LARRY J. RINGER LIBRARY
PROJECT PLAN
City Council Meeting June 12, 2014
PROJECT BACKGROUND
2008 Bond Authorization
Proposal adding approximately 15,000 SF/parking
Different proposals without clear scope of work
Ringer Library Operations Audit report April 2014
Council Presentation in May 2014
PROJECT PLAN
Proceed with project within framework of audit report recommendations
Summary of audit recommendations (13) Specific redesign recommendations (11)
PROJECT PLAN
Specific direction to not pursueCoffee shop / BookstoreComputer labA second branchAdditional book drops
General design principlesConsider long – term operational costsReceive staff inputRemember noise reduction
PROJECT SCHEDULE
RFQ advertises in July 2014
Short list interviews September 2014
Design contract award in October 2014
Design complete in October 2015
Construction complete in October 2016
PROJECT BUDGET
Budget: $8,385,000
Expended to date: $6,919.23
Balance: $8,378,080.77
Staff Recommendation:Proceed with design within framework of audit report recommendations