Resource Recovery Transfer Stations – Design & Operating ...€¦ ·...
Transcript of Resource Recovery Transfer Stations – Design & Operating ...€¦ ·...
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 1
WasteMINZ Annual Conference
Claudelands, Hamilton, New Zealand 17-19 October 2012
Resource Recovery Transfer Stations – Design
& Operating Principles Geoff Thompson
Sinclair Knight Merz Pty Limited Environment and Infrastructure Consultants
Phone +61 7 3026 8033 INTRODUCTION As is the case for the development of any project, the planning and design stage of a waste transfer station has the most influence over its ultimate success. Probably the two earliest facility planning decisions to be made are its location and the types of wastes it will receive. Having made those fundamental decisions, four key choices about the operation of the transfer station will largely determine its final form:
Resource recovery – What is to be recovered? How? Where within the facility will recovery occur?
Safety – How to manage the risk of users falling from height into bins and pits and keep users and waste separate. Other safety issues must be considered but this one has the most influence over the final form of this station.
Handling and load out of residual waste – Fixed versus mobile plant? Degree of compaction required? Number of supervisory staff? Importance of load-out speed?
Mode of residual waste transport – How far to disposal point? Need for unloading equipment? Time taken to unload? Payload capacity?
Until the ideal of zero or near-zero waste is achieved, the final two matters, and especially the last (residual waste transport mode) will significantly influence the whole of life economics of a transfer station project. Generally this choice has the greatest impact on the most expensive phase of the project – operation. The following attempts to set out the pros and cons of the various options within each of the above four fundamental planning parameters.
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 2
RESOURCE RECOVERY PHILOSOPHY What to recover? Only high value items eg metals Lower operations cost
Reduced impact of resource recovery and waste minimisation message.
Recover everything possible Highest recovery of resources
Higher operations cost
How to recover? Passive drop off by customer
Lower operations cost Lower recovery of resources Contamination of materials unless supervised
Active recovery from customer by site staff
Highest recovery of resources Least effort for customer Higher operations cost
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 3
Where to recover? Before pay point (gatehouse)
Strongest waste reduction message Extra supervision to prevent deposit of residual
waste
After pay point
Long term fee setting flexibility Even users with no residual waste must use
gatehouse
At residuals drop off location
Lower capital cost (no need for separate facility) Lower operating cost (share supervision with
residuals drop off zone) Lower recovery of resources
Before residuals drop off location
Better recovery of resources Higher capital and operating costs
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 4
SAFETY - FALLS FROM HEIGHTS AND USER/WASTE SEPARATION There are other safety issues to be managed at transfer stations, but guarding against users falling into residual waste push pits/bins and separating users from waste material can have expensive implications for the ongoing costs of handling residual waste materials. Larger Stations – users include tipping vehicles
Push pit (deep)
Quick and well defined separation of waste from user.
Fall protection along edge can result in hand and/or lifting injuries
Flat floor
No falls from height Less waste/user separation requires more
supervision
Smaller stations – users unload by hand
Open top bins
Quick and well defined separation of waste from user.
Fall protection barriers can result in hand and/or lifting injuries
Push pit (shallow)
No falls from height Quick and well defined separation of waste from
user.
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 5
Tipping bucket
No falls from height Quick and well defined separation of waste from
user. If tipping bucket breaks down, a replacement
cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative system
Slower movement of waste from customer to bin/pit
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 6
HANDLING AND LOAD OUT OF RESIDUAL WASTE Handling = Moving residual waste from point of deposit to point of load out. No Handling Direct deposit into transfer container/truck
Low capital cost Limited compaction possible No storage other than transfer container
capacity No chance for last minute resource recovery
once in container Not suitable for large vehicle customers
Handling between points of deposit and load out via mobile plant
Deep push pit
Compaction Storage
Less supervision of traffic required
Higher capital cost (retaining walls) No chance for last minute resource recovery
once in pit
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 7
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 8
Shallow push pit
Last minute resource recovery possible Some in-pit compaction Some in-pit storage Less supervision of traffic required Medium capital cost
Flat floor
Last minute resource recovery possible Lower capital cost Compaction Storage More supervision of traffic required Better suited to users with tipping vehicles
than hand unloaders
Handling between points of deposit and load out via fixed plant Conveyor
Mobile loader not required If conveyor breaks down, a replacement
cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative handling system
Walking Floor
Mobile loader not required If walking floor breaks down, a replacement
cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative handling system
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 9
Loading of Transfer Trucks Top load – direct
Fast load out Higher capital cost (higher retaining walls
required)
Top load – push wall
Medium load out speed
Medium capital cost (lower retaining walls required)
Stationary compactor
Can reduce need for mobile plant when part of a push pit or flat floor system (only the loader function is required, not compaction)
Strong (heavy) container needed to withstand compactor force. Therefore, lesser waste payload
If compactor breaks down, a replacement cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative loading system
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 10
Slug packer
Can reduce need for mobile plant when part of a push pit or flat floor system (only the loader function is required, not compaction)
Pre compaction means container can be of lower strength and lighter (aluminium). Higher payload of waste
High capital cost of slug packer If slug packer breaks down a replacement
cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative loading system.
Baling
Allow uses of lower cost, flat top transfer trucks Less/no compaction required at landfill Less litter at landfill because bales are tied
Capital and operating costs of baling equipment Additional floor area required for loading of bales
onto truck If baling equipment breaks down, a replacement
cannot be borrowed/hired and fitted quickly. Therefore, need a contingency plan which uses an alternative loading system.
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 11
RESIDUAL WASTE TRANSPORT
Open-top bins (hook-lift, roll-on roll-off)
Lower capital cost Self unloading
Lower pay loads (3-15t)
Flat bed truck to carry baled waste
Lower capital cost Larger pay loads
Unloading plant required Slower unloading
Semi trailer (tipper) Fastest unload Larger pay loads (20t) Self unloading (note risk of hang-ups)
Medium capital cost Stability while unloading
Semi trailer (walking floor)
Larger payloads (steel body 20 tonne; aluminium body 25 tonne)
Self unloading Higher capital cost
B-Doubles
Same length as semi trailer but more axles to share load. Therefore, larger payloads (30-44t)
Mini B-double can unload by tipping due to smaller trailer size
Special measures such as shredding are likely to be required to fully exploit available payload (weight)
Difficult to unload both containers without unhitching rear trailer. Therefore, slower unloading
Higher capital cost.
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 12
A-Doubles or Road Trains
Highest truck payloads (45-55t in two trailer form)
Need walking floor to unload safely Discharge each trailer separately. Therefore,
slower unloading Generally not allowed on urban roads and many
non-urban roads High capital cost
Rail
Largest payload (1000t) Must rehandle waste containers onto trucks to
unload at landfill. Separate rail to road inter-modal facility required.
Special unloading equipment required to unload waste containers.
Highest capital and operating costs (train, rail infrastructure, inter-modal and unloading)
Need large waste throughput to fill train quickly. Otherwise odour etc impacts of aging waste.
C:\USERS\GATHOMPSON\DOCUMENTS\PAPERSPRESENTATIONS\HAMILTON,NZ WASTEMINZ OCT 2012\PAPER.DOC 24 OCTOBER 2012 PAGE 13
CONCLUSIONS Four key planning aspects of a transfer station will largely dictate its final form and operational success:
Resource recovery philosophy
Safety
Handling and load-out of residual waste
Mode of transporting residual waste off site. While the above tabulation should assist transfer station proponents to plan such facilities, it can be seen that there is no clear answer for some of the choices required. Many issues require a trade-off between competing priorities including the familiar one of capital versus operating funds availability. For all systems, other than those with a low percentage of residual waste or a very short distance to disposal location, the highest system cost component is the haul of residuals to disposal location. The larger the quantity of residual wastes and the longer the haul to the location of residuals disposal, then the greater will be the whole of life economic benefit of investing capital up front to improve transport efficiencies and to a lesser extent, residuals handling and load out. Such efficiencies come from getting as much material on the transfer truck/train/ship as possible. Within a class of transport – say trucks for example – the transport operating costs vary little with weight carried. These costs are closely related to hours of vehicle operation. For the usual example of transfer by truck, the cost of wages, insurance, vehicle registration etc are largely independent of payload. Fuel and servicing are influenced to a small degree by payload but are far more related to the number of hours of operation. The very strong influence of residual waste transfer on system economics will reduce as its quantity reduces.