SHORTAGE OF RESOURCES 3-D TEAM10 SIORI TAKADA, AKIRA MORITA, ITSUKI SAITO, TARO SOENO.
Resource Allocation Men, Material, Money are three resources required for any activity. If...
-
Upload
peregrine-lindsey -
Category
Documents
-
view
212 -
download
0
Transcript of Resource Allocation Men, Material, Money are three resources required for any activity. If...
![Page 1: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/1.jpg)
Resource Allocation
Men , Material, Money are three resources required for any activity.
If shortage of resources the activity cannot be completed in time
Project mgr has to come across resource constraints
Hence the job of project mgr is to plan and allocate resources for different activities so that resource utilization is optimized.
1
![Page 2: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/2.jpg)
Two situations Resource Leveling –
analysis aims at stabilization of rate of resource utilization by various activities at different times without changing the project duration.
Resources are constraints while time is in plenty.
Resource Smoothing (Loading)- analysis aims to reduce peak demand for resources and
reallocating among activities of a project in a manner so that the total project duration remains shortest.
Time is constraint but resources are not the constraints.Period of max. demand for resources are identified and
non critical activities are staggered by re scheduling them according to the floats for balancing resource requirements
2
![Page 3: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/3.jpg)
Bar Chart or Gantt Chart
It requires list of activities & estimated time of completion of individual activity.
Pictorial devices in which activities are represented by horizontal bars on the ‘ time axis’
![Page 4: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/4.jpg)
S- chart
Display of cumulative costs, labour hours or other quantities plotted against time.
Indicator and its used for many applications such as target, baseline, cost , time
![Page 5: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/5.jpg)
Draw the resource loading chart and gantt chart. What is the peak requirement of the resource and on which day it
occurs. Q6b-2007
Activity Preceding Activity
Duration (Days) Total Manpower required
A - 3 60
B - 4 84
C A 2 22
D A 3 36
E B 6 72
F D,E 3 18
G C 5 35
H F 6 42
I G,H 7 56
5
![Page 6: Resource Allocation Men, Material, Money are three resources required for any activity. If shortage of resources the activity cannot be completed in.](https://reader036.fdocuments.us/reader036/viewer/2022083006/56649f2f5503460f94c487a5/html5/thumbnails/6.jpg)
A project consists of 9 activities for which data is given below. Draw the resource loading chart for the project. What is the maximum requirement of the cash and on which day it occurs
Q7(b)-2008
Activity Immediate Predecessor
Duration (Days) Total cash flow required for the activity (Rs. Lakhs)
A - 5 25
B - 5 30
C A 10 40
D B 7 28
E A 6 12
F C,D 8 24
G C,D 6 15
H E,F 5 10
I G 4 12
6