RFUC-install-11-08
description
Transcript of RFUC-install-11-08
FibeAir® RFU-C
Installation Guide
Part ID: BM-0133-0 Doc ID: DOC-00017708 Rev a.01
November 2008
Notice This document contains information that is proprietary to Ceragon Networks Ltd.
No part of this publication may be reproduced, modified, or distributed without prior written authorization of Ceragon Networks Ltd.
This document is provided as is, without warranty of any kind.
Registered TradeMarks Ceragon Networks® , FibeAir® and CeraView® are registered trademarks of Ceragon Networks Ltd.
Other names mentioned in this publication are owned by their respective holders.
TradeMarks CeraMapTM, ConfigAirTM, PolyViewTM, EncryptAirTM, CeraMonTM, EtherAirTM, and MicroWave FiberTM, are trademarks of Ceragon Networks Ltd.
Other names mentioned in this publication are owned by their respective holders.
Statement of Conditions The information contained in this document is subject to change without notice.
Ceragon Networks Ltd. shall not be liable for errors contained herein or for incidental or consequential damage in connection with the furnishing, performance, or use of this document or equipment supplied with it.
Information to User Any changes or modifications of equipment not expressly approved by the manufacturer could void the user’s authority to operate the equipment and the warranty for such equipment.
Copyright © 2008 by Ceragon Networks Ltd. All rights reserved.
Corporate Headquarters: Ceragon Networks Ltd. 24 Raoul Wallenberg St. Tel Aviv 69719, Israel Tel: 972-3-645-5733 Fax: 972-3-645-5499 Email: [email protected] www.ceragon.com
European Headquarters: Ceragon Networks (UK) Ltd. 4 Oak Tree Park, Burnt Meadow Road North Moons Moat, Redditch, Worcestershire B98 9NZ, UK Tel: 44-(0)-1527-591900 Fax: 44-(0)-1527-591903 Email: [email protected]
North American Headquarters: Ceragon Networks Inc. 10 Forest Avenue, Paramus, NJ 07652, USA Tel: 1-201-845-6955 Toll Free: 1-877-FIBEAIR Fax: 1-201-845-5665 Email: [email protected]
APAC Headquarters: Ceragon Networks APAC (S'pore) Pte Ltd 100 Beach Road #27-01/03 Shaw Towers Singapore 189702 Tel.: 65 65724170 Fax: 65 65724199
Contents
Chapter 1 Installation .................................................................................... 1-1
General ................................................................................................................................ 1-1
Installation Components ................................................................................................... 1-2
1+0 Direct Mount Installation ............................................................................................ 1-3
1+1 Direct Mount Installation ............................................................................................ 1-5
1+0 Remote Mount Installation ......................................................................................... 1-8
1+1 Remote Mount Installation ....................................................................................... 1-10
Media Device (Antenna Mount) Losses ......................................................................... 1-13
Direct Mount for Nokia FlexiHopper Antennas ............................................................. 1-14
Antenna Connection ........................................................................................................ 1-15
Antenna Adapter .............................................................................................................. 1-16
Packing.............................................................................................................................. 1-17
Transportation.................................................................................................................. 1-17
Inspection ......................................................................................................................... 1-17
Chapter 2 Acceptance & Commissioning Procedures............................... 2-1
General ................................................................................................................................ 2-1
Site Acceptance Procedure............................................................................................... 2-2
1+0 Commissioning Procedure ........................................................................................ 2-7
1+1 Commissioning Procedure ........................................................................................ 2-9
2+0 XPIC Commissioning Procedure............................................................................. 2-12
FibeAir RFU-C Commissioning Log............................................................................... 2-15
Appendix A Frequency Information.............................................................A-1
General ................................................................................................................................A-1
RFU Frequency Bands.......................................................................................................A-1
6-8 GHz Frequency Channels ...........................................................................................A-8
Safety Precautions & Declared Material
Fiber Optic Line Precautions
Before turning on the equipment, make sure that the fiber optic cable is intact and is connected to the transmitter.
Do not attempt to adjust the laser drive current.
Do not use broken or non-terminated fiber optic cables/connectors or look straight at the laser beam.
ATTENTION: The laser beam is invisible!
The use of optical devices with the equipment will increase eye hazard.
CLASS 1 LASER PRODUCT
Complies with IEC 60 825-1:1993 + A1:1997 + A2:2001, and EN 60825-1:1994 + A1:1996 + A2:2001
General Equipment Precautions
Use of controls, adjustments, or performing procedures other than those specified herein, may result in hazardous radiation exposure.
When working with a FibeAir IDU, note the following risk of electric shock and energy hazard: Diconnecting one power supply disconnects only one power supply module. To isolate the unit completely, disconnect all power supplies.
Machine noise information order - 3. GPSGV, the highest sound pressure level amounts to 70 dB (A) or less, in accordance with ISO EN 7779.
!!
!!
!!
!!
!!
!!
!!
Safety Precautions & Declared Material (continued)
Static electricity may cause body harm, as well as harm to electronic components inside the device.
Anyone responsible for the installation or maintainance of the FibeAir IDU must use an ESD Wrist Strap.
ESD protection measures must be observed when touching the IDU.
To prevent damage, before touching components inside the device, all electrostatic must be discharged from both personnel and tools.
RoHS Compliance Declaration
电子信息产品有毒有害物质申明 Electronic Information Products Declaration of Hazardous/Toxic Substances
危害物质 Hazardous Substance
成分名称 Component 铅
Lead (Pb)
汞 Mercury
(Hg)
镉 Cadmium
(Cd)
六价铬 Hexavalent
Chromium (Cr VI)
多溴联苯 Polybrominated Biphenyls (PBB)
多溴二苯醚 Polybrominated Diphenyl Ethers
(PBDE)
单板 / 电路模块 PCB/Circuit Modules
Comply Comply Comply Comply Comply Comply
结构件 Mechanical Parts
Comply Comply Comply Comply Comply Comply
电缆 Cables
Comply Comply Comply Comply Comply Comply
Précautions de sécurité
Précautions relatives à la ligne à fibre optique
Avant de mettre l'équipement en marche, s'assurer que le câble à fibre optique est intact et branché à l'émetteur.
Ne pas essayer de régler le courant de commande du laser.
Ne pas utiliser de câble/connecteur à fibre optique cassé ou sans terminaison et ne pas regarder directement le faisceau laser.
ATTENTION : le faisceau laser est invisible !
L’utilisation de dispositifs optiques avec l'équipement augmente le danger pour les yeux.
PRODUIT LASER DE CLASSE 1
Conforme aux normes CEI 60 825-1:1993 + A1:1997 + A2:2001, et EN 60825-1:1994 + A1:1996 + A2:2001
Précautions générales relatives à l'équipement
L’utilisation de commandes ou de réglages ou l'exécution de procédures autres que celles spécifiées dans les présentes peut engendrer une exposition dangereuse aux rayonnements.
L’usage de FibeAir IDU s’accompagne du risque suivant d'électrocution et de danger électrique : le débranchement d'une alimentation électrique ne déconnecte qu'un module d'alimentation électrique. Pour isoler complètement l'unité, il faut débrancher toutes les alimentations électriques.
Bruit de machine d’ordre - 3. GPSGV, le plus haut niveau de pression sonore s'élève à 70 dB (A) au maximum, dans le respect de la norme ISO EN 7779.
!!
!!
!!
!!
!!
!!
!!
Sicherheitsmaßnahmen
Vorsichtsmaßnahmen bei faseroptischen Leitungen
Vergewissern Sie sich vor dem Einschalten der Anlage, dass das faseroptische Kabel unbeschädigt und mit dem Sender verbunden ist.
Versuchen Sie nicht, den Laser-Antriebsstrom zu regulieren.
Verwenden Sie keine defekten oder gespleißten faseroptischen Kabel/Stecker und sehen Sie nicht direkt in den Laserstrahl.
ACHTUNG: Der Laserstrahl ist unsichtbar!
Durch den Einsatz optischer Geräte zusammen mit der Anlage erhöht sich das Gesundheitsrisiko für die Augen.
LASERPRODUKT DER KLASSE 1
Entspricht den Normen IEC 60 825-1:1993 + A1:1997 + A2:2001 sowie EN 60825-1:1994 + A1:1996 + A2:2001
Allgemeine Vorsichtsmaßnahmen für die Anlage
Wenn andere Steuerelemente verwendet, Einstellungen vorgenommen oder Verfahren durchgeführt werden als die hier angegebenen, kann dies gefährliche Strahlung verursachen.
Beachten Sie beim Arbeiten mit FibeAir IDU das folgende Stromschlag- und Gefahrenrisiko: Durch Abtrennen einer Stromquelle wird nur ein Stromversorgungsmodul abgetrennt. Um die Einheit vollständig zu isolieren, trennen Sie alle Stromversorgungen ab.
Maschinenlärminformations-Verordnung - 3. GPSGV, der höchste Schalldruckpegel beträgt 70 dB(A) oder weniger gemäß EN ISO 7779.
!!
!!
!!
!!
!!
!!
!!
FibeAir® RFU-C Installation Guide 1-1
Chapter 1: Installation
General This guide provides installation procedures for FibeAir RFU-C:
About FibeAir RFU-C
RFU-C is a state-of-the-art Radio Frequency Unit which is fully software configurable and supports a broad range of capacities and interfaces.
The RFU supports low to high capacities for traditional voice and Ethernet services, as well as PDH/SDH/SONET or hybrid Ethernet and TDM interfaces.
This innovative platform uses an “on-the-fly” upgrade method, whereby network operators only buy capacity as needed, benefiting from savings on initial investments and OPEX.
Traffic capacity throughput and spectral efficiency are optimized with the desired channel bandwidth. For maximum user choice flexibility, channel bandwidths can be selected together with a range of modulations of from QPSK to 256 QAM.
High spectral efficiency is ensured using the same bandwidth for double the capacity, via two carriers, with vertical and horizontal polarizations. This feature is implemented by a built-in XPIC mechanism.
RFU-C works together with two types of indoor units. For PDH/SDH/SONET, the RFU works with the FibeAir 1500R indoor unit. For Ethernet, RFU-C works with the FibeAir IP-10 indoor unit. Together, FibeAir RFU-C and FibeAir 1500R/IP-10 IDUs provide a powerful, reliable, and comprehensive solution for a variety of wireless network scenarios and requirements.
RFU-C works with:
FibeAir 1500R FibeAir IP-10
RFU-C operating in co-channel dual polarization (CCDP) mode, using the cross polarization interference canceller (XPIC) algorithm, two carriers signals can be transmitted over a single channel, using vertical and horizontal polarization. This enables double capacity in the same spectrum bandwidth.
Required Tools
The following tools are required for the RFU-C installation:
Socket key wrench metric set
Adjustable wrench
FibeAir® RFU-C Installation Guide 1-2
Installation Components The following illustrations show the components involved in the installation procedures.
RFU-C
Coupler Holder with Coupler V/H Twist
Remote Pole Mount Kit
FibeAir® RFU-C Installation Guide 1-3
1+0 Direct Mount Installation
To install RFU-C in a direct mount 1+0 configuration, do the following:
1. If needed, change the antenna polarization by rotating the RFU-C in accordance with the relevant antenna installation guide.
Vertical Pole Horizontal Pole
2. Spread grease on the O-ring supplied with the antenna.
3. Place the O-ring in its location on the antenna transition.
4. Remove the sticker from the RFU-C antenna interface.
5. Mount the RFU-C on the antenna according to the system configuration, and make sure that the twist is set for the desired polarization (horizontal or vertical).
FibeAir® RFU-C Installation Guide 1-4
6. Insert four screws and washers provided with the kit, and tighten them.
FibeAir® RFU-C Installation Guide 1-5
1+1 Direct Mount Installation To install RFU-C in a direct mount 1+1 configuration, do the following:
1. If needed, change the antenna polarization according to the relevant antenna installation guide.
2. Spread grease on the two O-rings supplied with the kit and place them in their locations.
3. Mount the twist on the coupler according to the relevant antenna polarization (as shown in the illustrations below), using four screws and washers supplied with the kit.
FibeAir® RFU-C Installation Guide 1-6
4. Spread grease on the O-ring supplied with the antenna.
5. Place the O-ring on the antenna transition.
6. Mount the coupler holder on the antenna using the screws and washers supplied with the kit.
7. Spread grease on the O-rings supplied with the holder coupler kit.
8. Place one O-ring on each side of the coupler.
9. Remove the sticker from both RFU-C antenna interfaces.
10. Mount both RFU-Cs on the holder coupler.
11. For each RFU-C, insert four screws and washers, and tighten them, as shown in the following illustration.
FibeAir® RFU-C Installation Guide 1-7
FibeAir® RFU-C Installation Guide 1-8
1+0 Remote Mount Installation 1. Mount the Ceragon remote mount device on the pole, as shown in the following illustration.
2. Remove the sticker from the RFU-C antenna interface.
3. Mount the RFU-C on the Ceragon remote mount device.
4. Insert four screws and washers, and tighten them.
5. Spread grease on the O-ring supplied with the flexible waveguide.
FibeAir® RFU-C Installation Guide 1-9
6. Place the O-ring in the flexible waveguide flange groove.
7. Spread grease on the O-ring supplied with the flexible waveguide.
8. Place the O-ring in the other end of the flexible waveguide flange groove.
9. Mount the flexible waveguide on the antenna, and tighten the screws and washers.
6-13 GHz
15-38 GHz
FibeAir® RFU-C Installation Guide 1-10
1+1 Remote Mount Installation 1. Mount the Ceragon remote mount device on the pole.
2. Mount the coupler holder on the Ceragon remote mount device using the screws and washers supplied with the kit.
FibeAir® RFU-C Installation Guide 1-11
3. Spread grease on the O-rings supplied with the coupler holder kit.
4. Remove the sticker from both RFU-C antenna interfaces.
5. Place one O-ring on each side of the coupler.
6. Mount both RFU-Cs on the coupler holder.
7. For each RFU-C, insert four screws and washers, and tighten them.
8. Spread grease on the O-ring supplied with the flexible waveguide.
9. Place the O-ring in the flexible waveguide flange groove.
10. Mount the flexible waveguide on the Ceragon coupler, and tighten the screws and washers.
11. Spread grease on the O-ring supplied with the flexible waveguide.
12. Place the O-ring in the other end of the flexible waveguide flange groove.
13. Mount the flexible waveguide on the antenna, and tighten the screws and washers.
FibeAir® RFU-C Installation Guide 1-12
FibeAir® RFU-C Installation Guide 1-13
Mediation Device (Antenna Mount) Losses
Per Terminal Losses (dB) Configuration Mount Path
6-8 GHz 11 GHz 13-15 GHz 18 GHz 23-32 GHz 38 GHz
Direct - 0.1 0.1 0.1 0.1 0.1 0.1 1+0
Remote - 0.5 0.5 1.2 1.5 1.5 1.5
Main-Main 1.4 1.4 1.4 1.4 1.6 1.8 Direct Sec-Main,
Main-Sec 6 6 6 6 6 6
Main-Main 1.9 1.9 2.6 2.9 3.1 3.3 1+1 HSB
Remote Sec-Main, Main-Sec 6.5 6.5 7.2 7.5 7.5 7.5
2+0 XPIC Remote - 0.5 0.5 1.2 1.5 1.5 1.5
Notes: 1. The antenna interface is always the RFU-C interface.
2. If other antennas are to be used, an adaptor with a 0.1 dB loss should be considered.
Loss (dB) Item
6-8 GHz 11 GHz 13-15 GHz 18-32 GHz 38 GHz
Flexible Waveguide 0.5 0.5 1.2 1.5 1.5
Main Coupler 1.4 1.4 1.4 1.5 1.5
Secondary Coupler 6 6 6 6 6
Twist 0 0 0 0 0
Note: The numbers above are typical losses per component.
FibeAir® RFU-C Installation Guide 1-14
Direct Mount for Nokia FlexiHopper Antennas RFU-C can be directly mounted on a Nokia FlexiHopper 6-38 GHz, 1-6 ft antenna, in 1+0 and 1+1 configurations.
An adapter is used for the direct mount, as shown in the following illustration.
RFU-C to Nokia
FlexiHopper Antenna Adapter
FibeAir® RFU-C Installation Guide 1-15
Antenna Connection RFU-C uses Andrew, RFS and antennas Xian Putian,
The following catalog items should be used:
• Andrew: VHLP/HP series
• RFS: SB/SU series
• Xian Putian: WTG series
RFU-C can be mounted directly for all frequencies (6-38 GHz) using the following antenna types (for integrated antennas, specific antennas PNs are required):
• Andrew: VHLP series
• RFS: SB/SU series
• Xian Putian: WTG series
For remote mount installations, the following flexible waveguide flanges should be used (millimetric). The same antenna type (integrated) as indicated above can be used (recommended).
Other antenna types using the flanges listed in the table below may be used.
Frequency (GHz)
Waveguide Standard
Waveguide Flange
Antenna Flange
6 WR137 PDR70 UDR70
7/8 WR112 PBR84 UBR84
11 WR90 PBR100 UBR100
13 WR75 PBR120 UBR120
15 WR62 PBR140 UBR140
18-26 WR42 PBR220 UBR220
28-38 WR28 PBR320 UBR320
If a different antenna type (CPR flange) is used, a flange adaptor is required. Please contact your Ceragon representative for details.
FibeAir® RFU-C Installation Guide 1-16
Antenna Adaptor When mounting RFU-C on an antenna upon which a 1500P ODU (11-38 GHz) direct mount was installed previously, the following adaptor is required (frequency-dependent).
Antenna adaptor used when replacing 1500P ODU direct mount
FibeAir® RFU-C Installation Guide 1-17
Packing The equipment should be packed and sealed with moisture absorbing bags.
Transportation The equipment should be prepared for public transportation. The cargo must be kept dry during transportation, in accordance with ETS 300 019-1-2, Class 2.3.
It is recommended that the equipment be transported to the installation site in its original packing case.
If intermediate storing is required, the packed equipment must be stored in a dry and cool environment, and out of direct sunlight, in accordance with ETS 300 019-1-1, Class 1.2.
Inspection Check the packing lists and verify that the correct equipment part numbers and quantities are found in the packages that arrived.
FibeAir® RFU-C Installation Guide 2-1
Chapter 2: Acceptance & Commissioning Procedures
General This chapter provides Ceragon's recommended Acceptance and Commissioning Procedure for FibeAir RFU-C. Acceptance and commissioning should be performed after initial setup is complete.
The purpose of this procedure is to verify correct installation and operation of the installed link and the interoperability with customer end equipment.
Ceragon's Acceptance and Commissioning procedure includes the following stages:
Site Acceptance Procedure
Commissioning of radio link in a 1+0 configuration
Commissioning of radio link in a 1+1 configuration
Commissioning of radio link in a 2+0 XPIC configuration
The Site Acceptance Procedure is a checklist that summarizes the installation requirements of the site at which the products were installed.
The commissioning tests cover the required configuration information that should be recorded, and the tests that should be performed on the radio link in 1+0, 1+1 and 2+0 configurations.
Note: RFU-C works together with two types of indoor units. For SDH/SONET, the RFU works with the FibeAir 1500R indoor unit. For Ethernet, RFU-C works with the FibeAir IP-10 indoor unit.
FibeAir® RFU-C Installation Guide 2-2
Site Acceptance Procedure The purpose of the following procedures is to verify that all installation requirements were noted and checked. Following this procedure will ensure proper, long-lasting, and safe operation of the product.
The checklist below summarizes the installation requirements of the site.
SITE ACCEPTANCE CHECKLIST
1. SITE INFORMATION
Customer:
Radio model:
Site name:
Site code:
Radio link code:
Site address:
2. ANTENNA MOUNTING
Antenna mount type:
Mount is of sufficient height to clear local obstructions OK
Mount is safely positioned to not cause a safety hazard OK
Mount is secure and perpendicular OK
Mount is grounded as per site specifications OK
All steelwork is Galvanized or Stainless Steel as appropriate OK
3. ANTENNA
Antenna type (model and size):
Antenna is securely fixed to mount OK
Antenna is grounded as per site specifications OK
Antenna sway braces are installed correctly (where applicable) OK
Antenna Radome is securely fitted (where applicable) OK
Water drain plugs are fitted and removed, as appropriate OK
Antenna sealing O-Ring is properly fitted and not damaged OK
Antenna/Launch unit polarization is as per link requirements OK
FibeAir® RFU-C Installation Guide 2-3
SITE ACCEPTANCE CHECKLIST
(continued)
4. OUT-DOOR UNIT
Type of RFU mount: (Direct or Remote mount)
RFU is securely mounted to the antenna or pole OK
RFU is grounded as per installation instructions OK
RFU polarization is as per link requirements OK
RFU is installed properly and has no physical damage OK
For Remote-Mount Only:
Remote mount kit is securely mounted to the pole OK
Waveguide has no physical damage and connectors are sealed OK
All waveguide bolts are secured using washers and lock-washers, as appropriate OK
Flexible waveguide is secured to the pole OK
6. COAX CABLE
Overall cable length:
Cable type:
N-Type connectors assembled properly on the cable OK
Cable connected securely to RFU and IDU OK
Cable connector is weather-proofed (sealed) at the RFU OK
At the RFU, cable has a service/drip loop to prevent moisture from entering the connector OK
Cable is secured using suitable restraints to fixed points at regular intervals (0.5 m recommended) OK
Cable has no sharp bends, kinks, or crushed areas. All bends are per manufacturer specifications OK
Grounding/lightning protection is as per site specifications OK
Lightning protection type and model:
Cable point-of-entry to building/shelter is weather-proof OK
Cable ends are properly labeled OK
FibeAir® RFU-C Installation Guide 2-4
SITE ACCEPTANCE CHECKLIST
(continued)
7. WAVEGUIDE
WG type:
WG is connected securely to RFU and Antenna OK
WG connector is weather-proofed (sealed) at the RFU OK
At the RFU, the WG has a service/drip loop to prevent moisture from entering the connector OK
WG is secured using suitable restraints to fixed points at regular intervals (0.5 m recommended) OK
WG has no sharp bends, kinks, or crushed areas. All bends are per manufacturer specifications OK
WG ends are properly labeled OK
8. IN-DOOR UNIT
IDU is securely mounted to the rack OK
IDU is located in a properly ventilated environment OK
IDU fans are functional and air flow to the fans is not disrupted OK
IDU and rack are grounded as per site specifications OK
Traffic cables and connections are properly terminated as per manufacturer/cable instructions OK
All cabling is secured, tidy, and visibly labeled OK
9. DC POWER SUPPLY - Two Inputs
Measured DC voltage input to the IDU: (-40.5 to -60 VDC)
Power-Supply maximum current: (at least 3 Ampere)
Power-Supply is properly grounded OK
DC power backup type:
IDU DC connector is secure and the DC input leads are correctly terminated (no bare wires are visible) OK
IDU DC connector (+) and (GND) leads are shorted and GND is grounded OK
10. RACK INSTALLATION
Rack is mounted to the shelter floor with four screws OK
Rack is mounted to the shelter wall with two screws OK
FibeAir® RFU-C Installation Guide 2-5
SITE ACCEPTANCE CHECKLIST
(continued)
11. REMARKS/NOTES
12. GENERAL INFORMATION
Name:
Title:
Company:
Signature:
Site accepted by:
Date:
Name:
Title:
Company:
Signature:
Site approved by:
Date:
Site Acceptance Checklist Notes
The following notes provide important additional information about the Site Acceptance Checklist.
1. Antenna Mounting
Mounting pole is of sufficient height to clear local obstructions, such as parapets, window cleaning gantries, and lift housings.
Mounting Pole is of sufficient height, and is safely positioned, so as not to cause a safety hazard. No person should be able to walk in front of, or look directly into the path of the microwave radio beam. Where possible, the pole should be away from the edge of the building.
Mounting pole is secure and perpendicular. A pole that is not perpendicular may cause problems during antenna alignment.
Mounting pole is grounded as per site specifications. All operators and site owners have specific requirements regarding the grounding of installations. As a minimum, typical requirements are such that any metal structure must be connected to the existing lightning protection ground of the building. Where it extends beyond the 45 degree cone of protection of existing lightning conductors, additional lightning protectors should be installed.
All steelwork is Galvanized or Stainless Steel, as appropriate to prevent corrosion.
FibeAir® RFU-C Installation Guide 2-6
2. Antenna
Antenna is grounded as per site specifications. See the third point in the Antenna Mounting section above.
Antenna sway braces are fitted and installed correctly, where applicable. Typically, for an antenna of 1.2 m or larger, an extra sway brace is fitted to the mounting frame of the antenna. This sway brace should not be mounted to the same pole as the antenna, but should be installed directly back to the tower or an alternative point.
Antenna Water Drain Plugs are fitted and removed, where appropriate. Some antennas have moisture drain plugs installed at various points around the antenna. The purpose of these plugs is to allow any moisture that forms on the inside of the antenna or radome to drip out and prevent a pool within the antenna. Only the plugs at the bottom of the antenna, after installation, should be removed. All other plugs should be left in position.
3. RFU (Radio Frequency Unit)
The RFU is grounded as per installation instructions. See the third point in the Antenna Mounting section above.
The RFU polarization is as per link requirements and matches the polarization of the antenna.
4. Indoor Unit
The main traffic connections are correctly terminated and crimped as per cable and connector manufacturer instructions. All fiber optic patch leads should be routed carefully and efficiently, using conduits to prevent damage to the cables.
All other user terminations are secure and correctly terminated.
All labeling is complete as per site requirements. Labeling is specific to each customer. At a site with only one installation, labeling may be unnecessary. However, at sites with multiple installations, correct and adequate labeling is essential for future maintenance operations.
Typical labeling requirements include:
Antenna labels - for link identity and bearing RFU labels - for link identity, frequency, and polarization Coax cable labels - for link identity, close to the RFU, IDU, and either end of any joint IDU labels - for link identity
FibeAir® RFU-C Installation Guide 2-7
1+0 Commissioning Procedure
Scope This section describes the recommended commissioning tests for a FibeAir RFU-C radio link in a 1+0 configuration.
The purpose of the commissioning tests is to verify correct and proper operation of the product.
Commissioning Test The following tests should be performed on each installed link.
Link Verification
“Radio” LED on the IDM front panel is green, indicating the radio link is up.
Received Signal Level (RSL) is up to +/- 4 dB from the expected (calculated) level at both ends of the link.
Radio Bit Error Rate (BER) is 10E-11 or higher.
If working with ATPC, ATPC is operating as expected (RSL = reference level).
After connecting test equipment or end equipment to the line interfaces, all LEDs on the front panel of the IDM are green.
Line Interfaces Test
155 Mbps Interface - connect SDH/SONET/ATM test equipment to the 155 Mbps interface and verify error-free operation for at least 1 hour. Use a physical or software loop at the far end.
FE/GbE Interface - connect a Packet Analyzer to the Fast Ethernet interface and verify error-free operation (no packet loss) for at least 1 hour. Use a physical loop at the far end.
2 Mbps/1.5 Mbps - connect PDH test equipment to the E1/T1 interface and verify error-free operation for at least 1 hour. Use a physical or software loop at the far end.
Interoperability Verification
Connect customer end equipment to the line interfaces, and verify correct operation.
Further interoperability tests should be performed in accordance with the specific requirements of the connected end equipment.
FibeAir® RFU-C Installation Guide 2-8
Management Verification
Install CeraView element manager software on the PC, and launch the program.
Verify that you can manage the link and that you are able to perform changes to the link configuration (frequency channel, Tx power, system name, time & date, etc.) via CeraView.
Verify that CeraView reports the correct parameters when performing the above.
Verify that there are no active alarms on the link.
If the management station is located at a remote site (Network Operation Center), verify that the management station can manage the link and receive traps.
Loopback Operation
Perform line loopback, IDU loopback, RFU loopback, and Remote loopback, and verify that the system operates accordingly.
FibeAir® RFU-C Installation Guide 2-9
1+1 Commissioning Procedure
Scope This section describes the recommended commissioning tests for a FibeAir RFU-C radio link in 1+1 HSB (Hot Standby) and SD (Space Diversity) or FD (Frequency Diversity) configurations (internal protection).
The purpose of the commissioning tests is to verify correct and proper operation of the product.
Note that in this section:
Primary refers to the RFUs connected to the top-most antenna in an SD configuration.
Secondary refers to the RFUs connected to the bottom antenna in an SD configuration.
Commissioning Tests
The following tests should be performed on each installed link.
Link Verification
The following steps should be repeated for each of the four RFU combinations (Primary-Primary, Primary-Secondary, Secondary-Primary, Secondary-Secondary).
“Radio” LED on the IDM front panel is green, indicating the radio link is up.
Received Signal Level (RSL) is up to +/- 4 dB from the expected (calculated) level at both ends of the link.
Radio Bit Error Rate (BER) is 10E-11 or higher.
If working with ATPC, ATPC is operating as expected (RSL = reference level).
After connecting test equipment or end equipment to the line interfaces, all LEDs on the front panel of the IDM are green.
Line Interfaces Test
155 Mbps interface - connect SDH/SONET/ATM test equipment to the 155 Mbps interfaces using splitters, and verify error-free operation for at least 1 hour. Use physical loop between the splitters at the far end.
FE, GbE interface - connect a Packet Analyzer to the Fast Ethernet interfaces using an FE splitter, and verify error-free operation (no packet loss) for at least 1 hour. Use a physical loop at the far end.
2 Mbps/1.5 Mbps - connect PDH test equipment to the E1/T1 interfaces using splitters, and verify error-free operation for at least 1 hour. Use a physical loop between the splitters at the far end.
FibeAir® RFU-C Installation Guide 2-10
Switching Tests
Define each of the N channels as preferred (one at a time) for errorless switching to the +1 channel. The regular channel supports hitless switching to the +1 channel.
155 Mbps Interface
Connect SDH/SONET/ATM test equipment to the 155 Mbps interfaces using splitters. Use physical loop between the splitters at the far end. Verify that there are no alarms.
Perform the following switching tests from one IDM to the other, and verify the system switches automatically.
- Power: power off the active IDM
- Radio: disconnect the coax cable of the active IDM
- Line: disconnect the 155 Mbps line input of the active IDM
- Management: force a switch using CeraView
For diversity configurations, verify that each receiver is receiving its own signal, and then mute the active RFU. Verify that the receiver at the far end still receives from the diversity path. Verify that there are no errors in the test equipment.
FE, GbE Interface
Connect a Packet Analyzer to the Fast Ethernet interfaces using splitters. Use a physical loop between the splitters at the far end. Verify no alarms exist.
Perform the following switching tests from one IDM to the other, and verify the system switches automatically.
- Power: power off the active IDM
- Radio: disconnect the coax cable of the active IDM
- Management: force a switch using CeraView
2/1.5 Mbps Interface
Connect PDH test equipment to the interfaces using splitters. Use a physical loop between the splitters at the far end. Verify no alarms exist.
Perform the following switching tests from one IDM to the other, and verify the system switches automatically.
- Power: power off the active IDM
- Radio: disconnect the coax cable of the active IDM
- Management: force a switch using CeraView
Interoperability Verification
Connect the customer end equipment to the line interfaces and verify correct operation.
Further interoperability tests should be performed in accordance with the specific requirements of the connected end equipment.
FibeAir® RFU-C Installation Guide 2-11
Management Verification
Install CeraView element manager software on the PC and launch the program.
Verify that you can manage the link and that you are able to perform changes to the link configuration (frequency channel, Tx power, system name, time & date, etc.) via CeraView.
Verify that CeraView reports the correct parameters when performing the above.
Verify that there are no active alarms on the link.
If the management station is located a t a remote site (Network Operation Center), verify that the management station can manage the link and receive traps.
FibeAir® RFU-C Installation Guide 2-12
2+0 XPIC Commissioning Procedure
Scope
This section describes the recommended commissioning tests for a FibeAir RFU-C radio link in a 2+0 XPIC Co-Channel-Dual-Polarization configuration.
The purpose of the commissioning tests is to verify correct and proper operation of the product.
Important! Since operation of the XPIC system depends on correct installation, make sure the guidelines for XPIC system installation provided below are followed correctly.
XPIC Installation Guidelines
Antenna and RFU Installation
1. Install the dual polarization antenna and point it in the direction of the other site.
2. Install the two RFUs on a dual polarization antenna using the appropriate mounting kit, and mark the RFUs with V and H respectively.
IDU-RFU Cable Installation
1. Install two cables between the RFUs and the drawers (IDMs). Note that cable length difference should not exceed 10 meters.
2. Mark the cables with V and H respectively, and make sure V is connected to the right drawer and H is connected to the left drawer.
3. Mark the drawers respectively.
Antenna Alignment
1. Power up drawer V on both ends of the link and configure it to the desired frequency channel and maximum power.
2. Align the antennas, one at a time, until expected RSL is achieved. Make sure the achieved RSL is no more than +/-4 dB from the expected level.
Polarization Alignment
Polarization alignment is required to verify that the antenna feeds are adjusted, to ensure that the antenna XPD (Cross Polarization Discrimination) is achieved.
Polarization adjustment should be done on one antenna only.
1. Power up drawer V on both ends of the link and record the RSL reading on one end.
2. Power off drawer V on that end and power on drawer H.
FibeAir® RFU-C Installation Guide 2-13
3. Check the RSL obtained on this RFU on H pol, and compare it to the RSL obtained by the RFU installed on the V pol.
4. Verify that XPI (Cross Polarization Interference) is at least 25 dB
where:
sites.both at used onspolarizati orthogonal with RSLLink RSLsites.both at usedon polarizati same with theRSLLink RSL
XPOL
POL
→→
−= XPOLPOL RSLRSLXPI
5. If XPI is less than 25 dB, adjust the feed polarization by opening the polarization screw and gently rotating the feed to minimize the RSLXPOL.
Note that polarization alignment is not always possible since the RSLXPOL may fall below the sensitivity threshold of the RFU.
It is also recommended to try to maximize the XPI as much as possible, by aligning the polarization.
XPIC Commissioning Tests
Individual Link Verification
Before operating in XPIC configuration, each of the links (V and H) should be commissioned individually in order to verify its proper operation.
1 Power up only drawer V at both ends and verify its frequency channel and Tx power configuration.
2 Verify that the RSL is no more than +/-4 dB from the expected level.
3 Run BER stability test on the link for at least 15 minutes to ensure error-free operation.
4 Power up only drawer H at both ends and verify its frequency channel and Tx power configuration.
5 Verify that the RSL is no more than +/-4 dB from the expected level.
6 Run BER stability test on the link for at least 15 minutes to ensure error-free operation.
XPIC Configuration Verification
1 Using the XPIC cable, connect the two RFUs at each end to the TNC connectors. Make sure the cable is no longer than 3 meters.
2 Configure the drawers to work in XPIC mode.
3 Verify that the RSL at all four RFUs is no more than +/-4 dB from the expected level.
4 Verify that no alarms exist (if a 155 Mbps line is connected).
5 Run BER stability test on each of the 155 Mbps links for at least 1 hour to ensure error-free operation.
Note: In a 2+2 configuration, repeat each step above for each of the four coupled RFU combinations.
FibeAir® RFU-C Installation Guide 2-14
XPIC Recovery Verification
In order to verify XPIC operation, simulate the faults described below.
1 Disconnect the IDU-RFU cable for each of the drawers (one at a time), and verify that the other link is operating.
2 Disconnect the XPIC cable and check that the relevant alarms are generated.
3 Power down each of the drawers and verify that the other link is operating.
4 Swap the V and H cables and check that the relevant alarm is generated.
5 Mute and then un-mute one RFU at a time and verify that the other link is operating.
Note: In a 2+2 configuration, repeat each step above for each of the four coupled RFUs connected to the two standby IDUs.
2+2 Verification
Perform the tests specified in Switching Tests in the 1+1 Commissioning Procedure section earlier in this guide.
In this case, the switch will be from a main IDU connected to the main V and main H RFUs, to the secondary IDU connected to the coupled V and coupled H RFUs.
FibeAir® RFU-C Installation Guide 2-15
FibeAir RFU-C Commissioning Log The Commissioning Log is an integral part of the commissioning procedure and should be filled in for each installed link.
The Commissioning Log gathers all relevant information regarding the installed link and contains a checklist of all recommended commissioning tests.
Maintaining the Commissioning Log is important for tracking your installations, and to provide essential data for Ceragon Networks.
Upon completing the Commissioning Log, send the log to Ceragon support center at [email protected].
FIBEAIR RFU-C LINK COMMISSIONING LOG
1. GENERAL INFORMATION
Customer:
Radio model:
Configuration:
Radio link code:
Site 1 name & add:
Site 2 name & add:
2. IN-DOOR UNIT Site 1 Drawers
Right / Left Site 2 Drawers
Rigt / Left
IDC model:
Wayside channel:
IDC p/n:
IDC s/n:
SW IDC:
Drawer model
Main channel
Drawer p/n
Drawer s/n
Modem s/n
FW Mux:
FW Modem:
Cfg Modem:
FibeAir® RFU-C Installation Guide 2-16
FIBEAIR RFU-C LINK COMMISSIONING LOG
(continued)
3. RFU Site 1 Drawers
Right / Left Site 2 Drawers
Right / Left
RFU model:
RFU p/n:
RFU Main s/n:
SW RFU:
Tx frequency (MHz):
Rx frequency (MHz):
Link ID:
Tx power (dBm):
ATPC on/off:
ATPC ref level:
RFU polarization:
4. ANTENNA Site 1 Drawers Right / Left
Site 2 Drawers Right / Left
Antenna model:
Antenna size:
Manufacturer:
Mounting type:
Mounting losses:
5. LINK PARAMETERS Site 1 Drawers
Right / Left Site 2 Drawers
Right / Left
Link distance:
Rain zone:
Expected RSL (dBm):
Expected Diversity RSL (dBm):
RSL Main (dBm):
RSL Diversity (dBm):
Deviation from exp?
RSL ≤4 dB?
FibeAir® RFU-C Installation Guide 2-17
FIBEAIR RFU-C LINK COMMISSIONING LOG
(continued)
6. COMMISSIONING TESTS Site 1 Drawers
Right / Left Site 2 Drawers
Right / Left
Front panel LEDs: All green All green All green All green
Line loopback: Pass Pass Pass Pass
IDU loopback: Pass Pass Pass Pass
RFU loopback: Pass Pass Pass Pass
Radio BER: Pass Pass Pass Pass
STM-1 test: Pass Pass Pass Pass
Fast Ethernet test: Pass Pass Pass Pass
8 x E1/T1 test: Pass Pass Pass Pass
E3/DS3 test: Pass Pass Pass Pass
Wayside E1 test: Pass Pass Pass Pass
Wayside Eth test: Pass Pass Pass Pass
XPIC test: Pass Pass Pass Pass
Switching test: Pass Pass Pass Pass
7. MANAGEMENT CONFIGURATION Site 1 Site 2
Eth Main IP address:
Eth Coupled IP address:
Eth IP mask:
Serial IP address:
Serial IP mask:
Default router:
In-band enabled?
Gateway/NE:
In-band channel 1:
In-band channel 2:
Ring IP address:
Ring IP mask:
Network ID:
8. REMARKS/NOTES
FibeAir® RFU-C Installation Guide 2-18
FIBEAIR RFU-C LINK COMMISSIONING LOG
(continued)
9. INSTALLATION INFORMATION
Name:
Company:
Date: Installed by:
Signature:
Name:
Company:
Date: Commissioned by:
Signature:
FibeAir® RFU-C Installation Guide A-1
Appendix A: Frequency Information
General This appendix provides frequency information for FibeAir RFU-C.
RFU Frequency Bands
RFU-C is available for ITU-R, CEPT, and FCC channels, in accordance with the table below.
All RFU-Cs (6-38 GHz) support 7-56 MHz bands (for capacities of from 10 to 500 Mbps).
56 MHz bandwidth is supported for all frequencies (6-38 GHz).
The following table lists the frequency bands, sub-bands, and duplex spacing supported by RFU-C.
For a detailed list of the low frequency channels, see the appendix at the end of this document.
Frequency Band
Separation MHz Standard Tx Low
MHz Tx High
MHz
* 6L GHz
(variable) 252.04,
240,260, 266, 300
ITU-R F.383-7,
ITU-R F.384-7
CEPT 14-01E
ITU-R F.497-6
CFR47 101.147
5900-6500 5900-6501
* 6H GHz (variable) 340,160,
170,500
ITU-R F.383-7
CEPT 14-01E
CFR47 101.147
6400-7100 6400-7101
* 7 GHz
(variable) 154,161,168,182,196,2
45,300
ITU-R F.385-7, Annex 3
ITU-R F.385-8, Rec 1-4, Annex 1,3,4
CEPT 02-06 Annex 1
7100-7900 7100-7900
* 8 GHZ
(variable) 119,154,208,266,300,310,311.32,5
30
ITU-R F.386-6,
Annex 4,3
CEPT 02-06
7700-8500 7700-8500
FibeAir® RFU-C Installation Guide A-2
Frequency Band
Separation MHz Standard Tx Low
MHz Tx High
MHz
490 10721-10949 11211-11439
490
ITU-R F.387-9,
CEPT 12-06 rec.12
CFR47 101.147 10961-11189 11451-11679
530 10701-10929 11231-11459
11 GHz
530 ITU-R F.387-9, Annex 2
CEPT 12-06 rec.3 10941-11169 11471-11699
266 12751-12863 13017-13129 13 GHz
266
ITU-R F.497-6,
CEPT 1202F 12863-12975 13129-13241
315 14648-14760 14963-15075
315 14732-14844 15047-15159
420 14501-14725 14921-15145
420 ITU-R F.636-3
14697-14921 15117-15341
490 14403-14657 114893-15117
490 ITU-R F.636-3
14627-14851 15117-15341
644 ACA (ITU-R F.636-3) 14613-14697 15257-15341
15 GHz
728 CEPT 12-07E 14501-14613 15229-15341
1008,1010 17700-18200 18710-19210
1008,1010
ITU-R F.595-8
CEPT 12-03E 18150-18690 19160-19700
1120 17728-18113 18848-19233
1120 18113-18553 19233-19673 18 GHz
1560 ITU-R F.595-8
CFR47 101.147 17700-18150 19260-19710
1008 ITU-R F.637-3, Annex 3
CEPT 12-02E 22000-22600 23000-23600
1200 CFR47 101.147 21200-21800 22400-23000
1200 ITU-R F.637-3, Annex 4 21800-22400 23000-23600
1232 21224-21784 22456-23016
23 GHz
1232 ITU-R F.637-3, Annex 1
21784-22344 23016-23576
800 24250-24450 25050-25250
1008 24549-24997 25557-26005 26 GHz
1008 24997-25445 26005-26453
1008 27548-27996 28556-29004 28 GHz
1008
ITU-R F.748-4, Annex 2 CEPT 13-02E
27996-28444 29004-29452
FibeAir® RFU-C Installation Guide A-3
Frequency Band
Separation MHz Standard Tx Low
MHz Tx High
MHz
812 31815-32207 32627-33019 32 GHz
812
ITU-R F.1520-2
CEPT (01) 32179-32571 32991-33383
700 38600-38950 39300-39650
700
ITU-R F.749-2, Annex1
CEPT 12-01E
CFR47 101.147 38950-39300 39650-40000
1000 38050-38500 39050-39500
1260 37058-37618 38318-38878
38 GHz
1260
ITU-R F.749-2,
Annex 3,1 37618-38178 38878-39438
FibeAir® RFU-C Installation Guide A-4
* Low Frequency Bands and Frequency Channel Allocation
Frequency TR Spacing/Block Channel Tx Low
MHz Tx High
MHz
1-3 5941-6049 6181-6289 240A
4-6 6061-6169 6301-6409
1-4 5931.2-6048.2 6183.2-6300.2
3-6 5992-6106 6244-6358 252A
5-8 6049.8-6166.8 6301.8-6418.8
1-4 5916.4-6033.3 6168.4-6285.4 252B
5-8 6035-6151.9 6287-6404
1-2 5941-6029 6201-6289 260A
3-4 6061-6149 6321-6409
1-4 5927-6039 6193-6305
L6 GHz
266A 5-8 6039-6151 6305-6417
300A 2-3 5973.5-6091.5 6273.5-6391.5
1-6 6540.5-6609.5 6710.5-6769.5
7-12 6610.5-6669.5 6770.5-6829.5 170A
13-16 6670.5-6709.5 6830.5-6869.5
1-4 6446-6594 6786-6934 340A
5-8 6606-6754 6946-7094
1-4 6426-6574 6766-6914 340B
5-8 6586-6734 6926-7074
H6 GHz
340C 1-2 6694-6750 7034-7090
1-2 7428-7484 7582-7638
2-3 7456-7512 7610-7666
3-4 7484-7540 7638-7694 154A
4-5 7512-7568 7666-7722
1-2 7442-7498 7596-7652
2-3 7470-7526 7624-7680 154B
4-5 7526-7582 7680-7736
1-2 7128-7184 7282-7338
2-3 7156-7212 7310-7366
3-4 7184-7240 7338-7394
7 GHz
154C
4-5 7212-7268 7366-7422
FibeAir® RFU-C Installation Guide A-5
Frequency TR Spacing/Block Channel Tx Low
MHz Tx High
MHz
1-2 7124.5-7180.5 7285.5-7341.5
2-3 7152.5-7208.5 7313.5-7369.5
3-4 7180.5-7236.5 7341.5-7397.5 161A
4-5 7203-7264.5 7364-7425.5
1-2 7249.5-7305.5 7410.5-7466.5
2-3 7277.5-7333.5 7438.5-7494.5 161B
4-5 7333.5-7389.5 7494.5-7550.5
1-2 7424.5-7480.5 7585.5-7641.5
2-3 7452.5-7508.5 7613.5-7669.5 161C
4-5 7508.5-7564.5 7669.5-7725.5
1-2 7549.5-7605.5 7710.5-7766.5
2-3 7577.5-7633.5 7738.5-7794.5 161D
4-5 7633.5-7689.5 7794.5-7850.5
1-2 7115.5-7189.5 7276.5-7350.5
2-3 7164.5-7238.5 7325.5-7399.5
4-5 7415.5-7489.5 7576.5-7650.5 161F
5-6 7464.5-7538.5 7625.5-7699.5
1-2 7421-7477 7582-7638
2-3 7449-7505 7610-7666 161I
4-5 7505-7561 7666-7722
1-2 7414-7470 7582-7638
2-3 7442-7498 7610-7666
7 GHz
161J
4-5 7498-7554 7666-7722
FibeAir® RFU-C Installation Guide A-6
Frequency TR Spacing/Block Channel Tx Low
MHz Tx High
MHz
1-2 7485.5-7538.5 7646.5-7699.5 161K
2-3 7513.5-7566.5 7674.5-7727.5
1-2 7443-7499 7611-7667
2-3 7471-7527 7639-7695 168B
4-5 7527-7583 7695-7751
1-2 7414-7470 7596-7652
2-3 7442-7498 7624-7680 182A
4-5 7498-7554 7680-7736
1-3 7107-7191 7303-7387 196A
3-5 7163-7247 7359-7443
1-4 7428-7540 7673-7785 245A
5-8 7540-7652 7785-7897
1-5 7136-7284 7436-7584
7 GHz
300A 6-9 7286-7404 7586-7704
1-3 8279-8335 8398-8454 119A
4-6 8321-8377 8440-8496
1-2 8203-8259 8357-8413
2-3 8231-8287 8385-8441 154A
4-5 8287-8343 8441-8497
1-4 8050-8162 8258-8370 208A
5-7 8162-8246 8370-8454
1-4 8025-8095 8275-8345 250A
5-8 8081-8151 8331-8401
252A 1-2 7976-8034 8228-8286
1-4 7912-8024 8178-8290 266A
5-8 8024-8136 8290-8402
266B 1-2 7926-8010 8192-8276
1-4 7726-7844 8026-8144 300A
5-8 7846-7964 8146-8264
1-3 7731-7839 8041-8149
8 GHz
310A 4-6 7851-7959 8161-8269
FibeAir® RFU-C Installation Guide A-7
Frequency TR Spacing/Block Channel Tx Low
MHz Tx High
MHz
1-3 7905-7989 8215-8299
2-4 7933-8017 8243-8327 310C
4-6 7989-8073 8299-8383
1-2 7905-7989 8215-8299
2-3 7933-8017 8243-8327 310D
4-5 7989-8073 8299-8383
1-4 7733.7-7850.7 8045-8162 311A
5-8 7852.3-7969.3 8163.6-8280.6
1-4 7718.9-7835.8 8030.2-8147.1 311B
5-8 7837.5-7954.4 8148.8-8265.7
8 GHz
530A 1-2 7746-7774 8276-8304
FibeAir® RFU-C Installation Guide A-8
6-8 GHz Frequency Channels Note: For additional channel schemes, please contact your Ceragon representative.
6L GHz (5.85-6.45 GHz)
ITU-R F.383-7 [1-3]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 5955.00 1 6195.00
2 5995.00 2 6235.00
3 6035.00 3 6275.00
4 6075.00 4 6315.00
5 6115.00 5 6355.00
240
6 6155.00 6 6395.00
ITU-R F.383-7 [0] / FCC 101.147(i8)
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 5945.20 1 6197.24
2 5974.85 2 6226.89
3 6004.50 3 6256.54
4 6034.15 4 6286.19
5 6063.80 5 6315.84
6 6093.45 6 6345.49
7 6123.10 7 6375.14
252.04
8 6152.75 8 6404.79
FibeAir® RFU-C Installation Guide A-9
FCC 101.147(i7)
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 5935.32 1 6187.36
2 5945.2 2 6197.24
3 5955.08 3 6207.12
4 5964.97 4 6217.01
5 5974.85 5 6226.89
6 5984.73 6 6236.77
7 5994.62 7 6246.66
8 6004.5 8 6256.54
9 6014.38 9 6266.42
10 6024.27 10 6276.31
11 6034.15 11 6286.19
12 6044.03 12 6296.07
13 6053.92 13 6305.96
14 6063.8 14 6315.84
15 6073.68 15 6325.72
16 6083.57 16 6335.61
17 6093.45 17 6345.49
18 6103.33 18 6355.37
19 6113.22 19 6365.26
20 6123.1 20 6375.14
21 6132.98 21 6385.02
22 6142.87 22 6394.91
23 6152.75 23 6404.79
252.04
24 6162.63 24 6414.67
FibeAir® RFU-C Installation Guide A-10
ITU-R F.384-7
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 5955.00 1 6215.00
2 6015.00 2 6275.00
3 6075.00 3 6335.00 260
4 6135.00 4 6395.00
ITU-R F.497-6 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 5941.00 1 6207.00
2 5969.00 2 6235.00
3 5997.00 3 6263.00
4 6025.00 4 6291.00
5 6053.00 5 6319.00
6 6081.00 6 6347.00
7 6109.00 7 6375.00
266
8 6137.00 8 6403.00
FibeAir® RFU-C Installation Guide A-11
6H GHz (6.45-7.1 GHz)
ITU-R F.384-7
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 6460.00 1 6800.00
2 6500.00 2 6840.00
3 6540.00 3 6880.00
4 6580.00 4 6920.00
5 6620.00 5 6960.00
6 6660.00 6 7000.00
7 6700.00 7 7040.00
340
8 6740.00 8 7080.00
FCC 101.147(k7)
T/R Separation
n (L)
Center Frequency
MHz n (H)
Center Frequency
MHz
1 6545 1 6715
2 6555 2 6725 170
3 6565 3 6735
4 6585 4 6745
5 6595 1 6755
6 6605 2 6765
7 6615 3 6775
8 6625 4 6785
9 6635 5 6795
10 6645 6 6805
11 6655 7 6815
12 6665 8 6825
13 6675 9 6835
14 6685 10 6845
15 6695 11 6855
160
16 6705 12 6865
FibeAir® RFU-C Installation Guide A-12
7 GHz (7.1-7.9 GHz)
ITU-R 385-7 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7442 1 7596
2 7470 2 7624
3 7498 3 7652
4 7526 4 7680
154A
5 7554 5 7708
ITU-R 385-7 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7456 1 7610
2 7484 2 7638
3 7512 3 7666
4 7540 4 7694
154B
5 7568 5 7722
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7138.5 1 7299.5
2 7226 2 7387
3 7428 3 7589 161
4 7526 4 7687
FibeAir® RFU-C Installation Guide A-13
ITU-R 385-7 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7442 1 7687
2 7470 2 7715
3 7498 3 7743
4 7526 4 7771
5 7554 5 7799
6 7582 6 7827
7 7610 7 7855
245
8 7638 8 7883
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7138.5 1 7299.5
2 7166.5 2 7327.5
3 7194.5 3 7355.5
4 7222.5 4 7383.5
5 7250.5 5 7411.5
11 7145.5 11 7306.5
12 7173.5 12 7334.5
13 7201.5 13 7362.5
14 7229.5 14 7390.5
21 7152.5 21 7313.5
22 7180.5 22 7341.5
23 7208.5 23 7369.5
24 7236.5 24 7397.5
31 7159.5 31 7320.5
32 7187.5 32 7348.5
33 7215.5 33 7376.5
161A
34 7243.5 34 7404.5
FibeAir® RFU-C Installation Guide A-14
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7263.5 1 7424.5
2 7291.5 2 7452.5
3 7319.5 3 7480.5
4 7347.5 4 7508.5
5 7375.5 5 7536.5
11 7270.5 11 7431.5
12 7298.5 12 7459.5
13 7326.5 13 7487.5
14 7354.5 14 7515.5
21 7277.5 21 7438.5
22 7305.5 22 7466.5
23 7333.5 23 7494.5
24 7361.5 24 7522.5
31 7284.5 31 7445.5
32 7312.5 32 7473.5
33 7340.5 33 7501.5
161B
34 7368.5 34 7529.5
FibeAir® RFU-C Installation Guide A-15
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7438.5 1 7599.5
2 7466.5 2 7627.5
3 7494.5 3 7655.5
4 7522.5 4 7683.5
5 7550.5 5 7711.5
11 7445.5 11 7606.5
12 7473.5 12 7634.5
13 7501.5 13 7662.5
14 7529.5 14 7690.5
21 7452.5 21 7613.5
22 7480.5 22 7641.5
23 7508.5 23 7669.5
24 7536.5 24 7697.5
31 7459.5 31 7620.5
32 7487.5 32 7648.5
33 7515.5 33 7676.5
161C
34 7543.5 34 7704.5
FibeAir® RFU-C Installation Guide A-16
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7563.5 1 7724.5
2 7591.5 2 7752.5
3 7619.5 3 7780.5
4 7647.5 4 7808.5
5 7675.5 5 7836.5
11 7570.5 11 7731.5
12 7598.5 12 7759.5
13 7626.5 13 7787.5
14 7654.5 14 7815.5
21 7577.5 21 7738.5
22 7605.5 22 7766.5
23 7633.5 23 7794.5
24 7661.5 24 7822.5
31 7584.5 31 7745.5
32 7612.5 32 7773.5
33 7640.5 33 7801.5
161D
34 7668.5 34 7829.5
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7435 1 7596
2 7463 2 7624
3 7491 3 7652
4 7519 4 7680
161I
5 7547 5 7708
FibeAir® RFU-C Installation Guide A-17
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7428 1 7589
2 7456 2 7617
3 7484 3 7645
4 7512 4 7673
161J
5 7540 5 7701
ITU-R 385-7 [0]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7498 1 7659
2 7526 2 7687 161K
3 7554 3 7715
ITU-R 385-7 [3]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7457 1 7625
2 7485 2 7653
3 7513 3 7681
4 7541 4 7709
168B
5 7569 5 7737
FibeAir® RFU-C Installation Guide A-18
ITU-R 385-7 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7428 1 7610
2 7456 2 7638
3 7484 3 7666
4 7512 4 7694
182
5 7540 5 7722
ITU-R 385-7 [3]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7121 1 7317
2 7149 2 7345
3 7177 3 7373
4 7205 4 7401
196
5 7233 5 7429
ITU-R 385-7 [4]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7442 1 7687
2 7470 2 7715
3 7498 3 7743
4 7526 4 7771
5 7554 5 7799
6 7582 6 7827
7 7610 7 7855
245
8 7638 8 7883
FibeAir® RFU-C Installation Guide A-19
8 GHz (7.8-8.5 GHz)
ITU-R 386-6 [4]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7926 1 8192
2 7954 2 8220
3 7982 3 8248
4 8010 4 8276
5 8038 5 8304
6 8066 6 8332
7 8094 7 8360
266
8 8122 8 8388
ITU-R 386-6 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7747.70 1 8059.02
2 7777.35 2 8088.67
3 7807.00 3 8118.32
4 7836.65 4 8147.97
5 7866.30 5 8177.62
6 7895.95 6 8207.27
7 7925.60 7 8236.92
311.32A
8 7955.25 8 8266.57
FibeAir® RFU-C Installation Guide A-20
ITU-R 386-6 [1]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 7732.875 1 8044.195
2 7762.525 2 8073.845
3 7792.175 3 8103.495
4 7821.825 4 8133.145
5 7851.475 5 8162.795
6 7881.125 6 8192.445
7 7910.775 7 8222.095
311.32B
8 7940.425 8 8251.745
ITU-R 386-6 [3]
T/R Separation
n (L)
Center Frequency
MHz
n (H)
Center Frequency
MHz
1 8293 1 8412
2 8307 2 8426
3 8321 3 8440
4 8335 4 8454
5 8349 5 8468
119
6 8363 6 8482