    Risk Assessment Tool

    Residual Risk Reduction (R3)

    Danny Viator Tony Spencer

    Superior Energy Liberty Mutual

    Broussard, LA Metairie, LA

    April, 2010

  • 8/8/2019 Residual Risk Reduction (R3)

    2/42

    Definition-Residual Risk

    ReductionA process that involves a study to:

    Analyze jobs Identify hazards and existing controls

    Determine the level of risk

    Identify controls to reduce risk Measure the amount of risk reduction

  • 8/8/2019 Residual Risk Reduction (R3)

    3/42

    Some Facts About Risk

    An inherent feature of systems; a qualitythat always exists to some degree

    Is definable in terms of three factors(Frequency, Likelihood, & Severity)

    Once it is defined, it can be quantified

    The quantity of risk can be changed bychanging these factors

  • 8/8/2019 Residual Risk Reduction (R3)

    4/42

    The Risk Factors

    Frequency (Exposure Opportunity)

    How often the exposure exists

    Likelihood (Chance of Occurrence)

    Severity (Degree of Harm) Worst Plausiblescenario

  • 8/8/2019 Residual Risk Reduction (R3)

    5/42

    Risk Rating Scale

    Rating Frequency Likelihood Severity

    1 < once per shiftor day

    2 > once per shiftor day

    3 > once per hour

    4 > once per fiveminutes

    5 At all times

  • 8/8/2019 Residual Risk Reduction (R3)

    6/42

    Risk Rating Scale

    Rating Frequency Likelihood Severity

    1 Impossible

    2 Unlikely

    3 Possible

    4 Probable

    5 Multiple

  • 8/8/2019 Residual Risk Reduction (R3)

    7/42

    Risk Rating Scale

    Rating Frequency Likelihood Severity

    1 First Aid

    2 Medical Treatment

    3 Lost time, full recovery

    4 Some permanentimpairment

    5 Major permanentimpairment or death

  • 8/8/2019 Residual Risk Reduction (R3)

    8/42

    Risk Rating Scale

    Rating Frequency Likelihood Severity

    1 < once per shiftor day

    Impossible First Aid

    2 > once per shiftor day

    Unlikely Medical Treatment

    3 > once per hour Possible Lost time, full recovery

    4 > once per fiveminutes

    Probable Some permanentimpairment

    5 At all times Multiple Major permanentimpairment or death

  • 8/8/2019 Residual Risk Reduction (R3)

    9/42

    Risk = F x L x S

    The quantity of risk can be changed bychanging the risk factors

    Eliminating a step

    Changing how a step is done

    Implementing new/revised controls

  • 8/8/2019 Residual Risk Reduction (R3)

    10/42

    Organizing the R3 Team

    Team leader

    -Familiar with the mechanics of R3

    -Can facilitate group decision making Group-Multi-disciplinary

    -Health & Safety

    -Operations-Engineering

  • 8/8/2019 Residual Risk Reduction (R3)

    11/42

    R3 Example

    Climbing & Working on ProductionChristmas Trees

  • 8/8/2019 Residual Risk Reduction (R3)

    12/42

    Production Tree Examples

  • 8/8/2019 Residual Risk Reduction (R3)

    13/42

    Production Tree Examples

  • 8/8/2019 Residual Risk Reduction (R3)

    14/42

    Production Tree Examples

  • 8/8/2019 Residual Risk Reduction (R3)

    15/42

    Production Tree Examples

  • 8/8/2019 Residual Risk Reduction (R3)

    16/42

    Exposure Example

  • 8/8/2019 Residual Risk Reduction (R3)

    17/42

    Exposure Example

  • 8/8/2019 Residual Risk Reduction (R3)

    18/42

  • 8/8/2019 Residual Risk Reduction (R3)

    19/42

    Production Tree R3 Team

    -Warren-Corporate Safety -Tony-Ins LC

    -Danny-Division Safety -Terry-Broker-John-Division Safety -Clint-Falls Rep

    -Joe-Division Safety

    -Joe P-Trainer-Spencer-Training Director

  • 8/8/2019 Residual Risk Reduction (R3)

    20/42

    R3TM BaselineFacility: Superior Wireline Division Exposure: Falls While Working

    on Production Trees

    System: Production Trees Date: May, 2009

    Task: Evaluating the task of climbing and working on production trees

    Concern Current Controls F L S Risk New Controls F L S Risk

    Employees exposedto falls while eitherclimbing up or downproduction trees

    Orientation, JSEA, WorkBoots, Clean Tree, 3 PtClimbing, DedicatedClimbing Training, StopWork Authority, BehaviorBased Safety

    4 3 4 48

    Risk Index1 48 Risk Index2

    Liberty Mutual NMLP

  • 8/8/2019 Residual Risk Reduction (R3)

    21/42

    R3TM SubsequentFacility: Superior Wireline Division Exposure: Falls While

    Working on Production Trees

    System: Production Trees Date: May, 2009

    Task: Evaluating the task of climbing and working on production trees

    Concern CurrentControls

    F L S Risk New Controls F L S Risk

    Employeesexposed tofalls whileeither climbingup or downproductiontrees

    All of the controls in theBaseline Assessment plus JobSpecific Fall ProtectionProcedures

    4 2 2 16

    Risk Index1 Risk Index216

    Liberty Mutual NMLP

  • 8/8/2019 Residual Risk Reduction (R3)

    22/42

    R3TM WorksheetFacility: Superior Wireline Division Exposure: Falls While Working

    on Production Trees

    System: Production Trees Date: May 2009

    Task: Evaluating the task of climbing and working on production trees

    Concern Current Controls F L S Risk New Controls F L S Risk

    Employees exposedto falls while eitherclimbing up or downproduction trees

    Orientation, JSEA, WorkBoots, Clean Tree, 3 PtClimbing, Stop WorkAuthority, Behavior BasedSafety

    4 3 4 48 All of the controls in theBaseline Assessmentplus Job Specific FallProtection Procedures

    4 2 2 16

    Risk Index1 48 Risk Index2 16

    Liberty Mutual NMLP

  • 8/8/2019 Residual Risk Reduction (R3)

    23/42

    Overview of Tree

  • 8/8/2019 Residual Risk Reduction (R3)

    24/42

    Use of Fall Protection

  • 8/8/2019 Residual Risk Reduction (R3)

    25/42

    Production Tree

    Residual Risk Reduction

    R3 = [(RI1 RI2)/RI1 X100] = % Reduction

    48-16 = 67% Reduction48x100

  • 8/8/2019 Residual Risk Reduction (R3)

    26/42

    R3 Example

    Wire Sticks

    While Reaming Packing

  • 8/8/2019 Residual Risk Reduction (R3)

    27/42

  • 8/8/2019 Residual Risk Reduction (R3)

    28/42

  • 8/8/2019 Residual Risk Reduction (R3)

    29/42

  • 8/8/2019 Residual Risk Reduction (R3)

    30/42

    Exposure Example

  • 8/8/2019 Residual Risk Reduction (R3)

    31/42

    Exposure Example

  • 8/8/2019 Residual Risk Reduction (R3)

    32/42

    Exposure Example

  • 8/8/2019 Residual Risk Reduction (R3)

    33/42

    Wire Sticks R3 Team

    -Warren-Corporate Safety -Tony-Ins LC

    -Danny-Division Safety

    -John-Division Safety

    -Ryan-Division Safety

    -Matt-Corporate Safety

    -Robert-Operations

    -BJ-Training

    R3TM B li

  • 8/8/2019 Residual Risk Reduction (R3)

    34/42

    R3TM BaselineDivision-Superior Wireline Division-Slickline

    Exposure-Wire Sticks

    System-Stuffing Box Packing Date-October, 2009

    Task-Evaluating the task of reaming out stuffing box packings

    Concern Current Controls F L S Risk New Controls F L S Risk

    Slickline Operatorsand Helpers are

    exposed to receivingwire sticks in thehands while they arereaming out stuffingbox packings

    New employee orientation,JSAs, Safety meetings,

    Kong Gloves, Pig tail & viceprocedure recommended,Stop Work Authority,Behavior Based Safety

    5 4 3 60

    Risk Index 60

    Liberty Mutual NMLPPoster 3

    R3TM S b t

  • 8/8/2019 Residual Risk Reduction (R3)

    35/42

    R3TM SubsequentDivision-Superior Wireline Division-Slickline

    Exposure-Wire Sticks

    System-Stuffing Box Packing Date-October, 2009Task-Evaluating the task of reaming out stuffing box packings

    Concern Current Controls F L S Risk New Controls F L S Risk

    Slickline Operators andHelpers are exposed toreceiving wire sticks inthe hands while theyare reaming out stuffingbox packings

    All controls listed in theBaseline assessmentplus packing mfg toream out to 0.125(vs.0.092), shop to reamout to 0.125, supplyream assist tool to allfield operators, add JSAon reaming specifics,safety meetingemphasis on for next 90

    days on these controlsby field safety staff

    5 2 1 10

    Risk Index 10

    R3TM W k h t

  • 8/8/2019 Residual Risk Reduction (R3)

    36/42

    R3TM WorksheetDivision-Superior Wireline Division-Slickline

    Exposure-Wire Sticks

    System-Stuffing Box Packing Date-October, 2009Task-Evaluating the task of reaming out stuffing box packings

    Concern Current Controls F L S Risk New Controls F L S Risk

    Slickline Operatorsand Helpers areexposed to receivingwire sticks in thehands while they arereaming out stuffingbox packings

    New employee orientation,Kong Gloves, Pig tail &vice procedurerecommended, Stop WorkAuthority, Behavior BasedSafety

    5 4 3 60 All controls listed in theBaseline assessmentplus packing mfg toream out to 0.125(vs.0.092), shop toream out to 0.125,supply ream assist toolto all field operators,add JSA on reamingspecifics, safetymeeting emphasis on

    for next 90 days onthese controls by fieldsafety staff

    5 2 1 10

    Risk Index 60 10

  • 8/8/2019 Residual Risk Reduction (R3)

    37/42

    Assist Tool

  • 8/8/2019 Residual Risk Reduction (R3)

    38/42

    Assist Tool

  • 8/8/2019 Residual Risk Reduction (R3)

    39/42

    Residual Risk Reduction

    R3 = [(RI1 RI2)/RI1 X100] = % Reduction

    60-10 = 83% Reduction60x100

  • 8/8/2019 Residual Risk Reduction (R3)

    40/42

    R3 Analysis

    Define the

    F-L-S scales

    Define the system to

    be studied

    (Activity)

    Identify the

    concerns to

    be analyzed

    (Incidents)

    Score each concern

    on the F-L-S scales

    Identify/Analyze

    controls

    Identify

    New

    controls

    Implement the new

    controls

    Re-score the

    concerns with

    the new controls

    Report the R3

    as a Safety

    Outcome!

  • 8/8/2019 Residual Risk Reduction (R3)

    41/42

    Other R3 Examples

    Handling Chicksan pipe

    Vehicle traffic flow pattern in an oilfieldyard

    Climbing on/off of vacuum tank trailers

    Working on a burn table at a mfg plant

    Changing catalyst in a cat cracker Access to bucket truck by Linemen

  • 8/8/2019 Residual Risk Reduction (R3)

    42/42

    So Whats In It For Me?

    R3 provides a means for examiningsystems

    R3 gets the people closest to the risk in

    systems involved in its reduction It illustrates how interventions affect risk

    It provides both upstream & downstream

    measures for safety efforts R3 motivates action to reduce risk from

    hazards in systems