REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M....

21
REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June 2015

Transcript of REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M....

Page 1: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRYF. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer

FCC dump meeting18th June 2015

Page 2: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 2

Outline

• Current status @ LHC• Dilution kicker requirements• Beam dump line geometry• Conclusion

18/06/2015

Page 3: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 3

Reminder – LHC system

18/06/2015

MKBH

Magnets per system 4

Max. system defl. angle 0.278 mrad

Kick strength per magnet 1.624 Tm

Hor. aperture 58 mm

Ver. aperture 32 mm

Frequency 14.2 kHz

MKBV

Magnets per system 6

Max. system defl. angle 0.277 mrad

Kick strength per magnet 1.077 Tm

Hor. aperture 66 mm

Ver. aperture 36 mm

Frequency 12.7 kHz

Dilution kickersMKB

Dump blockTDE

~ 600 m

Page 4: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 4

Installation in the tunnel

18/06/2015

Courtesy: L. Ducimetiere

Page 5: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 5

BTVDD screenshot

18/06/2015

Page 6: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 6

FCC beam dumps

• ~ 10600 bunches with a bunch spacing of 25 ns.• Bunches separated by 1.8 mm on the TDE (Given by max. Temperature in Carbon

(1500 Celsius) - A. Lechner).• Bunch equally spaced dumped on the beam dump block. Requires frequency modulation of the dilution kicker.

18/06/2015

Page 7: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 7

How it should look like:

18/06/2015

R=20 cm

Page 8: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 8

Zoom into the first bunches

18/06/2015

1.95 mm 6 mm

Page 9: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 9

Frequency and amplitude of the dilution kickers

18/06/2015

Page 10: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 10

Frequency modulation

18/06/2015

Page 11: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 11

Requirements for FCC dilution kickers

• B rho @ 50 TeV: 166.666 Tm• Max deflection angle with the current design @ 50 TeV: 0.044 mradDrift space between MKB and TDE: 4.6 km

Possible Mitigations:• Increase number of elements.• Increase of current.• Tilted MKB to gain in both planes.??• Install Quadrupole to get more kick:

• Variation of the drift length beam dump line geometry.

18/06/2015

MKBH MKBVQuad Quad

Page 12: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 12

FCC layout

18/06/2015

• 2 dump insertions (length: 4.2 km ).• Extraction and betatron collimation.

Page 13: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 13

Beam dump line geometry (1/3)

18/06/2015

1.4 km dump insertion 2.8 km collimation insertion

2 km dump line

• 2 km dump line (for dilution system / drift)• Dump cavern should be separated from circulating beam.• Dumped beam is only about 0.7 m separated in hor. plane from FCC circulating beam, after

2 km.• Needs ~100 m of 16 T dipole at 167’000 Tm.

Courtesy: W. Bartmann

Page 14: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 14

Dump line elements

1.4 km dump insertion

2.0 km dump line

Kicker Septum 10 mrad bendMKB

Absorber

18/06/2015

Would require: 0.12 mrad total deflection in the MKB, Keep aperture from LHC MKB= 11 magnets (hor). Min. extraction energy: 3.3 TeV – gain factor 7 (energy-scaling) in aperture? Will be

reduced by higher .b

2.8 km collimation

Page 15: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 15

Beam dump line geometry (2/3)

1.4 km dump insertion2.8 km collimation insertion

2 km dump line

• 2 km arc bend gives 150 mrad angle• 150 m separation between dump cavern and ring.• No additional dipoles needed.• Collimation in the downstream arc needed.

18/06/2015

Courtesy: W. Bartmann

Page 16: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 16

Dump line elements

1.4 km dump insertion 2 km dump line

Kicker Septum MKBAbsorber

18/06/2015

arc

Would require: 0.099 mrad total deflection in the MKB. Keep aperture constant = 9 magnets (hor).

Page 17: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 17

Beam dump line geometry (3/3)

18/06/2015

1.4 km dump insertion 2.8 km collimation insertion

2 km dump line

~ 1 km dump line

• Feed dump line through collimation insertion.• Reduces complexity of the system – less kick strength needed in

kicker and septum, no additional dipoles, no additional collimation in the arc.

• Radiation limitations?• Hot area – access limitations?• Bigger tunnel diameter?• Distance between collimator and dump line?

Page 18: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 18

Dump line elements

18/06/2015

1.4 km dump insertion 2 km dump and collimation line

Kicker Septum

Absorber

Collimation

MKB

arc

Would require: 0.055 mrad total deflection in the MKB. Keep aperture constant = 6 magnets (hor).

Page 19: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 19

Conclusions

• MKB requirements:• max. deflection between 0.1 mrad and 0.055 mrad depending on dump insertion geometry.• Frequency up to 10 MHz.• First assumption: keep apertures as in LHC.• How much redundancy needed?

• 3 options for beam dump insertion design.• With 100m dipoles and collimation downstream.• Without dipoles and with dedicated collimation.• Going straight through collimation insertion into beam dump line using arc separation

18/06/2015

Feasible?

Page 20: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 2018/06/2015

Thank you for your attention!

Page 21: REQUIREMENTS FOR FCC DILUTION KICKERS AND BEAM DUMP LINE GEOMETRY F. Burkart, W. Bartmann, M. Fraser, B. Goddard, T. Kramer FCC dump meeting 18 th June.

FCC dump meeting 2118/06/2015