![Page 1: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/1.jpg)
Request for Qualifications for CMGC Services for the Yerba Buena Island
Westside Bridges Project
RFQ 17/18-12
Pre-Proposal Conference
SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY
July 20, 2018
![Page 2: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/2.jpg)
Today’s Agenda
2
Project Background
RFQ Scope of Services
SOQ Evaluation
SOQ Requirements
RFQ Key Information
Q&A
![Page 3: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/3.jpg)
Project Location
![Page 4: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/4.jpg)
Project Setting
![Page 5: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/5.jpg)
Site Conditions – Treasure Island Road
5
Steep Terrain
Limited Access
![Page 7: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/7.jpg)
Structure No. 1 (Retrofit))
![Page 8: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/8.jpg)
Site Conditions – Retrofit Bridges
8
Steep Terrain
Erosion / Slides
![Page 9: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/9.jpg)
Structure No. 4 (Retrofit)
![Page 10: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/10.jpg)
Structure No. 7A / 7B (Retrofit)
![Page 11: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/11.jpg)
Structure No. 8 (Retrofit)
![Page 12: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/12.jpg)
Site Conditions – Replacement Structures
12
![Page 13: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/13.jpg)
Structure 2 (Demolish)
![Page 14: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/14.jpg)
Structure 3 (Demolish)
![Page 15: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/15.jpg)
Structure 6 (Demolish)
![Page 16: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/16.jpg)
Replacement Project
16
![Page 17: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/17.jpg)
Replacement Project
17
![Page 18: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/18.jpg)
Replacement Project
1
8
![Page 19: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/19.jpg)
TIMMA Tolling
1
9
![Page 20: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/20.jpg)
Road Closures to Expedite Construction
20
Close Westside I-80 Ramps
Close Treasure Island Road between Macalla
Road and Forest Road Intersections
![Page 21: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/21.jpg)
21
CABLE HOUSE
Project Challenges that warrant CMGC Delivery
► Geotechnical – Unstable
Soil Swale
► Steep terrain –
Construction Access
► Complex Bridge/Wall
Foundation Construction
► Rock Anchor (110’ long)
Tie-back Retaining Walls
► Environmental constraints
– Birds, Plants, etc.
► Storm water - proximity to
SF Bay
► Cost Containment
![Page 22: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/22.jpg)
CM Responsibilities and Services
22
RFQ pages 33-34:
Construction Manager Responsibilities
Cost-Related Preconstruction Services
Schedule-Related Preconstruction Services
Administrative-Related Preconstruction Services
![Page 23: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/23.jpg)
RFQ Scope of Services
23
Pre-construction Tasks (RFQ page 105):
Task 1: Project Team Kickoff Workshop
Task 2: Initial Approach to Cost Meeting
Task 3: Partnering
Task 4: Project Meetings and Document Review
Task 5: Risk Management
Task 6: Innovation Management
Task 7: Project Construction Schedule Development
Task 8: Project Construction Cost Estimate Development
Task 9: Development of Subcontracting Plan
Task 10: Development of DBE Goal Plan
Task 11: Preconstruction Field Work
Task 12: Construction Agreed Price Bid(s) of Fixed Unit Price Bid
![Page 24: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/24.jpg)
RFQ Evaluation Criteria
24
Scored SOQ Categories (RFQ page 25):
Proposer Organization and Key Personnel
Firm Experience and Past Performance
Project Understanding and Approach
![Page 25: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/25.jpg)
SOQ Format Requirements
25
SOQ organization (RFQ page 37):
Transmittal Letter and Appendix C – Form G
Six text sections:
▪ Section 1 – Legal Structure
▪ Section 2 – Financial Capacity
▪ Section 3 – Safety Program
▪ Section 4 – Firm Experience and Past Performance
▪ Section 5 – Proposer Organization and Key Personnel
▪ Section 6 – Project Understanding and Approach (max 15 pages)
Appendices:
▪ Appendix A – Resumes
▪ Appendix B – Legal Documents
*Cover letter, each section and two appendices shall be combined in one three-ring binder
![Page 26: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/26.jpg)
SOQ Submission Requirements
26
Submitted by 8/10; 2:00 p.m. (RFQ page 23):
One unbound original of SOQ & cost proposal
Four bound hard copies of proposal & cost proposal
One electronic copy of proposal & cost proposal
Exhibits
▪ Appendix C, Forms A-M (Forms H and I sealed separately)
▪ Appendices D and E (sealed separately from cost proposal)
![Page 27: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/27.jpg)
RFQ Key Information
27
Funding:
Federal Highway Bridge Program and State Prop 1B Funds
Budget: Pre-construction Services Contract Limit: $675,000
Estimated Construction Contract Value: $55,300,000
DBE Goal: Will be established near end of final design
Schedule:
Pre-construction Contract Award: October 2018
Anticipated Award of Construction Contract: December 2019
Substantial Completion of Project: August 2021
![Page 28: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/28.jpg)
RFQ Key Information
28
Important Dates:
July 24 (5:00 pm): Written questions due to [email protected]
July 30: SFCTA posts responses to questions
August 10 (2:00 pm): Proposals due to SFCTA’s offices
August 20: Invitations to interview sent
August 27-31: Interviews tentatively scheduled
![Page 29: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/29.jpg)
CM/GC Contractor Services for YBI Westside Bridges Retrofit Project
Project Name: Yerba Buena Island (YBI) Westside Bridges Retrofit
Description: Construction Manager/General Contractor (CM/CG) contractor services
for YBI Westside Bridges Retrofit
Estimated Contract: $675,000 Preconstruction Services; $55.3M Construction
Funding Source: Federal Highway Bridge Program and State Prop 1B Funds
Projected DBE Goal: DBE will be established near end of final design. DBE certified by
California Unified Certification Program (CUCP) for Construction Phase
RFQ Issuance: July 10, 2018
Project Schedule: Preconstruction Services: October 2018 thru December 2019
Construction: January 2020 thru August 2021
Project Contact: Eric Cordoba, [email protected]
Service Specialties: Preconstruction Services and Construction of: undercrossing structure,
bridge retrofit, retaining walls, bridge demolition, roadway realignment
29
![Page 30: Request for Qualifications for CMGC Services for the Yerba ... · Request for Qualifications for CMGC Services for the Yerba Buena Island Westside Bridges Project RFQ 17/18-12 Pre-Proposal](https://reader033.fdocuments.us/reader033/viewer/2022042012/5e72c5f7ebcea606bc60e1c9/html5/thumbnails/30.jpg)
SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY
Questions?