Resources, Timeline & Contingency
UCN CDR (Sept/2010)
- Work Breakdown Structure- Timeline/Schedule- Human Resources & Manpower Profile- Capital Resources & Contingencies- Liquefier Recap
Note:Canadian Funding Agencies (e.g. NSERC) strictly forbid the inclusion of contingency funding in grant requests.
Explicit allocation of funds for contingency spending would not normally appear in budget tables.
Outline
Project PhaseWBS 2
Beamline
WBS 2.1
SpallationTargetWBS 2.2
Shielding Structure
WBS 2.3
HeliumLiquifier
WBS 2.4
Installation
WBS 2.6
KickerSeptumDipole (1UB2)QuadrupolesSteering MagnetsBeamline LayoutVacuum SystemDiagnosticsControl SystemServicesShine BlockersBeamline H/W
TargetMonitors/InterlocksRemote HandlingOverall Assembly
ShieldingSafetyD2O
He Liquifier PlantTRIUMF PartsCompressorServicesControls
201320142015
UCN Facility ProjectWork Breakdown Structure
Level 3: Work Packages
UCNSourceWBS 2.5
Isopure CryostatHeavy Ice CryostatNeutron guidesUCN bottleModerator
Level 2: Subsystems
Pre-Project PhaseWBS 1
UCN Facility
UCN Facility Project Work Breakdown Structure (Level 3: Work Packages)
Dipole (1UB2) WBS 2.1.3
Specs, Design, Tender & Order
WBS 2.1.3.1
1UB2 MagnetFabrication
WBS 2.1.3.2
Vacuum Box
WBS 2.1.3.3
PowerSuppliesWBS 2.1.3.4
SpecifyReview & finalize specsPrepare bids for vendorsBid timePlace order
Preliminary designReviewFinish designAcceptance testsShip & receive at TRIUMFUnpackPrepare for field mappingField map 1UB2Overall assembly
DesignCheck dwgsFabricateAssemble and prep. to install
SpecifyReviewPrepare tender docsBid timePlace orderFabricate (vendor)Acceptance tests (vendor)Ship & receive p/s at TRIUMFCheckout, hookup services, & prep for magnet tests
Level 4: Deliverables
Level 5: Tasks (on Resource-Loaded Schedule)
Resource-Loaded Schedule and WBS(Vijay Verma, Mark Keyzer)
See Printouts for details
SHIELDING – Base LayerSHIELDING – Outer Layers
HELIUM LIQUIFIER:
UCN APPARATUS:Spallation TargetVacuum, Monitoring & SafetyUCN Source (Install Japanese Parts)
TRIUMF PartsServicesCompressor Building Mods.Controls
S + O + P
O + P
S+D+R F+I
P + De + I
S + D + R F + A
S+R D O + F A+T
I T
S + D + R F + A I+TS + D + R O + P I
O + P I I
A AssembleB BidsC ConceptsCm CommissionD Detail DesignDe DevelopmentF FabricateI InstallO OrderP ProcurePd ProductionR ReviewS SpecsT TestUI UnInstall
Remove M11 & Replace SeptumRemove 1BVB2
BL1A Temporary Shielding S + D + R IRemove M13, PIENU UI
S+D+R+F+A UI+I
UI
BEAMLINE:KickerSeptumDipoleQuadrupoles.
Power SuppliesRemaining Beamline (Vac,Serv,Cntrl,Diag,Safety,B/L)ASSY/INSTALL & Commission
S + D + R
S + D + R
S + D + R
P
S
S
A
TF A I
I
ITP
TP
TA
P + TO
D F + AI T + Cm
B/L REMOVAL & CLEAN-UP:
Steering Magnets (8”) S + D F + A + T
He Liquifier Plant S + R + O P + A + T
S+D+R
I
ConstructionDesignARIEL B
Layout of TRIUMF UCN Activity (Beam in 2015)Overview of Schedule
SHIELDING – Base LayerSHIELDING – Outer Layers
HELIUM LIQUIFIER:
UCN APPARATUS:Spallation TargetVacuum, Monitoring & SafetyUCN Source (Install Japanese Parts)
TRIUMF PartsServicesCompressor Building Mods.Controls
S + O + P
O + P
S+D+R F+I
P + De + I
S + D + R F + A
S+R D O + F A+T
I T
S + D + R F + A I+TS + D + R O + P I
O + P I I
A AssembleB BidsC ConceptsCm CommissionD Detail DesignDe DevelopmentF FabricateI InstallO OrderP ProcurePd ProductionR ReviewS SpecsT TestUI UnInstall
Remove M11 & Replace SeptumRemove 1BVB2
BL1A Temporary Shielding S + D + R IRemove M13, PIENU UI
S+D+R+F+A UI+I
UI
BEAMLINE:KickerSeptumDipoleQuadrupoles.
Power SuppliesRemaining Beamline (Vac,Serv,Cntrl,Diag,Safety,B/L)ASSY/INSTALL & Commission
S + D + R
S + D + R
S + D + R
P
S
S
A
TF A I
I
ITP
TP
TA
P + TO
D F + AI T + Cm
B/L REMOVAL & CLEAN-UP:
Steering Magnets (8”) S + D F + A + T
He Liquifier Plant S + R + O P + A + T
S+D+R
I
ConstructionDesignARIEL B
Layout of TRIUMF UCN Activity (Beam in 2015)Overview of Schedule
Ariel construction Aug/2011-Feb/2013UCN Design during ARIEL ConstructionUCN (main) Construction after ARIEL Completion
UCN Manpower Requirements from RLSBreakdown by Group & Resource, in Person-Months
Cal.Year Science Des.Office Mach.Shop Tech+Plant O/S: outside Subtotal SubtotalPhys Acc.Phys Engrs Designers Machinists Controls Electrical Electronics Mechanical Contractors Total (w/o O/S) (w/o O/S & Phys)
2010 0.04 0.00 0.00 0.08 0.00 0.00 0.00 0.00 0.00 0.00 0.1 0.1 0.12011 0.62 0.00 0.20 0.17 0.00 0.00 0.00 0.00 0.00 0.25 1.2 1.0 0.42012 0.90 0.08 2.51 0.77 0.13 1.08 0.00 0.08 0.48 0.37 6.4 6.0 5.12013 0.88 0.59 2.77 1.75 1.39 0.88 0.08 0.88 3.23 0.92 13.4 12.5 11.62014 0.74 0.08 0.84 0.80 0.86 0.19 0.18 0.28 3.83 0.83 8.6 7.8 7.12015 0.66 0.00 0.55 0.28 0.46 0.19 0.00 0.17 1.23 0.28 3.8 3.5 2.9
Subtotals2010-15 3.8 0.8 6.9 3.8 2.8 2.3 0.3 1.4 8.8 2.7 33.6 30.9 27.1
Human Resources Requirements in units of Person-YearsAccel & Engr Electr & Controls
Load on Design OfficeLoad on Machine Shop (Peaks in 2013)
UCN “Rolled Up” Manpower Requirements
Load on Mech.Techs (Peaks in 2014)
Load on TRIUMF-basedmanpower peaks in 2013
UCN Manpower Profile
2010 2011 2012 2013 2014 2015 Year
FTE
14
12
10
8
6
4
2
0
Outside Contractors (CFI)
TRIUMF/CFI Manpower
UCN Manpower Funding Scenarios
14
12
10
8
6
4
2
0
FTE
2010 2011 2012 2013 2014 2015Year
2010 2011 2012 2013 2014 2015Year
(Scenario 1) (Scenario 2)
Outside Contractors (CFI) CFI-funded Manpower TRIUMF Manpower
Scenario 1:TRIUMF-CFI Matched Profile Funding
Scenario 2: CFI Front-Loaded Funding
Positive Impacts of UCN at TRIUMF
• 17 FTE-years injected from CFI into TRIUMF- Mid 2011 – junior engineer Project engineer
- Late 2011 – designer
- Mid 2012 – mechanical technician
- Junior people hired to impact TRIUMF succession management
• Engagement of technical staff at TRIUMF (e.g. detector facilities) through new project• Hardware opportunities for interested faculty and for training HQP.• Future long-term physics program opportunities.
Capital Cost Estimates
Capital ResourcesBreakdown by item and funding sources (cash or in-kind)
Capital Contributions for Liquefier
ContingencySummary of Human Resources Contingency
Summary of Capital Resources Contingency
Helium Liquefier (Recap)
• UCN group recently engaged outside cryogenic consultant to examine options A solution that satisfies both the needs of UCN and CMMS was identified.
• Costs may be reduced by importing an existing large KEK compressor (which KEK has allocated funds to refurbish and ship) and large buffer tanks.
• A new cold box will be required.
• Cost estimate for a new liquefier is $1.5M to $2M (includes cost for KEK to refurbish and ship compressor, and large buffer tanks).
• Since SR liquid helium costs alone are $400k per year, new liquefier would pay for itself in one 5-year cycle (UCN funds are allocated to cover the first few years of operational costs).
• There is an additional cost of $700k for transfer lines and installation
The End
Risks & Mitigation: UCN FacilityKicker Risetime problem (upgrade switches)
Rep rate problem (extensive offline testing, upgrade components)
Spallation Target Cooling Leaks (consult RH techs) Mechanical Extraction
UCN Source Lower UCN rate (extensive testing in Japan) Cooldown problems (extensive testing in Japan)
Liquefier Budget & Schedule for new parts ASME recertification for old parts Space issues: Compressor size vs Annex space
Manpower Issues Priority Conflicts (UCN HR Contingency, Acsion, Staggering) Availability of Appropriate Skills (CFI manpower budget)
Budget Issues CFI, TRIUMF, Japan: Total and Cashflow Operational Phase Unforseen Cost Overruns (Flexibility of funding) Inflation & Currency Exchange