Welcome, Introduction and Purpose Mandla Sibanyoni
Objective/s of the Pre-Tender Briefing &
Plant Site Inspection
Mandla Sibanyoni
Procurement & Transformation Mandla Sibanyoni
Scope of work and technical requirements Tsepo Matekane
Discussion, Questions & Answers All
Closing Remarks Mandla Sibanyoni
1. CONDITION OF AWARD
Anyone awarded this Contract will not be allowed to participate in the
subsequent Plant and Design Build Contract.
2. PROCUREMENT PROCESS
2.1 Two envelope tender process
Functional evaluation (Technical and Transformation)
Price and BBBEE
2.2 Tender submission
Two separate envelopes and clearly marked
No Financial Information in envelope A
2.3 Tender evaluation
Preferential Procurement Regulations, 2017
First stage: Functional evaluation
Transformation, 50 points, minimum 28 points. Points scored above
minimum requirements
Technical, 100 points, minimum 53 points and minimum points for key
personnel as per minimums stipulated in Table 2Financial Standing,
Second stage: Price and BBBEE status level
2.4 Compliance submission
Mandatory documents / non mandatory
2.5 Disqualification Criteria
Failing to achieve the following minimum scores:
28 (of 50) points for Functional Transformation.
53 (of 100) points for Functional Technical.
for personnel as per minimums stipulated in Table 2.
The Tenderer that does not attend the compulsory briefing meeting
2. COMMUNICATION
All clarifications must be sent to [email protected]
3. CLOSING DATE
06 April 2018 at 14:00hrs at 265 West Avenue, Tuinhof Building, Stinkhout
Wing, Ground floor, CENTURION, 0157
4. REGISTRATION ON THE NATIONAL TREASURY’S CSD
Must be registered prior submission of tender. Members of Joint Ventures must
also be registered prior submission of tender.
5. TENDER VALIDITY PERIOD
180 days from the closing date.
6. FRONTING
Zero tolerance
7. JOINT VENTURES OR CONSORTIUM
Right to review the joint venture or consortium agreement or Memorandum Of
Understanding
1. TRANSFORMATION REQUIREMENTS
1.1 OWNERSHIP: PARTICIPATION OF BLACK OWNED ENTERPRISE
(BOE)
Minimum 45% participation of BOE
1.2 EMPLOYMENT
Minimum
30% participation of BPP in MANCO Person-months.
40% participation of BPP in the Specialist Person-months
45% participation of BPP in the Environmental Person-months
50% participation of BPP in the Engineering Person-months
50% participation of BPP in the Project Management Person-months
1.3 SKILLS DEVELOPMENT
Minimum requirement
Two bursaries bursaries
Project overview
The Western Cape Water
Supply System serves
the City of Cape Town and
Surrounding smaller towns
And irrigators.
The system consist of infrastructure
Components owned and operated
By both CCT & DWS.
This particular tender is however only
Restricted to taking water from
The Berg River through pipeline into
the Voelvlei Dam (Refer to sketch)
The project involves the transfer of 23 million m3/ a from the Berg River to existing Voelvlei Dam from 2021
It entails construction of a weir and abstraction works
Construction of the water transfer system at a discharge rate of approx. 4 m3/s (i.e. pump station and a 1.7mᴓ pipeline of about 6.3km long; 35m dynamic head), including off-take to the existing SwartlandWater Treatment Works to facilitate summer releases into the Berg River for environmental water requirements, thus eliminating the need to utilise the existing canal from which water losses occur
Construction of appurtenant works – fishway, canoe chute, roads, etc.
Project also entails the decommissioning of the existing canal that will be redundant due to the construction of the above
Electricity supply and associated installations to energise
the pump station
Implementation of measures to mitigate the impact of the
project on the environment, in accordance with the EA (June
2017) and EMPr (not yet in place)
The Employers procurement strategy is based on the FIDIC
Plant Design and Build Contract to implement this project.
We therefore require Professional Service Provider (PSP) to
provide the following services
Task 1: Tender Review
Task 2: Design Review
Task 3: Construction Monitoring
Task 4: Post Construction Monitoring
Task 5: Project Management
Task 1 : Tender Documentation Review
The employer (TCTA) has prepared the draft tender document for the Plant and Design Build Contract (FIDIC yellow book). The Consultant shall critically review the Tender document
The Consultant shall study all the existing information and provide the following services
Review of preliminary design, Consultant shall review previous designs, assess all relevant information and establish whether or not any additional information is required
The review and assessment will cover the following:
• Review the DWS feasibility study reports covering the planning and design of BRVAS to confirm the decisions and to determine where additional studies will be required to supplement available data
• Review the cost analysis of the system
• Review of position and layout of the infrastructure
• Review the operation rule/philosophy of the scheme
• We will expect the Consultant to identify gaps, discrepancies, errors or omissions and give recommendations
Tender Evaluation and Award of the Plant & Design Build
Contract
The Consultant shall assist TCTA with the tendering process and establishment of the Plant and Design Build Contract
In conjunction with TCTA, Consultant will organize a site inspection and meetings for Tenderers as well as assist in providing clarifications during the Tender
Participate in contract negotiations between TCTA and the preferred Tenderer
Participate in the preparation of the Memorandum of Understanding (MOU)
Environment (Natural and Social)
The Consultant will be expected to review and make inputs
into the Environmental Management Programme for
construction as required to be submitted to Department of
Environmental Affairs
Consultant shall also highlight specific areas where
environmental and social requirements may impose
particular conditions or create operational restraints on the
project
Land Acquisition
Consultant shall provide ongoing support prior to commencement of the Plant and Design Build Contract to ensure that contractors will be given access to site timeously
Health and Safety
Consultant shall ensure compliance with OHS act and the Construction Regulations 2014
These are the tasks under Task 1
Task 2: Design Review
Consultant will review and/or approve documents submitted
by the Contractor
Documents such as field investigation reports, studies and
surveys, designs, schedules and drawings
Environmental (Natural and Social) documents from the
Contractor will be reviewed by Consultant as well.
Task 3: Construction Monitoring
The Consultant shall provide suitably qualified personnel to monitor and administer the Plant and Design Build Contract
Task 4: Post Construction Monitoring
The objective of this task is to monitor completed infrastructure during the defects liability/notification period
Task 5: Project management
Project management section covers all the tasks required to fulfil Project Management requirements. This task is applicable to all the tasks above:
Full details of this task outlined explicitly in the tender document