Resort Project - Feasibility Final Report - 22082014

download Resort Project - Feasibility Final Report - 22082014

of 25

Transcript of Resort Project - Feasibility Final Report - 22082014

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    1/25

    Prepared by:

    Kumar & Joseph

    Chartered Accountants

    www.kumarandjoseph.com

    Feasibility study fora proposed Resortat Kovalam

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    2/25

    Contents

    Executive Summary .............................................................................................................. 3

    Feasibility .......................................................................................................................... 4

    Introduction and Background ................................................................................................ 5

    Introduction ....................................................................................................................... 5

    Background for investment ................................................................................................ 5

    Promoters .......................................................................................................................... 5

    Demand Analysis .................................................................................................................. 6

    Introduction ....................................................................................................................... 6

    Kovalam and Tourism ........................................................................................................ 6

    Geography ........................................................................................................................ 6

    Climate .............................................................................................................................. 6

    Food and Drinks ................................................................................................................ 6

    Requirement and Demand Analysis for Resorts ................................................................ 6

    Location Advantages ......................................................................................................... 8

    Advantages of Resort Setup in Trivandrum ....................................................................... 8

    Project Profile ....................................................................................................................... 9

    Profile of the Proposed Resort ........................................................................................... 91. Process/Steps ............................................................................................................. 10

    2. Infrastructure and Amenities ........................................................................................ 10

    Financial Plan ..................................................................................................................... 11

    Assumptions .................................................................................................................... 11

    Feasibility Indicators............................................................................................................ 14

    Annexure ............................................................................................................................ 20

    Break Up Of Project Cost ................................................................................................ 20

    Project Implementation Tracker .......................................................................................... 24

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    3/25

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    4/25

    Feasibility study for a proposed Resort at Kovalam 4

    Feasibility

    To assess the financial viability of the proposed Project, a feasibility model was created to account forthe revenue streams, expenses, and variables associated with the development and operation of theproject. It is important to keep in mind that the model and the resulting measures of financialperformance are based on general assumptions and enquiry. The results are as follows:

    Internal Rate of Return & Net Present Value

    Project IRR 30.41%

    Project NPV 76.03 lakhs

    Discounted Payback period 5 years

    Normal Payback period 5 years

    Cost of Capital Assumptions

    Equity contribution 100%

    Cost of Equity (assumed) 15%

    The Project IRR is 30.14% which is more than the Cost of Equity which is assumed to be 15%. NPValso shows a positive value.

    Moreover from the graphical representation above, we can see the total revenue trend is steeplyrising whereas total cost trend rise is moderate, resulting in increasing profit trend. Since project isdepicting increasing trend of revenue and profit, the project is viable and acceptable.

    -8,19,913 -6,26,655

    5,93,810

    14,84,694 24,45,123 29,00,312

    36,94,313 35,01,055

    52,29,700

    70,89,008

    86,89,76796,59,498

    28,74,400 28,74,400

    60,78,000

    92,10,000

    1,21,82,800

    1,38,02,800

    Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

    Profit/Loss Total Cost Total Revenue

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    5/25

    Feasibility study for a proposed Resort at Kovalam 5

    Introduction and Background

    Introduction

    The Kovalam resort project is promoted by NRI couple, Anuj Narayanan & Meera Anuj. Anuj andMeera have been living abroad for the last 15 years and it has been their dream to construct amedium sized resort aimed at providing a very traditional and malayalee experience for tourists. Thepromoters have 40 cents of land in Kovalam, a major tourist destination of Kerala and South India,which they plan to develop and construct 6 cottages with all modern facilities. Another 4 cottages areplanned and will be commissioned as part of Phase II of the project.

    It has been proposed to start the development and construction of the resort by January 2015 andcommission the phase I of the project by April 2016.

    This project report covers the market and financial feasibility of Phase I & II of the project.

    Background for investment

    Tourism is an ever rising industry in any country. The revenue it brings and the employmentopportunities it provide, both directly and indirectly, has gained it a lot of recognition in favourablegovernment policy making.

    Also there is a lot of potential if there are vacant lands available in tourist hot spots. The promotersthemselves own ancestral land property in Kovalam, the prime tourist destination of Kerala.The present trend of tourist attraction is economy and cost effectiveness. This has a favorable impacton the project as it is a small scale business and the cost expectations of the tourist would match.

    Promoters

    Mr. Anuj Narayanan

    He is currently working as Senior Project Engineer at Qatar Petroleum in Doha,Qatar. Anuj was born in New Delhi and completed schooling in Cochin/ Mumbai.He is a bachelors degree holder in Mechanical Engineering. He has 19 years ofexperience in Oil and Gas Industry.

    Mrs. Meera Anuj

    She is born and brought up in Trivandrum, is a holder of Masters degree inCommerce and has been working as a teacher in Delhi Public School, Doha,Qatar.

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    6/25

    Feasibility study for a proposed Resort at Kovalam 6

    Demand Analysis

    Introduction

    With the Arabian Sea in the west, the Western Ghats in the east and networked by 44 rivers, Keralaenjoys unique geographical features that have made it one of the most sought after touristdestinations in Asia. Also its climate is ideal for tourist visits around the year, making its tourismmarket active all throughout the year.

    Kovalam and Tourism

    Kovalam Beach is one if the finest beaches in India and the most attractive tourist centre of Kerala. Itis 13 kms south of Thiruvananthapuram, the capital city of Kerala, hailed as Gods Own Country. It islocated on the western coast of India near the extreme south of the mainland. It is close toKanyakumari, another important tourist destination, which also makes it a frequently visited spot.Napier Museum, Sri Chitra Art Gallery, Padmanabhaswamy Temple, Padmanabhapuram Palace,Kowdiar Palace, Ponmudi hill station are certain other places of tourist importance in

    Thiruvananthapuram, and they are reasonably close by Kovalam. In 2010, as many as 1,08,639foreign tourists visited Kovalam and the number of domestic tourist is even higher.

    Geography

    Kerala is made up of fourteen districts. Each of them has a distinct character. Thiruvananthapuram(also known as Trivandrum) is the capital of Kerala, famous for its Kovalam beach (rated as one of thetop ten beaches of the world). Geography is destiny in Kerala with the monsoon winds bringing thegift of life annually. Its monsoons are likened to a battalion of wild elephants.

    Climate

    Being situated very close to the sea, Kovalam has a moderate climate. Heavy showers are

    experienced during the months June, July and August due to the South-West Monsoon. The North-East Monsoon brings light rainfall during the months September, October, November and December.December to February is pretty cool. The annual rainfall is about 310 cm. In summer the temperaturerises to a maximum of 35 C while in winter it is around 25 C. The climate between October to Marchis around an average of 25 C, making it the ideal period for tourism.

    Food and Drinks

    Kerala has a variety of delicious food specialties. Rice is the staple food. It is accompanied withvarious curries, curd, pappad, pickles and other side dishes. The non-vegetarian dishes are made ofmutton, beef and chicken. Fish is also a favourite dish. A dessert called payasam usually follows themain course of food. The popular thirst aids are buttermilk and tender coconut water.

    Kovalam being a tourist village of the state, there are a wide range of restaurants and parlourscatering to all kinds of international cuisines such as French, Chinese, Italian, Continental etc.

    Requirement and Demand Analysis for Resorts

    The survey conducted in 2013, by the department of tourism from the details collected fromaccommodation units all over Kerala reveals that the foreign tourist visit in Kerala was 8,58,143during 2013, with an increase of 8.12% from previous year figures. Also, domestic tourist visits hadan increase of 7.75% and statistics for the same was 1,08,57,811 visitors.

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    7/25

    Feasibility study for a proposed Resort at Kovalam 7

    Tourist visit in Kerala

    Tourism is an ever developing sector. From the graph given above, it is clearly evident that tourist visitin Kerala is on the rise, especially domestic tourist visits. Hence, there is an increasing demand forimprovements in the tourism sector. This provides profitable opportunities for new entrants and theirsuccess lies in their ability to provide quality services to their clients at a reasonable cost.

    Out of the 1,17,15,954 tourist visiting Kerala in the year 2013, 18,24,879 tourists (about 16%) arevisiting Trivandrum and wont be missing the beautiful Kovalam. So, on an average 18 lakh peopleare visiting the Kovalam beach every year and this number is rising each year.

    The average tourist visits for each of the 14 districts is approximately around 7% whereas inTrivandrum it was 16%, more than double the average.

    The revenue acquired directly and indirectly from tourism sector during the year 2013 wasRs.22,926.55 Crores and around 16% of this revenue can be apportioned to Trivandrum(i.e. Rs.3,668.2 Crores), making it evident that Trivandrum and Kovalam are indeed the bestoptions to attract tourists and to start new investments.

    Although other tourist spots are somewhat in a 10 km distance, tourists often chooses to stay atKovalam because of the rush and traffic in the city. Hence, a higher occupancy rate is experienced in

    Kovalam compared to that in the city.

    6,59,265 7,32,985 7,93,696 8,58,143

    85,95,075

    93,81,4551,00,76,854

    1,08,57,811

    2010 2011 2012 2013

    Foreign Tourist Domestic Tourist

    0

    20,00,000

    40,00,00060,00,000

    80,00,000

    1,00,00,000

    1,20,00,000

    Foreign Tourist inkerala

    Foreign Tourist inTrivandrum

    Domestic Touristin kerala

    Domestic Touristin Trivandrum

    2012 2011

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    8/25

    Feasibility study for a proposed Res

    Location Advantages

    The shimmering water of the vever green coconut trees and cwithin a 20 minutes drive to theresort. Moreover Kovalam is als

    It is also very easily acceDestination of Kerala and wiAirport run way of Trivandspiritual tourism, eco-touris

    With a record arrival of moryear 2011-12, Trivandrum h

    There are many tourist destiBeach, Napier museum andDam, Kuthira Malika palaceand beaches and many othe

    Advantages of ResortThe Government of Kerala has

    To facilitate the investors, apconversion and allotment of lanallotment of land for setting up o

    ort at Kovalam

    st expanse of the Arabian Sea, the never endoastal line, away from all the hush and traffic ocity, all makes Kovalam an ideal and suitable locconsidered a safe place in Kerala in terms of la

    sible by Air, Train, Road and Water. It is alsll start getting International Chartered Flights inum Airport. Trivandrum is going to make hea, health tourism and rural tourism.

    than 3 lakh foreign tourists and 25 lakh domes s been one of the most popular destinations for

    nations in or near the city including Kovalam beZoo, Agasthyarkoodam peak, Neyyar Wildlife S

    , Sree Padmanabha Swamy temple, Ponmudi,rs.

    Setup in Trivandrumccorded a high priority to attract private investm

    ropriate amendments have been made in thin rural and urban areas. This has facilitated itourism units in the state by private sector initiat

    8

    ing panorama of thef the city yet locatedation for putting up a

    and order.

    the leading touristview of the extendedway in the area of

    ic tourists during theall.

    ch, Sanghumukhamanctuary and Neyyaroovar, Varkala cliffs

    nt in tourism sector.

    e relevant rules forthe conversion and

    ive.

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    9/25

    Feasibility study for a proposed Resort at Kovalam 9

    Project Profile

    Profile of the Proposed Resort

    The resort is located in 40 cents of land located in Kovalam, Thiruvananthapuram. The Project isproposed to be launched in 2 Phases. Phase I will have 6 cottages, a multi-cuisine restaurant and a24x7 coffee shop. 4 more cottages will be set up at a later stage as part of Phase II of the project.

    The cost of Phase I of the project is estimated at 80 lakhs which will be funded entirely by thepromoters of the project. The estimated cost of the phase II of the project is 47 lakhs and will be partlyfunded by the promoters and partly by the funds generated from the operations of Phase I.

    Project at a glance

    Project period Phase I Phase II

    Project Start Year 2015 2018

    Construction period in months 15 6

    Investment (in 000s) Phase I Phase II

    Project Cost (in 000s) 7000 4700

    Contingencies (in 000s) 1000 300

    Total Investment (in 000s) 8000 5000

    Debt Equity Ratio Phase I Phase II

    Debt Nil Nil

    Equity 100% 76%

    Funds generated from operations of Phase I 0 24%

    Built up Area Phase I Phase II

    Nos. Sq ft Area Nos. Sqft Area

    Cottages 6 800 4800 4 800 3200

    Reception and Lobby 1 1000 1000 - - -

    Restaurant and Kitchen 1 1200 1200 1 700 700

    GymTotal Area 7000 3900

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    10/25

    Feasibility study for a proposed Resort at Kovalam 10

    1. Process/Steps

    Following are the necessary steps required to construct the resort:

    Feasibility Study

    Market and financial analysis and projections

    Finalization of the Layout

    Completion of site survey, design of plant & buildings, auxiliary & ancillary buildings, mechanicalutilities, electrical services and system

    Planning for enabling works, like construction of waterlines, power lines and sewerage, office,labour camp, communication facility etc.

    Approach and Internal Roads

    Employee Hiring Process

    Marketing

    2. Infrastructure and Amenities

    Air conditioned cottages

    Airport transfers

    Audio visual equipped

    Business centre

    Cable TV

    Car parking

    Doctor on call

    Fax service

    Fire safeguards

    Laundry facilities

    Photocopy services

    Power back-up

    Restaurant

    Safe deposit

    Travel desk

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    11/25

    Feasibility study for a proposed Resort at Kovalam 11

    Financial Plan

    The financial plan consists of a 6 year profit and loss projection, cash-flow projection, projectedbalance sheet, and calculation of financial feasibility indicators. Together they constitute a reasonable

    estimate of projects financial feasibility.

    Underlying Assumptions used in the financial projections are briefly described below for easyreference.

    Assumptions

    General assumptions used in the Financial Projections are given below:

    Phase I Phase II

    Project Start Year January 2015 October 2018

    Total Investment (Rs in 000s) 8000 5000

    Construction period 15 months 6 months

    Funding

    Debt Nil Nil

    Equity 100% 76%

    Income from Phase I operations 0 24%

    Project Cost and Funding assumptions

    in 000s

    A. Building Phase I Phase IIBuilding Construction 3,344 2,723

    Plant & Machinery 970 725

    Furniture & Fixtures 2,033 1,252

    Miscellaneous Fixed Assets 653

    Total (A) 7,000 4,700

    B. Others

    Pre-Operative cost 500 -

    Statutory compliance fees 300 150

    Consultancy and technical fees 200 150

    Total (B) 1,000 300

    Project Cost (A+B) 8,000 5,000

    The breakup of the cost of construction is annexed to at the end of the project report underAnnexure A.

    Phase I of the project will be entirely funded by Anuj Narayanan & Meera Anuj, promoters of theproject. Phase II of the project will be 75% funded by the promoters and 25% from operations ofPhase I

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    12/25

    Feasibility study for a proposed Resort at Kovalam 12

    Income Assumptions

    Rental rate in Rs Year 1 &2 Year 3 Year 4 Year 5 Year 6

    Season 3,500 4,500 5,500 6,500 7,500

    Off-Season 2,000 3,000 4,000 5,000 6,000

    Average Occupancy %

    Year 1 & Year 2 30%

    Year 3 50%

    Year 4 70%

    Year 5 75%

    Year 6 75%

    No. of cottages

    Phase I 6

    Phase II 4

    Rental Income in 000s Year 1 &2 Year 3 Year 4 Year 5 Year 6

    Season 1,134 2,430 4,158 5,265 6,075

    Off-Season 648 1,620 3,024 4,050 4,860

    Total 1,782 4,050 7,182 9,315 10,935

    Food & Beverages in000s Year 1 &2 Year 3 Year 4 Year 5 Year 6

    Breakfast 194 432 756 972 1,134

    Dinner 648 1,296 2,117 2,592 2,916

    Snacks & Coffee shop 250 300 400 500 600

    Total 1,092 2,028 3,273 4,064 4,650

    Expense Allocation

    Major components of the variable cost and its allocation are as follows:

    Components As a % of

    General & Administration charges 5% of revenue

    Repairs & Maintenance 5% of rental income

    Food & Beverages Cost 30% of F&B income

    Insurance & Legal Charges 10% of rental income

    Utilities 10% of rental income

    Miscellaneous 7% of rental income

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    13/25

    Feasibility study for a proposed Resort at Kovalam 13

    Major components of the fixed costs are as follows:

    Components Annually in Rs.

    Salaries 648,000

    Electricity 180,000

    Office expenses 120,000

    Repairs & Maintenance 200,000

    The year on year increase on fixed expenses from 3rd year onwards is assumed at 5 %

    Depreciation

    Depreciation is calculated as per rates mentioned in the Income Tax Act 1961 and the detailedschedule is attached as part of the projected financial statements.

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    14/25

    Feasibility study for a proposed Resort at Kovalam

    Feasibility Indicators

    The cost of capital is assumed at 15%

    Project IRR

    Description Year 0 Year 1 Year 2 Year 3 Ye

    Initial Investment (8,000)

    Phase II investment (5,000)

    Profit as per P&L A/c (1,029) (836) 928 5

    Add: Depreciation 1,027 834 684 1

    Provision for Tax - - 398 2

    (8,000) (3) (3) (2,990) 9

    Project IRR 30.41%

    Normal payback period

    Project IRR

    Description Year 0 Year 1 Year 2 Year 3 Ye

    Initial Investment (8,000)

    Phase II investment (5,000)

    Profit as per P&L A/c (1,029) (836) 928 5

    Add: Depreciation 1,027 834 684 1

    Provision for Tax - - 398 2

    (8,000) (3) (3) (2,990) 9

    Project present value (8,000) (8,003) (8,005) (10,995) (1

    Normal payback period 5 years

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    15/25

    Feasibility study for a proposed Resort at Kovalam

    Discounted Payback Period

    Description Year 0 Year 1 Year 2 Year 3 Ye

    Initial Investment (8,000)

    Phase II investment (5,000)

    Profit as per P&L A/c (1,029) (836) 928 5

    Add: Depreciation 1,027 834 684 1

    Provision for Tax - - 398 2

    (8,000) (3) (3) (2,990) 9

    NPV (8,000) (2) (2) (1,966) 5

    Discounted payback (8,000) (8,002) (8,004) (9,970) (4

    Discounted payback period 5 years

    Project NPV Description Year 0 Year 1 Year 2 Year 3 Ye

    Initial Investment (8,000)

    Phase II investment (5,000)

    Add: Income before Depreciation,Amortisation and Interest

    (3) (3) 2,010 9

    Total (8,000) (3) (3) (2,990) 9

    NPV (8,000) (2) (2) (1,966) 5

    Project NPV 7,603

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    16/25

    Feasibility study for a proposed Resort at Kovalam

    Resort Project, Kovalam, Trivandrum

    Projected Profitability Statement

    Sch Year 12016-17

    Year 22017-18

    Year 32018-19 20

    Income

    Rental Income 1,782 1,782 4,050

    Food & Beverages 1,092 1,092 2,028

    Total 2,874 2,874 6,078

    Expenditure

    Employee Cost 1 648 648 680

    Office Expenses 120 120 126

    General & Administration charges 144 144 304

    Repairs & Maintenance 200 200 210

    Food & Beverages Cost 328 328 608

    Advertisement 300 300 315

    Insurance & Legal Charges 178 178 405

    Utilities 358 358 594

    Miscellaneous 201 201 425

    Interest on Capital 400 400 400

    Depreciation 2 1,027 834 684

    Profit /(loss) before tax (1,029) (836) 1,325

    Provision for Taxation @ 30% 398

    Profit/(loss) after tax (1,029) (836) 928

    Total 2,874 2,874 6,078

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    17/25

    Feasibility study for a proposed Resort at Kovalam

    Resort Project, Kovalam, Trivandrum

    Projected Balance Sheet

    Year 02015-16

    Year 12016-17

    Year 22017-18

    Year 32018-19

    Ye201

    Liabilities

    Fixed Capital 8,000 8,000 8,000 11,800 11

    Retained earnings/(acc.deficit) (1,029) (1,865) (938) 4

    Total shareholders' funds 8,000 6,971 6,135 10,862 16

    Total liabilities and equity 8,000 6,971 6,135 10,862 16

    Assets

    Work in Progress 5,000

    Cash in hand & at Bank (3) (5) 407 7

    Total Current Assets (3) (5) 5,407 7

    Fixed assets, net 8,000 6,973 6,140 5,455 9

    Total Assets 8,000 6,971 6,134 10,862 16

    Schedule 1

    Employee Cost (in 000s)

    Description No Salary Year 1 Year 2 Year 3

    General Manager/Front office manager 1 144 144 144 151

    Housekeeping 2 96 192 192 202

    Cook 1 144 144 144 151

    Helper 2 84 168 168 176

    Total 6 468 648 648 680

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    18/25

    Feasibility study for a proposed Resort at Kovalam

    Rate Year 1

    Description % OB Dep

    Building 5 3,344 168

    Plant& Machinery 25 970 243

    Furniture & Fixtures 10 2,033 203

    Miscellaneous Fixed Assets 25 1,653 413

    Total 8,000 1,027

    Schedule 2

    Depreciation (in 000s)

    Year 2 Year 3 Year 4

    CB/OB Dep CB/OB Dep CB/OB Addition Dep CB

    3,177 159 3,018 151 2,867 2,723 280 5

    728 182 546 136 409 725 284

    1,829 183 1,646 165 1,482 1,252 273 2

    1,240 310 930 232 697 300 249

    6,973 834 6,140 684 5,455 5,000 1,086 9

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    19/25

    Feasibility study for a proposed Resort at Kovalam

    Resort Project , Kovalam, Trivandrum

    Projected Cash Flow Statement

    Year 0 Year 1 Year 2 Year 3

    2015-16 2016-17 2017-18 2018-19 20

    Sources

    Net Profit as per P&L A/c (1,029) (836) 928

    Add:

    Add: Depreciation 1,027 834 684

    Provision for Tax - - 398

    Own Funds 8,000 3,800

    Total 8,000 (3) (3) 5,810

    Applications

    Provision for Tax - - 398

    Investment in Fixed Assets 8,000 5,000

    Total 8,000 - - 5,398

    Net Cash flow for the year - (3) (3) 412

    Cash and bank, beginning of year 8,000 - (3) (5)

    Cashflow for the year 8,000 (3) (3) 412

    Cash and bank, end of year - (3) (5) 407

    Drawings 10%

    Excess Cash / Surplus Funds 5%

    Investments 85%

    Opening Cash Balance - (3) (5)

    Cash Balance & Cash at Bank (3) (5) 407

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    20/25

    Feasibility study for a proposed Resort at Kovalam 20

    Annexure

    Break Up Of Project Cost

    Phase I Phase II

    A. Building: Sch 2015-16 2018-19

    Building Construction A 3,344 2,723

    Plant & Machinery B 970 725

    Furniture & Fixtures C 2,033 1,252

    Miscellaneous Fixed Assets 653

    Building Total 7,000 4,700

    B. Others

    Pre-Operative cost 500

    Statutory compliance fees 300 150

    Consultancy and technical fees 200 150

    Others Total 1,000 300

    Project Cost 8,000 5,000

    Schedule A

    in 000s

    Cost of Building Phase I Phase II

    Total Built up Area 7 3.9

    Rate per sq.ft 325 475

    Cost 2,275 1,853

    Electrical Work 15% 341 278

    Plumbing & Drainage 12% 273 222

    Consultant 20% 455 371

    Total 3,344 2,723

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    21/25

    Feasibility study for a proposed Resort at Kovalam 21

    Schedule B

    in 000s

    Plant & Machinery Phase I Phase II

    Air Conditioners 280 150

    Generator 100 100

    Bore well 60 40

    EPBAX 40 40

    Boiler 50 40

    CCTV 50 185

    Kitchen Equipments 100

    Fire Fitting 60 40

    Water Coolers 30 30

    Printers, Fax, Telex 60 30

    Computers 140 70

    Total 970 725

    Schedule C

    in 000s

    Furniture & Fixtures Phase I Phase II

    Total 2,033 1,252

    Schedule C1

    Reception, Lobby & Administration in '000s

    Counter 25

    Stationery 25

    Pigeon Hole 15

    Cupboard 50

    Safe deposit 40

    Sofa set 50

    Fixtures 20

    Luggage Carriers 15

    Miscellaneous 30

    Total 270

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    22/25

    Feasibility study for a proposed Resort at Kovalam 22

    Schedule C2

    Phase I Phase II

    Guest Room Nos Rate in 000s Nos Rate in 000s

    Cot

    Queen size 6 15,000 90 4 20,000 80

    Single 5 4,000 20 3 5,000 15

    Mattress

    Queen size 7 7,000 49 6 7,000 42

    Single 5 4,000 20 3 4,000 12

    Mattress Protector

    Queen size 7 1,600 11 6 1,600 10

    Single 5 900 5 3 900 3

    Side table 8 1,500 12 5 1,500 8

    Chair 12 1,000 12 8 1,000 8

    Coffee Table 8 1,000 8 4 1,000 4

    Cupboard/Luggage Rack 8 15,000 120 4 15,000 60

    Dressing Table and Mirror 6 5,000 30 4 5,000 20

    Television 9 20,000 180 4 20,000 80

    Telephones 10 600 6 6 600 4

    Bathroom Mirror 10 1,000 10 6 1,000 6

    Wash Basin 10 1,500 15 4 1,500 6

    WC 10 5,000 50 4 5,000 20

    Bath Tub 6 10,000 60 4 10,000 40

    Upholstery 200 200

    Fixtures 200 200

    Total 1,098 816

    Schedule C3

    Phase I Phase II

    Restaurant Nos. Rate in '000s Nos. Rate in '000s

    Tables 4 2,500 10 3 2,500 8

    Trays 10 500 5 5 500 3

    Chair 15 1,000 15 15 1,000 15

    Side Stations 2 10,000 20 2 10,000 20

    Upholstery 20 20

    Fixtures 20

    Total 90 65

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    23/25

    Feasibility study for a proposed Resort at Kovalam 23

    Schedule C4

    Phase I Phase II

    Guest Room Linen Nos. Rate in 000s Nos. Rate in 000s

    Single Bed Sheet 15 600 9 6 600 4

    Double Bed Sheet 20 1,000 20 10 1,000 10

    Blankets 20 1,000 20 10 1,000 10

    Blankets Cover 20 500 10 10 500 5

    Bed Cover 20 800 16 10 800 8

    Pillow Cover 40 200 20 20 200 4

    Hand Towel 80 150 12 40 150 6

    Bath Towel 80 400 32 40 400 16

    Bath Mat 40 150 6 20 150 3

    Total 145 66

    Schedule C5

    in 000s

    Stores & Housekeeping Phase I Phase II

    Racks, Cupboards & Shelves 100 75

    Bins 10 10

    Fixtures 20 20

    Total 130 105

    Schedule C6

    in 000s

    Kitchen & Kitchen Stewarding Phase I Phase II

    Kitchen Interiors Hobs, Cabinet etc. 200 100

    Glasses 50 50

    Cutlery & Crockery 50 50

    Total 300 200

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    24/25

    Feasibility study for a proposed Resort at Kovalam 24

    Project Implementation Tracker

    in months

    # Particulars Phase I Phase II

    1 Project research

    2 Preparation of feasibility report

    3 Preparation of Building plan

    4 Project approval

    5 Application for electricity & water

    6 Building construction

    7 Purchase & installation of Plant & Machinery

    8 Plumbing & electrification

    9 Furnishing and interior decoration

    10 Staff recruitment

    11 Trail runs and commissioning

    12 Land seeping

    13 Inauguration and commercial roll out

    Total Implementation Period 15 6

  • 8/11/2019 Resort Project - Feasibility Final Report - 22082014

    25/25