SECURING OTHER BUILDING-RELATED PERMITS ABOUT THE SERVICE Aside from a building permit, the Office of the Building Official/City Engineer’s Office issues other permits that are required before the renovation, construction or demolition of any structure. Office of issues other permits that are required before the renovation, construction or demolition of any structure. TYPES OF PERMITS AND REQUIREMENT(S) ELECTRICAL PERMIT This document is required before putting up new or additional, or altering electrical installations involving at least 20 outlets or a capacity of 4 Kw. For new buildings, this form as part of the requirements for a Building Permit application. REQUIREMENTS: 1. Electrical Permit Application Form signed by a professional Electrical Engineer 2. Electrical Plans 3. Electrical Specifications 4. Bill of Materials and Cost Estimates. MECHANICAL PERMIT This is required before the installation of new or additional, removal or alteration of machinery of at least 20 HP. For new buildings, this forms part of the requirements for a Building Permit application. REQUIREMENTS: Mechanical Permit Application Form signed by a professional Mechanical Engineer. Mechanical Plans Mechanical Specifications Bill of Materials and Cost Estimates SANITARY/PLUMBING PERMIT This document is required before the construction of new or additional, or altering existing plumbing installations, water supply, storm drainage, water purification and sewerage treatment plants. For new buildings, this forms part of the requirements for a Building Permit application. REQUIREMENTS: Sanitary/Plumbing Permit Application Form signed by a Sanitary Engineer or Master Plumber Sanitary/Plumbing Plans Sanitary/Plumbing Specifications

description

building requirements

Transcript of Requireemnts of Building Permits

SECURING OTHER BUILDING-RELATED PERMITSABOUT THE SERVICEAside from a building permit, the Office of the Building Official/City Engineers Office issues other permits that are required before the renovation, construction or demolition of any structure. Office of issues other permits that are required before the renovation, construction or demolition of any structure.TYPES OF PERMITS AND REQUIREMENT(S)ELECTRICAL PERMITThis document is required before putting up new or additional, or altering electrical installations involving at least 20 outlets or a capacity of 4 Kw. For new buildings, this form as part of the requirements for a Building Permit application.REQUIREMENTS:1. Electrical Permit Application Form signed by a professional Electrical Engineer2. Electrical Plans3. Electrical Specifications4. Bill of Materials and Cost Estimates.MECHANICAL PERMITThis is required before the installation of new or additional, removal or alteration of machinery of at least 20 HP. For new buildings, this forms part of the requirements for a Building Permit application.REQUIREMENTS: Mechanical Permit Application Form signed by a professional Mechanical Engineer. Mechanical Plans Mechanical Specifications Bill of Materials and Cost EstimatesSANITARY/PLUMBING PERMITThis document is required before the construction of new or additional, or altering existing plumbing installations, water supply, storm drainage, water purification and sewerage treatment plants. For new buildings, this forms part of the requirements for a Building Permit application.REQUIREMENTS: Sanitary/Plumbing Permit Application Form signed by a Sanitary Engineer or Master Plumber Sanitary/Plumbing Plans Sanitary/Plumbing Specifications Bill of Materials and Cost EstimatesFENCING PERMITThis is permit secured prior to actual construction of a fence.REQUIREMENTS: Fencing Permit Application Form Fencing Plan Bill of Materials and Cost Estimates Lot Plan with certification of a Geodetic Engineer that the proposed fence will not encroach on adjoiningPROPERTIES Transfer Certificate of Title (TCT) Deed of Sale/Lease Contract/Contract to Sell (if the TCT is not in the name of the owner/applicant) Updated RealPROPERTYTax Declaration Certificate of RealPROPERTYTax PaymentDEMOLITION PERMITThis permit is secured prior to the systematic dismantling or destruction of a building or structure in whole or in part.REQUIREMENTS: Demolition Permit Form Sketch Plan of area to be demolished Certificate of RealPROPERTYTax PaymentTEMPORARY SERVICE CONNECTION PERMITThis permit is secured for temporary service connection to a power utility for lighting and power for construction, Christmas decorative lighting, lighting of cemeteries, temporary lighting for carnivals/fiestas, testing, etc.REQUIREMENTS: Permit Form (DPWH Form NO. 96-005-E) Building Permit (for new construction) Electrical Plan/Layout Fire Safety Inspection Certificate (FSIC)EXCAVATION AND GROUND PREPARATION PERMITThis permit is secured prior to actual ground preparation and excavation after the building line is established. It is also a requirement for a water connection request to Manilad Water Services, Inc. (MWSI).REQUIREMENTS: Accomplished Permit Form (MPW Form No. 77-014-B) For MWSI connection purposes, present accomplished MWSI Application FormSIDEWALK CONSTRUCTION PERMITThis permit is secured prior to the construction and repair of sidewalksREQUIREMENTS: Accomplished Permit Form (MPW Form No. 77-015-B)2. Sketch plan of sidewalk to be constructed/repairedSCAFFOLDING PERMITThis permit is secured whenever theERECTIONof scaffolding occupies street linesREQUIREMENTS: Accomplished Permit Form (MPW Form No. 77-017-B) Sketch plan of street line to be occupiedSIGN PERMITThis permit is secured prior to the installation,ERECTION, attachment painting of any form of signage.REQUIREMENTS: Sign Permit Form Building Permit Form whenever there is a concrete structure. Structural Analysis Zoning Clearance Electrical Permit Form, whenever there is an electrical connection Fire Clearance whenever there is an electrical connection Sketch plan of signage to be installedERECTED Location/vicinity plan Lot documents whenever it occupies a private lot DPWH clearance (for national roads/highways)FEE(S) Please refer to the revised National Building Code.HOW TO AVAIL OF THE SERVICEFOLLOW THESE STEPSIT WILL TAKE YOUPLEASE APPROACH

1. Secure Application FormsSecure the relevant permit forms from the Building Official Staff.5 minutesReceiving Officer

2. Evaluation and AssessmentThe technical staff evaluates and assesses the submitted plans and pertinent documents for compliance with the requirements of the building code, referral codes, laws and ordinances.Average of 2 hours and 30 minutes(Maximum of 4 hours)

3. Processing of PermitsBuilding Staff processes the plans and pertinent documents and prepares the Order of Payment for final approval of the Building Official.2 daysBuilding Official Staff

4. Endorsement to Building Official for Final Evaluation Issuance of Order of PaymentIf the documents are in order, the applicant receives an Order of Payment stating the fees to be paid.2 daysBuilding Official

5. Payment of FeesProceed to the City Treasurers Office and pay the requisite fees.You will be issued an Official Receipt30 minutesCashier, City Treasurers Office

6. Submit Official ReceiptGo back to the office of the Building Official and submit your Official Receipt.10 minutesBuilding Official

8. Approval of PermitBuilding Official approves the permit.4 hoursBuilding Official

9. Release of PermitThe Building Permit is issued 4 hours after submission of the Official Receipt.30 minutesReleasing Clerk

APPLYING FOR AN OCCUPANCY PERMITABOUT THE SERVICEA Occupancy Permit is required before any building/structure is used or occupied. It is usually secured after the completion of a structure. It is also required if there is any change in the existing use or occupancy classification of a building, structure or any portion thereof.GENERAL REQUIREMENTS: Certificate of Completion from the Building Official Certificate of Completion Mechanical, Electrical and Sanitary/Plumbing Logbook of building construction and Building Inspection Sheet duly accomplished by the contractor (if undertaken by contract) and signed and sealed by the architect or civil engineer in charge of construction Certificate of Final Electrical Inspection Final Fire Safety Inspection Report by the Bureau of Fire Protection Zoning Conformance issued by the Zoning Administrator As built plans (for any deviations from the approved plans)FEE(S) Please refer to the revised National Building Code.