Richard Simpson Master Plan 2012

11
Richard Simpson Park Master Plan

description

 

Transcript of Richard Simpson Master Plan 2012

Page 1: Richard Simpson Master Plan 2012

Richard Simpson Park Master Plan

Page 2: Richard Simpson Master Plan 2012

Lake Room

ArlingtonYacht Club

Page 3: Richard Simpson Master Plan 2012
Page 4: Richard Simpson Master Plan 2012

Current IssuesCurrent Issues

Lack of a long-term master plan for the park

Placement of the new building in the floodplain

Existing park infrastructure Parking lot Drainage Traffic flow Restroom / pavilion structures

Closure of Royaloak Drive

Page 5: Richard Simpson Master Plan 2012
Page 6: Richard Simpson Master Plan 2012

New Lake Room ConceptNew Lake Room Concept

Page 7: Richard Simpson Master Plan 2012

New Lake Room ConceptNew Lake Room Concept

Page 8: Richard Simpson Master Plan 2012

Description Design Construction Total

New Building $ 109,182 $ 909,848 $

1,019,029

Site Work $ 74,323 $ 619,362 $

693,685 Attached Public Restrooms

$ 26,497 $ 220,805 $

247,301

Administrative Costs     $

126,200

  Total Project Cost $

2,086,216

2008 Bond Funding $

939,386 FY14 Parks Gas

Funding $

1,146,830

Current Project EstimateCurrent Project Estimate

Page 9: Richard Simpson Master Plan 2012

ProcessProcess

Two public meetings

Project Website

Email Blasts

Planning and Development Committee

Two Park Board Meetings

Park Board Work Session

Q&A document

Consulted with City Departments

Page 10: Richard Simpson Master Plan 2012

Next StepsNext Steps

Seek Park Board adoption of the master plan at December 10th meeting

Informal staff report to City Council on December 18th

Seek City Council approval of the consultant contract for construction documents of the new building

Begin design work in February

Page 11: Richard Simpson Master Plan 2012

QuestionsQuestions