Rigid Pavement_1.docx
Transcript of Rigid Pavement_1.docx
![Page 1: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/1.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Table of Contents
Chapter 1..........................................................................................................................................3
Introduction......................................................................................................................................3
1.1 General...................................................................................................................................3
1.2 Rigid pavements....................................................................................................................3
Chapter 2..........................................................................................................................................5
Design Methodology and Analysis..................................................................................................5
2.1 General...................................................................................................................................5
2.2 Factors governing design.......................................................................................................5
2.3 Design period.........................................................................................................................5
2.4 Traffic consideration..............................................................................................................5
2.4.1 Design lane.....................................................................................................................5
2.4.2 Design Traffic.................................................................................................................5
2.5 Composition of traffic in terms of axles................................................................................9
2.6 Temperature Differential.......................................................................................................9
Composition and strength of foundation.....................................................................................9
2.7 Embankment Soil...................................................................................................................9
2.7.1 Subgrade.........................................................................................................................9
2.7.2 Subbase.........................................................................................................................11
2.8 Concrete strength.................................................................................................................11
2.9 Fatigue behaviour of cement concrete.................................................................................11
2.10 Design of Slab Thickness..................................................................................................12
2.11 Design of rigid pavement as per IRC: 58-2011.................................................................13
2.11.1 Design for pavement bonded option...........................................................................14
Chapter 3........................................................................................................................................15
Conclusion.....................................................................................................................................15
3.1 Conclusion...........................................................................................................................15
ASC Infratech Pvt. Ltd. Page | 1
![Page 2: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/2.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
LIST OF TABLES
Table No Page No
2.1 Diverted Traffic on Segment-III & Segment-IV 6
2.2 Estimation of traffic growth 7
3.1 Pavement Thickness at Location 1 15
LIST OF FIGURES
Figure No Page No
1.1 Typical Cross Section of Rigid Pavement 4
1.2 Elastic plate resting on viscous foundation 4
2.1 Chart Determining Effective CBR of Subgrade 10
ASC Infratech Pvt. Ltd. Page | 2
![Page 3: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/3.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Chapter 1
Introduction
1.1 General
A highway pavement is a structure consisting of superimposed layers of processed materials
above the natural soil sub-grade, whose primary function is to distribute the applied vehicle loads
to the sub-grade. The pavement structure should be able to provide a surface of acceptable riding
quality, adequate skid resistance, favourable light reflecting characteristics, and low noise
pollution. The ultimate aim is to ensure that the transmitted stresses due to wheel load are
sufficiently reduced, so that they will not exceed bearing capacity of the subgrade. Two types of
pavements are generally recognized as serving this purpose, namely flexible pavements and rigid
pavements. This report gives an overview about rigid pavement design.
1.2 Rigid pavements
Rigid pavements have sufficient flexural strength to transmit the wheel load stresses to a wider
area below. A typical cross section of the rigid pavement is shown in Figure 1.1 rigid pavements
are placed either directly on the prepared sub-grade or on a single layer of granular material.
Since there is only one layer of material between the concrete and the sub-grade, this layer can
be called as base or sub-base course.
In rigid pavement, load is distributed by the slab action, and the pavement behaves like an elastic
plate resting on a viscous medium as shown in Figure 1.2. Rigid pavements are constructed by
Portland cement concrete (PCC) and had analyzed by plate theory instead of layer theory,
assuming an elastic plate resting on viscous foundation. Plate theory is a simplified version of
layer theory that assumes the concrete slab as a medium thick plate which is plane before loading
and to remain plane after loading Bending of the slab due to wheel load and temperature
variation and the resulting tensile and flexural stress.
ASC Infratech Pvt. Ltd. Page | 3
![Page 4: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/4.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Fig 1.1 Typical Cross Section of Rigid Pavement
Fig 1.2 Elastic plate resting on viscous foundation
ASC Infratech Pvt. Ltd. Page | 4
![Page 5: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/5.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Chapter 2
Design Methodology and Analysis
2.1 General
For the present project Rigid pavement design has been considered at Toll Plaza locations.Rigid
pavement design methodology is based on the guidelines of IRC: 58-2011which has been used.
2.2 Factors governing design
Following are the main factors governing design of concrete pavements:
1. Design period.
2. Design commercial traffic volume.
3. Composition of traffic in terms of single, tandem, tridem and multi-axles.
4. Climatic conditions.
5. Composition and strength of foundation.
6. Lateral placement characteristics of commercial vehicles.
7. Directional distribution of commercial vehicles.
8. Axle load spectrum.
2.3 Design period
For rigid pavements, the initial pavement structure is designed and analyzed for a performance
period of 30 years.
2.4 Traffic consideration
2.4.1 Design lane
It is the lane which carrying the maximum number of commercial vehicles. Each lane of two-
lane two-way and the outer lane of multi-lane highways are to be considered as design lane.
2.4.2 Design Traffic
Seven day 24-hour count had made for estimating average daily traffic. Generally a minimum of
5percent annual growth rate of commercial vehicles shall be taken. The collected data consists of
both day and night traffic trends, so that bottom-up cracking (BUC) formed due to day time
traffic and top-down traffic (TDC) cracking caused due to night time traffic is analysed.
ASC Infratech Pvt. Ltd. Page | 5
![Page 6: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/6.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
2.4.2.1 Traffic analysis
The traffic at toll plaza locations is given in Table 2.1. (Refer table 1.21 in traffic report)
Table 2.1 Total Tollable Traffic at TVC-1 at CH-4 km
Total Tollable Traffic volumeTVC-1 at Ch:184 km
SL.No Type of vehicles PCU FactorNo of
VehiclesNo of Vehicles
PCU
1
Car/ Jeep / Van+ Taxi-car/ jeep/ van/Utility
1 1486 1486
2 Mini Buses 1.5 11 173 Bus 3 185 556
4
LCV+ LVG(Mini LCV/ Pick Up /Utility)
1.5 224 336
5 2 Axle Truck 3 214 643
6 3 Axle Truck 3 97 291
7MAV+ Heavy Mach+ Oversize. 4.5 19 86
TOTAL 2237 3415
For the current project the Total Two-way Commercial Traffic (cvpd) in the year of completion
of construction is 364cvpd (2Axle & 3Axle = 343, MAV = 21).
The average annual growth of commercial vehicles is taken as 5%.
The cumulative number of commercial vehicles during the design period may be
estimated from the following expression as shown in Equation 2.1
C=365× A {(1+r )n−1}
r(2.1)
Where
C = Cumulative number of commercial vehicles during the design period
A = Initial number of commercial vehicles per day in the year when the road is opened to traffic
r = Annual rate of growth of commercial traffic volume (expressed as decimal)
n = Design period in years.
ASC Infratech Pvt. Ltd. Page | 6
![Page 7: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/7.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Table 2.2 Estimation of traffic growth
Year AADT Total Traffic (No.) Cumulative Traffic
2Axle & 3 Axle MAV CV* 2Axle & 3 Axle MAV CV*
2014 311 19 330 113515
2015 327 20 347 119191
2016 343 21 364 125150 7646 132796 132796
2017 360 22 382 131408 8028 139436 272232
2018 378 23 401 137978 8430 146408 418640
2019 397 24 421 144877 8851 153728 572368
2020 417 25 442 152121 9294 161415 733782
2021 438 27 464 159727 9758 169485 903268
2022 459 28 488 167713 10246 177960 1081227
2023 482 29 512 176099 10758 186857 1268085
2024 507 31 538 184904 11296 196200 1464285
2025 532 32 564 194149 11861 206010 1670295
2026 559 34 593 203857 12454 216311 1886606
2027 586 36 622 214049 13077 227126 2113733
2028 616 38 653 224752 13731 238483 2352215
2029 647 39 686 235990 14417 250407 2602622
2030 679 41 720 247789 15138 262927 2865550
2031 713 44 756 260178 15895 276074 3141623
2032 748 46 794 273187 16690 289877 3431501
2033 786 48 834 286847 17524 304371 3735872
2034 825 50 876 301189 18401 319590 4055461
2035 866 53 919 316249 19321 335569 4391031
2036 910 56 965 332061 20287 352348 4743378
2037 955 58 1014 348664 21301 369965 5113343
2038 1003 61 1064 366097 22366 388463 5501807
2039 1053 64 1117 384402 23484 407886 5909693
2040 1106 68 1173 403622 24659 428281 6337974
2041 1161 71 1232 423803 25892 449695 6787669
2042 1219 74 1294 444993 27186 472180 7259848
2043 1280 78 1358 467243 28545 495789 7755637
2044 1344 82 1426 490605 29973 520578 8276215
2045 1411 86 1498 515136 31471 546607 8822821
C = 8822821
ASC Infratech Pvt. Ltd. Page | 7
![Page 8: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/8.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Average No of axles per commercial vehicle, (each tandem axle set is counted as one
axle unit. Similarly, each tridem axle set is counted as one axle) is 2.35
Cumulative number of standard axles during design period is C * 2.35 = 20743603
Proportion of traffic in predominant direction is 0.5
Design traffic factor (0.25 for 2-lane 2-way. For multilane highways the value is 0.25 X
0.5) is 0.125
The edge flexural stress caused by axle loads for bottom-up cracking is the maximum when outer
tyre imprint touches the longitudinal edge. Stress in the edge region is low when the tyre imprint
is 150mm away from longitudinal edge. The edge flexural stress is small when the wheels are
close to the transverse joints.
Traffic factors for BUC and TDC are given below:
Traffic factor for BUC analysis (for six-hour period during day) is 0.2
Traffic factor for TDC analysis (for six-hour period during night) is 0.3
It is recommended that 25 percent of the total traffic in the direction of predominant traffic may
be considered for design of pavement for bottom-up cracking.
Design axle repetitions for BUC analysis (for 6 hour day time traffic) is 0.2*0.25*
20743603 = 1037180
The design traffic for top-down cracking analysis will be a portion of the design traffic considered for bottom-up cracking analysis.
Proportion of vehicles with spacing between front and the first rear axle less than the
spacing of transverse joints is 0.55
Design axle repetitions for TDC analysis (for 6-hour night time traffic) is
0.55*0.3*0.25*20743603 =855674
Expected number of applications of different axle load groups during the design period can be
estimated using the details of commercial traffic volume expected rate of growth of commercial
traffic and the information about axle load spectrum and the number of single, tandem and
tridem axles obtained from axle load survey. Since front axles (steering axle) with single wheels
ASC Infratech Pvt. Ltd. Page | 8
![Page 9: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/9.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
on either side cause only negligible bottom-up fatigue damage, it is only the rear axles that may
be included in the axle load spectrum.
2.5 Composition of traffic in terms of axles
Proportion of Front single (steering) Axles = 40.4%
Proportion of Rear single Axles = 38.6%
Proportion of tandem Axles =17.5%
Proportion of Tridem Axles =3.4%
2.6 Temperature Differential
Temperature differential between the top and bottom fibres of concrete pavements causes the
concrete to curl, giving rise to stresses. Recommended temperature differentials for concrete
slabs for different states of India are given in IRC: 58-2011.
As the project is in Maharashtra state, Maximum day-time Temperature Differential in
slab, °C (for bottom-up cracking) is 20.3°C
Night-time Temperature Differential in slab, °C (for top-down cracking) is 20.3/2 + 5
=15.15°C
It is suggested that the maximum positive and negative temperature differentials are assumed to
be constant for the six hour period during the day between 10 AM and 4 PM and for the six hour
period between 0 AM to 6 AM during night hours respectively.
Composition and strength of foundation
2.7 Embankment Soil
Behaviour of the embankment soils had to be studied before so that if it contains soils like
expansive clays, marine clays, soft clays, black cotton soil etc. are harmful to the subgrade soil.
2.7.1 Subgrade
Smaller diameter plate can be used in case of homogeneous foundation from practical
consideration and the test values obtained with plates of smaller diameter may be converted to
the standard 750 mm plate value using Equation
k 750=k ∅ (1.21∅+0.078) (2.2)
ASC Infratech Pvt. Ltd. Page | 9
![Page 10: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/10.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
where
(I) = plate diameter, meter
k ∅ = modulus of subgrade reaction (MPa/m) with plate diameter ∅
k 750 = modulus of subgrade reaction (MPa/m) with plate diameter of 750 mm
For estimating the effective CBR value of subgrade, the CBR and ‘k’ value of embankment soil
below 500mm subgrade should be determined. From the figure 2.1, effective CBR of subgrade
can be determined.
Fig 2.1 Chart Determining Effective CBR of Subgrade
If there is a significant difference between the CBRs of the select subgrade and embankment
soils, the design should base on effective CBR as per IRC 58-2011. The embankment CBR is
considered as 7% and subgrade CBR as 15% for the entire stretch, so the effective CBR of the
subgrade is determined as 12.5% all along the stretch by using the graph as shown in Figure 2.1
ASC Infratech Pvt. Ltd. Page | 10
![Page 11: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/11.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Effective modulus of subgrade reaction of foundation is 300 MPa/m
Modulus of subgrade reaction of subgrade is 62 MPa/m
2.7.2 Subbase
The main purpose of the subbase is to provide a uniform, stable and permanent support to the
concrete slab laid over it. In the light of these requirements, subbase of Dry Lean Concrete
(DLC) having a 7-day compressive strength of 10MPa as per IRC-SP: 49 is recommended.
Thickness of Granular Subbase is 150mm
Thickness of Dry Lean Concrete subbase is 150mm
2.8 Concrete strength
Flexural strength of concrete is required for the purpose of design of concrete slab. Flexural
strength can be obtained after testing the concrete beam as per procedure given in IS 516.
M40 grade is considered for Pavement Quality Concrete (PQC)
Unit weight of Concrete is 24 KN/m3
Usually, concrete design is based on 28 days strength.
Modulus of elasticity and poison’s ratio of concrete E and µ values are taken as 30000
MPa and 0.15 respectively for the concrete with 28 day flexural strength of 4.5 MPa.
Radius of relative stiffness m= 0.622
2.9 Fatigue behaviour of cement concrete
The ratio between the applied flexural stress and the flexural strength of concrete is known as
stress ratio (SR).
If the SR is less than 0.45 implies concrete can sustain infinite number of repetitions and more
than 0.45, number of load repetitions required to cause cracking decreases. Relation between
fatigue life (N) and SR is given below
N = unlimited for SR<0.45
ASC Infratech Pvt. Ltd. Page | 11
![Page 12: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/12.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
N=[ 4.2577SR−0.4325 ]
3.268
When0.45≤SR≤0.55 (2.3)
log10 N=¿ 0.9718−SR0.0828
For SR>0.55¿ (2.4)
These equations are used for the analysis of bottom-up and top-down cracking.
2.10 Design of Slab Thickness
Type of pavement considered
Carriageway Two lane two way
Shoulders :- Tied concrete shoulders ? (yes/no) yes
Transverse joint spacing (m) 4.5
Lane width (m) 3.5
Transverse Joints have dowel bars? (yes/no) yes
The flexural stress due to the combined action of traffic loads and temperature differential
between the top and bottom fibres of concrete slab is considered for design of pavement
thickness.
The trial thickness of concrete slab is taken as 260mm.
Load Transfer Efficiency Factor for TDC analysis β =0.66 for joints with dowels.
The flexural stress at the bottom layer of the concrete slab is the maximum during the day time
and when the excess axle loads act midway on the pavement slab produces ‘bottom-up cracking’.
In this type of cracking, Single axles cause highest stress followed by tandem and tridem
respectively.
During the night hours, the top surface is cooler than the bottom surface and the slab curl up
resulting in loss of support.
For BUC analysis:
Front single (steering) Axles = Proportion of Front single* Design axle repetitions for
BUC analysis = 0.404%* 1037180= 419365
ASC Infratech Pvt. Ltd. Page | 12
![Page 13: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/13.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Rear single Axles = Proportion of Rear single Axles* Design axle repetitions for BUC
analysis = 0.386%* 1037180 = 400644
Tandem Axles = Proportion of Tandem Axles* Design axle repetitions for BUC analysis
= 0.175%* 1037180 = 181600
Tridem Axles = Proportion of Tridem Axles* Design axle repetitions for BUC analysis =
0.034%* 1037180 = 35571
For TDC analysis:
For location 1:
Front single (steering) Axles = Proportion of Front single* Design axle repetitions for TDC
analysis = 0.404%* 855674= 345976
Rear single Axles = Proportion of Rear single Axles* Design axle repetitions for TDC
analysis = 0.386* 855674= 330531
Tandem Axles = Proportion of Tandem Axles* Design axle repetitions for TDC analysis =
0.175* 855674= 149820
Tridem Axles = Proportion of Tridem Axles* Design axle repetitions for TDC analysis =
0.034* 855674= 29346
The cumulative fatigue damage expressions for Bottom-up cracking and Top-down cracking are
given below
CFD (BUC )=∑i
j n iN i
(10 AM ¿4 PM ) (2.5)
CFD (BUC )=∑i
j n iN i
(0 AM ¿6 AM ) (2.6)
Where Ni = allowable number of wheel load and temperature differential cycles for ith load group.
ni = Predicted number of wheel load and temperature differential cycles for ith load group.
2.11 Design of rigid pavement as per IRC: 58-2011
The axle load spectrum data, Bottom-up Cracking fatigue analysis for day-time (6 hour) traffic
and positive temperature differential, Top-Down Cracking fatigue analysis for night-time (6
ASC Infratech Pvt. Ltd. Page | 13
![Page 14: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/14.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
hour) traffic and negative temperature differential, Design of dowel bars and tie bars of two
locations are shown in Annexure 1a, 1b, 1c, respectively.
2.11.1 Design for pavement bonded option
Subgrade CBR (%) = 15
Granular Subbase Thickness (mm) = 150
Effective k-value from Tables 2 and 3 (MPa/m) = 69.2For k of 75.9 MPa/m and for
Doweled Joint and Tied Concrete Shoulders,Slab Thickness
(m) =0.26
Trial Slab thickness (m) over DLC, h1 0.235
Provide DLC thickness (m), h2 0.15
Elastic Modulus of Pavement Concrete (MPa), E1 30000
Elastic Modulus of DLC (MPa), E2 13600
Poisson's Ratio of Paving Concrete, m1 0.15
Poisson's Ratio of DLC, m2 0.2
Depth to Neutral axis, m (See Fig.6) 0.16
Flex Stiffness of design Slab 44.95
Flex Stiffness of Partial Slab Provided 32.56
Flex Stiffness of DLC 18.24
Total Flexural Stiffness Provided = 32.56 + 18.24 = 50.80
which is more than the Flexural Stiffness of the Design Slab = 44.95
Hence, Provide a Slab of thickness (m) 0.2 over DLC of thickness (m) 0.15
ASC Infratech Pvt. Ltd. Page | 14
![Page 15: Rigid Pavement_1.docx](https://reader036.fdocuments.us/reader036/viewer/2022082610/55cf9229550346f57b9422c5/html5/thumbnails/15.jpg)
Two lanes with paved shoulders from Ane-Ghat to Start of Ahmednagar bypass of NH-222 in the State of Maharashtra under Rigid pavement ReportNHDP-IV on EPC Basis
DN002 Rev 0
Chapter 3
Conclusion
3.1 Conclusion
The following gives the thickness of different layers of rigid pavement in without pavement bonded option and with paved bonded option.
Table 3.1 Pavement Thickness at Location 1
Description Without pavement bonded option
With pavement bonded option
Pavement Quality Concrete (mm)
260 200
Dry Lean Concrete (mm) 150 150
Granular Subbase (mm) 150 200
Subgrade (mm) 500 500
Length, Diameter and spacing of Dowel bars (mm)
500, 25 & 300
Length, Diameter and spacing of tie bars (mm)
650, 12 & 700
ASC Infratech Pvt. Ltd. Page | 15