Review of systems relating to Code Part 2, Divisions 1 to 4 … · Review of systems relating to...
Transcript of Review of systems relating to Code Part 2, Divisions 1 to 4 … · Review of systems relating to...
Network Quality & Reliability of Supply (NQRS) Code Audit
Review of systems relating to Code Part 2, Divisions 1 to 4
INDEPENDENT ASSURANCE REPORT
August 2016
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
i
Mr John Paolino
Senior Compliance Specialist
Regulatory Compliance
Western Power
363 Wellington Street
Perth WA 6000
7 September 2016
Dear John,
Re: 2015/16 Network Quality & Reliability of Supply (NQRS) Code Audit
I am pleased to provide our Independent Assurance Report resulting from the audit on the operation of the
systems that are in place to monitor compliance with Part 2 of the Electricity Industry (Network Quality &
Reliability of Supply) Code 2005 for the 2015/16 financial year.
I confirm my approval of the content of the report, and that it is an accurate presentation of the audit findings
and CutlerMerz’ opinions.
Sincerely,
Ryan Dudley
Principal
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
ii
Table of Contents
Executive Summary ................................................................................................................... 1
1 Introduction ..................................................................................................................... 3
1.1 Audit objective .................................................................................................................................................... 3
1.2 Western Power’s key systems and procedures .................................................................................................. 3
2 Audit Approach ............................................................................................................... 4
2.1 Audit scope ......................................................................................................................................................... 4
2.2 Audit standard ..................................................................................................................................................... 4
2.3 Audit steps .......................................................................................................................................................... 4
2.4 Audit team ........................................................................................................................................................... 5
2.5 Western Power key staff ..................................................................................................................................... 5
2.6 Audit grades ........................................................................................................................................................ 6
3 Western Power’s response to previous recommendations ......................................... 7
4 Performance summary ................................................................................................... 8
5 Observations ................................................................................................................. 10
6 Recommendations ........................................................................................................ 12
Appendix A Detailed findings ............................................................................................. 13
Appendix B Information provided ...................................................................................... 25
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
1
Executive Summary
The Electricity Industry (Network Quality & Reliability of Supply) Code 2005 (the “Code”) requires that Western
Power arrange for an independent expert to audit, and report on, the operation of the systems in place for
monitoring compliance with Part 2 of the Code.
CutlerMerz (“we”) have been engaged by Western Power to conduct the independent audit for the 2015/16
financial year. As required by the Code, the objective of the audit is to assess whether Western Power has
adequate controls (Process and Systems) in place to monitor compliance with each obligation under the Code.
We conducted the audit in accordance with the Economic Regulation Authority Western Australia (ERA)
Guidelines for Audit and the Australian Standard on Performance Engagements (ASAE 3500). Accordingly, our
audit report provides reasonable assurance as defined in ASAE 3500.
The key findings, areas for improvement and observations arising from the audit are as follows.
Assessment of the adequacy of controls
► In relation to all but one clause of Part 2 of the Code, we are of the opinion that Western Power has a
strong control environment and have assessed the adequacy of controls as “A – Adequate controls –
no improvement needed”.
► Clause 10(2) requires that Western Power consider whether, in specified circumstances, it should
supply electricity by alternative means to a customer who will be affected by a proposed interruption.
Western Power’s process for monitoring compliance with the requirement for providing alternate power
supplies to mitigate interruptions needs improvement.
Western Power’s process for achieving the Code requirement is through the Electronic Network Access
Request (ENAR) system. The system, which is used to plan outages on the network, prompts the user
to answer either “yes” or “no” as to whether an alternate supply is required during a planned outage. We
found that there is no process that supports the user to determine the “specified circumstances” to be
considered when making this assessment. Further, in the sample reviewed during the audit, the user
had answered “no” for a planned outage where the use of alternate supply would be interpreted as
being appropriate under the Code i.e. an outage was planned for 9.5 hours and the Code requires an
alternate supply be considered for outages exceeding 6 hours (or 4 hours if temperatures are forecast
to exceed 30 degrees Celsius).
We have assessed the adequacy of controls in relation to clause 10(2) to be “B – Generally adequate
controls – improvement needed”. It is recommended that Western Power introduce a process to
ensure that the use of alternate power supplies is considered for planned outages, in view of the
specific circumstances identified in the Code.
Observations
Overall, we consider Western Power’s systems in relation to Part 2 of the Code to be adequate.
Notwithstanding this, we have also made observations in Section 5 of this report that relate to opportunities for
improvement that in our opinion would contribute to better network quality and reliability outcomes, irrespective
of the adequacy of controls:
► Under the requirements of the Code, interruptions arising from weather events are included (without
any exceptions) in determining performance reliability. As a consequence, Western Power consistently
reports a substantial number of breaches against a portion of the Code requirements (which Western
Power advises are predominantly due to outages occurring during extreme weather events). Western
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
2
Power is also required to make payments to customers where they make a claim against these
breaches.
While we have assessed Western Power’s systems for monitoring reliability performance as being
adequate, we are aware that other jurisdictions (as well as the AER) allow for the exclusion of extreme
weather events for reliability reporting and compliance requirements. This contributes towards:
i. Service providers not being required to invest to reinforce the network to withstand extreme
weather events; and
ii. Underlying performance being more effectively monitored, rather than sustaining unrealistic
reliability targets which include the distortion from extreme weather event anomalies. Effective
monitoring of underlying performance drives tighter focus on achieving the reliability objectives in
general, and particularly in remediating poor performing sections of the network.
We consider that given Western Power’s transition to the national regulatory regime, it may be
appropriate to consider amending the Code to allow for the exclusion of extreme weather events, using
well established principles, from the reliability performance measurements.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
3
1 Introduction
CutlerMerz was engaged by Western Power to conduct an independent audit and report on the operation of the
systems that are in place to monitor compliance with Part 2 of the Electricity Industry (Network Quality &
Reliability of Supply) Code 2005 (the “Code”) for the 2015/16 financial year.
The requirement for an audit of these systems relating to Part 2 of the Code is based on clause 26 of Part 4 –
Division 3, which reads as follows:
Part 4 — Duties incidental to the prescribed standards
Division 3 — Performance reporting
26. Annual report on monitoring systems
(1) A transmitter and a distributor must, as required by subsection (2), arrange for an
independent expert to audit, and report on, the operation of the systems that the
transmitter or the distributor has in place for monitoring its compliance with Part 2 or an
instrument made under section 14(3).
(2) An audit under subsection (1) is to be carried out in respect of the operation of such
systems during each year ending on 30 June.
1.1 Audit objective
The objective of the audit is to make an independent assessment of the operation of the systems used by
Western Power for monitoring its compliance with Part 2 of the Code between 1 July 2015 and 30 June 2016.
1.2 Western Power’s key systems and procedures
With regards to compliance with the Code, Western Power has implemented a number of systems and
procedures in order to achieve compliance. The key systems are identified below.
Reliability
PowerOn Fusion (PoF): PoF is a leading industry tool for network control and management. It
integrates call centre, network control, and data capture and removes much of the manual processing
that is traditionally prone to human-error in relation to monitoring customer notifications and network
reliability data. Data is extracted and stored from PoF within the Data Warehouse, and then reliability
data is processed for reporting via the Network Reliability Data Validator (NRDV). Although there is
always room for improvement at data interface and processing points, CutlerMerz considers the PoF /
Data Warehouse / NRDV system to be a strong system for capturing and processing customer and
network information.
Electronic Network Access Request (ENAR): The ENAR system is used to request planned outages
and capture information in relation to the works. It is a functional tool for ensuring compliance with the
code in relation to planned outage requirements.
Power quality
Power quality: Power quality notifications are captured through PoF, before being actioned through
business as usual processes. CutlerMerz considers this to be a generally appropriate system for
managing power quality issues.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
4
2 Audit Approach
We assessed Western Power’s compliance with the applicable Code requirements by undertaking the following:
A review of Western Power’s systems designed to meet the compliance requirements;
A review of Western Power’s systems designed to monitor compliance; and
Identifying any opportunities for improvement.
The full approach is summarised as follows (refer to the Audit Plan for further detail):
A risk-based approach to focus the audit on higher risk areas – based on Australian/New Zealand
Standard 31000:2009 (Risk Management – Principles and Guidelines);
Fieldwork to interview Western Power personnel at the head office and operational office. This helped
to gain an appreciation of the control environment, information systems, control procedures, compliance
attitude and outcome compliance;
Sampling procedures in accordance with ASA 500 and ASA 530 (Audit Sampling); and
Reporting in accordance with using the format prescribed in the Authority Guidelines (Guidelines
Section 11), ASAE 3000 and AEAE 3500.
2.1 Audit scope
The scope of the audit covers the systems in place at Western Power to monitor compliance against Part 2 of
the Code, which includes four divisions:
Division 1 - Quality Standards
Division 2 - Standards for the interruption of supply to individual customers
Division 3 - Standards for the duration of interruptions of supply in particular areas
Division 4 - Variations of obligations under this Part
2.2 Audit standard
The audit scope is based on the Audit Guidelines1. An audit plan was developed by the auditor based on the
requirements in the Audit Guidelines, a review of Part 2 of the Code and the auditors experience conducting
reviews and audits of the systems and procedures for monitoring quality and reliability of electricity network
businesses.
The audit report was subsequently reviewed and approved by Western Power.
2.3 Audit steps
The audit steps are summarised in Table 1.
1 Audit and Review Guidelines: Electricity and Gas Licences, April 2014, Economic Regulation Authority Western Australia
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
5
Table 1: Audit steps
Audit step Tasks
Planning Desktop review of policy and procedures
Prepare audit plan
Field audit
Control room visit Wednesday 20 August
Western Power office Thursday 21 August
Western Power office Friday 22 August
Off-site review and reporting Review supplementary documentation and prepare audit report
2.4 Audit team
The audit team is outlined in Table 2.
Table 2: Audit team
Name Role Responsibility
Ryan Dudley Audit Director and
Lead Auditor
Overall responsibility for the delivery of the audit and participation in field audits
Adam Homan Project Manager
and Auditor
Day-to-day management and delivery of the audit plan, field audits and audit report
2.5 Western Power key staff
The key Western Power staff that have participated in the audit are identified in Table 3.
Table 3: Western Power key staff
Title / Role Key Area(s) of Discussion
Network Operations – Network Operations Development Manager Planned and unplanned outage management
Network Operations – Quality and Compliance Officer Network Operations quality systems and documentation
Network Operations – Network Control Room Manager Planned and unplanned outage management
PowerOn Fusion
Network Operations – Compliance Business Analysts PowerOn Fusion
Customer Service – Complaints & Resolution Team Leader Customer service
Customer Service – Senior Process & Governance Analyst Customer service
Customer Service – Planned Outage Notification Team Leader Customer service
Planned outage management
Customer Service – Access Solutions Manager Customer agreements
Instruments from the Minister
Information & Communications Technology – Senior Information
Consultant
IT systems (including PowerOn Fusion, Data Warehouse, and
Network Reliability Data Validator)
Network Planning – Senior Asset Strategy Engineer Data processing and reporting
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
6
Title / Role Key Area(s) of Discussion
Network Reliability Data Validator
Works Program and Planning – Scheduling Manager Planned outage management
Works Program Planning – Scheduling & Coordination Team
Leader Planned outage management
Works Program Planning – Outage Coordination & Compliance
Project Support Officer Planned outage management
Strategic Network Planning – Network Planning & Standards Network design to achieve compliance
Remediation of poor performing network elements
Network Planning – Senior Planning Engineer Network design to achieve compliance
Remediation of poor performing network elements
Network Planning – Senior Asset Strategy Engineer Power quality management
Asset Operations, Operational Maintenance – Senior Technical
Officer
Field implementation of power quality investigations
Field implementation of mobile generators (for both planned and
unplanned outages)
Regulatory Compliance – Senior Compliance Specialist General reporting and compliance issues
2.6 Audit grades
The evaluation of compliance was undertaken by adapting the compliance grades outlined in the Audit
Guidelines to assess the adequacy of controls rating only. This is shown in Table 4.
Table 4: Audit compliance ratings
Performance audit compliance and controls rating scales (adapted from ERA Audit Guidelines)
Adequacy of Controls (Process and Systems) Rating
Rating Description
A Adequate controls – no improvement needed
B Generally adequate controls – improvement needed
C Inadequate controls – significant improvement required
D No controls evident
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
7
3 Western Power’s response to previous recommendations
The systems and procedures to ensure compliance against Part 2 of the Code were previously audited by
Deloitte for the 2014-15 period. There were no recommendations made as a result of this audit.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
8
4 Performance summary
Table 5 summarises the compliance rating for each Code related licence condition using the rating scale
described in Section 2.6.
As required by the Audit Guidelines, the primary objective of the audit ratings is to provide an independent
assessment of Western Power’s adequacy of controls for monitoring compliance to the Code licence conditions.
The observations supporting the ratings in Table 5 are discussed in Section 5 while the detailed findings for
each licence condition and additional information on the rationale for each of the ratings can be found in
Appendix A.
Table 5: Audit ratings
Compliance
Obligation
Reference No. Licence Reference
Audit
Priority
applied
Adequacy of
Controls Rating
A B C D
462 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 5(1)
A distributor or transmitter must, as far as reasonably practicable, ensure that electricity
supply to a customer’s electrical installations complies with prescribed standards.
4
463 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 8
A distributor or transmitter must, so far as reasonably practicable, disconnect the supply
of electricity to installations or property in specified circumstances, unless it is in the
interest of the customer to maintain the supply.
4
464 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 9
A distributor or transmitter must, as far as reasonably practicable, ensure that the supply
of electricity is maintained and the occurrence and duration of interruptions is kept to a
minimum.
5
465 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 10(1)
A distributor or transmitter must, so far as reasonably practicable, reduce the effect of
any interruption on a customer.
4
466 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 10(2)
A distributor or transmitter must consider whether, in specified circumstances, it should
supply electricity by alternative means to a customer who will be affected by a proposed
interruption.
4
467 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 12(3)
A distributor must take prescribed action in the event of a significant interruption to a
small use customer.
5
468 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 13(2)
A distributor or transmitter must, so far as reasonably practicable, ensure that customers
in specified areas do not have average total lengths of interruptions of supply greater
than specified durations.
4
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
9
Compliance
Obligation
Reference No. Licence Reference
Audit
Priority
applied
Adequacy of
Controls Rating
A B C D
469 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 13(3)
The average total length of interruptions of supply is to be calculated using the specified
method.
5
470 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 14(8)
A distributor or transmitter must, on request, provide to an affected customer a free copy
of an instrument issued by the Minister and of any notice given under section 14(7) of the
Electricity Industry (Network Quality and Reliability of Supply) Code 2005.
5
471 Electricity Industry (Network Quality and Reliability of Supply) Code 2005 clause 15(2)
A distributor or transmitter that agrees with a customer to exclude or modify certain
provisions must set out the advantages and disadvantages to the customer of doing so in
their agreement.
3
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
10
5 Observations
All Western Power personnel that participated in the audit process demonstrated an understanding of the Code
and its requirements, and a commitment to effective management of power quality and network reliability by the
business.
Overall, we consider Western Power’s systems in relation to Part 2 of the Code to be adequate. The systems in
effect are generally consistent with those effected by peer businesses, and we have observed some peers with
less robust systems in place.
Notwithstanding the above, we observe that leading peers tend to have a sharper focus on ensuring their
specific requirements are achieved; in terms of the specific requirements being embedded throughout strategic,
tactical and day-to-day decision marking criteria. Based on observations, we consider that there are likely to be
three factors contributing to this, which are linked to the mechanisms of Western Power’s regulatory regime
rather than system capability:
1) The inclusion of extreme weather events in the reporting of reliability metrics has the effect of reducing
emphasis on achieving the requirements, where:
Reporting substantial breaches on an ongoing basis creates an environment where it is acceptable
that breaches are unavoidable; and
The distortion of the metrics by these events masks the underlying performance, which in turn may
reduce focus on monitoring, tracking and remediating these sections of the network.
2) We understand that it is not a requirement for Western Power to be audited on compliance against the
specific performance targets, including a validation of the figures that are captured and reported. We
understand that this audit, which focuses on the operation of the systems that are in place to monitor
compliance, is the only audit required in relation to power quality and reliability. We have observed an
iterative effect within peers that are audited for compliance (including a data accuracy validation
component), where focus on the requirements is continually sharpened.
3) Western Power also has reliability targets prescribed under its access arrangements (Service Standard
Benchmarks – SSB), which are different from those required under the Code. The SSBs are linked to a
performance incentive scheme that has positive/negative financial outcomes. Whilst Western Power’s
documentation considers both the requirements of the Code and the SSBs, we consider that focus will
naturally be sharper on achieving the SSBs which are linked to financial incentives.
In Section 6 it is recommended that a process be implemented to ensure relevant factors are duly considered in
determining the circumstances for when mobile generation should be deployed for a planned outage. The three
factors above are likely to have contributed to this process not presently being in effect.
Our observations in relation to the above are as follows (refer to detailed findings on Clause 10(2) in Appendix
A):
The ENAR system requires the originator of the outage request to consider whether mobile
generation is required (in the ENAR guide2 this is in the form of a prompt for a yes/no answer).
However, it does not appear to provide any further guidance on when a mobile generator would be
required. CutlerMerz has not observed a procedural document relating to the use of mobile
generators during planned outages.
2 DM#33995956
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
11
CutlerMerz has reviewed a sample planned interruption form3 for an outage affecting a life support
equipment (LSE) customer. This outage affected 117 customers over a period from 7am to 4:30pm
(9.5 hours). For this outage the ENAR requestor had answer “no” to the “Generators required?”
prompt and it does not appear that a mobile generator was used for this outage.
Western Power’s scheduling team has advised that they do consider using mobile generators under
the circumstances specified by the Code; however, CutlerMerz has not observed a procedure to
support this practice.
In relation to Clause 15(2), it is noted that Western Power has not entered into any agreements with customers
in relation to where the “prescribed standards” are not met. It may be considered appropriate under the Code for
Western Power to enter into agreements with customers based on the substantial number of breaches being
reported on an ongoing basis. However, in our view, it would be more appropriate to amend the relevant
clauses of the code to exclude extreme weather events. We consider that it would be impractical for Western
Power to enter into an agreement with each customer that may be subject to extreme weather events.
The detailed findings of the audit in relation to each obligation are provided in Appendix A.
3 DM#9431078
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
12
6 Recommendations
The recommendations from the audit are provided in Table 6.
Table 6: Audit recommendations
Table of Current Audit Non Compliances / Recommendations
A. Resolved during current Audit period
Manual
Ref.
Non Compliance / Controls improvement
(Rating / Legislative Obligation / Details of
Non Compliance or inadequacy of controls)
Date Resolved (&
management action taken) Auditors comments
N/A – there were no non-compliances / recommendations from previous audit (and hence, none that were required to be resolved during the
current audit period).
A. Unresolved at end of current Audit period
Reference
(no. /
year)
Non Compliance / Controls improvement
(Rating / Legislative Obligation / Details of
Non Compliance or inadequacy of controls)
Auditors’ recommendation
Management action
taken by end of audit
period
01/2016 Rating: B
Legislative Obligation: Electricity Industry (Network
Quality and Reliability of Supply) Code 2005 clause 10(2) –
A distributor or transmitter must consider whether, in
specified circumstances, it should supply electricity by
alternative means to a customer who will be affected by a
proposed interruption.
Details of inadequacy of controls: Whilst Western
Power’s ENAR system prompts the planned outage
requestor to state whether or not mobile
generation is required for a planned outage, there
does not appear to be procedural guidance, based
on the requirements of the Code, as to when these
should be deployed. It is noted that Western
Power’s scheduling team has advised that they do
consider using mobile generators under the
circumstances specified by the Code; however,
CutlerMerz has not observed a procedure to
support this practice. CutlerMerz has observed an
outage example of planned outage documentation
where the use of mobile generation may have been
considered appropriate based on the Code; but the
ENAR requestor did not request mobile generation
and it did not appear to be deployed in this
instance.
It is recommended that Western
Power introduce a process to ensure
that the use of alternate power
supplies is considered for planned
outages, in view of the specific
circumstances identified in the Code.
Western Power will review, and
if required improve, its current
processes relating to the use of
alternative power supply for
planned outages in
circumstances identified in
clause 10(2) of the Code.
Due date: 31 December 2016
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
13
Appendix A Detailed findings
The detailed findings from the audit are provided in Table 7.
Table 7: Detailed findings
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
An outline of the criteria for compliance Discussion of the evidence and how the compliance assessment was determined i.e. whether the evidence was sufficient to
demonstrate compliance or not.
Recommendations / Opportunities for Improvement are identified where relevant
Division 1 Compliance obligation reference No: 462
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 5(1)
Obligation: A distributor or transmitter must, as far as
reasonably practicable, ensure that electricity supply to a
customer’s electrical installations complies with prescribed
standards.
Context: The “prescribed standards” relates to the
standards for harmonics and voltage fluctuation – refer to
Code 2005, Part 2, Division 1, Clause 6(2) and Clause 7.
CutlerMerz has interviewed personnel responsible for power quality at Western Power, and reviewed relevant information as
appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems, processes and
mechanisms in place to practicably ensure compliance with the standards for harmonics and voltage fluctuations. These relate
to:
The design of the system and connections to the network;
Proactive monitoring of power quality performance; and
Reactive actions where Western Power becomes aware of a power quality issue.
Findings in relation to each of the above are discussed below.
System design
It is understood that Western Power designs its system in accordance with the Australian standards for Electromagnetic
Compatibility (EMC)4. CutlerMerz has reviewed the standards and found them to be effectively consistent with the
requirements of the Code in relation to both harmonics and voltage fluctuation.
4 Standards Australia / Standards New Zealand, Technical Report – Electromagnetic compatibility (EMC) – Part 3.14: Limits–Assessment of emission limits for harmonics, interharmonics, voltage fluctuations and unbalance for the
connection of disturbing installations to LV power systems, SA/SNZ TR IEC 61000.3.14:2013, EC/TR 61000-3-14, Ed.1.0 (2011)
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
14
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
CutlerMerz has reviewed the generator connection process5 and confirms that this requires a power quality assessment as
part of the preliminary assessment phase and a review of power quality commissioning results during the commissioning
phase. CutlerMerz understands that the assessments / reviews are based on the requirements of the standards.
Based on design and commissioning in accordance with the aforementioned standards, it can be expected that the system
will meet the power quality requirements of the Code upon the commissioning of assets. However, it is noted that power
quality issues arise due to equipment that customers connect to the network (often post-commissioning) – Western
Power’s mechanisms for proactive monitoring of power quality and reactive action are discussed below.
Proactive monitoring:
CutlerMerz considers that proactive monitoring of power quality at all customer connections would not be practical based
on the current metering technology employed within the network. This view is supported by the University of Wollongong
which undertook a National Long Term Power Quality Survey in 2013/14 in conjunction with Power Quality Australia.
Western Power participated in this survey and reviewed the resultant report6. CutlerMerz understands that based on the
survey it was recommended that approximately 350 power quality meters distributed throughout Western Power’s
network would statistically provide a 95% confidence of power quality readings across the network.
It is understood that prior to the 2013-17 regulatory period Western Power had approximately 100 power quality meters
installed on its network. These were capable of monitoring harmonic distortion only. CutlerMerz has reviewed Western
Power’s approved business case7 to install an additional 260 meters throughout the network. It is understood that the new
meters are capable of monitoring both harmonics and voltage fluctuation. It is understood that the 100 (harmonics only)
plus 260 (harmonics plus voltage fluctuation) meters are consistent with the survey outcomes and will provide 95%
confidence level for both harmonics and voltage fluctuation across the network.
CutlerMerz understands that Western Power downloads and analyses the data from the power quality meters once
annually to proactively monitor power quality across the network. It is understood that these reviews are undertaken to
assess compliance with the standards. In addition, Western Power reactively investigates individual power quality cases
where identified by field staff or through customer notification – Western Power’s mechanisms for reactive actions to
address power quality issues are discussed below.
5 DM#11874479 6 PQ Australia and University of Wollongong, National Long Term PQ Survey 2013/14 Participant Results, Western Power 7 DM#8880863
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
15
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
Reactive action:
CutlerMerz understands that Western Power has two primary mechanisms for “reactively” identifying power quality issues:
customer notification and when incidentally encountered by operational personnel.
CutlerMerz has reviewed Western Power’s process8 and investigations manual9 for addressing power quality issues that
have been identified. These appear reasonable to ensure that power quality issues that have been identified will be
addressed.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, as far as
reasonably practicable, ensure that electricity supply to a customer’s electrical installations complies with prescribed standards
for power quality.
Compliance obligation reference No: 463
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 8
Obligation: A distributor or transmitter must, so far as
reasonably practicable, disconnect the supply of electricity
to installations or property in specified circumstances,
unless it is in the interest of the customer to maintain the
supply.
Context: The “specified circumstances” are when
compliance with the standards for harmonics and voltage
fluctuation (refer to Code 2005, Part 2, Division 1, Clause
6(2) and Clause 7) cannot be achieved, and this may result
CutlerMerz has interviewed personnel responsible for power quality at Western Power, and reviewed relevant information as
appropriate. The power quality investigation process8 which identifies decision points for customers to be disconnected if:
Harmonics or voltage fluctuation are present that will “damage customer equipment” and the customer agrees with the
disconnection; and
If harmonics or voltage fluctuation are present that will “damage customer equipment” and the customer does not agree
with the disconnection, to disconnect “if there is a safety risk”.
Western Power has advised that during the auditable period there were no disconnections related to harmonics or flicker.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as
reasonably practicable, disconnect the supply of electricity to installations or property in specified circumstances, unless it is in
the interest of the customer to maintain the supply.
8 DM#1165772 9 DM#3494210
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
16
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
in damage to a customer’s electrical installations or
property.
Division 2 Compliance obligation reference No: 464
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 9
Obligation: A distributor or transmitter must, as far as
reasonably practicable, ensure that the supply of electricity
is maintained and the occurrence and duration of
interruptions is kept to a minimum.
CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as
appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems, processes and
mechanisms in place to practicably ensure that the supply of electricity is maintained and the occurrence and duration of
interruptions is kept to a minimum. These relate to:
Network planning;
Planned works management; and
Unplanned outage management.
Findings in relation to each of the above are discussed below.
Network planning:
CutlerMerz understands that Western Power designs its network in accordance with the Technical Rules prescribed by the
ERA and available on their website. In addition, CutlerMerz has reviewed relevant planning documents such as the planning
guidelines and asset strategy documents.
CutlerMerz understands that Western Power considers reliability as a key factor in prioritisation of maintenance
programmes and defect remediation.
CutlerMerz understands that Western Power has a process for reviewing network sections with poor reliability. The
Network Performance Reliability Strategy document describes how network elements are ranked based on frequency and
duration of interruptions for categories where Western Power exceeds the overall network SSBs (rural), and the worst
performing elements are considered for remedial action.
CutlerMerz considers the network planning processes outlined above to be broadly consistent with Western Powers peers,
and give due consideration to ensuring that the network is designed to minimise the occurrence and duration of
interruptions to customers.
Planned works management:
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
17
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
CutlerMerz understands that Western Power’s processes for implementing planned works consider approaches to minimise
the frequency and duration of outages experienced by customers.
CutlerMerz understands that the works scheduling team has visibility of the annual planned works programme. The
scheduling and dispatch process10 requires that both internal and external works are bundled into a consolidated schedule
within the Works Scheduling Management Systems to minimise the impact to customers.
CutlerMerz has reviewed the use of the Electronic Network Access Request (ENAR) user guide, and samples of ENAR forms
and has observed processes for the use of mobile generators to minimise outages to customers (i.e. completed ENAR form).
CutlerMerz has not observed a procedural document relating to the use of mobile generators during planned outages.
CutlerMerz has observed the identification of outage areas though the ENAR system and resultant switching schedules and
observed that Western Power has processes to ensure that outages to enable planned works are confined to network areas
to minimise the number of customers affected.
Unplanned outage management:
CutlerMerz understands that Western Power has several processes in place to minimise the duration and number of
customers affected during an unplanned outage. These relate to both control room procedures and procedures for field
personnel.
It is noted that whilst field personnel make decisions on the ground regarding how to repair the network following a fault,
access to the network and all switching operations (both those performed remotely from the control room and those
performed by field switching operators) are executed under direction from the control room operator. CutlerMerz has
reviewed the procedures for fault restoration11 and priority restoration guideline12. These documents demonstrate that
Western Power has processes in place to prudently restore power in a way that minimises the duration and number of
customers affected.
CutlerMerz understands that Western Power uses a “priority response” approach for unplanned outage management in the
field, which is aimed to make the network safe and restore power as soon as possible, and leaving major repair works to be
10 High Level In-depth S&D Work Flow Process 11 DM#1530872 12 DM#8482502
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
18
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
scheduled for regular maintenance crews. CutlerMerz has reviewed the dispatch procedures13 which demonstrates the
priority dispatch process.
CutlerMerz understands that Western Power uses mobile generators during unplanned outages to minimise the outage
duration and customers affected. CutlerMerz has reviewed Western Power’s procedural document14 which details the
process for the deployment of generators during unplanned outages.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as
reasonably practicable, ensure that the supply of electricity is maintained and the occurrence and duration of interruptions is
kept to a minimum.
Compliance obligation reference No: 465
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 10(1)
Obligation: A distributor or transmitter must, so far as
reasonably practicable, reduce the effect of any
interruption on a customer.
CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as
appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems, processes and
mechanisms in place to practicably reduce the effect of any interruption on a customer. These relate to:
Reducing the frequency and duration of outages in general;
Communication with customers in relation to outages; and
Special consideration and prioritisation of customers likely to be most affected by an outage.
Findings in relation to each of the above are discussed below.
General measures for reducing the frequency and duration of outages:
Refer to discussion in relation to clause 9 above.
Customer communication:
CutlerMerz understands that Western Power has two primary mechanisms for communicating planned outages with customers
– posting letters in the mail and card drops. CutlerMerz has reviewed the process for notifying customers for planned outages15
13 DM#1531117 14 DM#2123938 15 DM#8224570
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
19
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
which details the process. It is noted that through this process the identification of customers to be notified relies on PowerOn
Fusion (PoF) and the ENAR systems (refer to Section 2).
Customers likely to be most affected:
Western Power places increased effort on manging customers who are likely to be more adversely affected, or where an
outage these to these customers will adversely affect the community more broadly. These customers include:
Life support equipment (LSE) customers;
Utilities and essential services (e.g. Main Roads, traffic lights); and
Sensitive load customers (e.g. hospitals).
CutlerMerz has reviewed the procedural documents for customer notifications15, fault restoration11, the priority restoration
guideline12, the priority dispatch procedures13, and procedures for the deployment of generators during unplanned outages14 –
these procedures all give consideration to “sensitive” customers in some capacity.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as
reasonably practicable, reduce the effect of any interruption on a customer.
Compliance obligation reference No: 466
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 10(2)
Obligation: A distributor or transmitter must consider
whether, in specified circumstances, it should supply
electricity by alternative means to a customer who will be
affected by a proposed interruption.
CutlerMerz has interviewed personnel responsible for mobile generator dispatch at Western Power, and reviewed relevant
information as appropriate. Based on this consultation, CutlerMerz considers that Western Power has a number of systems,
processes and mechanisms in place to supply electricity by alternative means to a customer who will be affected by a proposed
interruption. These relate to:
Planned outages; and
Unplanned outages.
Findings in relation to each of the above are discussed below.
Planned outages:
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
20
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
Context: The “specified circumstances” are when:
The interruption is expected to exceed 6 hours, or 4
hours if forecast maximum temperatures are expected
to be greater than 30 degrees Celsius (as issued by the
Bureau of Meteorology in Perth);
The effect of the interruption on the customers’
business is likely to be substantial; or
The interruption will affect a person with life support
needs and requires electricity for the operation of
equipment that caters to those needs.
The ENAR system requires the originator of the outage request to consider whether mobile generation is required (in the ENAR
guide16 this is in the form of a prompt for a yes/no answer). However, it does not appear to provide any further guidance on
when a mobile generator would be required. CutlerMerz has not observed a procedural document relating to the use of mobile
generators during planned outages. CutlerMerz has reviewed a sample planned interruption form17 for an outage affecting a
life support equipment (LSE) customer. This outage affected 117 customers over a period from 7am to 4:30pm (9.5 hours). For
this outage the ENAR requestor had answer “no” to the Generators required?” prompt and it does not appear that a mobile
generator was used for this outage. Western Power’s scheduling team has advised that they do consider using mobile
generators under the circumstances specified by the Code; however, CutlerMerz has not observed a procedure to support this
practice.
Unplanned outages:
It is noted that the Code refers to “proposed interruption[s]”. Notwithstanding, Western Power’s process for the use of mobile
generators14 during unplanned outages outlines that mobile generation should be considered if the estimated “fix time” is less
than 6 hours.
Finding: Whilst Western Power’s ENAR system prompts the planned outage requestor to state whether or not mobile
generation is required for a planned outage, there does not appear to be procedural guidance, based on the requirements of
the Code, as to when these should be deployed. It is noted that Western Power’s scheduling team has advised that they do
consider using mobile generators under the circumstances specified by the Code; however, CutlerMerz has not observed a
procedure to support this practice. CutlerMerz has observed an outage example of planned outage documentation where the
use of mobile generation may have been considered appropriate based on the Code; but the ENAR requestor did not request
mobile generation and it did not appear to be deployed in this instance.
Compliance obligation reference No: 467
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 12(3)
CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as
appropriate.
It is noted that Western Power has reported a substantial number of incidents where the “prescribed standards” have not been
met in previous years (for both outage duration and number of interruptions standards); and Western Power advises the same
outcome in 2015/16. It is understood that these cases are predominantly due to extreme weather events. CutlerMerz considers
16 DM#33995956 17 DM#9431078
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
21
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
Obligation: A distributor must take prescribed action in the
event of a significant interruption to a small use customer.
Context:
The “prescribed actions” are:
To remedy the cause or causes of the interruption so
that the prescribed standard is met; or
Enter into an agreement to the small use customer’s
satisfaction for the supply of electricity to the
customer.
The “prescribed standard” is the supply of electricity for 9
years in every 10 without the interruption of supply
exceeding:
An interruption of more than 12 hours continuously; or
9 interruptions in Perth CBD and urban areas, or 16 in
other areas (in the preceding year).
The definition of “significant interruption” is not meeting
the prescribed standard.
it impractical for Western Power to meet the prescribed standards during extreme weather events. It is noted that in other
Australian jurisdictions such events would be excluded, which would allow the underlying performance to be monitored. In
CutlerMerz’ view, it would be appropriate to amend this clause of the code to exclude extreme weather events.
Notwithstanding the above, it is understood that Western Power has a process for reviewing poor performing sections of the
network (referred to as “hot spots”). CutlerMerz has reviewed Western Power’s Network Reliability Performance Strategy18,
which details how Western Power considers both its Service Standard Benchmarks (SSB) applicable under its Access
Arrangement, and the requirements of the Code; the strategy then forms a considered position on remediating “hot spots”.
Western Power has advised that they have not entered into any agreements with small use customers in relation to providing
lower than the prescribed standards.
Finding: CutlerMerz notes that Western Power consistently reports a substantial number of incidents where the “prescribed
standards” are not met. This appears to be predominantly due to extreme weather events. In CutlerMerz’ view, it would be
appropriate to amend this clause of the code to exclude extreme weather events. It is also noted that Western Power has not
entered into any agreements with small use customers in relation to providing lower than the prescribed standards; further to
the above, CutlerMerz considers that it would be impractical for Western Power to enter into an agreement with each
customer that may be subject to extreme weather events.
Notwithstanding the above, CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected
to, so far as reasonably practicable, remedy sections of the network with poor reliability.
Division 3 Compliance obligation reference No: 468
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 13(2)
CutlerMerz has interviewed personnel responsible for reliability at Western Power, and reviewed relevant information as
appropriate. The findings on Western Power’s processes and systems to ensure compliance with reliability obligations are
detailed within the findings relating to Division 2. It is noted that Western Power’s network planning and outage management
processes consistently consider risk factors in terms of reliability and customers affected, which naturally leads to greater focus
on reducing higher density areas i.e. Perth CBD, then other areas, then the remainder of the network (assuming greater
18 DM#12596515
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
22
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
Obligation: A distributor or transmitter must, so far as
reasonably practicable, ensure that customers in specified
areas do not have average total lengths of interruptions of
supply greater than specified durations.
Context:
The overall “specified durations” are:
Perth CBD: 30 minutes
Urban (other than Perth CBD): 160 minutes
Other areas: 290 minutes
number of customers per feeder in higher density areas). The SSBs also drive focus in this area. Further, Western Power’s
Network Reliability Performance Strategy18 details how Western Power considers both its Service Standard Benchmarks (SSB)
applicable under its Access Arrangement, and the requirements of the Code; the strategy then forms a considered position on
remediating “hot spots”.
As per Division 2 - clause 12(3), CutlerMerz notes that the Code does not allow for the exclusion of extreme weather events,
which is understood to have resulted in Western Power not meeting its overall targets. Again, CutlerMerz considers that this is
due to impracticality of the Code (i.e. in not excluding extreme weather events) rather than due to inappropriateness of
Western Power’s processes and systems.
Finding: As per Division 2 - clause 12(3), CutlerMerz notes that Western Power consistently reports not meeting the “specified
durations”. This appears to be predominantly due to extreme weather events. Again, CutlerMerz’ considers it would be
appropriate to amend this clause of the Code to exclude extreme weather events.
Notwithstanding the above, CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected
to, ensure that customers in specified areas do not have average total lengths of interruptions of supply greater than specified
durations.
Compliance obligation reference No: 469
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 13(3)
Obligation: The average total length of interruptions of
supply is to be calculated using the specified method.
Context:
The overall “specified method” is to be calculated as at 30
June in each year:
by taking the average total length, in minutes, of
interruptions of supply to customer premises in an area
CutlerMerz has interviewed personnel responsible for reliability systems and calculations at Western Power, and reviewed
relevant information as appropriate.
Western Power calculates the average total length of interruptions using its Network Reliability Data Validator (NRDV) system.
The NRDV system is configured to run Structured Query Language (SQL) to interrogate the Data Warehouse (which captures
and stores reliability data generated by PowerOn Fusion). CutlerMerz has observed the queries being run in NRDV to produce
the reliability calculations and considers this to be an appropriate system to generate the required reports. It should be noted
that CutlerMerz has not reviewed the SQL coding or attempted to reproduce the calculations to verify their accuracy.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as
reasonably practicable, calculate the average total length of interruptions using the specified method.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
23
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
during each year of the period of 4 years ending on that
day; and
by then taking the average of the 4 annual figures
determined above.
Division 4 Compliance obligation reference No: 470
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 14(8)
Obligation: A distributor or transmitter must, on request,
provide to an affected customer a free copy of an
instrument issued by the Minister and of any notice given
under section 14(7) of the Electricity Industry (Network
Quality and Reliability of Supply) Code 2005.
Context:
If, having regard to the advice of the Authority, the
Minister is satisfied that it is appropriate to do so, the
Minister may by “Instrument”:
Exempt the transmitter or distributor from compliance
with the provision concerned; and
Attach to the exemption a condition that another
provision, in place of the provision for which an
exemption is granted, is to be complied with by the
transmitter or distributor in the supply of electricity.
CutlerMerz has interviewed personnel responsible for customer services at Western Power, and reviewed relevant information
as appropriate.
Western Power has advised that no “instruments” have been issued by the Minister during the audit period, and nor are there
any previously issued instruments that are applicable within the audit period.
Interaction with the Minister is through Western Power’s Government Relations division, and interactions with customers is
through Western Power’s Customer Services division. CutlerMerz considers that this would be an appropriate structure to
provide to an affected customer a free copy of an instrument issued by the Minister (should the Minister issue a notice in
future and a customer then request a copy of the instrument.
Finding: CutlerMerz considers that Western Power’s systems, processes and mechanisms can be expected to, so far as
reasonably practicable, provide to an affected customer a free copy of an instrument issued by the Minister upon request.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
24
NQRS Code, Part 2: Division #
Compliance Obligation and Context Findings
“Section 14(7)”- The Minister may at any time, after
obtaining the advice of the Authority, by notice in writing
to the transmitter or distributor revoke or vary an
instrument above including by imposing any further
condition to be complied with by the transmitter or
distributor.
Compliance obligation reference No: 471
Clause: Electricity Industry (Network Quality and Reliability
of Supply) Code 2005 clause 15(2)
Obligation: A distributor or transmitter that agrees with a
customer to exclude or modify certain provisions must set
out the advantages and disadvantages to the customer of
doing so in their agreement.
CutlerMerz has interviewed personnel responsible for customer services at Western Power, and reviewed relevant information
as appropriate.
Western Power has advised that no “agreements” are in place with customers to exclude or modify certain provisions of Part 2
of the Code. As noted in relation to Division 2 – clause 12(3), Western Power consistently reports a substantial number of
incidents where the “prescribed standards” are not met (which appears to be predominantly due to extreme weather events).
Finding: It may be considered appropriate under the Code for Western Power to enter into agreements with customers where
the “prescribed standards” are not met. However, in CutlerMerz’ view, it would be more appropriate to amend the relevant
clauses of the code to exclude extreme weather events. CutlerMerz considers that it would be impractical for Western Power
to enter into an agreement with each customer that may be subject to extreme weather events.
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
25
Appendix B Information provided
The information provided during the audit is provided in Table 8. It should be noted that Western Power also
responded directly via email and provided document hard-copies throughout the fieldwork – these items are not
included in Table 8.
Table 8: Information provided
Document name Reference No.
Annual Reliability and Power Quality Report – For
the period 1 July 2014 to 30 June 2015
DM#13019660
eNAR User Guideline DM#33995956
Dispatching Fault Jobs DM#1531117
Restoration of Feeders and Reclosers DM#1530872
Review of the Use of Emergency Response
Generators
DM#:12950187
Emergency Response Generators (LV) DM#2123938
Quality of Supply Resolution DM#1531190
Prioritising Network Restoration Guideline DM#8482502
Technical Report, Electromagnetic compatibility
(EMC), Part 3.14: Limits—Assessment of
emission limits for harmonics, interharmonics,
voltage fluctuations and unbalance for the
connection of disturbing installations to LV power
systems
SA/SNZ TR IEC 61000.3.14:2013
National Long Term PQ Survey 2013/2014
Participant Results, Western Power
PQ Australia, University of Wollongong
Power Quality Investigations Manual DMS#3494210
DRAFT*****PPG Connection Process. 0-10 MW
generators connected at 33kV or less, excluding
0-30kVA inverter and PV. Refers to full installed
capacity at one lot or connection point.****DRAFT
DM#11874479v1
Power Quality / TVI Complaint Handling Process
DMS#1165772 v5A
LV Power Quality Management – (AA3) 2012/13
to 2016/17
DM#8880863
Identification and Notification of Customers for
Planned Interruptions
DM:8224570 v37A
LSE Daily Audit – Archive 2015_09 Sept.xlsm Spreadsheet
Copy of Customer Assist - LSE Daily Audit
(9131948)_.xlsm
Spreadsheet
Copy of Notification Working Document_.xlsm Spreadsheet
Customer Service Planned Outage Audit &
Approval Procedure
DM#9847816
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
26
Document name Reference No.
Outage Coordination & Compliance Team
Checklist 5, 1 Day Prior to the Interruption – Final
checklist
eNAR Number: 279636
Access Offer Template No reference number
Electricity Transfer Access Contract (template) No reference number
Data Warehouse TCS Subject Area Data Flow
Chart
No reference number
ENMAc, SOAP Interface, SOAP Interface
Architecture
P118-01-01 v1.2
WR2667 – Reporting Strategy – ENMAC TCS No reference number
Conductor Clashing Mitigation Strategy DM#6034312
Summary Strategy for Mitigating Distribution
Overhead Conductor Clashing
DM#11829820
Distribution Automation Strategy DMS#3127544
Distribution Automation – Guideline #01, Recloser
Placement Strategies – Metro
No reference number
Rural Protection Settings Guidelines
For Feeder CB, Reclosers, Sectionalisers, and
Fuses
DMS# 1068147v5
Recloser Placement Formula No reference number
Network Reliability Performance – Strategy DM#12596515
Risk Based Renewal Methodology –
Distribution Overhead
No reference number
Distribution Network Planning Guidelines: An
Interpretation of the Technical Rules
DM#4880519
Transmission Planning Guidelines: Interpretation
of the Technical Rules
DM#8494654
High Level In-depth S&D Work Flow Process 13775228
Planned Interruption Form DM#9431078
Network Quality & Reliability of Supply (NQRS) Code Audit
CMPJ0039-02 – Independent Assurance Report - Network Quality & Reliability of Supply (NQRS) Code Audit
27