Using Hand tools
Employees working too close to each other with hand tools
Dust and heatEnvironmental Condition
Employees working too close to each other with hand tools
Improper use of tools
Environment / Property Damage
Property Damage
Property, and Personnel
Injury to personnel
M
M
M
M
H
H
M
M
employees will be informed through Tool box talks to work too close to each other and working task to be identified for each
Proper PPE to be used and Welfare facilities, cold water, shaded area, adequate rest period regularlyStand by vehicle should be available at site all time
Employees should not work not too close to each other and working task to be identified for each
Use the right tools for the right job
Hand tools should check and provide proper sticker to ensure the safety of the workers
Foreman to check if back fill procedure is being complied
L
L
L
L
Supervisor
Supervisor
Supervisor
Supervisor
TASK DESCRIPTION EXACAVATION FOR CABLE LAYING DATE 06/06/2012
PROJECT LOCATION TRANSCO LDC REF NO TRA 03
LIKELIHOOD CONSEQUENCES
Insignificant(Minor Problem Easily Handled by Normal Day to Day Processes)
Minor(Some Disruption Possible)
Moderate (Significant Time/Resources Required)
Major (operations severely damaged)
Catastrophic(Business Survival Is At Risk Damage)
Almost Certain(e.g, ˃90% chance)
High High Extreme Extreme Extreme
Likely(e.g, Between 50%and 90% chance)
Moderate High High Extreme Extreme
Moderate(e.g., Between 10 %and 50% chance)
Low Moderate High Extreme Extreme
Unlikely(e.g., Between 3% and 10% chance) Low Low Moderate High Extreme
Rare
(e.g., <3% chance) Low Low Moderate High High