REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY … · 2018-10-11 · materials supply,...
Transcript of REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY … · 2018-10-11 · materials supply,...
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY
INSTRUMENTATION SYSTEM
ISRO PROPULSION COMPLEX
Indian Space Research Organization
Department of Space, Government of India
Mahendragiri-627 133
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
TABLE OF CONTENTS
SL.NO CHAPTER PAGE NO
ANNEXURE-A Scope of work & services
1 Introduction 01
2 Instrumentation system requirements 01
2.1 Definition of field, Cable Termination
Room (CTR) & control room
instrumentation
01
2.2 Instrumentation system – channel wise
requirements 02
2.3 Instrumentation system wise
requirements 03
2.3.1 Measurement system 03
2.3.2 Safety Instrumentation system 07
2.3.3 Command system 08
2.3.4 Auxiliary Instrumentation 09
2.3.5 Powering of Equipment's 12
2.3.6 Grounding of Equipment's 12
2.3.7 Console & Control Room Table -
Equipment mounting and wiring 13
3 Scope of contract 13
3.1 Detailed engineering 14
3.2 Equipment and material supply 15
3.3 Erection and Commissioning 18
3.3.1 General instructions 18
3.3.2 Erection and commissioning
works 21
3.3.3 Testing and evaluation 43
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
3.4 Documentation 45
ANNEXURE -B Control room layout 47
ANNEXURE -C Instrumentation System Configuration and
schematic diagram
50
ANNEXURE -D Instrumentation Rack General Assembly
Drawing 74
ANNEXURE -E Specification & Sub-vendor directory 84
ANNEXURE -F T & E Sheet format 192
ANNEXURE-G Process & Instrumentation Diagrams and
Layout 196
ANNEXURE -H Price Format 198
ANNEXURE-I Terms and Conditions 204
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Annexure A (Scope of work & services)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 1
1. INTRODUCTION
The scope of this work package includes detailed engineering, equipments &
materials supply, installation & wiring of field elements, canalization of field
instruments such as pressure sensors, E/P valves, etc., wiring of instrumentation
racks, erection of cable trays, laying of cables on cable trays, testing & evaluation of
instrumentation system and preparation of documentation for this instrumentation
system.
2. INSTRUMENTATION SYSTEM REQUIREMENT
2.1. DEFINITION OF FIELD, CABLE TERMINATION ROOM (CTR) & CONTROL
ROOM INSTRUMENTATION
The Field, CTR & Control room Instrumentation system includes four
sub systems namely Command System, Measurement System, Safety System
and Auxiliary System. Field refers to the location where the test facility and
its associated fluid systems are located. Field elements refer to pressure
transmitter, level sensors, temperature probes, temperature transmitters,
turbine flow meters, mass flow meters, magnetic flow meters, junction boxes
and Solenoid Valves (SOV) etc. located in field. In cable termination room,
the valve driver rack, barrier, totalizer, Remote control system, integrated
Data Acquisition System, power supplies, instrumentation racks, etc. will be
located.
Test operator console, control system local node, auxiliary system
controls, etc. will be located in the control room.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 2
2.2. INSTRUMENTATION SYSTEM – CHANNEL WISE REQUIREMENTS
Sl. No System Facility
Requirement Spare
Total
channels
A Facility Measurement System
01 Absolute Pressure 35 18 53
02 Vacuum Pressure 08 05 13
03 Differential Pressure for Level 02 01 03
04 Temperature-RTD 13 02 15
05 Temperature-TC 15 02 17
06 Flow – Turbine flow meter 04 01 05
07 Flow – Mass flow meter 04 01 05
08 Flow – Magnetic flow meter 08 02 10
09 Differential Pressure for flow 08 03 11
Sub Total-A 97 35 132
B Test Article Measurement System
01 Pressure 08 08 16
02 Temperature – TC 42 06 48
03 Temperature – RTD 12 04 16
04 Temperature – Pyrometer 02 01 03
05 Temperature – Imaging camera 01 01 02
06 Thrust 04 02 06
07 Valve current monitoring 08 02 10
08 Voltage monitoring 08 02 10
Sub Total-B 85 26 111
C Command System
01 E/P valve 128 32 160
02 Manual hardwired command 12 04 16
03 Engine valve 08 04 12
04 Control valve 04 02 06
Sub Total-C 152 42 194
D Auxiliary & Safety System
01 CCTV 08 00 08
02 Walky Talky 08 00 08
03 Inter Communication Units 06 00 06
04 Time code generator 01 - 01
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 3
05 Slave display 02 - 02
Sub Total-D 25 00 25
E Safety
01 MMH & N2O4 monitoring system 04 00 04
02 Fire Detection system 10 00 10
Sub Total-E 14 00 14
Total(A+B+C+D+E) 373 103 476
The instrumentation system configuration diagram for each of the above
new facility is given in Fig. No 1 to 17 of Annexure C.
2.3. INSTRUMENTATION SYSTEM WISE REQUIREMENTS
The scope involves procurement (except flow meters, Transducers & safety
sensors), installation & wiring of field elements, impulse tubing and erection
of cable trays, signal cable laying on cable trays, wiring of instrumentation
rack, junction box and interfacing between racks.
2.3.1. Measurement system
Test Article Pressure Measurement
Test article chamber pressure shall be measured through transducer. The
chain diagram is given in Annexure C-Fig.1 & 1a.
The transducer is of piezo-resistive type with diaphragm as primary sensing
element.
Current excited sensors are 4 wire configurations and voltage excited sensors
are 6 wire Wheatstone bridge configuration. Two wires are for exciting the
transducer, two wires for sense and two wires for sensor electrical output.
Sensor output is given to the Integrated Data Acquisition System (IDAS).
The required channel analog output of IDAS is given to Control system for
decision making if required.
The sensors are mounted on engine hardware and located in test bed and
this area fall under Class IIB of intrinsic safe classification.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 4
To ensure the intrinsic safety, intrinsic safe barriers are used. The barriers are
used for excitation, sense and signal line respectively.
Test Article Temperature (TC based) measurement system
This measurement chain is used to measure the test article temperature.
K-type thermocouples are used as sensors. The sensors are interfaced to
IDAS.
The required channel analog output of IDAS is given to Control system for
decision making if required.
Schematic is shown in Annexure C- Fig.No:2.
Test Article Temperature (RTD based) measurement system
This measurement chain is used to measure the test article temperature.
PT100 or PT500 are used as sensors. The sensors are interfaced to IDAS
through barrier.
The barriers are excited through 24V DC linear power supply. IDAS and 24V
DC linear power supply are housed inside instrumentation rack at CTR.
The required channel analog output of IDAS is given to Control system for
decision making if required.
Schematic is shown in Annexure C- Fig.No:3.
Facility Pressure (AP & VP) and DP Based Level measurement system
This measurement is used for the monitoring fluid line pressure, tank
pressure, vacuum pressure and tank level etc.
The SMART pressure transmitters (Absolute, Vacuum & Differential) with
built in electronics senses the pressure and converts the sensed pressure to a
corresponding 4 to 20mA electrical signal.
The SMART pressure transmitters (Absolute & Differential) are excited
through intrinsic safe Transformer Isolated Barrier (TIB). TIBs are powered
from 24V DC linear power supply. The TIBs and 24V DC linear power supply
are housed inside instrumentation rack at CTR.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 5
The output of TIB is given to Control system for acquisition, monitoring and
decision making if required.
Schematic is shown in Annexure C- Fig.No:4
Facility Temperature (RTD based) measurement system
This measurement chain is used for the monitoring facility fluid line
temperatures.
4 wire RTDs are used as sensors. The sensors are interfaced to temperature
transmitters.
The SMART temperature transmitters are exited through intrinsic safe TIB.
TIBs are powered from 24V DC linear power supply. The TIBs and 24V DC
linear power supply are housed inside instrumentation rack at CTR.
The output of TIB is given to Control system for acquisition, monitoring and
decision making if required.
Schematic is shown in Annexure C- Fig.No:5.
Facility Temperature (TC based) measurement system
This measurement chain is used for the monitoring facility fluid line
temperatures.
K-type thermocouples or thermocouple probes are used as sensors. The
sensors are interfaced to temperature transmitters.
The SMART temperature transmitters are exited through intrinsic safe TIB.
TIBs are powered from 24V DC linear power supply. The TIBs and 24V DC
linear power supply are housed inside instrumentation rack at CTR.
The output of TIB is given to Control system for acquisition, monitoring and
decision making if required.
Schematic is shown in Annexure C- Fig.No:6.
Facility flow measurement system (Turbine)
This measurement is used to measuring the flow rate of fluid filling in the
tank.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 6
Pre-amplifier will be mounted near to the turbine flow meter in field.
The pulse output of turbine flow meter is wired to preamplifier.
The preamplifier converts the pulse input to slew rate controlled pulses. This
output is wired to flow totalizer which is located in the CTR.
24V DC linear power supply powers pre amplifier and flow totalizer.
The flow totalizer and 24V DC linear power supply are housed inside
instrumentation rack.
The output of totalizer through voltage isolator is given to Control system for
acquisition, monitoring and decision making if required.
Schematic is shown in Annexure C- Fig.No:7.
Facility flow measurement system (Mass Flow Meter)
This measurement is used for the measuring the Mass flow rate of fuel &
Oxidiser fluid feed lines.
Coriolis type mass flow meter shall be used to measure the mass flow rate of
propellants.
Mass flow sensor and Remote Flow Transmitter (RFT) will be interfaced and
located in field.
Two wires are for exciting the RFT, two wires for analog output and two
wires for pulse output.
Remote Flow Transmitter (RFT) will be powered through the 24V linear
power supply.
Power supply will be mounted an instrumentation rack at CTR.
The output of Remote Flow Transmitter (RFT) is taken through the isolation
barrier and its output given to the Control system for acquisition, monitoring
and decision making if required.
Schematic is shown in Annexure C- Fig.No:8.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 7
Facility flow measurement system (Magnetic Flow Meter)
This measurement is used to measure the flow rate of water in cooling water
feed lines.
Magnetic flow meters are used for measuring the cooling water flow rate.
Flow meter will be powered through the 24V linear power supply.
The 24V DC linear power supply is housed inside instrumentation rack in CTR.
The output of flow meter is taken through the isolation barrier and its output
given to the Control system for acquisition, monitoring and decision making
if required.
Schematic is shown in Annexure C- Fig.No:9.
2.3.2. Safety Instrumentation system
N2O4 detector system
The N2O4 presence is continuously monitored by using N2O4 detectors.
Totally two numbers of N2O4 detectors are planned.
The sensors are mounted in field and the 4-20mA output is interfaced to
TIBs.
TIBs and the detectors are powered from 24V DC linear power supply. The
TIBs and 24V DC linear power supply are housed inside instrumentation rack.
The output of TIB is wired to the Control system for acquisition and
monitoring.
Additional configuration of wiring to be made for extending 24/7 monitoring
data at central safety unit.
Schematic is shown in Annexure C- Fig.No:10.
MMH detector system
The MMH presence is continuously monitored by using hydrocarbon
detectors.
Totally two numbers of hydrocarbon detectors are planned.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 8
The sensors are mounted in field and the 4-20mA output is interfaced to
TIBs.
TIBs and the detectors are powered from 24V DC linear power supply. The
TIBs and 24V DC linear power supply are housed inside instrumentation rack.
The output of TIB is given to control system for acquisition and monitoring.
Additional configuration of wiring to be made for extending 24/7 monitoring
data at central safety unit.
Schematic is shown in Annexure C- Fig.No:11.
UV/IR Flame detecting system
The flame presence is continuously monitored by using flame detectors.
Totally ten numbers of flame detectors are planned.
The sensors are mounted in field and the 4-20mA output is interfaced to
TIBs.
TIBs and the detectors are powered by 24V DC linear power supply. The TIBs
and 24V DC linear power supply are housed inside instrumentation rack at
CTR.
The output of TIB is given to control system for acquisition and monitoring.
Additional configuration of wiring to be made for extending 24/7 monitoring
data at central safety unit.
Schematic is shown in Annexure C- Fig.No:12.
2.3.3. Command system
E/P valve Command
The command signals (Digital Output) from control system actuates relays
housed inside instrumentation rack.
The acknowledgement of this command signal from auxiliary contact of relay
is patched to control system as Digital input.
The other set of contact of relay drives the Solenoid Valve (SOV) which is
mounted on SOV cubicle.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 9
The status signal from proximity sensors of Electro Pneumatic (E/P) valve
located in field run to Transformer Isolated Barrier (TIB).
Transformer Isolated Barrier for the Electro Pneumatic (E/P) valve status
shall be mounted and wired in the E/P valve status rack.
The outgoing signals (ON/OFF status) from TIB are terminated in Control
system Rack as Digital input signal.
Schematic diagram & wiring diagram of EP valve command system are shown
in Annexure C-Fig.No:13&13a respectively.
Control Valve command
The analog command (4 to 20mA) for operating the control valve is issued
from control system.
The analog command output will be wired to control valve through TIBs.
The position feedback of control valve from positioner is terminated in
control system through TIBs.
TIBs are powered through 24VDC linear power supply.
The TIBs and 24VDC linear power supplies are housed inside instrumentation
rack.
Schematic diagram is shown in Annexure C-Fig.No:14.
2.3.4. Auxiliary Instrumentation
Auxiliary system includes closed circuit television (CCTV) system,
Communication equipments and Timing system.
CCTV System
CCTV is designed for remotely monitoring and recording the videos of the
test facility for safety and surveillance monitoring of the process during
engine hot test and propellant filling, transfer from mobile tank to facility
tanks.
CCTV includes
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 10
1 Explosion proof PAN /tilt unit
2 Cameras with motorised zoom/focus lens
3 Switcher and Controller unit with joystick control or keyboard
4 Network Attached Storage with DVD writer
5 System Rack/Server Cabinets
6 Communication system & Signal cables (FOC/Ethernet/Others)
7 Large LED Display monitors of 55 & 86 Inches
8 IP video streaming equipment
9 Power supply units & surge protectors
10 Fibre optic transmission system for video & audio and data
11 Application Software
Schematic diagram is shown in Annexure C-Fig.No:15.
Inter communication system
Communication equipments are required for interpersonal communication
between the personnel working at test facility, cable termination room and
control room and to make any announcements during hot test or cold flow
trials or transfer of propellant etc.
Inter communication system includes
1 Explosion proof Intercom station
2 Non explosion proof Intercom stations
3 Centralized Server and Controller unit
4 Network Audio recorder
5 Loudspeakers
6 Headset /microphones
7 Audio distribution unit
8 Audio mixers
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 11
9 Ethernet cables
10 Power supply units
11 Wireless units
12 POE power injector
13 System Software along with Drivers
14 Application Software with License
The intercom base stations are mounted in consoles/racks. Schematic
diagram is shown in Annexure C-Fig.No:16.
Timing System
Timing system are designed to Generate GPS/IRNSS based universal time
code signals with an accuracy of 1ms or better with output in analog IRIG-B
/ IRNSS format and TCP/IP packets. UTC generator time code is connected to
a timing server, which will be the timing master for synchronizing all the
servers, operator stations and PLC control system for time tagged logging of
data.
Timing system includes
1 GPS/IRNSS based Universal Time Code Generator
2 Centralized Time Server and Controller unit
3 Network Ethernet switches
4 Network Time display units
5 Time distribution unit
6 Ethernet cables
7 Power supply units
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 12
8 System Software along with Drivers
9 Application Software with License
Schematic diagram is shown in Annexure C-Fig.No:17.
The scope involves procurement, wiring and mounting of all auxiliary
equipments, interface cable laying and its wiring.
2.3.5. Powering of Equipments
For equipment powering 230V, 50Hz power outlet is available in CTR and
control room at MCB panel.
This power inlet and outlet needs to be planned at the bottom of the rack
with proper protection scheme. Subsequently, it will be distributed to
equipment, racks and consoles.
The power cable shall be laid in conduits and terminated in different
coloured Terminal blocks/ sockets on one side.
The other end termination shall be made in MCBs.
Power earth strip provided at the bottom of floor / cable trench needs to be
used for proper power grounding.
The scope of work involves conduit laying and laying of cable through
conduits with one end termination in MCB and the other end termination
in instrumentation rack, console or other equipments.
2.3.6. Grounding of Equipments
Separate instrumentation and power earth grounding strips are available in
the cable termination room and control room.
The instrumentation earth and power earth are separately maintained.
In each instrumentation rack, isolated instrumentation earth strip shall be
planned.
The instrumentation cable shields shall be connected to earthing strip in
each rack and in turn to instrumentation earth strip running through the
building.
All the equipment body are to be connected to power earth.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 13
The work involves laying of cable with one end termination in racks / rack
equipments and the other end termination in grounding strip.
2.3.7. Console & Control Room Table - Equipment mounting and wiring
One number of 5 segment and two numbers of 2 segment are planned for
New Test Facility.
Test operator console shall be used to position the Personal Computers (PC)
for real time parameter display, real time plotting the graph and data
processing.
The Personal Computers (PC), key switches, indicators, power supply and
intercommunication equipments, etc will be mounted in consoles.
Wiring of Key switches & ON / OFF switches, etc. are needs to be connected
to the remote I/O nodes available in the CTR.
The scope involves, equipment mounting and its wiring. Also powering of
all equipments is to be carried out.
3. SCOPE OF CONTRACT
The scope of contractor includes
Detailed engineering
Equipments and Material supply as per list attached in
Annexure -E.
Erection and commissioning which includes
Installation and Mounting of equipments & field
elements.
Wiring of field elements & instrumentation rack.
Erection of cable trays, laying of signal cables, impulse
tubes, pneumatic tubes on cable trays.
Powering and grounding of equipments.
Testing & evaluation of instrumentation system.
Documentation
Detailed scope of above activities is given below.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 14
3.1. DETAILED ENGINEERING
The following input documents shall be referred during detailed engineering
Annexure-A: Scope of work and services.
Annexure-B: Control room layout
Annexure-C: Instrumentation system Configuration &schematic
diagram.
Annexure-D: Instrumentation rack General Assembly layout
Annexure-E: Specification and sub vendor directory.
Annexure-F: Sample Testing and Evaluation sheets.
Annexure-G: P&I diagram
The following documents will be provided by Department during Detailed
Engineering
The sensor mounting procedure recommended by manufacturer for
Pressure transducer, flow, Temperature and safety sensors.
Detailed Measurement /Command Plan
The points explained in chapter 3.3 shall also be considered during detailed
engineering phase. The following documents shall be prepared and
submitted by the contractor for the approval from the Department during
detailed engineering.
Specification document which includes the detailed specification of all
items & accessories supplied by contractor, its part number and test
plans.
Quantity Estimation of items including the accessories under supply of
contractor’s scope and its specifications.
Selection of all major equipments including Model matrix and sizing
sheets with supporting documents like latest catalogues.
Instrument /equipment erection diagram
Instrument/equipment mounting procedure
Cable &Cable tray routing layout diagram
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 15
Pneumatic/Impulse tubes routing diagram
Instrument rack General Assembly diagrams
Instrumentation rack signal flow and ferruling details
Equipment powering layout diagram
Conduit routing layout inside control room & CTR for power
distribution.
Equipment earthing scheme / layout inside control room & CTR
Field Instrument, Junction Box and control room cable Termination
and ferruling details
Testing and evaluation plan.
Quality assurance plan
3.2. EQUIPMENTS AND MATERIAL SUPPLY
a. The list of field instruments & materials which are freely issued by
Department for the execution of this work package are given below:
Control System
Absolute pressure Transducers
Temperature Probes, RTD and thermocouples
Safety sensors
Command Systems
PLC System
File Servers (Qty: 02 nos.)
Operator stations (Qty: 03 nos.)
Programming node (Qty: 01 no.)
Processing node (Qty: 01 no.)
Measurement Systems
Mass Flow meters
Turbine Flow meters with Pre-Amplifiers
Magnetic flow meter
Pressure Transducer
Temperature Sensor (RTD & T/C)
load cell
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 16
Test Operator Console
Integrated Data Acquisition System (IDAS)
File Servers
Computers with monitors
Network switches
List of items to be supplied by Contractor
Pressure Transmitters with manifolds
Temperature transmitters
Solenoid dual coil including plunger unit
Isolation barrier
Zener Barrier for RTD
High Frequency TIB for Transducer output
Voltage isolator
Pulse isolator
Hall effect sensor
Relays
Flow Totalizer for turbine FM
Proximity sensor
SMPS & Linear Power supplies
PVC armoured and un-armoured cables
PTFE cables
Single core tefflon cables
Power cables
Indicators, Authorization keys, Switches with indicators,
Industrial standard connectors (108 pin), 7 pin circular connectors & 32
pin circular connectors
Miniature K-Type TC connector
Terminal Blocks
Junction box
Compression fittings & SS tubes
Cable trays
Structural materials supply & fabrication
Canopy
Instrumentation Racks with accessories
Cable glands
Cable entry Plate , Connector Mounting Plate, Metal conduits, Metal
flexible hoses suitable for conduit, 4/3/2 way metal junction box
suitable for conduit bends, elbows, Tees and couplers of required
quantities
Operator chair
CCTV system, Inter communication system & Timing system
Harnessing materials
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 17
b. The list of items to be supplied by the contractor and its specification
along with recommended brands is given in Annexure-E.
c. The contractor shall source the list of items only from the
recommended brands indicated here in Annexure-E.
d. In case the contractor proposes to source the items from any other
brands, necessary prior approval from the department need to be
obtained.
e. The required accessories and its quantity shall be worked out by the
contractor. The quantity of accessories shall include 20% spare or 1
number whichever is higher.
f. The exact quantity and the list of items required for commissioning
the facility will be finalized during detailed engineering and 10%
quantity variation is permitted for supply and erection as per contract.
g. For few items, part number/model matrix are given as guidelines for
the contractor to select the product. However it is the responsibility of
the contractor to decide up on the finalized model matrix complying
to the specifications given with the latest available catalogues.
h. Wherever mentioned, the material despatch shall be carried out only
after the test certificate/calibration certificate/ inspection report
approvals.
i. The vendor shall submit finalized Specification document which
includes the detailed specification of all items & accessories supplied
by contractor, its part number, test certificates, approvals and
calibration and guarantee certificates.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 18
3.3. ERECTION AND COMMISSIONING
3.3.1. General Instructions
Tools for Erection & Commissioning
1. The contractor shall bring necessary tools required for erection &
commissioning of the instruments & components and an instrument
work shop shall be made ready at the erection site.
2. Erection & commissioning works shall be carried out strictly according
to the specifications stipulated in the contract, documents/drawings
approved by department during detailed engineering. Also it shall be
carried out as per the supervision of the department’s representative.
3. The Contractor shall provide and maintain a formal system for
documenting technical clarification from the Department.
4. Only correctly signed documents which are marked Approved for
Construction” (AFC) shall be used for installation work.
5. Only the best trade practices and correct tools shall be used and all
works are expected to be completed in a neat and safe manner.
6. Welding shall be done only by qualified personnel.
7. Electrical installation shall only be performed by appropriate qualified
trade persons.
8. Holes shall be drilled or punched and not burnt out by gas torches or
electric arcs.
9. Piping and tubing shall be formed with the appropriate pipe or tube
bending equipment by qualified personnel.
10. Instrument/equipment shall be mounted using suitable stands/
brackets/clamps. As far as possible all field instruments shall be
mounted on instrument support stands. These shall be installed on
floors, RCC columns and walls using approved make anchor fasteners /
Hilti bolts and on steel structure by drilling suitable holes and using
chromium plated/galvanized bolts and nuts or in exceptional cases by
welding. After welding, the slag on weld surface shall be removed and
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 19
one coat each of Red-oxide primer and paint shall be applied over the
surface.
11. Equipment shall be installed in a neat, workman like manner so that it
is level, plumb, square and properly aligned and oriented.
12. Field Instruments should not be supported from impulse lines, hand
rails and vibrating structures.
13. Instruments shall be located such that it is easy to approach for
operation and maintenance. Cover can be removed without
obstruction and there should not be any problem in re-glanding the
cable later on.
14. All indicating instruments shall be located such that its scale is
conveniently visible to plant operator.
15. Canopy shall be provided for all the instruments, JBs and SOV located
outdoor.
16. All threaded opening of the instruments shall be protected by suitable
Aluminum /Chromium plated plugs.
17. During installation of the signal and control cables and prior to
connection up to the instruments, the cables shall be checked for the
insulation resistance, continuity and tagging.
18. If the insulation resistance is not found within the limits, these cables
shall not be used. The contractor should lay new cables, meeting the
continuity and insulation resistance requirements, without any cost
implication.
19. The signal and control cable wires shall be connected to respective
terminals, as per the wiring drawings.
20. Field equipment shall be properly grouped at a convenient location
based on the equipment layout diagrams.
21. Allocation of grouping of channels based on signal levels in junction
boxes and racks shall be finalized during detailed engineering.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 20
22. Separate trays shall be used for routing pneumatic tubes and cables.
23. Field transmitters (pressure, temperature, flow, etc.) shall be mounted
on 2” pipe stands. The instrument stands shall have a suitable height
so that instrument shall be mounted at 1.4m from ground or platform
/ catwalk. If the instrument to be mounted on a catwalk / platform the
preferred location shall be on the outside of the hand railing.
24. Field instruments, which are exposed to open terrain, shall be
provided with weather canopy.
Handling & storage of Instruments
25. The Contractor shall be responsible for the collection of “free-issue”
instrument items, transportation, storage and safe custody of the
equipment's until completion of its installation and acceptance by
Department’s representative. This excludes the control system.
Contractor shall maintain a stock system to enable material tracking
throughout the installation & commissioning of the facility.
26. All instruments shall be visually examined by the Contractor on receipt
to ensure that they have not been damaged in transit. Instruments
shall then be replaced in their original packing and housed in a
separate secure, dry, cool storage area provided by the department.
27. If any item is damaged by the contractor, new item may be procured
and replaced by the contractor with their own cost or the cost of the
item will be deducted from the contractor’s bill.
28. When unpacking is necessary, care shall be taken to ensure that
accessories are not mislaid or mixed.
29. Instruments shall not be left lying around the construction area.
30. All covers and plugs on the instrument connections shall be left in
place until connections are used.
Installation Preparation
31. Verify that instrument process connections ports before tapping.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 21
32. Sensitive electronic instruments/components shall be protected
during welding, drilling & filing activities.
33. Metal filing and metal or wood shaving shall be prevented from falling
on the components/ports/connectors.
34. Instrument stands and mounting brackets shall be fabricated
according to design drawings approved by the department.
35. Identification tags shall be attached to each field component bearing
its instrument number in accordance with P&I drawings/ Instrument
schedules.
36. Nameplate shall be attached to all junction boxes and racks. Name
plates shall be of stainless steel with black lettering shall be provided
for field instruments and junction box.
37. Nameplates shall be of plastic type for racks.
3.3.2. Erection and Commissioning Works
3.3.2.1. Measurement and safety system
Test Article pressure measurement system
1. Transducers are planned to measure the test article chamber
pressure.
2. The transducers shall installed by Department.
3. Six core armoured PVC cable shall be used between vacuum
chamber connector plate to junction box.
4. Multi core individual shielded un-armoured PVC cable shall be
used between junction box to instrumentation rack.
5. All the cables shall be tagged as per the P&I diagram.
6. Outside of the junction box all the cables shall be tagged by
suitable SS plate.
Test Article Temperature measurement system
1. RTD and Thermocouple temperature sensors shall be planned for
test article temperature measurements.
2. RTD and Thermocouple temperature probes shall be installed by
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 22
Department.
3. Four core armoured PVC cable shall be used between RTD sensors
to junction box.
4. Two core thermocouple extension cables shall be used between
thermocouple (TC) sensors to junction box.
5. Multi core individual shielded un-armoured PVC cable shall be
used between junction box for RTD to instrumentation rack.
6. Multi core thermocouple extension cables shall be used between
junction box for TC to instrumentation rack.
7. All the cables shall be tagged as per the P&I diagram.
8. Outside of the junction box all the cables shall be tagged by
suitable SS plate.
Facility pressure measurement system
1. HART protocol based SMART Pressure Transmitters shall be
planned for facility absolute pressure measurements. HART
management system (HMS) is planned for re-ranging and
calibrating the sensor.
2. The transmitters for Absolute pressure shall be installed in the
transmitter mounting post (2” pipe) as per drawing approved by
Department. Mounting shall be done as per 3.3.2.14.
3. A three way two valve manifold for absolute pressure
measurement shall be installed with the transmitter.
4. Impulse lines for pressure transmitters shall be of 12.7 mm (1/2”)
OD SS tube and 1.6mm wall thickness suitable for the process
pressure.
5. Suitable double compression SS tube fittings shall be used to
connect process line, impulse tubes and instruments.
6. The length of impulse lines shall not exceed 5 meters.
7. Impulse tubing shall be hydro tested for 1.5 times of the rated
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 23
pressure.
8. Impulse tubing shall be carried out as per procedure explained in
3.3.2.7.
9. Two core armoured PVC cable shall be used between facility
transmitters (Pressure) to junction box.
10. Multi-core un-armoured PVC cable shall be used between junction
box to instrumentation rack.
11. All the cables shall be tagged as per the P&I diagram.
12. Outside of the junction box all the cables shall be tagged by
suitable SS plate.
DP based level measurement system
13. HART protocol based SMART Differential Pressure Transmitters
shall be planned for facility tank level measurements. HART
management system (HMS) is planned for re-ranging and
calibrating the sensor.
14. The transmitters for tank level shall be installed in the transmitter
mounting post (2” pipe) as per drawing approved by Department.
Mounting shall be done as per 3.3.2.14.
15. Five way valve manifold with block equalizing and drain valves for
differential pressure (level) measurement shall be installed with
the transmitter.
16. Impulse lines for pressure transmitters shall be of 12.7 mm OD SS
tube and thickness (1.6mm) suitable for the process pressure.
17. Suitable double compression SS tube fittings shall be used to
connect process line, impulse tubes and instruments.
18. The length of impulse lines shall not exceed 5 meters and shall be
without any joint.
19. Impulse tubing shall be hydro tested for 1.5 times of the rated
pressure.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 24
20. Impulse tubing shall be carried out as per procedure explained in
3.3.2.7.
21. Two core armoured PVC cable shall be used between facility
transmitters (Pressure) and junction box.
22. Multi-core un-armoured PVC cable shall be used between junction
box to instrumentation rack.
23. All the cables shall be tagged as per the P&I diagram.
24. Outside of the junction box all the cables shall be tagged by
suitable SS plate.
Facility Temperature measurement system
25. RTD and Thermocouple temperature sensors with HART protocol
based Temperature Transmitters shall be planned for facility
temperature measurements.
26. RTD and Thermocouple temperature probes shall be installed as
per recommendations of manufacturer and drawing approved by
Department.
27. The temperature transmitters shall be installed in the transmitter
mounting post (2” pipe) as per drawing approved by Department.
Mounting shall be done as per 3.3.2.14.
28. Four core shielded armoured PVC cable shall be used between
temperature transmitter and RTD sensor.
29. Two core thermocouple extension cables shall be used between
temperature transmitter to thermocouple (TC) sensor.
30. Two core armoured PVC cable shall be used between
Temperature transmitters and junction box and multi core un-
armoured PVC cable shall be used between junction box to
instrumentation rack.
31. All the cables shall be tagged as per the P&I diagram.
32. Outside of the junction box all the cables shall be tagged by
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 25
suitable SS plate.
Flow measurement system
33. Turbine flow meters, Mass flow meters and Magnetic flow meters
shall be planned for facility flow measurements.
34. Flow meter shall be installed as per recommendations of
manufacturer and drawing approved by Department.
35. The flow preamplifier shall be mounted as per drawing approved
by Department. Mounting shall be done as per 3.3.2.14.
36. Two core armoured PVC cable to be laid from preamplifier to
pickup coil.
37. Four core armoured PVC cable shall be used between flow
transmitter and junction box for magnetic and preamplifier for
turbine flow meter channels.
38. 4 core armoured PVC cable to be laid between mass flow sensor to
mass flow transmitter.
39. Six core armoured PVC cable shall be used between flow
transmitter and junction box for mass flow meter channels.
40. Multi core un-armoured PVC cable shall be used between junction
box to instrumentation rack.
41. All the cables shall be tagged as per the P&I diagram.
42. Outside of the junction box all the cables shall be tagged by
suitable SS plate.
Safety measurement system
43. N2O4, MMH sensor and UV/IR flame detectors shall be used as
safety detectors.
44. Safety detectors shall be installed as per recommendations of
manufacturer and drawing approved by Department.
45. Two core armoured PVC cable shall be used between safety
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 26
sensors and junction box.
46. Multi core un-armoured PVC cable shall be used between field
junction box to CTR.
General instruction for Measurement and safety system
47. All multi-core PVC cables shall be laid on cable trays.
48. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
done as per 3.3.2.10 & 3.3.2.14.
49. The multi-core un-armoured PVC cables from the field entering in
to CTR shall pass through a transit plate. Refer to chapter 3.3.2.12.
50. In CTR multi core un-armoured PVC cables from field junction
boxes shall be terminated in industrial standard connectors
mounted inside facility instrumentation rack.
51. Different instrumentation racks are identified for different
measurement like pressure, temperature, flow and safety
measurements, etc.
52. This rack houses all TIBs and 24V DC linear power supply required
for realizing individual measurements. The TIBs are of 24V DC
powered and shall be powered from power supply. These TIBs
provide dual 2 to 10V output.
53. The flow totalizers are panel mountable and shall be mounted in
flow rack.
54. Output of the TIB shall be connected to control system rack
through industrial standard connectors.
55. Termination at control system rack shall also need to be done.
56. The rack wiring details are explained in 3.3.2.16.
57. Un-armoured PTFE cables shall be used for inter rack
communication and these cables shall be laid in trays inside CTR.
Cable laying and cable tray laying procedures are explained in
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 27
chapter 3.3.2.9 &3.3.2.13 respectively.
3.3.2.2. Command system
EP Valve Command system
58. The EP valve command chain is planned with dual coil solenoid
valve.
59. Solenoid valves shall be mounted on the SOV cubicles.
60. The location of SOV cubicles shall be finalized during detailed
engineering.
61. The SOV cubicles shall be mounted as per mounting procedure
explained in chapter 3.3.2.10.
62. 8 Nos. of solenoid valves shall be mounted in one SOV cubicle.
63. The length of command tubing from SOV cubicle to the
EP valve actuator shall be less than 10 meter, so that nearby
commands are grouped together.
64. Command tubing shall be carried out between EP valve actuator
and SOV cubicles using 8mm OD SS tube. Pneumatic tubing shall
be carried out as per procedure explained in 3.3.2.8.
65. Bulk head union type compression tube fitting shall be used at SOV
cubicle side to terminate solenoid outlet and E/P valve actuator
tube.
66. Pneumatic tubing shall be pneumatic tested for 1.1 times of the
rated pressure.
67. 2 core 18AWG shielded PTFE cable shall be used inside the cubicle
Junction box to SOV coil for command.
68. Diode terminal blocks needs to be used in all the SOV cubicle
junction boxes.
69. SMPS based redundant power supplies are to be used for the
command operation.
70. Multi-core armoured PVC cables to be used between SOV cubicles
to valve driver rack.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 28
71. Two proximity switches are to be provided to indicate open &
close status for each E/P valve. An interface required for
positioning the proximity switch needs to be fabricated / carried
out by the contractor.
72. Four core shielded armoured PVC cable shall be used between EP
valve proximity switch junction box and field junction box. The
proximity switch junction box to be mounted in the E/P valve by
using suitable IIB certified box with terminal blocks.
73. Multi core un-armoured PVC cables shall be used between field
junction boxes and valve status rack.
General instruction for command system
74. All multi core PVC cables shall be laid on cable trays.
75. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
done as per 3.3.2.10 & 3.3.2.14.
76. The multi core un-armoured PVC cables from the field entering in
to CTR shall pass through a transit plate. Refer to chapter 3.3.2.12.
77. In CTR multi core PVC cables from field junction boxes shall be
terminated in industrial standard connectors mounted inside
command racks.
78. The EP valve command inputs from the control system shall be
terminated in EP valve command rack. The relays, contactor and
power supplies shall be accommodated in these racks. Separate
power supply shall be planned for Command Acknowledgement
and field actuation. The command acknowledgement shall be
connected to control system through industrial standard
connector. The field command shall be wired to field junction box
through industrial standard connector. These industrial standard
connectors shall be housed inside same rack.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 29
79. The E/P valve status from the field (digital input), shall be
terminated in status rack. This rack houses status TIBs powered
from SMPS based power supply. The status output of rack shall be
connected to control system through industrial standard
connector.
80. The rack wiring details are explained in 3.3.2.16.
81. Un-armoured PTFE cables shall be used for inter rack
communication and these cables shall be laid in trays inside CTR.
Cable laying and cable tray laying procedures are explained in
chapter 3.3.2.9 &3.3.2.13 respectively.
82. Termination of valve driver input and valve status output at
control system rack shall also need to be done.
Control Valve Command system
83. Control valve shall have smart valve positioner with integrated
position transmitter.
84. Four core armoured PVC cable shall be used between JB and
control valve smart valve positioner for command and position
feedback.
85. Multi core un-armoured PVC cables shall be used between field
junction boxes to CTR.
86. Command tubing shall be carried out between control valve smart
valve positioner and SOV cubicles using 8mm OD SS tube.
Pneumatic tubing shall be carried out as per procedure explained
in 3.3.2.8.
87. Pneumatic tubing shall be pneumatic tested for 1.1 times of the
rated pressure.
88. All multi core PVC cables shall be laid on cable trays.
89. All Cable laying & cable tray laying shall be done as per 3.3.2.9 &
3.3.2.13 respectively. Junction box mounting and wiring shall be
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 30
done as per 3.3.2.10 & 3.3.2.14.
90. The multi core PVC cables from the field entering in to CTR shall
pass through a transit plate. Refer to chapter 3.3.2.12.
91. In CTR multi core PVC cables from field junction boxes shall be
terminated in industrial standard connectors mounted inside
command system racks. The rack wiring details are explained in
3.3.2.16.
92. Un-armoured PTFE cables shall be used for inter rack
communication and these cables shall be laid in trays inside CTR.
Cable laying and cable tray laying procedures are explained in
chapter 3.3.2.9 & 3.3.2.13 respectively.
93. Termination at control system rack shall also need to be done.
3.3.2.3. Auxiliary System
CCTV system
94. The CCTV camera structures are to be fabricated and erected in
the field at location identified by the department suitable enough
to withstand the adverse wind condition at IPRC site. The
fabrication drawing to be prepared by Contractor and approved by
Department. Mounting shall be done as per 3.3.2.14.
95. The cameras are to be mounted on top of the erected camera
structure using appropriate fasteners.
96. Power cable has to be laid and terminated to the camera from
CTR.
97. Armoured PVC cables / Coaxial / ethernet cables are to be laid
from CCTV unit to Auxiliary rack at CTR and CTR to control room
Armoured PVC cables and fibre optic cables to be laid for pan/tilt
and lens control and for transmission of video to control room.
98. The cables have to be routed from the cameras in the field using
flexible metal hoses or Pipes. Suitable cable glands are to be used
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 31
for all the cables entering and exiting from the CCTV cameras.
99. The video management software has to be installed in the
Network access storage (NAS)n servers and configured for
operation and recording the videos and checked for its functioning
in controlling up to 16 cameras.
100. The video data shall be interfaced to video monitor controller
for display of the CCTV video on to large led display monitors and
in console for operators to monitor from centrally located NAS
Video storage system.
101. The video recording must be programmable for selectable
video resolution, frame rate, encoding bit rate, bandwidth, audio
encoding, recording schedule, continuous, event based or motion
detection.
102. The software should have multiple streaming capabilities for
simultaneous recording, archiving and live viewing.
103. Grounding earth pit has to be made near the camera structure
as per the IS standards wherever required.
104. Cable has to be laid using suitable cable trays for routing the
cables to the CCTV cameras.
105. All Cable laying and cable tray laying procedures are explained
in chapter 3.3.2.9 &3.3.2.13 respectively.
Intercommunication system
106. Suitable structures are to be fabricated for mounting wired
intercom units and erected in the field at location identified by the
department, suitable enough to withstand the adverse wind
condition at IPRC site. The fabrication drawing to be prepared by
Contractor and approved by Department. Mounting shall be done
as per 3.3.2.14.
107. In control room intercommunication equipments shall be
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 32
located at racks/consoles.
108. Power cable has to be laid and terminated to the Intercom
from UPS positioned inside the cable terminal.
109. Multi core PVC cables are to be laid from intercom unit to
Control room via CTR for communication purpose.
110. Align the Microphone output card, line cards and power
amplifier for optimum sound reception at field and at control
room.
111. Mount the speakers at suitable height in the field using
fabricated structure and on the ceiling at control room.
112. Terminate the speakers to the individual intercom units using
two core twisted pair cable.
113. Interface the audio signal from the intercom to the video
streaming unit using buffer amplifier.
114. Interface the intercom units in the field to the control room
intercom using fiber optic transmitter and receivers and
appropriate interface units so that the audio is clearly heard both
at control room intercom and field intercom units.
115. All Cable laying and cable tray laying procedures are explained
in chapter 3.3.2.9 &3.3.2.13 respectively.
Wireless System
116. Wireless units are to be programmed for the approved
frequencies after obtaining licensee from WPC.
Timing System
117. The network display has to be mounted on the wall or on
structures at command room or CTR.
118. POE has to connect to the display unit and powered.
119. Necessary software modules has to provided for interfacing the
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 33
Time server with Command control PLC and other system
120. All Cable laying and cable tray laying procedures are explained
in chapter 3.3.2.9 &3.3.2.13 respectively.
3.3.2.4. Console and Control room table wiring
121. There shall be one number of 5 segment and two numbers of 2
segment consoles in new Control Centre.
122. The equipments like intercom units, switches, keys and indicators
shall be mounted in console segments and this output shall be
connected to the corresponding cable which will come from the
CTR or control room.
123. The required 24V DC power supply for the switches shall be
mounted in console cabinets.
124. The 24” LED monitors and PCs shall be mounted in each segment.
The powering of all console equipments shall be done.
3.3.2.5. Powering of equipment's
125. For equipment powering, power distribution boards with MCBs is
available in the control room and CTR.
126. The 230V, 50Hz powering layout shall be made for all equipments
housed in instrumentation racks & consoles in the control room
and CTR.
127. The power cable shall be routed through conduits and near
console/rack flexible hoses shall be used.
128. The terminations on the equipment side shall be in different
coloured terminal blocks or in distribution board or in plugs based
on the equipment. The other end termination shall be made in
MCBs.
129. Standard wiring procedure shall be followed with termination
using suitable lugs, ferrules, cable and cable conduit identification
tags.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 34
3.3.2.6. Grounding of equipment's
130. The cable shield shall be terminated in copper strips provided in
the instrumentation rack and isolated from power earth and finally
connected to instrumentation earth strips in the control room and
CTR.
131. The chassis of equipments shall be connected to power earth. The
cable laying shall be done neatly and the cables shall be harnessed
properly.
132. Termination ends shall be with suitable lugs and shall be ferruled.
3.3.2.7. Impulse Tubing
133. 12.7 mm OD S.S. tubes shall be used as impulse tubes. Instrument
tubing shall be laid as per standard on cable trays. The width of
cable trays shall be selected as per number of instrument tubing
laid.
134. The tube routing shall be carried out as per approved drawing.
135. Transmitters shall be mounted above the process pipe line and
continuous slope shall be provided in the impulse line between
transmitter and process line.
136. S.S. Tubes shall be cleaned with lint free cloth dipped in acetone
and pulled through the tube using nylon wire until all dirt/dust is
removed. As a check for thorough cleaning of tubes, last lint free
cloth shall be as clean as new. This is to be done in presence of the
department’s representative. Outside surface of tube shall also be
cleaned by rubbing manually with lint free cloth soaked in acetone.
Tubes shall be cleaned by blowing dust free GN2 before laying.
137. Tube bends shall be made with approved and appropriate sizes of
tube benders. Bends shall be of uniform curvature and smooth and
shall be free from wrinkles, flattening and kinks. Use of filler
material during bending is prohibited. Hot bending is also not
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 35
permitted.
138. Tubes shall be clamped at intervals not exceeding 1 meter with the
help of special spacer and clamps.
139. Impulse lines and their supports should be kept away and free
from vibrating structures or equipment. Minimum bending radius
should be taken as 2.5 times the tube OD.
140. To avoid corrosion of SS Tubes, contacts of SS Tubes with CS/MS
surfaces should be avoided by installing brass shims / foil in
between SS Tubes and CS / MS Surface.
141. Wherever impulse lines run side by side, they should be neatly
bunched together with bolted straps and screwed clamps. Tubing
should be ganged vertically rather than horizontally to avoid
collection of dust, dirt and other corrosive conditions.
142. S.S. Tubes are terminated by using approved make of double
ferrule type fittings.
143. Fittings shall be installed by qualified fitters who have to undergo
qualification test to be conducted by the Quality Surveillance
Engineer of the department.
144. Tubes shall be identified at both ends by line number/ instrument
number/equipment number to which it is terminated by Anodized
Aluminium tags of rectangular shape and shall be tied to the tube
securely by 16 gauge S. S. wire.
3.3.2.8. Pneumatic Tubing
145. The scope of work covers installation, routing as per approved
drawing, clamping, supporting and connection of 8mm OD SS tube
with fittings.
146. S.S. Tubes shall be cleaned with lint free cloth dipped in acetone
and pulled through the tube using nylon wire until all dirt/dust is
removed. As a check for thorough cleaning of tubes, last lint free
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 36
cloth shall be as clean as new. This is to be done in presence of the
department’s representative. Outside surface of tube shall also be
cleaned by rubbing manually with lint free cloth soaked in acetone.
Tubes shall also be cleaned by blowing dust free GN2 before
laying.
147. Tube bends shall be made with approved and appropriate sizes of
tube benders. Bends shall be of uniform curvature and smooth and
shall be free from wrinkles, flattening and kinks. Use of filler
material during bending is prohibited. Hot bending is also not
permitted.
148. S.S. Tubes are terminated by using approved make of double
compression type ferrule fittings. At the place of termination/joint,
tubes shall be cut square and burrs if any shall be removed by fine
emery paper without reducing wall thickness of the tube. Tube
shall be cut with approved brand of tube cutter only.
149. Fittings shall be installed by qualified fitters who have to undergo
qualification test to be conducted by the Quality Surveillance
Engineer of the department.
150. Tubing shall be routed on the cable trays and shall be clamped at
the intervals not exceeding 1 m. The tubing shall be run in such a
manner to provide maximum protection against physical damage.
Tubing runs shall be neatly dressed and grouped together
wherever possible. Tubes shall be ganged vertically rather than
horizontally to avoid collection of dirt, dust and other corrosive
material.
151. Tubes which are to be terminated on the instruments, may be
subjected to vibrations during operation, a semi-circular loop shall
be formed on the tube near the termination point to avoid
damage to the tubes during operation. All such instruments shall
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 37
be identified in consultation with the department Engineer, before
termination of the tubes.
152. Tubes shall be identified at both ends by line number/instrument
number/equipment number to which it is terminated by Anodized
Aluminium tags of rectangular shape and shall be tied to the tube
securely by 16 gauge S. S. wire.
153. Compression unions shall be used for joining the tubes. At the joint
an offset of around six inches (3 inches on each side of the joint)
shall be given on the tube run from the tray, so that the fitting will
be away from the surface of the tube support and have free access
for tightening and checking of leaks during test. Joints on adjacent
tubes in a bundle shall be staggered suitably to avoid interference.
154. All the air supply lines shall be pneumatically tested by the
contractor, using dry air at 8 bar. The joint should be bubble tight.
3.3.2.9. Laying of Cables
155. All cable routes shall be carefully measured and cut to the required
length, leaving sufficient amount for the final connections of the
cable to the terminals on either end.
156. The scope of work consists of laying and termination of multi core
cables at various Junction Boxes / Terminal blocks. Supply of cable,
cable harnessing materials, end Terminals & Identification ferrules
is in the scope of contractor.
157. Cable shall be of single piece and joint is not allowed from one
termination to the other termination.
158. Cables shall be rigidly supported on cable trays, individually or in
groups as required using individually cast or malleable iron
galvanized clips. Distance between the two cable supports shall
not be more than 1 m.
159. Physical protection shall be provided wherever required.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 38
160. Cables are to be terminated on the junction box/instruments using
appropriate size of cable glands/lock nuts and rubber washer with
gland hoods. Suitable seal cone grip compression gland shall be
used for armoured and un-armoured cable. All glands should be of
NPT at junction box and Instrument side.
161. Each of the cables shall be tagged with cable number punched
clearly in SS tags and tied to the cable at both the ends and at 15m
intervals.
162. Cables, wires shall be connected on the field instruments/terminal
blocks using lugs. Wire identification shall be provided by inserting
printed PVC sleeves with ferrule number.
163. Cable shall be laid and terminated as per approved cable
scheduling.
164. All wires shall be checked for proper identification, continuity and
insulation before taking up wiring connections.
165. Power Cables and control cables shall be laid in separate Cable
Trays as per IEEE 518-1982.
166. All cable screens/shields shall be earthed.
167. Care should be taken to avoid sharp bending and kinking of
conductor, damaging of insulation and stressing the cable beyond
the pulling force recommended by the manufacturer. Minimum
radius of bend of an insulated cable shall be 12 D for un-armoured
cable and 15 D for armoured cable.
168. While terminating the cable at the devices, a loop involving around
0.5 m extra cable shall be provided.
3.3.2.10. Junction Boxes and SOV cubicles
169. Junction boxes shall be supplied and mounted in suitable support
structure. The fabrication of support structure shall be done by the
party with approved drawing.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 39
170. The cable entry to Junction boxes shall be through cable glands
with PVC hoods.
171. Every cable should enter to junction box through suitable cable
glands.
172. Cable Glands shall be of Single & double (whichever suitable for
the cable type) Compression NPT type made from nickel coated
brass with PVC Hoods.
173. Cables, wires shall be connected to the junction box terminal
blocks using lugs. Wire identification shall be provided by inserting
printed PVC sleeves with ferrule number.
174. All unused holes shall be plugged with SS plug.
175. In general, all cable entries from field elements shall be through
sideways and all cables to CTR shall be from bottom.
176. The JBs shall be tagged according to tagging philosophy followed in
respective units.
177. Cables entering and exiting from the JBs are needs to be identified
with suitable SS tags.
SOV cubicles
178. SOV cubicles shall be supplied and mounted in suitable support
structure. The fabrication of support structure shall be done by the
party with approved drawing.
179. Every cable should entering to cubicle junction box through
suitable cable glands.
180. Cable Glands shall be of double (whichever suitable for the cable
type) Compression NPT type made from nickel coated brass with
PVC Hoods.
181. Cables, wires shall be connected to the cubicle junction box
terminal blocks using lugs. Wire identification shall be provided by
inserting printed PVC sleeves with ferrule number.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 40
182. All unused holes shall be plugged with SS plug.
183. In general, all cable entries from CTR shall be from bottom.
184. Suitable adaptor to be provided for output of the pneumatic signal
from the SOV.
185. Cables entering and exiting from the cubicle JBs are needs to be
identified with suitable SS tags.
3.3.2.11. Canopy Requirement
186. All junction box and field instruments which are kept outside shall
be provided with pre-fabricated canopy for Rain and Sunlight
protection.
187. The canopy shall be fabricated by powder coated MS plates of 2
mm thickness.
188. Group instruments such as pressure transmitters or flow
transmitters or junction boxes, etc. shall be covered by single type
of suitable canopy after discussing with facility team. Accordingly
the work needs to be executed.
189. The fabrication drawings shall be prepared and shall be approved
by Department.
3.3.2.12. Multi Cable Transit Plate
190. Multi Cable Transit Plate shall be planned for control room and
CTR.
191. The transit plate shall be mounted in control room / CTR entry
hole which is already available in the room.
192. The plate shall be drilled with suitable holes matching to cable
diameter.
193. The multi-core PVC cables shall pass through the holes and shall be
provided with cable glands at the holes.
194. Additional holes may be provided for future augmentation. Such
holes may be properly sealed with dummy glands to avoid the
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 41
entry of dust and insects inside the CTR or control room.
3.3.2.13. Cable Trays
195. Instrument cabling shall be through trench/overhead.
Main Cable Way /Trench : Ladder Tray (size based on requirement)
Local Branch Cable Way : Perforated Tray (size based on
Requirement)
196. Ladder trays shall be used from control room to CTR. These ladder
trays run inside cable trench/ structural supports.
197. Ladder trays shall be used from CTR to JBs. These ladder trays run
inside cable trench & structural supports.
198. Perforated G.I. trays shall be used from junction boxes to
individual instruments.
199. Ladder trays shall be used inside CTR & control room.
200. Suitable cable clamps shall be supplied for binding the cables /
tubes at every 2 m for horizontal and 0.5 m for vertical.
201. Structural supports for the cable/tubing trays shall be fabricated as
per approved drawings and shall be inspected before erection.
3.3.2.14. Structural support
202. Structural support for the Instrument mounting post, camera post,
Junction box, pressure transmitters, temperature transmitters and
flow transmitter, etc. shall be fabricated using MS structural
materials and sharp corners shall be smoothened by grinding.
203. The fabrication shall be carried out with drawing approved by
Department.
204. Structural materials shall be painted with one coat of Red-oxide
Primer and two coats of Grey enamel Paint.
3.3.2.15. Cable Trays – Structural support fabrication
205. Perforated G.I. trays shall be used for cable and SS tube laying.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 42
206. The structural supports for this shall be fabricated as per approved
drawings and shall be inspected before erection.
207. All the welding points shall be painted with one coat of red-oxide
primer and two coats of Grey enamel Paint shall be applied.
208. The cable trays shall be welded to the support structures. The
burrs at welding points shall be removed and painted with silver
colour paint
3.3.2.16. Instrumentation Rack-Equipment Assembly & Wiring
209. The instrumentation racks shall be installed and commissioned at
control room and CTR located at different locations.
210. The instrumentation racks are wired for full capacity.
211. All the required material for rack wiring like cable manager, filler
plates, L-angles, din-rails, terminal blocks (different colors), lugs,
ferrules, tefflon cables, etc. needs to be provided by the contractor
in toto.
212. The instrumentation rack shall be double and single racks 42U
height effective spacing.
213. Design of rack shall be in such a way, to provide proper
operational and maintenance access and conceal interconnecting
wires and cables.
214. Wires shall be housed in PVC cable ducts of suitable dimensions to
accommodate system cables, signal cables and power cables.
215. PVC cable ducts shall be organized to run electric wires according
to their voltage level and function. Power supply wires and low
voltage signal wires shall not be grouped together in the same
cable duct.
216. Wiring for different voltage signals shall be terminated separately
on dedicated terminal strips.
217. All the terminal blocks shall be DIN rail mountable.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 43
218. Power supply shall be provided with fan tray for cooling.
219. The incoming cables from the field shall be terminated in 108 pin
industrial standard connector and the connectors needs to be
supplied by the contractor.
220. Multi-core un-armoured PTFE cable shall be used for
interconnection between instrumentation racks.
221. These cables shall be terminated in 108 pin industrial standard
connectors at the rack output and also at control system or
Integrated Data acquisition rack.
222. The cable trays and its structural support required for cable laying
shall be provided.
223. Cable entry in all instrumentation rack shall be from bottom
3.3.3. TESTING AND EVALUATION
3.3.3.1. Test Equipments
224. The contractor shall bring all the required test and measure
instruments required for testing and evaluation. The standard
Source / Measure equipments with calibration validity traceable to
national standards shall be used by the contractor. The
equipments of ±0.02% accuracy class of shall be used for sourcing
and measuring.
3.3.3.2. Testing and Evaluation
225. Only preliminary details regarding testing and evaluations are
given below. However the contractor shall prepare detailed
Testing and evaluation procedure and formats during detailed
engineering phase. As per the approved procedures, the
contractor shall carry out the testing and evaluation. The final
results shall be entered in relevant formats and finally to be
approved by Department.
226. Check all the instruments for proper mounting and sealing. Check
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 44
for proper routing & dressing of wiring. Ensure the availability of
terminal strip nos., Wire nos., tags and ferrules. Ensure proper
grounding of racks/equipments.
227. Check and log insulation resistance of all cables, continuity of
wiring of all instrument loops as per the relevant drawings.
228. Integrity test up to sensor shall be done.
229. Power supply load test: All the power supplies shall be load tested
up to 80% of rated load. The stability and ripple test shall also be
carried out.
Measurement & safety system
230. A known input signal shall be fed from calibrated
source/communicator and the output shall be recorded in the
control system/Data logger. The results are to be entered in a
format. The sample format is given in Annexure-F. The format will
be finalised at the time of detailed engineering.
Command System
231. Manual command shall be issued from control system and the
voltage at the SOV coil end in the case of E/P valve shall be
measured.
232. Also coil resistance shall be measured.
233. Polarity and health of the diode also to be checked and to be
logged in the T&E sheet for the E/P valve chain.
234. For control valve the percentage of control valve opening shall be
checked. For switches functioning shall be checked.
235. Also in simulation mode, command acknowledgements shall be
checked in control system.
236. The results are to be entered in a format. The sample format is
given in Annexure-F.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 45
237. The format will be finalised at the time of detailed engineering.
Auxiliary system
238. Each camera has to be checked for its operation like pant/tilt,
zoom /focus, recording & configuration from the control room.
239. Functional verification of all auxiliary system equipment.
3.3.3.3. Inspection & Quality Surveillance
240. The contractor shall prepare detailed inspection & quality
surveillance plan for all the items and services provided by the
contractor.
241. All Instrumentation items supplied by the contractor (Annexure E)
and services covered by this contract shall be subjected to
inspection and testing by department’s representatives.
242. The inspection by the department’s representative and issue of
inspection certificate thereon shall in no way limit the liabilities
and responsibilities of the contractor in meeting the specification
and quality requirements specified.
243. The contractor shall supply the material test certificates/
calibration certificates (wherever mentioned) for the items under
the supply of contractor’s scope.
244. The contractor shall supply and maintain an independent
comprehensive database system containing inspection & testing
and performance records for each instrument.
3.4. DOCUMENTATION
245. The contractor shall provide with 3 sets of hard copy and a soft
copy for the purpose of documentation. Each instrumentation rack
will be provided with the corresponding approved drawing for
ready reference. The lists of documents are to be provided by the
contractor at the different phases specified thereupon are as
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 46
follows:
246. The contractor shall submit the documents specified under
detailed engineering in chapter 3.1–1 set of hard copy& Soft copy.
247. Catalogues, Test certificate, warrantee/guarantee certificates and
inspection report for the materials /items which are under the
contractor scope of supply
248. The following documents shall be submitted by the contractor
during erection& commissioning phase
Operation & Maintenance manual including Technical &
installation details.
Approved fabrication, mounting and layout drawings.
249. Test and evaluation reports.
250. Up on completion of commissioning activities, as-built version of
all documents approved during detailed engineering.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 47
ANNEXURE –B
(CONTROL ROOM LAYOUTS)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 48
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 49
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 50
ANNEXURE -C
(INSTRUMENTATION SYSTEM CONFIGURATION &
SCHEMATIC DIAGRAM)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 51
Measurement System Configuration
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 52
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 53
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 54
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 55
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 56
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 57
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 58
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 59
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 60
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 61
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 62
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 63
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 64
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 65
Command System Configuration
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 66
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 67
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 68
Fig no.:13
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 69
Fig no.:13a
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 70
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 71
FIG NO: 15. SCHEMATIC DIAGRAM OF CCTV SYSTEM
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 72
Command . Instrumentation Rack
Control Room
SPK-N
SPK-1
19” Rack mount
Intercom
station-1
19” Rack
mount
19” Rack
mount
19” Rack
mount
Power Supply
Explosion proofintercomsta
tion
SPK-1
SPK-N
Auxiliary RackSwitch
Explosion proof intercom station
Power Supply
230V in
SPD
230V in SPD
SPD SPD
FIG NO: 16. SCHEMATIC DIAGRAM OF INTERCOMMUNICATION SYSTEM
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
FIG NO: 1
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
FIG NO: 17. SCHEMATIC DIAGRAM OF TIMING SYSTEM
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 73
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 74
ANNEXURE -D
(INSTRUMENTATION RACK GENERAL ASSEMBLY LAYOUT)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 75
Table-A INSTRUMENTATION RACKS AT CTR
Instrumentation Rack Wiring Requirements
System Rack No
Test Article Pressure Rack MR1
Test Article Temperature (TC & RTD) Rack MR2
Facility Pressure Rack MR3
Facility Temperature Rack MR4
Facility Flow Rack MR5
PLC Remote Node Rack CR1
E/P Valve Driver Rack CR2
E/P Valve Status Rack CR3
Power supply Rack CR4
PID Rack CR5
Auxiliary Rack AUX1
Network Rack NW1
Integrated Data Acquisition System IDAS
Table-B INSTRUMENTATION RACKS AT CONTROL CENTRE
Instrumentation Rack Wiring Requirements
PLC - Local node Rack CR1-1
Auxiliary system Rack AUX2
Network Rack NW2
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 76
General Arrangement for Test Article Pressure Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 77
General Arrangement for Test Article Temperature Rack
General Arrangement for Facility Pressure Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 78
General Arrangement for Facility Temperature Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 79
General Arrangement for Facility Flow Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 80
General Arrangement for Valve Driver Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 81
General Arrangement for Valve Status Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 82
General Arrangement for PID Rack
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 83
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 84
ANNEXURE -E
(SPECIFICATIONS &SUB-VENDOR DIRECTORY)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 85
Table-B (Following items to be supplied by the Contractor for the New Test
Facility)
Sl.No Items Unit Qty. Recommended Brands
1
Pressure Transmitters
with manifolds
Nos.
50
Absolute Pressure:
Rosemount : 3051TA ; SMAR :
LD400; YOKOGAWA : EJX610A;
HONEYWELL: STA 800
Differential Pressure:
Rosemount : 3051CD ; SMAR :
LD400; YOKOGAWA : EJX110A;
HONEYWELL: STD 800
Vacuum Pressure :
Rosemount : 3051TA ; SMAR :
LD400; YOKOGAWA : EJX610A;
HONEYWELL: STA 800
Manifold:
2 Temperature transmitter Nos. 28
SMAR: TT301
Rosemount :3144P
Honeywell: STT 850
3 Solenoid dual coil
including plunger unit Nos. 100
1. M/s. Asco
2. M/s. Herion
3. M/s. Parker
4
Isolation Barrier (IB)
TIB for transmitters Nos.
150
Pepperl + Fuchs,
MTL & Stahl
TIB for status
Nos.
120
TIB for Control valve
command
Nos.
10
TIB for Control valve feed
back
Nos. 10
ZB for Transducer
Excitation
Nos. 20
ZB for Transducer Sense
Nos. 20
ZB for Transducer output
Nos. 20
TIB for Transducer
current Excitation
Nos. 10
Zener Barrier for RTD
Nos. 20
High Freq. TIB for
Transducer output
Nos. 12
5 Voltage isolator Nos. 90 Pepperl + Fuchs ,
MTL & Stahl
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 86
6 Pulse isolator Nos. 10 Pepperl + Fuchs ,
MTL, Stahl & masibus
7 Hall effect sensor
Nos. 32
NANA, SOYNIA
8 Relays
Nos. 200
Phoneix, OMRON
9 Flow Totalizer for turbine
FM
Nos. 07
Pepperl + Fuchs ,
MTL & Masibus
10 Proximity sensor Nos. 190
Pepperl + Fuchs, OMRON, Rockwell
Automation, Long Vale Ltd,
Euroswitch, CaroGavazzi, IFM
electronic
11
Power supply
24V±20%,20A (SMPS R)
Nos. 10
TDK lambda,
ApLab, MASIBUS, Imec
Vinit Electronics,
Elixer electronics,
Ajana electronics
24V±10%, 10A(SMPS R)
Nos. 10
0-72V, 10A(SMPS R)
Nos. 02
0-100 V, 10A(SMPS R)
Nos. 02
±15V, 5A(Linear)
Nos. 02
24V±10%, 10A(linear)
Nos. 08
24V±10%, 20A(linear)
Nos. 04
12 PTFE cables
6 core shielded cable
(22AWG) m
500
1. M/s. Meerut PTFE Products
Pvt Ltd., Meerut
2. T&F Insulation Pvt Ltd.,
Bulandshahr
3. Delton Cables Ltd., New Delhi
4. FLU-TEF Industries.,
Ahmedabad
5. Satellite Cables., Ahmedabad
6. Techno Cables Pvt Ltd.,
Secundrabad
7. TCL Special cables., New Delhi
8. Advance Cables, Bangalore
9. Tempsens Instruments Pvt
Ltd, Udaipur.
32 core shielded cable
(22AWG) m 100
64 core shielded cable
(22AWG) m 200
96 core shielded cable
(22AWG) m 1000
13
PVC armoured cables
2 core armoured PVC
cable
m 3000
1. M/s. Meerut PTFE Products
Pvt Ltd., Meerut
2. T&F Insulation Pvt Ltd.,
Bulandshahr 4 core armoured PVC
cable
m 3500
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 87
6 core armoured PVC
cable m 1000
3. Delton Cables Ltd., New Delhi
4. FLU-TEF Industries.,
Ahmedabad
5. Satellite Cables., Ahmedabad
6. Techno Cables Pvt Ltd.,
Secundrabad
7. TCL Special cables., New Delhi
8. Advance Cables, Bangalore
9. Tempsens Instruments Pvt
Ltd, Udaipur.
10 Core armoured PVC
Cable m 11000
PVC un-armoured cables
32 Core un-armoured
PVC Cable m 1000
64 Core un-armoured
PVC Cable m 1500
96 Core un-armoured
PVC Cable m 1500
14
PTFE cables
18AWG Single core wire
(Red & black) m 2000
1. M/s. Meerut PTFE Products
Pvt Ltd., Meerut
2. T&F Insulation Pvt Ltd.,
Bulandshahr
3. Delton Cables Ltd., New Delhi
4. FLU-TEF Industries.,
Ahmedabad
5. Satellite Cables., Ahmedabad
6. Techno Cables Pvt Ltd.,
Secundrabad
7. TCL Special cables., New Delhi
8. Advance Cables, Bangalore
9. Tempsens Instruments Pvt
Ltd, Udaipur.
22AWG Single core wire
(red, black, Green,
orange, blue & white)
m 10000
24AWG Single core wire
(red, black, Green,
orange, blue & white)
m 750
15
T/C Extension Cable
Single pair T/C extension
cable
m 2000 1. Thermocab
2. Fabrica
3. Tempsons 32 core T/C extension
cable m 800
16
Power cable
1.5 sq.mm m 1000 Finolex, Poly Cab, V Guard, RR Kabel,
Havells, Lapp, Kundan 2.5 sq.mm m 650
17
Earth cable
2.5 sq.mm m 1000 Finolex, Poly Cab, V Guard, RR Kabel,
Havells, Lapp 4 sq.mm m 300
18 Indicators , Switches &Keys
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 88
Indicators Nos. 50 1.Tyco
2.Amphenol
3.Honeywell
4.Entrelac
5. Technique
6.Warner
Authorization keys Nos. 20
Switches with Indicators Nos. 50
19 Industrial standard
Connectors (108 pin) Set 100
1. Wago
2. Phoenix
3. Weidmuller
20 7 pin Circular Connectors
Set 50
1. Wago
2. Phoenix
3. Weidmuller
4. Amphenol
21 32 pin Circular
Connectors Set 10
1. Wago
2. Phoenix
3. Weidmuller
4. Amphenol
22 Miniature K-Type TC
connector Set 150
1. Thermocab
2. Fabrica
3. Tempsons
23
Terminal block(2.5 sq.mm)
Terminal Blocks- No. of
levels:1 ; No of
terminals:2
Nos. 18000
1. Phoenix
2. Wego
3. Weidmullar
Terminal Blocks- No. of
levels:2 ; No of
terminals:4 with short
link
Nos. 200
Terminal Blocks- No. of
levels:2 ; No of
terminals:4 with cross
link
Nos. 100
Terminal Blocks- No. of
levels:1 ; No of
terminals:2 with diode in
series
Nos. 200
Terminal Blocks- No. of
levels:1 ; No of
terminals:2 with diode in
parallel
Nos. 200
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 89
Terminal block –
Powering (Red, Yellow
and Blue)
Nos. 500
24
Junction boxes
Type I : 600x400x225 Nos. 10
1. M/s Baliga Lighting Equipments
Ltd
2. M/s Flame Proof Equipments Pvt.
Ltd
3. M/s. Stahl, Chennai
4. M/s CEAG Flame Proof Control
Gears (P) Ltd
5. M/s FCG Power Industries Pvt.Ltd
6. M/s. EX Protecta
7. M/s. Pepperl +Fuchs Pvt. Ltd.
8. M/s. Charmin Type II : 300x300x165 Nos. 02
25
Compression fittings & SS tubes
12.7 mm SS tube; Wall
thickness: 1.6mm Mtrs. 200
SS Tubes
1. M/s. Swagelok
2. M/s. Sandvik
3. M/s. Ratnamani
4. M/s. Remi
Compression Ferrule Fittings
1. M/s. Swagelok
2. M/s. Parker
3. M/s. DK LOK
8 mm SS tube
Mtrs. 800
12.7mm SS tube union Nos. 100
12.7mm SS tube Tee Nos. 25
8 mm SS tube union Nos. 150
8 mm SS tube Tee Nos. 50
Bulk head union for 8mm
tube Nos. 150
½” NPT SS Plug Nos. 100
¼” NPT SS Plug Nos. 100
26
Cable trays
Perforated MS Cable
Trays- width: 50mm;
Height: 12mm; Thickness:
1.6mm
m 2500
1. M/s.Patny systems, Secundrabad
2. M/s.Elcon Instruments, Pune
3. M/s.Shruti Industries, Pune Perforated MS Cable
Trays- width: 100mm;
Height: 25mm; Thickness:
2.0 mm
m 1500
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 90
Perforated MS Cable
Trays- width: 150mm;
Height: 25mm; Thickness:
2.0 mm
m 1500
Perforated MS Cable
Trays- width: 300mm;
Height: 50mm; Thickness:
2.0 mm
m 1000
Ladder MS Cable Trays-
width: 300mm; Height:
75mm; Thickness: 2.0
mm
m 600
Ladder MS Cable Trays-
width: 600mm; Height:
75mm; Thickness: 2.0
mm
m 1500
27
Structural materials
supply & fabrication
(various sizes of L-
angle& channel and 2“
MS pipe etc.)
kg 10000 -NA-
28 Canopy Sq.m 15 -NA-
29
Instrumentation (600mm
W) Racks with
accessories
Nos. 12
1. Rittal
2. Schnider Instrumentation
(1200mm W) Racks with
accessories
Nos. 02
30
Cable glands Suitable for the cable given
below (Nickel coated Brass Type)
2 core armoured PVC Nos. 250
1. Trinity
2. Hummel
3. Weidmuller
4. Lapp
4 core armoured PVC Nos. 300
6 core armoured PVC Nos. 50
10 core armoured PVC Nos. 120
32 core un-armoured PVC Nos. 5
64 core un-armoured PVC Nos. 15
96 core un-armoured PVC Nos. 15
32 core PTFE Nos. 05
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 91
64 core PTFE Nos. 10
96 core PTFE Nos. 50
2 core TC cable Nos. 100
32 core TC cable Nos. 10
31 Cable entry Plate Nos. 20 -NA-
32 Connector Mounting
Plate Nos. 25 -NA-
33
Metal conduits, Metal
flexible hoses suitable
for conduit, 4/3/2 way
metal junction box
suitable for conduit
bends, elbows, Tees and
couplers of required
quantities.
lot 1 -NA-
34 Operator chair Nos. 30 Godrej, Featherlite, Merryfair
35 CCTV system Details as per
table 1 Aux @
page 191
Brands mentioned in specification 36 Inter communication
system
37 Timing system
38
Harnessing Materials
Lasing tie
Mtrs. 5000
1. Phoenix
2. Wego
50mm cable tie (Pack of
1000 nos.)
Pack 100
100mm cable tie (Pack of
1000 nos.) Pack 100
150mm cable tie (Pack of
1000 nos.)
Pack 100
200mm cable tie (Pack of
1000 nos.) packs 100
250mm cable tie (Pack of
1000 nos.) packs 100
300mm cable tie (Pack of
1000 nos.)
packs 100
400mm cable tie (Pack of
1000 nos.) packs 25
500mm cable tie (Pack of
1000 nos.) packs 25
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 92
1. PRESSURE TRANSMITTERS & MANIFOLDS
SPECIFICATION FOR SMART ABSOLUTE PRESSURE TRANSMITTER
Sl.No Parameters Specification
1 Type SMART Absolute Pressure Transmitter
2 Measurement Range As per Table 1
3 Service Medium As per Table 1
4 Maximum Turndown Ratio (TD) 100:1
5 Output Two wire 4–20 mA with superimposed Digital
communication HART protocol.
6 Power Supply 12 to 30 V DC.
7 Local Indication 4½ digits LCD – Local Alpha Numeric Digital
display in Engineering units.
8 Hazardous Area Certification Both Intrinsically safe and Explosion proof
suitable for use in Hydrogen atmosphere.
(CENLEC / CSA / FM / ATEX or any equivalent
approval).
9 Safety Integrity Level Standard
(SIL)
Safety Instrumented System Certification as per
IEC 61508 standard, SIL 2 or above.
10 Zero & Span Adjustments Zero and Span are to be adjusted from the
Handheld HART Communicator and provision
for local adjustment to be set anywhere within
the range limits.
11 Failure mode alarms High alarm ≥ 21.0 mA
Low Alarm ≤ 3.6 mA
12 Accuracy
@ TD 8:1 for URL<200 Bar and
@ TD 2.5:1 for URL>200 Bar
≤± 0.09 % of Calibrated span (including the
effect of Terminal - Based linearity, hysteresis &
repeatability)
13 Ambient Temperature Effect for
28°C variation
@ TD 8:1 for URL<200 Bar and
@ TD 2.5:1 for URL>200 Bar
≤ ± 0.4 % span
14 Stability ≤± 0.12 % of URL for 10yrs.
15 Power Supply Effect ≤± 0.005 % of Calibrated Span per Volt.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 93
16 Over Pressure limit Over pressure limit of selected transmitters
shall be 1.5 times of URL
17 Nominal Operating
Temperature
-40 to 80oC
18 Response time ≤ 150 millisecond
19 Wetted Material As per Table 1
20 Fill Fluid As per Table 1
21 Transient / Lightning Protection 3KA crest (8/20 microSec) as per IEEE C62,41.2,
IEC61000-4-4 and IEC61000-4-5
22 Drain vent port Not required.
23 Electrical Connection ½ " – 14 NPT (F) with SS plug for dust proof.
24 Transmitter Process connection ½ " – 14 NPT (F) or suitable for the quoted
manifold
25 Housing Material Polyurethene covered aluminium with ½”-14
NPT conduit entry.
26 External Grounding screw
assembly on transmitter body
Required
27 Mounting Bracket Stainless Steel Bracket with SS fasteners, bolts,
nuts, washers and U-clamps suitable for 2 inch
pipe mounting.
28 Calibration Calibration shall be carried out at room
temperature in 5 steps ascending and 5 steps
descending. Calibration certificate is to be
provided. Calibration shall be traceable to
National Standards.
29 Ingress Protection IP66/67
30 Manifold 2 way Valve manifold. The valve manifold shall
be manufacture by transmitter manufacturer
with catalogue part no and datasheets or from
one of the approved make: Parker / Swagelok /
Anderson. (Specifications as per enclosure)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 94
SPECIFICATION FOR SMART DIFFERENTIAL PRESSURE TRANSMITTER
Sl.No Parameters Specification
1 Type SMART Differential Pressure Transmitter
2 Measurement Range As per Table 1
3 Service medium As per Table 1
4 Turndown Ratio 100:1
5 Output Two wire 4–20 mA with superimposed Digital
communication HART protocol.
6 Power Supply 12 to 30 V DC.
7 Local Indication Min 4 1/2 digit LCD - Local Alpha Numeric Digital display
in Engineering unit.
8 Hazardous Area
Certification for all
Transmitters
Both Intrinsically safe and Explosion proof suitable for
use in Hydrogen atmosphere.
(CENELEC / CSA / FM / ATEX or any equivalent approval).
9 Safety Integrity Level
Standard (SIL)
Safety Instrumented System Certification as per IEC
61508 standard, SIL 2 or above.
10 Zero & Span
Adjustments
Zero and Span are to be adjusted from the Handheld
HART Communicator (HHC) and provision for local
adjustment to be set anywhere within the range limits.
11 Failure mode alarms High alarm ≥ 21.0 mA
Low Alarm ≤ 3.6 mA
12 Reference Accuracy
@ TD 5:1
≤ ±0.075%Span for URL above 100 mbar
≤ ± 0.1% span for URL below100 mbar
(including the effect of Terminal - based linearity,
hysteresis & repeatability).
13 Ambient Temperature
effect for 280 C
variation
@ TD 5:1
≤±0.4%Span for URL above 100 mbar
≤± 0.75% for URL below 100 mbar
14 Stability ≤±0.2%URL for 5 years , for URL above 100 mBar
≤±0.2% URL for 1 year, for URL below 100 mbar
15 Power Supply Effect ≤± 0.005 % of Calibrated Span per volt.
16 Mounting Position
Effect
Zero shifts can be calibrated out.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 95
17 Static Pressure effect Span error: ≤ ± 0.2 % of span / 70 bar for URL above 100
mbar.
Span error: ≤0.45 %span / 70 bar for URL below 100
mbar
18 Maximum Static
pressure
As per Table 1
19 Over pressure limit Over pressure limit of selected transmitters should be
1.25 times of URL (Upper range Limit) .
20 Nominal Operating
Temperature
-40 to 80oC
21 Response time ≤ 300 msec
22 Wetted Material As per Table 1
23 Fill Fluid As per Table 1
24 Transient / Lightning
Protection 3KV crest ( 8 / 20 microSec) as per IEEE
C62.41.2,IEC61000-4-4 and IEC61000-4-5
25 Drain vent port Not required.
26 Electrical Connection ½ " – 14 NPT (F) with SS plug for dust proof.
27 Transmitter Process
Connection
1/2” – 14 NPT (F) or suitable for the quoted manifold
Conduit entry.
28 Housing Material Polyurethane covered aluminium with ½ - 14 NPT
Conduit entry.
29 External Grounding
screw assembly on
transmitter body
Required.
30 Mounting Bracket Stainless Steel Bracket with SS fasteners, bolts, nuts,
washers and U-clamps suitable for 2 inch pipe mounting.
31 Calibration Calibration shall be carried out at room temperature in 5
steps ascending and 5 steps descending. Calibration
certificate is to be provided. Calibration shall be
traceable to National Standards.
32 Ingress Protection IP66/67
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 96
33 Manifold
5 Valve manifold. The manifold shall be manufactured
by transmitter manufacturer with catalogue part no and
datasheets or from one of the approved make: Parker /
Swagelok / Anderson. (Specifications as per enclosure)
SPECIFICATION FOR SMART VACUUM PRESSURE TRANSMITTER
Sl.No Parameters Specification
1 Type SMART Vacuum Pressure Transmitter
2 Measurement Range As per Table 1
3 Service Medium As per Table 1
4 Maximum Turndown Ratio (TD) 15:1
5 Output Two wire 4–20 mA with superimposed Digital
communication HART protocol.
6 Power Supply 12 to 30 V DC.
7 Local Indication Min 4 1/2 digits LCD – Local Alpha Numeric
Digital display in Engineering units.
8 Hazardous Area Certification Both Intrinsically safe and Explosion proof
suitable for use in Hydrogen atmosphere.
(CENLEC / CSA / FM / ATEX or any equivalent
approval).
9 Safety Integrity Level Standard
(SIL)
Safety Instrumented System Certification as per
IEC 61508 standard, SIL 2 or above.
10 Zero & Span Adjustments Zero and Span are to be adjusted from the
Handheld HART Communicator and provision
for local adjustment to be set anywhere within
the range limits.
11 Failure mode alarms High alarm ≥ 21.0 mA
Low Alarm ≤ 3.6 mA
12 Accuracy
@ TD 3:1
≤± 0.08 % of span (including the effect of
Terminal – based linearity, hysteresis &
repeatability).
13 Ambient Temperature effect for
28°C variation @ TD 3:1 ≤ ± 0.4 % span
14 Stability ≤ +/- 0.2 % of URL for 10 yrs.
15 Power Supply Effect ≤± 0.005 % of Calibrated Span per Volt.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 97
16 Over Pressure limit Over pressure limit of selected transmitters
shall be 1.25 times of URL
17 Nominal Operating
Temperature
-40 to 80oC
18 Response time ≤ 300 millisecond
19 Wetted Material As per Table 1
20 Fill Fluid As per Table 1
21 Transient / Lightning
Protection:
3KV creat (8/20 microSec) as per IEEE
C62.41.2,IEC61000-4-4 and IEC61000-4-5
22 Drain vent port Not required.
23 Electrical Connection ½ " – 14 NPT (F) with SS plug for dust proof.
24 Transmitter Process connection ½ " – 14 NPT (F) or suitable for the quoted
manifold
25 Housing Material Polyurethane covered aluminium with ½”-14
NPT conduit entry.
26 External Grounding screw
assembly on transmitter body
Required
27 Mounting Bracket Stainless Steel Bracket with SS fasteners, bolts,
nuts, washers and U-clamps suitable for 2 inch
pipe mounting.
28 Calibration Calibration shall be carried out at room
temperature in 5 steps ascending and 5 steps
descending. Calibration certificate is to be
provided. Calibration shall be traceable to
National Standards.
29 Ingress Protection IP66/67
30 Manifold 2 way Valve manifold. The valve manifold shall
be manufactured by transmitter manufacturer
with catalogue part no and datasheets or from
one of the approved make: Parker / Swagelok /
Anderson. (Specifications as per enclosure)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 98
5 Valve Manifold Specifications
Sl.No. Parameters Specification
1 Type 5 Valve manifold
2 Material MMH : Hastelloy C ;
UH 25, UDMH, N2O4, LH2, LOX, GH2,
GO2 GN2, GHe, Water, Kerosene : 316SS
3 Packing material PTFE
4 Seat type Integral
5 Instrument Connection Suitable for quoted transmitter interface
6 Process connection ½ inch – 14 NPTF
7 Maximum Operating pressure 400 bar manifold for transmitter static
pressure range upto 250 bar
680 bar manifold for transmitter static
pressure range 250 to 500 bar
8 Operating Temperature 0 to 100 deg C
9 Hydro Testing To be carried out at 1.5 times the
maximum operating pressure for all the
manifolds and certificate to be provided
10 Material Test certificate To be provided
11 Mounting Bolts To be supplied with SS material
12 Catalogue Detailed technical datasheet and
dimensional drawing to be provided
along with offer
2 Valve Manifold Specifications
Sl.No. Parameters Specification
1 Type 2 Valve manifold
2 Material MMH : Hastelloy C ;
UH 25, UDMH, N2O4, LH2, LOX, GH2,
GO2 GN2, GHe, Water, Kerosene : 316SS
3 Packing material PTFE
4 Seat type Integral
5 Instrument Connection Suitable for quoted transmitter interface
6 Process connection ½ inch – 14 NPTF
7 Maximum Operating pressure 400 bar manifold for transmitter static
pressure range upto 250 bar
680 bar manifold for transmitter static
pressure range 250 to 500 bar
8 Operating Temperature 0 to 100 deg C
9 Hydro Testing To be carried out at 1.5 times the
maximum operating pressure for all the
manifolds and certificate to be provided
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 99
10 Material Test certificate To be provided
11 Mounting Bolts To be supplied with SS material
12 Catalogue Detailed technical datasheet and
dimensional drawing to be provided
along with offer
IMPORTANR NOTE
1. Party shall quote with detailed technical specification and printed
product catalogue, manufacture datasheet containing product matrix
and part No de-codification details.
2. Party shall quote the models such that the max URL poof the particular
model meets the following requirement:
a. Absolute Transmitter for URL < 200bar, max URL should be < 8
times the measurement range.
b. Gauge Transmitter for URL > 200bar, max URL should be < 2.5
times the measurement range.
c. For Vacuum Transmitter max URL should be < 3 times the
measurement range.
d. For Differential Transmitter max URL should be < 5 times the
measurement range.
3. Technical compliance statement to our indented specification shall be
provided.
4. Operation Manual in English to be supplied.
5. The cost of the valve manifold need to be quoted along with pressure
transmitter.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 100
TABLE 1
LIST OF ABSOLUTE PRESSURE TRANSMITTERS
Sl.No Tag No. Range Medium
Wetted
Part
material
Fill Fluid Qty(Nos.)
1 LAPOT 0-30 Bar N2O4 SS304L Silicone oil 01
2 LAPFT 0-30 Bar MMH SS304L Silicone oil 01
3 LAPOTR 0-30 Bar N2O4 SS304L Silicone oil 01
4 LAPFTR 0-30 Bar MMH SS304L Silicone oil 01
5 LAPOT-S1 0-30 Bar N2O4 SS304L Silicone oil 01
6 LAPFT-S1 0-30 Bar MMH SS304L Silicone oil 01
7 LAPOX 0-25 Bar N2O4 SS304L Silicone oil 01
8 LAPFU 0-25 Bar MMH SS304L Silicone oil 01
9 LAPOXR 0-25 Bar N2O4 SS304L Silicone oil 01
10 LAPFUR 0-25 Bar MMH SS304L Silicone oil 01
11 LAPORU 0-250 Bar Air SS316 Silicone oil 01
12 LAPFRU 0-250 Bar Air SS316 Silicone oil 01
13 LAPORD 0-100 Bar Air SS316 Silicone oil 01
14 LAPFRD 0-100 Bar Air SS316 Silicone oil 01
15 LASRDO 0-100 Bar Air SS316 Silicone oil 01
16 LASRDF 0-100 Bar Air SS316 Silicone oil 01
17 LAPTO 0-10 Bar Air SS316 Silicone oil 01
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 101
18 LAPTF 0-10 Bar Air SS316 Silicone oil 01
19 LAPORU 0-25 Bar Air SS316 Silicone oil 01
20 LAPFRU 0-25 Bar Air SS316 Silicone oil 01
21 LAPPM 0-25 Bar Air SS316 Silicone oil 01
22 LAPPR 0-25 Bar Air SS316 Silicone oil 01
23 LAPORU-S1 0-250 Bar Air SS316 Silicone oil 01
24 LAPORD-S1 0-100 Bar Air SS316 Silicone oil 01
25 LAPORU-S1 0-25 Bar Air SS316 Silicone oil 01
26 LAPP804 0-300 Bar Air SS316 Silicone oil 01
27 LAPP808 0-300 Bar Air SS316 Silicone oil 01
28 LAPP804-S1 0-300 Bar Air SS316 Silicone oil 01
29 LAPP801 0-50 Bar Air SS316 Silicone oil 01
30 LAPP802 0-50 Bar Air SS316 Silicone oil 01
31 LADP900 0-20 Bar water SS316 Silicone oil 01
32 LADP900R 0-20 Bar water SS316 Silicone oil 01
33 LAPP909 0-20 Bar water SS316 Silicone oil 01
34 LAPP909R 0-20 Bar water SS316 Silicone oil 01
35 LADP900-S1 0-20 Bar water SS316 Silicone oil 01
36 LAPFT-S1 0-30 Bar MMH SS304L Silicone oil 01
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 102
LIST OF VACUUM PRESSURE TRANSMITTERS
Sl.No Tag No. Range Medium
Wetted
Part
material
Fill Fluid Qty(Nos.)
1 LAPV805 0-1000mBar Mixed Gas SS316 Silicone oil 01
2 VAPV806 0-1000mBar Mixed Gas SS316 Silicone oil 01
3 VAPV807 0-1000mBar Mixed Gas SS316 Silicone oil 01
4 LAPV801 0-1000mBar Mixed Gas SS316 Silicone oil 01
5 LAPV802 0-100mBar Mixed Gas SS316 Silicone oil 01
6 LAPV803 0-10mBar Mixed Gas SS316 Silicone oil 01
7 LAPV804 0-10mBar Mixed Gas SS316 Silicone oil 01
8 LAPV805-S1 0-1000mBar Mixed Gas SS316 Silicone oil 01
9 LAPV804-S1 0-10mBar Mixed Gas SS316 Silicone oil 01
LIST OF DIFFERENTIAL PRESSURE TRANSMITTERS
Sl.No Tag No. Range Medium
Wetted
Part
material
Fill Fluid Qty (Nos.)
1 LADP100 0-500mBar N2O4 SS304L Silicone oil 01
2 LADP200 0-500mBar MMH SS304L Silicone oil 01
3 LADP801 0-1000mBar Mixed Gas SS316 Silicone oil 01
4 LADP802 0-1000mBar Mixed Gas SS316 Silicone oil 01
5 LADP200-S1 0-500mBar MMH SS304L Silicone oil 01
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 103
2. TEMPERATURE TRANSMITTER
Inputs
: a. 2/3/4 wire Pt 100 IEC
: b. 2/3/4 wire Pt 500 IEC
: c. Thermocouples: B,E,J,K,N,R,S,T types, etc.
: d. Ohms: 0-2000Ω
: e. millivolt : -10 to 100 mV
Output Signal : Two-wire, 4-20mA with superimposed digital
communication (HART protocol)
Power Supply : 12 to 42 VDC
Digital Accuracy (Excluding
sensor)
: As per table 2
Minimum span : As per table 2
4-20 mA D/A accuracy : ≤ ± 0.03% of span
CJC accuracy for T/C : ±0.25 degC
Ambient Temp effect for 10 °C
variation in temperature
: • RTD (IEC: Pt50, Pt100): 0.04ohm
• Ohm (0...2000ohm) & RTD (IEC: Pt500):
0.3ohm
• mV (-10...100 mV) & TC (NBS: E, J, K, N): 15µV
Stability 0.05 %URL for 5 years
Indication : 4½ or 5 digit LCD indicator
Zero and Span Adjustment : By Hand-Held Terminal or Local adjustment.
Temperature Limits
: Operation: 15 to 500C
: Storage : 15 to 600C
Sensor Failure : In case of sensor or circuit failure, the self
diagnostics to drive the output to 3.9 or to 21.0mA,
user selectable.
Humidity Limits : 10 to 100% RH (non condensing)
Turn-on Time : ≤ 10 seconds
Update Time : ≤ 0.5 seconds
Damping : 0 to 30 sec (adjustable)
Power Supply Effect : ≤ ± 0.005% of calibrated span per volt.
EMI Effect : To be designed to comply with IEC standards
Alarm : As per NAMUR standards.
Configuration : To be done by a Hand- Held terminal (HART
protocol) or locally using switches.
Hazardous Location : Intrinsically safe certified ATEX II 2G Ex ia IIC T6.
Electrical connection : ½-14 NPT
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 104
Material of Construction : Painted copper aluminium housing, with Buna N 0-
rings on cover
Ingress Protection : IP66/67
Accessories : Mounting bracket to be supplied to mount on 2”
pipe
: HART compatible hand held communicator for
programming the transmitters.
Transmitter Requirement : As per table 2.1
Table 2
Range & Input
Accuracy
Type Range(°C) Min. Span (°C) Digital
Accuracy 0C
RTD Pt 100 -200 to 850 10 ± 0.2
Pt 500 -200 to 450 10 ± 0.2
T/C B 100 to 1800 50 ± 0.8
E -50 to 1000 25 ± 0.2
J -150 to 1200 30 ± 0.3
K -180 to 1350 60 ± 0.6
N -100 to 1300 50 ± 0.5
R 0 to 1750 40 ± 0.6
S 0 to 1750 40 ± 0.5
T -200 to 400 25 ± 0.3
OHM Ohm 0 to 2000Ω 20 Ω ±0.35 ohm
mV mV -10 to 100mV 3mV ± 0.02%
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 105
List of Temperature Transmitters Requirement for New Test Facility
Table 2.1
Sl.No. Legend Medium Operating range Sensor
1 LATO100 N204 -20 to 100 Deg C PT100
2 LATF200 MMH -20 to 100 Deg C PT100
3 LATP805 Mixed Gas 0 to 2000 Deg C T/C
4 LATP806 Mixed Gas 0 to 600 Deg C T/C probe
5 LATP807 Mixed Gas 0 to 127 Deg C T/C probe
6 LATP801 Air -25 to 60 Deg C PT100
7 LATP802 Air -25 to 60 Deg C PT100
8 LATP900 water 0 to 100 Deg C PT100
9 LATP909 water 0 to 100 Deg C PT100
10 LATP901 water 0 to 100 Deg C PT100
11 LATP902 water 0 to 100 Deg C PT100
12 LATP903 water 0 to 100 Deg C PT100
13 LATP904 water 0 to 100 Deg C PT100
14 LATP905 water 0 to 100 Deg C PT100
15 LATP906 water 0 to 100 Deg C PT100
16 LATP907 water 0 to 100 Deg C PT100
17 LATL1 Body of LC 0 to 200 Deg C K type T/C
18 LATL1R Body of LC 0 to 200 Deg C K type T/C
19 LATL2 Body of LC 0 to 200 Deg C K type T/C
20 LATL3 Body of LC 0 to 200 Deg C K type T/C
21 LATL4 Body of LC 0 to 200 Deg C K type T/C
22 LATLB Body of LC 0 to 200 Deg C K type T/C
23 Spare-1
Spare Transmitters
24 Spare-2
25 Spare-3
26 Spare-4
27 Spare-5
28 Spare-6
Note: Transmitters alone to be supplied
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 106
3. SOLENOID VALVE (Dual Coil)
1. Valve Body
Type: Three way, Normally closed
Body material : SS 316
Housing : Die cast Aluminium epoxy painted
Stem: SS 316/ SS304
Seat: Viton
End connection: Threaded female NPT conforming to ANSI-B1.20.1. 1/4"
NPT (F)
Mounting altitude: Any altitude without affecting their operation.
Orifice Size: <3 mm
2. Solenoid
Power supply : 24 VDC / 300 mA (max)
Solenoid coil: Suitable for continuous energization.
Enclosure: IP 65 & Protection IIB certified
Coil insulation: Class F as defined in IS: 1271
Coil pick up voltage: Between 50 to 70% of normal supply voltage.
Coil drop up voltage: Between 30% to 50% of nominal supply voltage.
Coil temperature rise: Not to exceed 70°C
Dual coil
Response Time : Less than 100 ms
Conduit connection: Enclosure shall have 1/2” NPT (F) connection for
power Supply cable
Mode of operation: Direct operated
Manual operation : Provision to open the valve using Lever
Freewheeling Diode : Two diode in series to be provided
3. Process condition
Fluid: GN2
Operating Pressure: Min. 2 bar, Max. 10 bar, Nominal: 7 bar
Service Life : 50,000 cycles
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 107
Operating Temperature: 30°C to 40°C
Relative humidity: up to 95%
4. JUNCTION BOX
1. Enclosure
• All Junction Box shall be explosion proof (IIB).
• The degree of ingress protection shall be IP66.
• The equipment shall be suitable for operating in humid & corrosive
atmosphere
• Junction box shall have housing of cast aluminium LM6 alloy
• All Junction Box shall be provided with neoprene gaskets.
• All accessories like nut, bolts, washers etc. shall be made of stainless steel
SS- 304.
• Conduit and cable entry- Side & Bottom Entry
• Door of JB- Hinged with proper locking arrangement to avoid entry of
dust and moisture
• Ambient temperature-50 deg C
• Ambient humidity-0-100 % RH
• Earthing : Two numbers of Earthing bolts for JB Earthing.
• Junction box size shall be as per the following dimensions:
600 x 400 x 225 mm
300 x 300 x 165mm
2. Terminal blocks
• Terminals shall be shrouded and shall be numbered as per the wiring
diagram. Minimum rating of the terminal block shall be 5 Amps.
• For Individual shielded multi-pair cables a separate terminal shall be
provided for each shield drain wire.
• Terminal Strip- screw cage clamp type capable of terminating 1 sq.mm
and 1.5 sq mm cables
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 108
3. Name plate
• Aluminium anodized nameplate indicating the equipment to be
controlled shall be provided on each local Junction Box. The particulars of
the plate will be supplied to the vendor. Nameplate shall be fixed by
screws and not pasted.
• The letter shall be engraved in black on white background.
• Certificate numbering date and gas group classification must be indicated
on the manufacturer’s nameplate on each junction box.
4. Mounting
Junction Box shall have 4 lugs for fixing on wall or fabricated steel support.
The lugs shall be offset so that the rear of the unit stays away from the
surface by at least 5mm. Two of the holes shall be round and the other two
oblong to facilitate correct positioning. All screws, nuts and studs etc. shall
be of electro galvanized or zinc passivated type.
5. Painting
The enclosure shall be treated & prepared for painting with two coats of
Dark admiralty grey shade 632 of IS-5 epoxy paint (Both inside and outside)
5. SS TUBES & COMPRESSION FERRULE FITTINGS
SS Tube:
1. Type : Seamless SS tubes
2. Outside Diameter : As given in Table 3
3. Wall Thickness : As given in Table 3
4. Material grade : As Given in Table3
5. Ends : Both the ends shall be plain with square cuts .All
the burrs at the ends of tubes shall be removed.
6. The tubes shall be supplied in lengths of 6 meters.
7. Test and Inspection : The tubes shall be tested and inspected as per the
quality assurance plan given in Table 4
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 109
8. Cleanliness : All the tubes shall be suitably cleaned/ pickled and
dried.
9. Documentation : Along with dispatch documents, the certificates of
test specified in the QAP (Table 4), Pre-delivery
Inspection certificate by the supplier’s quality
control (QC) inspector and guarantee certificate
shall be provided.
10. Marking and packing : The tubes shall be marked, packed and loaded for
transportation as per ASTM A 700. Identification
marks such as specification, material grade, heat
and batch number, size, wall thickness and year of
manufacturing shall be stencilled on each tube.
11. Quantity variation : The variation in the quantity of tubes supplied shall
be permissible to the extent of ± 10 % of the
quantity ordered.
Table 3:
Sl.
No
Outside
Diameter
Wall
Thickness Material Grade
1. 12.7mm 1.6 mm ASTM A 269 TP 304L/TP316 L
2. 8.0 mm 1.0 mm ASTM A 269 TP 304L/TP316 L
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 110
Table 4: QUALITY PLAN
Sl.
N
o
Test Compone
nt tested
Characteristics
sought for
Extend
of test
Test
Procedure
Acceptance
criterion
Form of
record
Pre Delivery inspection
Test
Performed
by
Test
witnessed
by
Records
reviewed
by
1 Visual
Inspection
All tubes Surface Finish 100% Visual
Examinatio
n
Workmen like
finish
Inspecti
on
Certifica
te
Supplier’s
quality
control
Inspector
- Purchaser
2 Chemical
Analysis
Specimen
from
tubes
Chemical
Composition
1 per
heat
ASTM A751 ASTM A269 Materia
l Test
Certifica
te
Supplier’s or
Govt
approved
Laboratory
- Supplier’s
QC
Inspector
&
Purchaser
3 Mechanical
test (Tensile
& hardness
Test)
Specimen
from
Tubes
Mechanical
Properties
1 per lot ASTM A370 ASTM A269 Materia
l Test
Certifica
te
Supplier’s or
Govt
approved
Laboratory
- Supplier’s
QC
Inspector
&
Purchaser
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 111
Sl.
N
o
Test Compone
nt tested
Characteristics
sought for
Extend
of test
Test
Procedure
Acceptance
criterion
Form of
record
Pre Delivery inspection
Test
Performed
by
Test
witnessed
by
Records
reviewed
by
4 Hydro-static
Pressure
test
Tubes Structural
Integrity under
pressure
100% ASTM A530 ASTM A530 Test
certifica
te
Supplier Supplier’s
QC
Inspector
Purchaser
5 Flattening Specimen
of 65mm
length cut
from the
ends of
the tubes
Ductility and
soundness
5% ASTM A530 ASTM A530 Test
certifica
te
Supplier Supplier’s
QC
Inspector
Purchaser
6 Inter
granular
corrosion
(IGC) test
Specimen
From
tubes
Grain Structure 1 per lot ASTM A262
practice
A/E
ASTM A262
practice A/E
Test
certifica
te
Supplier Supplier’s
QC
Inspector
Purchaser
7 Eddy
current Test
Tubes Internal Flaw
Detection
100% ASTM E426 ASTM E426 Test
certifica
Supplier Supplier’s
QC
Purchaser
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 112
Sl.
N
o
Test Compone
nt tested
Characteristics
sought for
Extend
of test
Test
Procedure
Acceptance
criterion
Form of
record
Pre Delivery inspection
Test
Performed
by
Test
witnessed
by
Records
reviewed
by
te Inspector
8 Cleaning Cleaning 100% CGAG-4.1
(or) ASTM
G-93
CGAG-4.1 (or)
ASTM G-93
certifica
te
Supplier Supplier’s
QC
Inspector
Purchaser
9 Dimension
checking
All tubes 100% Metrology Manufacture
drawing
Report Supplier Supplier’s
QC
Inspector
Purchaser
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 113
SPECIFICATIONS OF SS TUBE FITTINGS
1. Description of the item : SS Double compression Ferrule Fittings
2. Applicable standard : ASTM F 1387-99
3. Outer diameter of the
tube
: As per requirement
4. Type of fittings : Double compression Ferrule with Nut and body
(Type : IV as per ASTM F 1387)
5. Material of the fittings : Grade B, SS 304 L/SS 316L
6. Class : Class 10 ( 413.7 Bar)
7. Shape of the Fitting : As per Table 5
8. SS tube fittings to supplied as per requirement table-B
9. Tests & Inspection :
Certification of Testing: The vendor shall provide a certificate that samples of
fittings of the same design, material and manufacturing process as that of the
fitting supplied have been subject to standard performance tests (such as
examination of specimen, pneumatic proof test, hydrostatic proof test, impulse
test, flexure fatigue test, tensile test, burst test, repeat-assembly test and rotary
flexure test) as per Table 3 of ASTM F 1387.
Certification of raw material: The vendor shall provide a certificate of compliance
stating that all applicable requirements of raw material are met. Besides, copies
of the MIL certificates for the physical and chemical properties of the raw
materials shall be supplied.
Leakage test: One sample from each type of fitting shall be subjected to leakage
test with Helium Mass Spectrometer Leak Detector (MSLD) by tracer probe
technique. The acceptance criterion shall have leakage finer than 1 x 10-6
Std.cm3/sec.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 114
10. Marking : All fittings must be marked with following details
a) Pressure rating
b) Raw Material and Size of the
end connection
Conditions:
All the fittings shall be neatly packed before delivery.
The test and inspection certificates as mentioned in Para (9) shall be supplied before
delivery of the items to the Department. After approval of the certificates by
Department, the party has to dispatch the items.
6. PVC CABLE (Armoured and Un-armoured)
CONSTRUCTION:
96 Core (16x6core) PVC Data Cable (Un-Armoured)- FRLS Type
20AWG (7/0.31) Annealed tinned high conductivity copper conductor, insulated
with polyethylene, first pair coloured red and black, second pair coloured green and
orange and the third pair coloured blue and white, three pairs laid up to form a group,
aluminiummylar tape shielded with 7/0.31mm Annealed tinned copper drain wire run
continuously in contact with aluminium side of the tape, melinex tapped, PVC sheathed,
such 16 such groups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue in
colour.
64 Core (16x 4 core) PVC Data Cable (Un-Armoured)- FRLS Type
Pair of 7/0.31mm (20AWG) Annealed tinned copper conductor, insulated with
polyethylene, first pair coloured brown and grey, second pair coloured yellow and violet,
the two pairs laid up to form a group, melinex taped, mylar backed aluminium taped with
a drain wire of size 7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed,
such 16 groups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue in
colour.
32Core (16x 2 core) PVC Data Cable (Un-Armoured)- FRLS Type
Pair of 7/0.31mm (20AWG) Annealed tinned copper conductor, insulated with
polyethylene, two colour to form a pair and different colour to be selected to
differentiate the pairs of the cable, melinex taped, mylar backed aluminium taped with a
drain wire of size 7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed,
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 115
such 16 groups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue in
colour.
32Core (16x 2 core) PVC Data Cable (Armoured)- FRLS Type
Pair of 18AWG (19/0.25mm) Annealed tinned copper conductor, insulated with
polyethylene, two colour to form a pair and different colour to be selected to
differentiate the pairs of the cable, melinex taped, mylar backed aluminium taped with a
drain wire of size 7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed,
such 16 groups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue in
colour.
06Core (03x 2 core) PVC Data Cable (Armoured)- FRLS Type
pairs of 7/0.31mm (20AWG) Annealed tinned copper conductor, insulated with
polyethylene, First Pair : Red and black (Twisted), Second pair : Green and orange
(Twisted) and Third pair : Blue and White (Twisted), melinex taped, mylar backed
aluminium taped with a drain wire of size 7/0.31mm Annealed tinned copper, melinex
tapped, PVC sheathed, such 3 groups laid up, melinex tapped, overall sheathed with FRLS
PVC and Blue in colour.
04 Core (02x 2 core) PVC Data Cable (Armoured)- FRLS Type
Two pairs of 7/0.31mm (20AWG) Annealed tinned copper conductor, insulated
with polyethylene, two colour to form a pair and different colour to be selected to
differentiate the pairs of the cable, melinex taped, mylar backed aluminium taped with a
drain wire of size 7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed,
such 2 groups laid up, melinex tapped, overall sheathed with FRLS PVC and Blue in colour.
02 Core (01x 2 core) PVC Data Cable (Armoured)- FRLS Type
Two pairs of 7/0.31mm (20AWG) Annealed tinned copper conductor, insulated
with polyethylene, First Pair : Red and black (Twisted), Second pair : Green and
orange (Twisted), melinex taped, mylar backed aluminium taped with a drain wire of size
7/0.31mm Annealed tinned copper, melinex tapped, PVC sheathed, such a pair laid up,
melinex tapped, overall sheathed with FRLS PVC and Blue in colour.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 116
DETAILED SPECIFICATIONS:
1. Voltage grade : 300 V
2. Operating temperature : 0 Deg.C to 60 Deg.C
3. Conductor :
a) Material : Annealed Tinned copper as per IS:8130
b) Size of the conductor : 20AWG (7/0.31mm)
18AWG (19/0.25mm)
4. Insulation :
a) Material : solid polyethylene type-03of BS6234
b) Thickness (Nom.) : 0.40 mm
c) Pair colors :
96 Core (16x6core):
First Pair : Red and black (Twisted)
Second pair : Green and orange (Twisted)
Third pair : Blue and White (Twisted)
64 Core (16x4 core):
First pair : Brown and Grey (Twisted)
Second pair : Yellow and Violet (Twisted)
32 Core (16x2 core):
Different colour to form a different pairs
6 Core (3x2 core):
First Pair : Red and black (Twisted)
Second pair : Green and orange (Twisted)
Third pair : Blue and White (Twisted)
4Core (2x2 core):
First Pair : Red and black (Twisted)
Second pair : Green and orange (Twisted)
2Core (1x2 core):
First Pair : Red and black (Twisted)
d) No. of twists/mtr : 30 (Min)
e) Dia. over insulation (Nom.) : 1.75 mm
5. Screening over group :
a) Tapping before and after :
Thickness of melinex tape to be 0.025mm
(100% screening Coverage, min-20%
overlap)
b) Screening :
i) Material : Aluminiummylar tape
ii) Thickness : 0.044mm
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 117
iii) Coverage and overlap : 100% Coverage and 35% overlap
iv) Drain wire : 7/0.31mm Annealed tinned copper
6. Inner sheath :
a) Material : PVC type ST2 of IS:5831with FRLS
properties
b) Thickness (Nom.) : 0.65 mm
c) Color : Black
7. Outer sheath :
a) Material : PVC type ST2 of IS:5831with FRLS
properties
b) Thickness (Nom.) : 2.2 mm (96 & 64 Core)
2.0 mm (32,6,4 & 2 Core)
c) Color : Blue
8. a) Insulation elongation : 300%
b) Sheath elongation : 150%
c) Insulation T.S : 100 Kg/cm2
d) Sheath T.S : 125 Kg/cm2
9. a) Approx. overall diameter :
96 Core : 46.0 mm
64 Core : 38.0 mm
32 Core : 19.0 mm
06 Core : 10 mm
4 Core : 8 mm
2 Core : 5 mm
b) Tolerance : ± 2mm
10. Electrical parameters :
a) Conductor resistance at 20
deg.C :
20 AWG: ≤ 40.0 Ohms/Km
18 AWG: ≤ 21.5 Ohms/Km
b) Min. Insulation resistance of
finished cable at Room
Temperature
: 5000 Mohms-Km
c) Max. Mutual capacitance : 75.00 pF/m at 0.8/1.0KHz
d) Max. capacitance core to
screen at 0.8/1.0KHz : 400 pF/m
e) Max. drain wire resistance
(with screen contact) : 37 ohms/Km
f) Inductance : < 650 µH/Km
g) L/R Ratio : 20 AWG: < 25 H/ohm
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 118
18 AWG: < 40 H/ohm
h) Static noise : better than 60dB
i) Characteristic impedance
(typical) :
20 AWG: 450 ohm ± 15%
18 AWG: 350 ohms ± 15%
HV test :
i) Conductor to conductor : 1 KV for 1 minute
ii) Conductor to screen :
11. FRLS Tests :
1. Min Oxygen Index when
tested as per ASTM
D2863
: 29%
2. Min Temperature Index
when tested as per ASTM
D2863
: 250 Deg. C
3. Max Smoke Density rating
when tested as per ASTM
D2843
: 60%
4. Max Acid gas generation
when tested as per IEC
754 (I)
: 20%
5. Flammability test as per
IEEE 383,IEC 332-III
category-C and SS424
1475 CLF3
: Shall meet the requirement
12. General : Cable should be Anti-Rodent and Anti-
termite type
13. Cable mark :
a. The cable group number (1-16) shall
be printed on the cable at 0.5m
interval.
b. The cable type shall be embossed /
printed on the outer sheath at 1.0m
interval.
14. Length marking : At every meter on outer sheath.
15. Drum lengths :
i) Standard Continuous length : 96 & 64 & 32 Core: 500 meters
6, 4 & 2 Core: 1000 meters
ii) Tolerance : ±5%
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 119
Applicable only for Armoured Cables
16. Armouring
a) Material : Galvanized Steel round wire
b) Size : 1.4 mm dia
General Specifications:
1. Wherever PVC is specified virgin PVC should be used.
2. All cables should have ‘anti-rodant’ type outer sheath and should be
immune to termite attack. It is required to have these protections by
addition of chemicals to outer sheath.
3. Cable testing as stipulated in section 1 shall be conducted and necessary
conformity certificate should be supplied by the manufacturer.
4. Thermal aging test certificate to be provided by manufacturer for each type
of cable.
5. Cable should be manufactured relevant to the following standards.
a. Copper conductor : IS 8130 – 1984
b. Poly Ethylene (PE) insulation : BS 6234
c. PVC insulation : IS 5831.
d. FRLS properties : ASTM D2863, IEC 754(I),
IEC 332-III category-C and SS424 1475 CLF3
6. Proper packing material to be used during laying (manufacturing) in order
that the finished sheathed cable cross section is circular with a tolerance of
±5% of dia.
7. Cable should have proper laying to maintain circularity and tight packing
with outer sheath shall be ensured.
8. Cable drum should withstand transportation and handling.
9. The drums shall be proofed against attack by white ant or termite,
conforming to IS:10418:1982
Cable Testing
The following tests as per applicable IS/BS standard shall be conducted in the
presence of Department engineer and test certificate to be provided.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 120
a) Conductor resistance test
b) Cold bend test
c) Insulation resistance test
d) High voltage test
e) Mutual capacitance test
f) FRLS tests:
i. Min Oxygen Index test as per ASTM D2863
ii. Min Temperature Index test as per ASTM D2863
iii. Max Smoke Density rating test as per ASTM D2843
iv. Max Acid gas generation test as per IEC 754 (I)
v. Flammability test as per IEEE 383,IEC 332-III and SS424 1475 CLF3
The vendor shall provide test certificates for the above mentioned tests before dispatch.
The vendor shall dispatch the items only after the approval of test certificates by
Department.
7. CABLE TRAYS
Perforated Cable Tray:
Type : Perforated type cable tray
Material : Mild Steel As per IS: 2062 / 1079
Finish : Hot dip galvanized, Self-color.
Galvanizing : As per IS: 2629 / 4759
Length : Standard length of tray is 2500 / 3000mm
Loading : As per NEMA standard
Size : As per table 6
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 121
Table 6
WIDTH (mm) HEIGHT (mm) THICK (mm)
50 12 1.6
100 25 2.0
150 25 2.0
300 50 2.0
Note: Accessories like cross, Vertical bend, Reducer, Horizontal Tee, Coupler plates, necessary
Bolts & Nuts to be quoted as 1 lot.
Ladder type Cable Tray:
Type : Ladder
Material : Mild Steel As per IS: 2062 / 1079
Finish : Hot dip galvanized, Self-color.
Galvanizing : As per IS: 2629 / 4759
Length : Standard length of tray is 2500 / 3000mm
Rung Spacing : 250 mm
Loading : As per NEMA standard
WIDTH (mm) HEIGHT (mm) THICK (mm)
300 75 2
600 75 2
Operating temperature : 60 °C maximum
Humidity : Up to 95% RH
Note: Accessories like cross, Vertical bend, Reducer, Horizontal Tee, Coupler plates, necessary
Bolts & Nuts to be quoted as 1 lot.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 122
8. STRUCTURAL STEEL MATERIALS
1. Material : Structural steel includes steel sections, L
angles, Plates, steel pipes chequered & Plain
plates
2. Material Governing
standard
: IS 2062 (GRADE-A)
3. Dimensions governing
standard
: IS 808 & IS 1161
4. Certificates : Test certificates showing heat number, physical
and chemical properties of the items in
conformance to relevant standard shall be
sent along with dispatch documents.
9. CANOPY
1. Material : CRCA steel with RAL7035 light grey colour
powder coating
2. Thickness : 2mm
10. INSTRUMENTATION RACK
1. Size : Height - 42U
Width - 600 mm & 1200mm (requ. as per table-B)
Length- 800 mm
Standard : Conforms to DIN 41494 & EIA 310
2. Frame : Steel profiles
Vertical : 4 Nos -45 W x 70Lx 2000 H (mm)
Horizontal : Top 4 Nos & Bottom 4 Nos.
Front & Rear : 510W x 45H x 25L (mm)
Side : 25 W x 45H x 60L(mm)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 123
conforms to the specification of 7604 & 7588 IS -1285-1975
3. Steel frame along with side, top and bottom panels in steel.
4. Lockable front door made of toughened tinted glass of 5 mm Thick. Steel frame of
18 Gauge CRCA sheet.
5. Rear steel door to be provided with a lock facility made of 18 Gauge CRCA sheet
and to comply the specifications of IS-513-CRCA.
6. Side panels with slam latches vented top cover made of 18 Gauge CRCA sheet.
7. Cross support to be made up of 14 Gauge CRCA sheet comply the specifications in
IS-513- CRCA.
8. 100 mm Height Base Frame 600*800 mm for additional clearance for cable entry.
9. Base frame to be made up of 13 Gauge CRCA sheet and to comply the
specifications in IS-513-CRCA.
10. Equipment mounting channels made of 14 Gauge CRCA sheet and to comply the
specifications in IS 513 – CRCA.
11. Each rack should have 05 set of Equipment support angles to be made of 14
Gauge CRCA sheet as specified in IS-513-CRCA.
12. Bottom panel with cable gland plate for cable entry.
13. Maximum Load rating of 500 kg.
14. Cross ventilation to be done with 4 fan tray made of 14 Gauge CRCA sheet at
bottom with 10 micron filters.
15. Two sets of fan trays (in a group of 4 fans per set) to be provided for each rack.
16. Cooling fans to be provided at rear door top with ventilation holes.
17. Earthing continuity kit to be provided.
18. Two No of AC mains distribution board with 5 Nos of 5A socket (Horizontal
mounting to be provided).
19. Front and rear holed profiles (inter hole distance of 1U) for mounting equipment
supports to be provided. 2 Nos on the front side and 2Nos on the rear side.
20. Vertical cable tray to be made up of polymide with black colour cover to be
provided.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 124
21. Internal lighting to be provided with On/Off switch.
22. Side panels, Top & Bottom panels and doors to be powder coated with Light grey
EPOXY/Anti flame property specified in RAL 7035.
23. Frame to be made of Aluminium extrusions powder coated specified in RAL 7037
Dark Grey.
2. Accessories
1. Powder coated Support angles (14 Gauge CRCA
sheet)
Required qty. to be
supplied
2. Powder coated filler plates
3. - 1U Required qty. to be
supplied
4. - 2U Required qty. to be
supplied
5. - 3U Required qty. to be
supplied
6. - 4U Required qty. to be
supplied
7. - 5U Required qty. to be
supplied
8. - 6U Required qty. to be
supplied
9. Keyboard tray 10
10. 19” rack mountable polyamide cable manager with
cover(black colour)
Required qty. to be
supplied
11. Fasteners (Captive mounting hardware) 1500 (As 100No per
pack/rack)
Tests to be done
Powder coating As per Standard OS -02
Phosphate conversion coating As per IS 3618
Chromate conversion coating As per IS 11232
Salt spray test ASTM B 117 creepage should be less than
1/16th
after 100 hrs.
For corrosion protection Electroplating of zinc over steel plates to
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 125
be done as per IS 1573-1970
Corrosion Resistant Humidity test as per IS 101 R/T of 100%
and temperature cycle of 42-48 °C.
Non-yellowing properties No yellowing to occur after 200 hrs of
exposure to ammonium carbonate
Adhesion As per ASTM D3359
No blistering after 1. 2% H2 SO4 for 8 hrs.
2. 2% NaOH for 8 hrs.
3. 5% detergent solutions for 8 hrs.
4. In boiling water for 24 hrs.
Scratch test on rack To be done
Note:
The vendor has to provide the test certificates for the above tests before dispatch. The
items shall be delivered to Department only after the acceptance of test certificates.
11. SPECIFICATIONS OF TRANSFORMER ISOLATED BARRIERS
TIB FOR PRESSURE AND TEMPERATURE TRANSMITTER BASED MEASUREMENTS
Type : Transformer Isolated Barrier (Dual output)
HART communication interface possible
through both 4-20 mA outputs.
1. Input (Intrinsically Safe)
Input signal : 4 - 20 mA
Voltage at 20 mA : 16V min
2. Outputs (Not Intrinsically Safe)
Output voltage : 2-10V
Number of outputs : 2
Output resistance : 500 ohms
Ripple : <25mV
3. Power Supply:
Supply voltage : 20V- 35V DC
Power consumption : < 2.5 W
Connection type : Power rail and terminal
4. Details of certificate of conformity Group, Category, ignition protection Method:
: ATEX II 2 G EExia IIC T6
Voltage (Uo) : 25.4 VDC
Current (Io) : 86.8 mA
5. Transfer Characteristics
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 126
Transfer error : <10mV including calibration, linearity
hysteresis, supply and load variations
Temperature drift : 20 ppm/K
Frequency range (-3dB) : 0Hz-7.5 KHz
6. Galvanic Isolation Between
: Input & Output.
: Input & Power supply
: Output & Power supply.
7. General
Operating temperature : 15°C to 60°C
Power supply feed provision : Through power rails/Back plane
Mounting : DIN rail (35 mm)
II. TIB FOR CONTROL VALVE
1.Input (not intrinsically safe)
Connection type : Terminals
Current range : 4 - 20 mA
Max. Current input : 40 mA
2.Output (intrinsically safe)
Connection type : Terminals
Current output : 4…20 mA
Output load : <850 ohm
3.Power supply
Connection type : Power rail and terminal
Rated operational voltage : 20…35 VDC
4. Details of certificate of conformity Group, Category, ignition protection Method
: ATEX II 2 G EExia IIC T6
Voltage (Uo) : 25.2 VDC
Current (Io) : 93 mA
5. Transfer characteristics
Error : <0.1 % incl. non-linearity and hysteresis
Temperature : <0.01%/K
Rise time : < 10second
6. Galvanic Isolation Between
: Input & Output.
: Input & Power supply
: Output & Power supply.
7. General
Operating temperature : 15°C to 60°C
Power supply feed provision : Through power rails/Back plane
Mounting : DIN rail (35mm)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 127
III. TIB FOR E/P VALVE STATUS
1. Input
Type : Proximity/Relay.
No. of channel : 2
Reverse mode : To be provided
LED indication : Relay output & power supply
Connections Type : Terminals
Lead monitoring input current : <0.1 mA
2. Output (not intrinsically safe)
Connection type : Terminals
Output : signal; relay (4 ch. isolated o/p)
Minimum switching current : 2 mA/24V DC
Energized/De-energized delay : approx. 20 ms / approx. 20 ms
Mechanical Life : 10^7 switching cycles
3. Power supply
Connection type : Power rail and terminals
Rated operational voltage : 20…30 VDC
4. Details of certificate of conformity Group, Category, ignition protection Method
: ATEX II 2 G EExia IIC T6
Voltage (Uo) : 10.5 V
Current (Io) : 13 mA
5. Transfer characteristics
Switching frequency : 10 Hz
6. Galvanic Isolation Between
: Input & Output.
: Input & Power supply
: Output & Power supply.
7. General
Operating temperature : 15°C to 60°C
Power supply feed provision : Through power rails/Back plane
Mounting : DIN rail (35mm)
ZENER BARRIER FOR TRANSDUCER EXCITATION
Parameter Specification
Working voltage at 10 µA (V) <14V
Max.series resistance <29Ω
Fuse rating <160mA
Max. Supply Voltage <15 V
Leakage current <10µA
Ambient temperature 15° C to 60°C
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 128
Connection Self –opening connection terminals max
core cross- section 2x2.5 sq.mm
Mounting Mounting on 35mm DIN rail acc. To DIN
EN 60715
Hazardous Area certificate ATEX II 2 G EEx ia IIC T6
ZENER BARRIER FOR TRANSDUCER SENSE
Parameter Specification
Working voltage at 10 µA (V) 13V
Max.series resistance <380 Ω
Fuse rating <100 mA
Max. Supply Voltage <13.6 V
Leakage current <10µA
Ambient temperature 15° C to 50°C
Connection Self –opening connection
terminals max core cross-
section 2x2.5 sq.mm
Mounting Mounting on 35mm DIN rail acc. To
DIN EN 60715
Hazardous Area certificate ATEX II 2 G EEx ia IIC T6
ZENER BARRIER FOR TRANSDUCER OUTPUT
Parameter Specification
Working voltage at 10 µA (V) 6.8V
Max.series resistance <380 Ω
Fuse rating <100 mA
Max. Supply Voltage <8.1 V
Leakage current <10µA
Ambient temperature -20° C to 60°C
Connection Self –opening connection terminals max
core cross section 2x2.5 sq.mm
Mounting Mounting on 35mm DIN rail Required
Quantity of DIN Rail is to be provided.
Hazardous Area Certification ATEX II 2 G EEx ia IIC T6
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 129
ACCESSORIES
The party shall quote for all required accessories such as power rails, power feed
modules, Din rail, mounting kit, Backplane etc. as a single lot.
12. ZENER BARRIER FOR RTD (EXCITATION & SENSE)
Parameter Specification
Working voltage at 10 µA (V) <7V
Max.series resistance <110 Ω
Fuse rating 100 mA
Max. Supply Voltage 11 V
Ambient temperature 15° C to 50°C
Connection Self –opening connection
terminals max core cross-
section 2x2.5 sq.mm
Mounting Mounting on 35mm DIN rail. Necessary qty
of rails are to be supplied.
Hazardous Area Certification ATEX II 2 G EEx ia IIC
13. PULSE ISOLATOR
Function
(1) It should isolate pulses from a switch, proximity
detector, current pulse transmitter located in a hazardous
area.
(2) To power Pre Amplifier
Number of channels One.
Safe area output
Maximum Off- state values V=35V, I=10µA
Maximum On- state current 50mA
Hazardous-area input
Switch Output- on (off) if switch closed (open)
Proximity detector Meets NAMUR and DIN 19234 standards
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 130
Pulse (I) Supply 16.5v dc at 20 mA, shortcut current 24mA Out on
(off) >8.9mA (6.8mA)
Pulse (V) Input impedance >10kΩ
Switching point
voltage(Vsp)
3,6 or 12V (selectable) Output
on (off) if input >1.2* Vsp (<0.8* Vsp)
Switching hysteresis 0.11* Vsp typical
Pulse width
High 10µs minimum
Low 10µs minimum
Frequency range 0-50 KHz
LED indicators To be provided
Supply voltage 20-35V dc
Maximum current
consumption 65mA at 24V dc
Maximum power
dissipation within unit 1.35W at 24V
14. Specification of flow Signal Conditioner
Measuring method : Flow/ Speed measurement by period mode.
I. Input
a. Type : TTL pulses
b. Frequency range : 10Hz - 3000 Hz (Configurable through Front
panel keys).
II. Pre amplifier powering
:
Flow signal conditioner unit to provide a
24VDC, 50 m A, short circuit protected output
to power the flow preamplifier.
III. Output :
a. Analog output : 0 – 5V/ 0 – 10V (Selectable through front
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 131
b. Averaging
:
Analog output posted by the algorithm
should be an average of number of samples
as defined below:
10 Hz to120 Hz - 1 sample (minimum)
120 Hz to 600 Hz - 2 samples (minimum)
600 Hz to 3000 Hz – 5 samples (minimum)
c. Pulse output :
TTL, Output frequency equal to input
frequency.
d. Accuracy (Analog O/P) : ±0.05 % of FS
e. O/P impedance : ≤ 10 ohms
f. Response time
:
≤ 20 m sec for frequency range 120 Hz- 3000
Hz.
≤ 20 m sec + one period of the input for
frequency range 10 Hz- 120 Hz. IV. Display :
Separate display for Rate & Total to be
provided.
1. Totaliser
a. Display type : 8 digits
b. Resolution Configurable up to 3 decimal places
2. Rate display
a. Display type : 5 digits
b. Resolution : Configurable up to four decimal places.
c. Display Accuracy : ±0.1 % of FS
3. Display update rate Configurable from 0 .2 sec
V. Programming features
a. K factor (Configurable through
front panel keys). :
b. Analog Output. (Voltage
selectable through front panel
keys).
:
VI. Power supply :
230 V AC , 50 Hz
Mounting : Panel mounting with accessories
VII. Environment Specification
Operating temperature :
0-50 deg. C.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 132
Humidity :
95 % RH
15. SPECIFICATION FOR ELECTROMECHANICAL RELAY
Technical data:
Coil side:
Nominal i/p voltage : 24 VDC
Nominal i/p current : 18 mA
Typical response time : 8 ms
Typical release time : 10 ms
Protective circuit : Reverse polarity diode and freewheeling
Diode provision.
Contact side:
Contact type : 2-PDT
Contact material : AgNi
Maximum switching voltage : 250VAC/DC
Minimum switching voltage : 5VAC/DC (at 10 mA)
Minimum switching current : 10 mA
Limiting continuous current : 6 A
Interrupting rating max : 140 W (at 24 VDC)
General data:
Test voltage relay winding/relay contact : 4 KVAC (50 Hz, 1min)
Test voltage PDT/PDT : 2.5 KVAC(50 Hz, 1min)
Operating temperature : -400C to 60
0C
Mechanical life service : 3*107
cycles
Standards/Regulations : IEC 60664, EN 50178, IEC 62103
Connection data:
Connection method : Screw connection
Conductor cross section solid max : 2.5 mm2
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 133
Part No: PLC-RSC- 24 VDC/ 21-21-2967060
16. Hall Effect Sensor for Current Measurement with Mounting PCB
CURRENT TRANSDUCER
Measuring Range : I : 0 to 10A
II : 0 to 20A
Output voltage : 0 to 4V
Output impedance : < 50 Ω
Load resistance : ≥10 kΩ
Supply voltage : ± 15 V
Accuracy : ≤1 %
Response time : 3 μs
Ambient operating temperature : 0 to + 85 °C ・
Make : LEM
Current Sensor cards
35 mm din rail mountable current sensor cards.
Separate set of Input / Output & Power TBs of phoenix make are to be provided.
Fabricated on the PCB along with Identification Tags.
Din rail mount card holder to be provided.
LEDs should be provided for supply indication.
8/16 Nos of Hall sensors shall be mounted in PCB and shall have input, Output and
power supply connectors.
17. Signal Isolator
Sl. No. Technical specification
1 Type of input : Voltage input (±10V)
2 No. of input : One
3 Input Impedance : >100K・
4 Type of Output : Voltage output (±10V)
5 Output Resistance : <100・
6 No of outputs : 2 (with short circuit protection)
7 Isolation : 300V continuous
Between input and outputs
Between outputs
Between power supply and outputs
8 Power supply : 24V DC
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 134
9 Transfer Accuracy : ±0.1% FSO
10 Temperature Drift : ±0.005 % FSO per °C
11 Stability : ±0.1% FSO for 8hrs.
12 Ripple : ≤ 2mVpp
13 Response time : 1ms
14 Housing : ABS
15 Operating temperature : 20°C to 55°C
16 Humidity : 0 to 95% non condensing
17 Electromagnetic
Compatibility
: EN 61000-6-4:2007
18 Protection Class According
to IEC 529/EN 60 529
Housing IP40
Terminals IP20
19 Mounting : DIN rail ; 35mm
18. Technical Specifications for Redundant SMPS Power Supply
Dual Regulated SMPS DC Power Supplies. One unit should have two isolated
independent power supplies assembled in a Rack mount chassis. Output of the two
power supplies to be Diode ‘OR’ed to provide redundancy. The output terminals of both
power supplies shall be provided on the front panel and redundant mode is enabled by
connecting external links. The high current ‘OR’ing diode and heat sink shall be fitted in
the power supply chassis.
SPECIFICATION OF SMPS POWER SUPPLIES (24V±20%, 20A)
Input
Input voltage range 85V - 264V AC Single Phase
Frequency range , AC 47...63 Hz
Input fuse (internal) Yes
Conductor connection system Screw connection
Output
Rated output voltage 24 V DC ± 20 %
Output voltage range 18.24 V - 29.76 V (adjustable via a
potentiometer on front)
Rated (nominal) output current @ V rated 20 A @ 60 °C
Output current 20 A
Conductor connection system Screw connection
Indications Mains by neon lamp.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 135
CV mode and CC / CL mode by LEDs
on front panel.
Metering 3 ½ digit panel meters for output
voltage and current measurements.
Controls
Input ON / OFF Switch.
Voltage and current controls (coarse
& fine for voltage and current limit)
Terminations
Input by 3 core 1.5 mtr. Long mains
cord of appropriate rating.
Output by binding post terminals.
General data
Residual ripple, switching peaks ≤100 mV
Efficiency >85%
Overload protection Yes
Load Regulation 200mV
Line Regulation 150mV
Indication LED
Mounting position Horizontal DIN Rail Mountable in
19” Instrumentation Rack
Protection against reverse voltages from the
load
To be provided
Current limiting > 120 % IN
Approvals CE, UL or CSA
Operating temperature -25 °C...+70 °C
Warranty 1 year
SPECIFICATION OF SMPS POWER SUPPLIES (24V±10%, 10A)
Input
Input voltage range 85V - 264V AC Single Phase
Frequency range , AC 47...63 Hz
Input fuse (internal) Yes
Conductor connection system Screw connection
Output
Rated output voltage 24 V DC ± 10 %
Output voltage range 21.60 V - 26.40 V (adjustable via a
potentiometer on front)
Rated (nominal) output current @ V rated 10 A @ 60 °C
Output current 10 A
Conductor connection system Screw connection
Indications Mains by neon lamp.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 136
CV mode and CC / CL mode by LEDs
on front panel.
Metering 3 ½ digit panel meters for output
voltage and current measurements.
Controls
Input ON / OFF Switch.
Voltage and current controls (coarse
& fine for voltage and current limit)
Terminations
Input by 3 core 1.5 mtr. Long mains
cord of appropriate rating.
Output by binding post terminals.
General data
Residual ripple, switching peaks ≤100 mV
Efficiency >85%
Overload protection Yes
Load Regulation 200mV
Line Regulation 150mV
Indication LED
Mounting position Horizontal DIN Rail Mountable in 19”
Instrumentation Rack
Protection against reverse voltages from the
load
To be provided
Current limiting > 120 % IN
Approvals CE, UL or CSA
Operating temperature -25 °C...+70 °C
Warranty 1 year
SPECIFICATION OF SMPS POWER SUPPLIES (0-72 V, 10A)
Input
Input voltage range 85V - 264V AC Single Phase
Frequency range , AC 47...63 Hz
Input fuse (internal) Yes
Conductor connection system Screw connection
Output
Rated output voltage 0-72 V DC
Output voltage range 0 V - 72 V (adjustable via a
potentiometer on front)
Rated (nominal) output current @ V rated 10 A @ 60 °C
Output current 10 A
Conductor connection system Screw connection
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 137
General data
Residual ripple, switching peaks ≤100 mV
Efficiency >85%
Overload protection Yes
Load Regulation 200mV
Line Regulation 150mV
Indication LED
Mounting position Horizontal DIN Rail Mountable in
19” Instrumentation Rack
Protection against reverse voltages from
the load
To be provided
Current limiting > 120 % IN
Approvals CE, UL or CSA
Operating temperature -25 °C...+70 °C
Warranty 1 year
SPECIFICATION OF SMPS POWER SUPPLIES (0-100 V, 10A)
Input
Input voltage range 85V - 264V AC Single Phase
Frequency range , AC 47...63 Hz
Input fuse (internal) Yes
Conductor connection system Screw connection
Output
Rated output voltage 0-100 V DC
Output voltage range 0 V - 100 V (adjustable via
potentiometer on front)
Rated (nominal) output current @ V rated 10 A @ 60 °C
Output current 10 A
Conductor connection system Screw connection
General data
Residual ripple, switching peaks ≤100 mV
Efficiency >85%
Overload protection Yes
Load Regulation 200mV
Line Regulation 150mV
Indication LED
Mounting position Horizontal DIN Rail Mountable in
19” Instrumentation Rack
Protection against reverse voltages from
the load
To be provided
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 138
Current limiting > 120 % IN
Approvals CE, UL or CSA
Operating temperature -25 °C...+70 °C
Warranty 1 year
SPECIFICATION OF REGULATED LINEAR POWER SUPPLIES (24V±10%,10A)
Sl.No Description
1 Item
Single regulated linear DC power supply. One unit
should have one independent power supply
assembled in a 19 inch rack mount chassis. Output
of the power supply shall be taken out through 25A
metal diode. The voltage output terminals of
power supply shall be provided on the front panel.
The heat sink shall be fitted in the power supply
chassis at rear.
2 Input supply 230V AC, ±10%, 1φ, 50 Hz
3 Output Voltage 24V±10%
4 Output Current 0-10A DC
5 Line Regulation ±0.05% (for 10% change in supply voltage OR
better)
6 Load Regulation ±0.05% from no load to full load
7 Ripple & Noise <5mV RMS
8 Output impedance ≤0.05Ω
9 Output polarity Floating with respect to ground
10 Over voltage protection Crow-bar protection acting at approximately 36V
11 Current limit (overload)
Constant current fold back type protection having
automatic crossover characteristics settable from
10% to 110% max rated current by front panel
controls.
12 Display Independent digital panel meters for voltage and
current monitoring
13 Meter accuracy ±3 counts
14 stability ≤0.2% for eight hour after warming up
15 Remote sensing
provision Required
16 Safety isolation 1500V AC RMS for 1 minute
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 139
17 Transient recovery time ≤100µsec
18 Indications
1. Mains by neon lamp.
2. CV mode and CC / CL mode by LEDs on front
panel.
19 Metering 3 ½ digit panel meters for output voltage and
current measurements.
20 Controls
1. Input ON / OFF Switch.
2. Voltage and current controls (coarse & fine for
voltage and current limit)
21 Terminations
1. Input by 3 core 1.5 mtr. Long mains cord of
appropriate rating.
2. Output by binding post terminals.
22 Mounting provision 19” rack mountable
SPECIFICATION OF REGULATED LINEAR POWER SUPPLIES (±15V)
Sl.No Description
1 Item
Single regulated linear DC power supply. One unit
should have one independent power supply
assembled in a 19 inch rack mount chassis. Output
of the power supply shall be taken out through 25A
metal diode. The voltage output terminals of
power supply shall be provided on the front panel.
The heat sink shall be fitted in the power supply
chassis at rear.
2 Input supply 230V AC, ±10%, 1φ, 50 Hz
3 Output Voltage ±15V DC
4 Output Current 0-5A DC
5 Line Regulation ±0.05% (for 10% change in supply voltage OR
better)
6 Load Regulation ±0.05% from no load to full load
7 Ripple & Noise <5mV RMS
8 Output impedance ≤0.05Ω
9 Output polarity Floating with respect to ground
10 Over voltage protection Crow-bar protection acting at approximately 36V
11 Current limit (overload)
Constant current fold back type protection having
automatic crossover characteristics settable from
10% to 110% max rated current by front panel
controls.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 140
12 Display Independent digital panel meters for voltage and
current monitoring
13 Meter accuracy ±3 counts
14 stability ≤0.2% for eight hour after warming up
15 Remote sensing
provision Required
16 Safety isolation 1500V AC RMS for 1 minute
17 Transient recovery time ≤100µsec
18 Indications Mains by neon lamp.
CV mode and CC / CL mode by LEDs on front panel.
19 Metering 3 ½ digit panel meters for output voltage and
current measurements.
20 Controls
Input ON / OFF Switch.
Voltage and current controls (coarse & fine for
voltage and current limit)
21 Terminations
Input by 3 core 1.5 mtr. Long mains cord of
appropriate rating.
Output by binding post terminals.
22 Mounting provision 19” rack mountable
19. SPECIFICATION OF TEFFLON CABLES
1. 18 AWG SINGLE CORE WIRES
Inner conductor : Multi Stranded silver plated copper wire of
size AWG 18
Standard : MIL-W-16878 (or) JSS 51034
Core insulation : PTFE tape wrapped and fused
Insulation thickness : 0.25± 0.05 mm
Conductor dia (Nominal) : 1.27± 0.03 mm
Diameter of core including
insulation
: 1.87 ± 0.1 mm
Color : Red, Black, Green, White
Max. Resistance of the conductor
at 20 O
C
: 18.99Ω/Km
Roll : 100m ± 10%continuous per drum
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 141
23. 22 AWG SINGLE CORE WIRES
Inner conductor : Multi Stranded silver plated copper wire of size
AWG 22
Standard : MIL-W-16878 (or) JSS 5034
Core insulation : PTFE tape wrapped and fused
Insulation thickness : 0.50± 0.05 mm
Conductor dia (Nominal) : 0.80± 0.03 mm
Diameter of core
including insulation
: 1.30± 0.1 mm
Color : Red, Black, Green, White, Violet, Yellow
Max. Resistance of the
conductor at 20 O C
: 40Ω/Km
Packing length : 100m ± 10%continuous per drum
3. 24 AWG SINGLE CORE WIRES
Inner conductor : Multi Stranded silver plated copper wire of size
AWG 24
Standard : MIL-W-16878 (or) JSS 5034
Core insulation : PTFE tape wrapped and fused
Insulation thickness : 0.50± 0.05 mm
Conductor dia (Nominal) : 0.6± 0.03 mm
Diameter of core
including insulation
: 1.1± 0.1 mm
Color : Red, Black, Green, White, Violet, Yellow
Max. Resistance of the
conductor at 20 O C
: 48Ω/Km
Packing length : 100m ± 10%continuous per drum
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 142
20. SPECIFICATION OF PTFE CABLES
20AWG 6 CORE PTFE CABLE
Description
: PTFE insulated silver plated copper wire Size:
AWG 20/19/0.2mm, each core insulated and Pair
twisted, each pair laid in circular construction,
PTFE sheathed and 03 such pairs laid in circular
construction and overall shielded and PTFE
jacketed.
1. Inner conductor
:
Stranded silver plated copper wire of size AWG
20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 ± 0.05 mm
b) Core diameter : 1.57 ± 0.1 mm
3. No. of cores : Two cores twisted into pair with a twisted lay
of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Pair 1 : Red – Black.
Pair 2 : Green – Orange.
Pair 3 : Blue – White.
6. Max resistance of the
conductor at 20O
C
: 32.8 Ω/Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 ± 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19± 5 mm
11.Packing Length : 250mts ± 10% continuous
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 143
20AWG 32 CORE PTFE CABLE
Description
: PTFE insulated silver plated copper wire Size:
AWG 20/19/0.2mm, each core insulated and Pair
twisted, each pair laid in circular construction,
PTFE sheathed and 16 such pairs laid in circular
construction and overall shielded and PTFE
jacketed.
1. Inner conductor
:
Stranded silver plated copper wire of size AWG
20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 ± 0.05 mm
b) Core diameter : 1.57 ± 0.1 mm
3. No. of cores : Two cores twisted into pair with a twisted lay
of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Different colours to form a pairs
6. Max resistance of the
conductor at 20O
C
: 32.8 Ω/Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 ± 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19± 5 mm
11.Packing Length : 250mts ± 10% continuous
20AWG 32 CORE PTFE CABLE
Description
: PTFE insulated silver plated copper wire Size:
AWG 20/19/0.2mm, each core insulated and Pair
twisted, each pair laid in circular construction,
PTFE sheathed and 16 such pairs laid in circular
construction and overall shielded and PTFE
jacketed.
1. Inner conductor
:
Stranded silver plated copper wire of size AWG
20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 ± 0.05 mm
b) Core diameter : 1.57 ± 0.1 mm
3. No. of cores : Two cores twisted into pair with a twisted lay
of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Different colours to form a pairs
6. Max resistance of the
conductor at 20O
C
: 32.8 Ω/Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 ± 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19± 5 mm
11.Packing Length : 250mts ± 10% continuous
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 144
20AWG 64 CORE PTFE CABLE
Description
: PTFE insulated silver plated copper wire Size:
AWG 20/19/0.2mm, each core insulated and Pair
twisted, each pair laid in circular construction,
PTFE sheathed and 32 such pairs laid in circular
construction and overall shielded and PTFE
jacketed.
1. Inner conductor
:
Stranded silver plated copper wire of size AWG
20/19/0.2mm
2. Core Insulation : PTFE tape wrapped and fused
a) Insulation thickness : 0.25 ± 0.05 mm
b) Core diameter : 1.57 ± 0.1 mm
3. No. of cores : Two cores twisted into pair with a twisted lay
of 25 mm.
4. No of twists per meter : 40
5. Colour coding : Different colours to form a pairs
6. Max resistance of the
conductor at 20O
C
: 32.8 Ω/Km
7. Max capacitance : ≤75 pF/m
8. Shield : Silver copper braid.
a) Shield Gauge dia : 0.12 mm
b) Coverage : > 90%
9. Overall & individual Sheath : PTFE tape wrapped and fused
a) Sheath thickness : 0.35 ± 0.05 mm
b) Colour : Grey
10. Overall dia. of the cable : 19± 5 mm
11.Packing Length : 250mts ± 10% continuous
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 145
TEST DETAILS ON EACH OF THE ABOVE MENTIONED CABLES AS PER JSS: 51034
STANDARDS
The following tests are required to be carried out at manufacturer’s site.
NAME OF THE TEST EXPECTED REQUIREMENT
1. Dimensional check : As per standard
2. Concentricity of Insulation : Greater than 70%
3. Spark test : 3.4 kV for 1 sec
4. Conductor Resistance : As per standard
5. Dielectric withstanding voltage : 2.0kV for 1 minute
6. Insulation Resistance : 1500MΩ/km.Min
7. Silver coating thickness
over conductor : 1 micron Min
8. Conductor Elongation : 10% Min
9. Insulation tensile strength : 21× 106 N/m
2 Min
10. Insulation Elongation : Greater than150% Min
11. Cold Bend : -65° C for 4 Hours
12. Heat resistance : 290°C for 96 Hours
13. Wrap Back (307°C for 2 Hours) : No cracks. No dielectric
breakdown.
14. Flammability : i) Wire shall cease to burn less than 10 sec.
ii) Total length burnt or Charred not exceed 75 mm
ON FINISHED CABLE
1. Shielded coverage : 90%
2. Dielectric withstanding voltage between core and shield: 2 kV for 1 minute
Note:
1. The vendor shall provide sample piece during detailed engineering from the
manufacturer.
2. The tests shall be carried out in the presence of Department Engineer.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 146
3. The vendor shall provide test certificate before dispatch of items. The vendor shall
dispatch the item only after clearance of test certificates by Department.
21. SPECIFICATION OF POWER CABLE (2.5 mm2)
Type : PVC Insulated and PVC sheathed, flexible three core multi
stranded copper cable
Voltage grade : 1.1kV
Size of conductor : 2.5 mm2
Current rating : 16A
No of cores : Three (Red, Black and Green)
Conforming standard : IS/IEC standards
SPECIFICATION OF POWER CABLE (1.5mm2)
Type : PVC Insulated and PVC sheathed, flexible three core multi
stranded copper cable
Voltage grade : 1.1kV
Size of conductor : 1.5 mm2
Current rating : 06A
No of cores : Three (Red, Black and Green)
Conforming standard : IS/IEC standards
22. SPECIFICATION OF EARTHING CABLES
Inner conductor : Multi Stranded copper wire size of 2.5mm2 &
4 mm2
Insulation : PVC
Colour : Green
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 147
23. Industrial Standard Multi pin connector Specification
Male and Female Contacts
Type : Crimp
Contact Material : Copper alloy-hard gold plated Au
over NiGold plating thickness: 0.8 μm (Min) Ni
thickness: 2 μm (Min)
Contact size : 18 AWG and 20 AWG
Working Current : 10 A
Working voltage : 600 V
Insulation resistance : ≥ 100 M ohm
Contact resistance : ≤ 4 milli Ohm
Crimp connection
- Stripping length : 8.0 mm
Inserts:
No. of Poles : 108
Rated Voltage to UL/CSA : 600 V
Rated current : 10 A
Rated impulse withstand voltage : 4 kV
Pollution severity : 3 (Conductive pollution, or dry, non-
conductive pollution that is liable to be
rendered conductive thru condensation)
Insulation resistance : ≥ 1010
ohm
Material : Glass fiber reinforced Poly
Carbonate
Temperature Range : -40 oC …. +125
oC
Flammability to UL 94 : V 0
Mechanical service life : ≥ 500 mating cycles
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 148
Hoods
Materials : Die-Cast Aluminium
Surface : Powder coated RAL 7037(Grey)
Flammability to UL 94 : V 0
Cable entry : Bottom/Top
Cable entry dia. : M32
Protection : IP65
Base Housing (bulk head)
Material : Die-Cast Aluminium
Surface : Powder coated RAL 7037(Grey)
Flammability to UL 94 : V 0
Locking Mechanism : Double latch
Locking material : Stainless Steel
Cable entry dia : M32
Protection : IP65
Standards & Certifications
1. Certification : UL, CSA or equivlent
2. Standard : DIN EN 60 664.1
DIN EN 61 984
Cable Entry Gland
1. With suitable cable gland/clamp with strain relief features
2. Material/Colour : Polyamide 6/RAL 7035
3. Temperature range : -20°C….80°C
4. Class of protection : IP 65
5. The thread shall suit to the cable entry points at the Hood and Housing.
Sealing Plug
1. Material/Colour : Polyamide 6/RAL 7035
2. Temperature range : -20°C….80°C
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 149
3. Size : M32
4. The thread shall suit to the cable entry points at the Hood and Housing
24. SPECIFICATION FOR MINIATURE K- TYPE THERMOCOUPLE CONNECTOR
S.NO DESCRIPTION
1 Type
1. K –Type ( Chromel – Alumel)
2. Plug and Socket
2 Temperature Rating 2000C
3 Size
Plug: 16 X 20 X 8 mm
Socket:16 X 27 X 8 mm
4 Body Colour Yellow
5 Body Material Thermoplastic compound
6 Construction
Heavy duty with wire locking
provision
7 Polarity of Pins
To be marked and reverse polarity
protection to be provided
25. Specification of single pair Thermocouple Extension cable- Type “K”
This is standard conductor, twisted pair thermocouple extension cable with outer
PTFE jacket for Chromel / Alumel thermocouple having EMF / Temperature characteristics
as per ANSI MC 96.1 – Type”K”
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 150
Sl.No Description
1 Conductor material
1. Positive Element : Chromel (Size : 7/36
SWG)
2. Negative Element : Alumel (Size : 7/36 SWG)
2 EMF characteristics As per ANSI MC 96.1-Type”K”
3 Gauge of conductor
Stranded conductors of 7 strands each of 36
SWG
4 Conductor insulation
Teflon (PTFE) tape wrapped on individual
conductor and sintered of 10mils nominal wall
thickness
5 Number of pair Single pair
6 Outer jacket sintered
2 wraps of Teflon tape wrapped overall and
forming twin pair cable. a braid of fiberglass
yarn is applied under the outer PTFE jacket to
make the cable cross section round
7 Cable OD 3mm approx.
8 Temperature Rating Up to 2600C max.
9 Color coding
1. Positive Element : Chromel (Yellow)
2. Negative Element : Alumel (Red)
3. Outer jacket : Yellow
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 151
26. Specification of 32 Core (16 pair) Thermocouple Extension cable- Type “K”
This is standard conductor, twisted pair thermocouple extension cable with outer
PTFE jacket for Chromel / Alumel thermocouple having EMF / Temperature characteristics
as per ANSI MC 96.1 – Type”K”
Sl.No Description
1 Conductor material
1. Positive Element : Chromel (Size : 7/36
SWG)
2. Negative Element : Alumel (Size : 7/36
SWG)
2 EMF characteristics As per ANSI MC 96.1-Type”K”
3 Gauge of conductor
Stranded conductors of 7 strands each of 36
SWG
4 Conductor insulation
Teflon (PTFE) tape wrapped on individual
conductor and sintered of 10mils nominal wall
thickness
5 Number of pair 16 pair
6 Outer jacket sintered
2 wraps of Teflon tape wrapped overall and
forming twin pair cable. a braid of fiberglass
yarn is applied under the outer PTFE jacket to
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 152
make the cable cross section round
7 Cable OD 12mm approx.
8 Temperature Rating Up to 2600C max.
9 Color coding
1. Positive Element : Chromel (Yellow)
2. Negative Element : Alumel (Red)
3. Outer jacket : Yellow
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 153
27. SPECIFICATION OF PROXIMITY SENSORS
28. SPECIFICATION OF TERMINAL BLOCKS
Type : Cage Clamp
Insulating material : Polyamide 6.6
Contact material : Tinned Copper
Size of the wire : 12-22 AWG
Colour : Grey
Cable entry : Front,Top
Current rating : 20A
Nominal Voltage : 600V
Rated Surge voltage : 8kV
1. Application To sense the status of an E/P valve.
2. Type Inductive Type
3. Rated Operating Distance 4 mm
4. Output Polarity NAMUR
5. Assured Operating Distance 0-3.24 mm
6. Nominal Voltage ~ 8 VDC
7. LED Indication To be provided
8. Switching Frequency > 500 Hz
9. Hysteresis 1….15%
10. Reverse Polarity Protection Required
11. Short-Circuit Protection Required
12. Ambient Temperature 0-50 0C
13. Connection 2- wire
14. Housing Material Stainless Steel
15. Protection Degree IP67 certified, Temp Class T6
16. Electromagnetic
Compatibility
EN 60947-5-6 or Equivalent
17. Explosion Proof Ex II 1G Ex ia IIC
18. Dimensions M12
19. Cable Length Approx. 2.0 meters
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 154
Pollution Degree : 3
Voltage category :III
Flammability : UL94 V0
Compliance standard : IEC 60947-7-1
Mounting : Din rail: 35mm width
Accessories : End plate, Mounting rail, Marking
ferrule.
Types I
No: of terminals : 2
No of levels : 1
Types II :
No: of terminals : 4
No of levels :2 with internal short link.
Types III
No: of terminals : 4
No of levels :2 with cross link 3 pole.
Types IV
No: of terminals : 4
No of levels : 2 with Diode in series
Diode :1N 4007
Types V
No: of terminals : 4
No of levels : 2 with Diode in parallel.
Diode :1N 4007
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 155
Types VI
No: of terminals : 2
No of levels : 1
Colour : Separate for Phase, neutral and earth.
: Phase: Red ; Neutral : Black; Earth : Green
Size of the wire : 2.5 sqmm
Cross link : 3 pole and 5 pole
All Accessories like Separators, marking labels and end stoppers shall be included as one
lot
29. SPECIFICATION OF CABLE GLANDS
Metal cable Gland:
Type : Metric Threaded cable gland
Material : Nickel coated Brass
Cable Type : Un-armoured / armoured
Standard : European EN 50262
Operating Temperature : -30 °C to + 100 °C
Max. Continuous temperature : +70 °C
Protection : IP 67
Accessories : Lock nut, Washer
30. CABLE ENTRY PLATE
1. Material : CRCA steel with RAL7035 light grey colour
powder coating
2. Dimensions (mm) : 500H x 500W x 4mm thickness
31. MOUNTING PLATE
1. Material : CRCA steel with RAL7035 light gey colour
powder coating
2. Dimensions (mm) : 1600H x 480W x 2mm thickness
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 156
32. MS CONDUITS (FOR POWER CABLE LAYING)
1. Material : MS conduits
2. Dimensions as per
governing standard
: 20mm and 32mm
3. Colour : Painted black (Anti corrosive)
4. Thickness : 16 SWG
5. Joint by : Thread
6. Governing standard : IS 9537 Part-I 1980
33. INDICATORS, SWITCHES AND KEYS
INDICATORS
1. Connection Method : Plugin
2. Type of Head : Square
3. Illumination colors : Red, Green, Yellow
4. Illumination type : LED
5. Contact type : Silver
6. Service category : 24VDC ; 1A
7. Approximate dimension : 24mmx18mm
8. Mounting depth : 45mm
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 157
SWITCHES WITH INDICATORS
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action at two positions
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Square
6. Illumination colors : Red, Green, Yellow
7. Illumination type : LED
8. Contact type : Silver
9. Service Life : >2x106 cycles
11. Service category : 24VDC ; 1A
12. Approximate dimension : 24mmx18mm
13. Approximate Mounting
depth
: 45mm
MUSHROOM HEAD EMERGENCY STOP SWITCHES
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Mushroom head cap of polyimide
8. Contact type : Silver
9. Service Life : >2x106 cycles
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 158
11. Service category : 24VDC ; 1A
13. Approximate Mounting
depth
: 55mm
KEYS SWITCH
1. Contacts : NO-3; NC-3
2. Switching Action : Maintained Action at two positions
3. Ingress Protection(IP) : IP40
4. Connection Method : Plug in
5. Type of Head : Square
6. Key removable position : Position1 alone
7. Contact type : Silver
8. Service Life : >5x104 cycles
9. Service category : 24VDC ; 1A
10. Approximate Mounting
depth
: 50mm
General:
Ambient temperature : -25 deg C to +55 deg C
Rated Insulation Voltage : 300V AC
Over voltage category : III
Degree of Pollution :3
Electrical specification compliance : IEC 512-2-11
Shock Resistance : IEC 512-4
Accessories:
Protective covers, Blind plugs, labels, spare keys
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 159
34. OPERATOR CHAIRS
1. Overall Dimension : Total Height : 800 to 1200 mm
Overall Width : 700 to 750 mm
2. Backrest Height / width : Height ≥ 440 mm
3. Seat width/depth : Width ≥ 440 mm
4. Seat height adjustment : Pneumatic seat height adjustment shall be
provided for minimum of 90 mm. Seat height
shall be adjusted by lever for the required 5. Swivel Mechanism : Allows 360 degree lateral movement
6. Seat : Cushion seat
7. Backrest : Breathable polyester mesh
8. Base : 350 stiletto base stand for stability and
balance
9. Armrest : Fixed Loop armrest
10. Backbone : Die cast aluminium backbone in silver epoxy
powder coating.
11. Castors : Not required.
12. Lumbar support : Integral lumber support 28-48 mm placed in
the lumber region of the back, which
13. Fabric colour : Shall be selectable by Department. Party
shall provide different color sample fabrics
CCTV System
1. Specification for Explosion proof PTZ IP camera
Sl.no Details Description
Lens
1 Optic Zoom 30X
2 Aperture/Focal Length F1.4~F4.6, f=4.4~132mm
3 Angle of View 63.4° (Wide) ~ 2.3° (Tele)
4 Min. Work Distance 0.01m (Wide) ~ 1.5m (Tele)
Camera
5 Image Sensor ‘1/2.7 to 1/3" CMOS
6 Scanning System Progressive Scanning
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 160
7 Effective Pixels 2.0MP
8 S/N Ratio >50dB
9 Sensitivity
Color mode:
0.4 lux @ F1.4
(1/30s, 350mV equiv., AGC-Gain:
48dB)
0.1 lux @ F1.4
(1/8s, 350mV equiv., AGC-Gain: 48dB)
B/W mode:
0.01 lux @ F1.4
(1/8s, 350mV equiv., AGC-Gain: 48dB)
10 Sync System Internal
11 Iris Auto / Manual
12 Focus Auto / Manual
13 Shutter Speed Auto, 1/2 ~ 1/30000s selectable
Image
14 Max. Resolution 1920×1080
15 Image Mirror OFF/H-mirror/V-mirror/HV-mirror
16
17 DNR OFF/Manual/Auto
18 White Balance AUTO/MANUAL/SODIUM/MERCURY
19 AGC Built in
20 WDR OFF/WDR/AD WDR
21 BLC ON/OFF
22 Defog Required.
23 Other features
Sharpness adjustable, slow AE,
brightness mode, brightness
enhancing, HLC
level
Operational
24 No. of Presets 255
25 Auto pans Optional
26 Normal Tours 6 (each tour can be associated with 14
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 161
acts,
including Preset 1~32, Pattern 1~4,
AutoPan
1~4)
27 Home Return Required.
28 Timed Tours Required.
29 Auto Scan Required.
30 Motion Detection 4 areas or better
31 Alarm 2 alarm inputs, 1 relay output
32 Area Zoom Required.
33 Web Server Required.
34 Upgrade Online Required.
Network
35 Data Rate
Variable bit rate (vbr);
Constant bit rate (cbr):
256Kbps~10Mbps
36 Network Delay <300ms
37 Network Protocol
IPv6, IPv4, TCP, UDP, IGMP, DHCP,
FTP,
SNMP(V3), SMTP, NTP, RTP, RTSP,
RTCP, HTTP,
HTTPS, TSL, SSL, 802.1X, QoS, PPPoE,
DNS, ARP,
ICMP
Compression
38 Audio Compression G.711/G729
39 Video Compression H.264 high profile/M-JPEG
Interface
40
Audio Port 1 input (linear level, resistance: 1k_)
1 output (linear level, resistance:
600k_)
41
Network Port 1 * 10M/100M self-adaptive Ethernet
port,
RJ-45
Mechanical
42 Pan Rotation Angle 360° continous
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 162
43 Tilt Rotation Angle 180°
44 Pan Rotation Speed 0.1°/s to 30°/s
45 Tilt Rotation Speed 0.1°/s to 30°/s
Electrical
46 Input Voltage 100~240VAC
47 Frequency 50 Hz ±10%
48
49 Voltage Range ±10%
Environmental
50 Atmospheric Pressure 86kpa~110kpa
51 Storage Temp 40°F~158°F (-40°C~+70°C)
52 Relative Humidity 95%RH (+25°C)
53 Relative Humidity 95%RH (+25°C)
54 Application Field
For Division 1 and 2 hazardous
locations where
fire or explosion hazards may exist due
to the
presence of flammable gases or vapors
(Gas
Groups: II A, II B, II C; Temperature
Classes:
T1-T6);
For zone 21 and 22 hazardous
locations where
combustible dust clouds may occur
Physical
55 Material 316 stainless steel
56 Environmental Rating IP67 or better
57 Mounting
Surface, Wall, Corner, Pole Side, Pole
Pendant,
Pole Stand, Pole Top
Certifications and Approval
58 Product Certifications
ATEX , CNEx, ExdIICT6 Gb, DIP A21 TA,
T6 1,
IECEx, ExdIICT6 Gb, ExtIIICT80°C Db 2,
CE/EMC: EN 55022, EN 55024,
EN61000-3-2,61000-3-3 3,
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 163
FCC 4, CCOE 5, ISO 9001:2008
Preferred Make: Axis/Sony/Videotec/ Dvtel/ Bosch/ Pelco/Panasonic/ SIQURA
Control keyboard for Video Management System
General feature:
Joystick for Pan/tilt /Zoom control
LED display with adjustable contrast
Ergonomic keys
Macro function keys 10 Max
Mechanical:
ABS material
Rubber keys
3 axis proportional joystick with calibration and test
DB9 connector for firmware update
Electrical:
Power: 12 V DC, power adapter to be provided
Communications:
No. of ports : 3 x RS 485 serial line
No of ports for telemetry : 2 no’s.
No of ports for Matrix & multiplexer: 1 no.
No of RS232 ports : 1 no.
Compliance:
CE : EN50081-1, EN50130-4, EN60950, EN55022 Class B
FCC : part 15 class B
RS 485 DATA Multiplexer unit
General features :
No of input line : 1
No of output lines : 16
Electrical:
Power supply : 230, 50 Hz
Power consumption : 10 W (max)
Protection : built in fuse
Communications:
Telemetry transmission : RS 485 serial output
Transmission distance : 1200 meters
Control : Telemetry receivers
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 164
Environment:
Operating temperature : 0- 45 deg C
Humidity : 10-90 % non condensing
Mechanical:
Mounting : Rack mountable
Compliance:
CE : EN50081-1, EN50130-4, EN60065
Preferred Make: Extron/ Kramer/Pelco
Network switch Layer 2 with 1 G fiber SFP uplink ports
Interface Port speed:
Number of SFP ports : 16
Number of Copper ports : 4
10/100TX : RJ-45
100FX : SFP support
10/100/1000T : RJ-45
1000SX, 1000LX : SFP slot
Console RS232 : RJ-45 connector
Performance
System System capacity : 128MB RAM, 16MB flash memory, Up to 4,096 VLAN
ID, 8000 MAC address, Packet buffer memory 3Mbit
Throughput : up to50.6Mpps
Switching Capacity : 68 Gbps or higher
Switch fabric speed : 88Gbps or higher
Auto-negotiation, duplex, MDI/MDI-X
Physical & Environmental
Power input: 100 to 240 VAC, 50 to 60 Hz Internal Universal Power Supply
Dimensions: 19” Rack Mount (Mount Hardware included), Width: 1U Height
EMI/EMC: FCC Class A, CE, C-Tick, VCCI Class A
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 165
Safety: UL, CE
Software Functions
Interface Standards
IEEE 802.3 10T and 10FL
IEEE 802.3u 100TX
IEEE 802.3z 1000SX
IEEE 802.3ab 1000T
General Standards
IEEE 802.1D Bridging
IEEE 802.3x Backpressure/flow control
Multicast Standards
RFC 1112 IGMP snooping (ver. 1)
RFC 2236 IGMP snooping (ver. 2)
RFC 3376 IGMP snooping (ver. 3)
RFC 3376 IGMP querier
Support for 256 multicasts
Unregistered multicasts are dropped by default
VLAN
IEEE 802.1Q VLAN tagging
Up to 256 active VLANs
Port-based VLANs
MAC-based VLANs
Private VLANs
GARP VLAN Registration Protocol (GVRP)
QoS (Quality of Service)
IEEE 802.1p compliant Class of Service
Traffic prioritization using IEEE 802.1p, ToS, DSCP fields
Map IEEE 802.1p priorities to CoS queues to prioritize traffic at egress
Strict scheduling and weighted round robin
Security
Management security: username and
Password protection
SSHv2 for Telnet management
SSLv3 for Web management
RFC 1492 TACACS+
RFC 2618 RADIUS authentication
IEEE 802.1x Dynamic VLAN
IEEE 802.1x RADIUS accounting
IEEE 802.1x Multi-session mode
IEEE 802.1x Action on violation
IEEE 802.1x Single-host violation
IEEE 802.1x Guest VLAN timeout
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 166
IEEE 802.1x Authentication not-required
Security login banner
RFC 2865 IEEE 802.1x port-based
Network access control
MAC-based network access control
Guest VLANs
ACL – Access Control Lists
Management and Monitoring
WEB, CLI, Telnet, SSH, serial console port
RFC 1157 SNMPv1/v2c
RFC 2570 SNMPv3
RFC 1213 MIB-II
RFC 1573 Evolution of MIB-II
RFC 1215 TRAP MIB
RFC 1493 Bridge MIB
RFC 2863 Interfaces group MIB
RFC 1643 Ethernet like MIB
RFC 1757 RMON 4 groups:
Stats, History, Alarms, Events
RFC 2674 IEEE 802.1Q MIB
RFC 1866 HTML
RFC 2068 HTTP
RFC 854 Telnet
Preferred Make: D-link/allied Telesis/Cisco/HP/3M
Network Access storage (NAS)
Item Description
CPU Dual core processor 1.8 GHz or above
RAM 2 GB DDR III RAM or higher
Total Capacity 18 TB
6 x 3.5” or 2.5“ Hot swap SATA 6Gb/s Server class HDD
Raid Support RAID 0, 1, 10, 5, 5+1(HS), 10 and 6. JBOD, single disk
Online RAID capacity expansion
Online RAID-level migration
RAID recovery
Networking features TCP/IP (IPv4/IPV6)
VLAN 802.1Q
Port trunking
DHCP Client
CIFS/SMB, AFP/Netatalk3.2, NFS, Bonjour
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 167
HTTP, HTTPS, FTP, SFTP(admin), DDNS, NTP, Telnet, SSH,iSCSI,
SNMP, WebDAV
Support for VMware VSphere 4 and 5 via NRF and iSCSI
Windows Server 2008 support (Hyper-V & failover clustering)
Interface
requirement
2 x RJ45 10/100/1000Mbps (GbE) Ethernet ports
1x USB 3.0
2x USB 2.0
1x SATA
Backup management
features
Facility to backup and restore system configuration
Instant, scheduled backup management
Real time backup of server & clients
Support to third party backup software.
Support to data backup using USB/eSATA storage devices
LUN backup and restore
Disk management
features
Disk usage status management
Continuous monitoring and reporting of health of all HDD
User management
features
User quota management, user account management, user
group management
Windows Active directory support
Microsoft Networking (Samba) Host Access Control
LDAP directory services support
Shared folder
Concurrent connection
Sub folder permission
Expandability Support to connect external USB hard disk drives. Read / write
on FAT 32, NTFS, ext2/ext3/ext4 or HFS + formatted drives
Operation system
support
Linux, UNIX, Windows OS (Server 2008 R2/ Server 2003/7/XP)
32 bit and 64 bit
System tools Disk usage alert
E-mail alert
Backup, restore, reset system settings
System firmware upgrade
Configurable management port
Remote login by Telnet connection
Scheduled power on/off
Automatic power on after power loss
Smart fan setting
Wake-on-LAN
SNMP support
UPS support
Centralized monitoring of system logs using user friendly
management tool (System events logs, connection logs,
current connection of on-line users)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 168
Manual and advanced log filtering wizard support
Power supply Input 100-240v AC, 50-60 Hz with redundancy
FAN 1xquiet cooling fan
Form Factor Tower
Accessories Indian power card
CD / Manuals
LAN Cable and all other items required as part of installation
Operating
Temperature
0 – 40 C
Warranty 3 Years comprehensive warranty on hardware and technical
support
Preferred Make: Lenovo/EMC2 /Fujitsu/ Qnap
File Server
Supply & Installation of Server with 2 X Intel 8 core or more Xeon processor E5-
2690v2 series @ 3.0 GHz or more with 25 MB cache.
Processor 2 x Intel 8 core or more Xeon processor E5-2690v2 series @
3.0 GHz or more with 25 MB cache.
Memory 32 GB (2x16 GB or better) ECC DDR3 memory @ 1600 MHz
Drive Bays 8 or more x 2.5” / 3.5” for SAS hot plug drives.
Drive Controller Integrated or add-on SAS controller.
Hard Disk drives 6 x 600 GB SAS HDD 6G (10 K RPM)
RAID Controller Onboard or add-on RAID controller to configure RAID 6 with
512 MB Cache.
Removable media DVD-RW supermulti, slimline SATA.
Expansion slots 4 slots or more after configuring the requirements.
Bus slots Four PCI-Express slots or more.
Graphics Integrated Graphics controller.
Network on board - 2 x 1G Ethernet ports and additional 2x 1G Ethernet
port (External).
I/O ports & Connectors 4 USB.
Power supply 2x hot plug power supply (230V @ 50 Hz) Unit.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 169
Power 230V @ 50 Hz, Indian power cords to be supplied.
Form factor Rack – Server depth should not exceed 780 mm.
Fan Five or more hot-plug fans.
Software System management software
Rack Mountable 2U size
Warranty 3 Years
Make IBM / DELL/ HP/Fujitsu.
Optional:
Memory 16 GB (1x16 GB) ECC DDR3 memory @ 1600 MHz
HBA Support 2-port 4 Gbps PCIe FC HBA Adapter Card
19” Rack Mountable Kit should be supplied along with servers.
1. 1U Size 19” Rack Mountable Foldable LCD Monitor
Computer Connections 1
Console Selection Hotkey
Connectors External Console Ports: Keyboard (1 x 6 –pin Mini-Din Female,
1
x USB Type A Female), Video (1 x HDB-15 Female), Mouse (1 x
6 –pin Mini-Din Female, 1 x USB Type A Female)
KVM Ports: 1 x SPHD-15 Female
Power: 1 x 3-prong AC Socket
F/W Upgrade: 1 x RJ-11
External Mouse: 1 x USB Type A Female
Switches Reset: 1 x semi-recessed Pushbutton
Power: 1 x Rocker
F/W Upgrade: 1 x slide
LCD power: 1 x Pushbutton
LCD Adjustment: 4 x Pushbutton
LEDs Power: 1
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 170
Lock: 1 x Num Lock, 1 x Caps Lock, 1 x Scroll Lock
Emulation Keyboard/Mouse: PS/2, USB
Video 19” LCD: 1280 x 1024, DDC2B
Power Rating 100-240AC, 50-60 Hz, 1A
Environment Operating Temperature: 0-40oC
Storage Temperature: -20-60oC
Humidity: 0-80% RH, Non-condensing
Physical Housing: Metal
19” Rack Mountable Kit should be supplied along with Monitors.
Preferred Make: IBM/Fujitsu/HP/DELL
36 core Fiber Optic Armored cable
Fiber optic design : Glass fiber in multi tube loose
fibers with jelly fill
Fiber type & size : Single mode, 9/125 microns
Attenuation @1310 nm : 0.4 dB/Km Max.
Number of tubes : 6
Number of fibers per tube : 6
Loose tube material: PBTB
Loose tube inner diameter : 2.0 mm
Loose tube outer diameter : 3.0 mm
Armoring : Corrugated steel tape
Strength member material : Steel wire
Number of strength material : 1
Diameter of strength member : 2 mm
Minimum bending radius : 220 mm
Number of outer jackets : 2
Outer jacket material : HDPE
Outer jacket diameter/thickness : 12 mm/2 mm
Tensile strength : 4000 Newton’s
Crush resistance : 4000 N/mm
Preferred Make: HFCL/Birla Ericsson/Krone
HD VIDEO RECORDER
Electrical Power input 100 to 240 VAC; 50/60 Hz
Power consumption Max. 2.5 to 1.0 A (250 Watt)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 171
Video
Video standard PAL or NTSC auto-detection
Resolution 1920 x1080 PAL
Compression H.264,MPEG 4
Inputs 16 composite video 0.5 to 2 Vpp, 75 ohm
automatic termination
Outputs 16 composite video 1 Vpp, 75 ohm, sync
0.3 V ± 10%
Audio
Inputs 8 or 16 line in , mono RCA,
1 Vpp, 10 kohm
Output 2 line out, dual mono RCA, 1 Vpp, 10 kohm
Compression MPEG-1 layer II
Sampling rate 16,24 ,48 kHz per channel
Monitors
MON-A Live, playback, menus
VGA: analog RGB 1280x1024, 60/75 Hz
(NTSC/PAL)
CVBS: 1 Vpp, 75 ohm, BNC
Y/C
MON-B (Hybrid models only) Live
VGA: analog RGB 1024x768, 60/75 Hz
(NTSC/PAL)
CVBS: 1 Vpp, 75 ohm, BNC
Y/C
Display Modes
Monitor A Full, full sequence, quad, multi-screen (live
and playback), event call-up (live)
Monitor B(Hybrid models only) Full, full sequence, quad, multi-screen, event
call-up (live)
Frame rate PAL 25 IPS per channel (real time)
Multi-screen mode
16 channels
1, 2x2, 3x3, 4x4
Zoom 1.5x, 2x, 3x, 5x
Alarm Handling
Inputs Screw terminal, 8 or 16 inputs, configurable
NO/NC,
Max. input 40 VDC
Outputs Screw terminal 4 relay outputs, configurable
NO/NC, max. rated 30 VAC, 40 VDC, 0.5 A,
continuous -10 VA
Remote notification Via Control Center software
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 172
Malfunction relay Temperature related failures,
Voltage ratings, Disk failures
Connections
Ethernet 1 or 2 RJ45 modular jack, 8 pins shielded:
10/100/1000 Base-T
Biphase Screw terminal connector (5 outputs)
Maximum 5 controllable cameras per Biphase
output
Impedance 128 ohm, max. overvoltage
protection ±40 V, max. cable length 1.5 km
(0.9 miles)
PTZ control interface RS485
Serial interface RS232 output signals according to EIA/
TIA-232 F, max. input voltage ±25 V
2xDB-9 male connector
Intuikey keyboard
(KBD Digital or
KBD Universal)
Conforms to RS485, max. signal voltage
±12 V, power supply to keyboard 11 to
12.6 VDC at max. 400 mA
RJ11 modular jack 6 pins
USB Five USB 2.0 ports
10/100/1000 Base-
T network interfaces (max 2)
Connect with Bosch iSCSI Video Storage
Arrays
Network
Bandwidth control 0.1-100 Mbps limiter
Remote users Maximum 7 simultaneously connected
Control Center users
Protocol support TCP/IP, DHCP, DNS, and SNTP
IP cameras Up to 16 IP H.264 for DHR models
Storage
Internal HDD 2 TB per disk
Up to 4 hard disks
Redundancy RAID-4 (4 hard disks plus optional license
required)
Exporting
DVD Built-in DVD+R/RW recorder (optional)
USB Flash memory or external HDD (FAT32)
Network Bosch Video Client or Control Center Software
Security
Password protection Multi-level
Image authentication All recordings and archives in native file
format
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 173
Record Frame Rate
PAL Up to 25 IPS per channel at 4CIF
IP Channels Up to 25/30 IPS per channel at 4CIF, 720p60
and 1080p30
Recording
Overwrite modes Continuous, overwrite after 1 to 99 days
Pre-alarm recording Up to 120 s
Playback
Playback function Fast forward/reverse, frame forward/reverse,
freeze
Zoom 1.5x, 2x, 3x, 5x
Search mode Date/time, Event (motion, input), Text, Smart
Search
Preferred Make: Axis/Sony/Videotec/ Dvtel/ Bosch/ Pelco/Panasonic/ SIQURA
Preferred Make: Extron/ Kramer
Digital Video Management Software - Enterprise Level
Main Features:
Scalability
Independent of any camera or hardware manufacturer
Support for multiple servers, sites and clients
Support for H.264, MPEG-4 ASP,MJPEG
MPEG video compression technologies
Bandwidth optimized & multistreaming
Configuring video and recording
Export to various formats, including video from multiple cameras and with
viewer included
No software boundaries - hardware capability determines the no. of
devices and recordings per recording server
Open architecture
Virtual matrix
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 174
Image Enhancement Feature
Motion Detection and Alerts
Flexibility
Simultaneous Recording and Playback
Web integration
Automatic Archiving
Facility to schedule activities base on time or event
Ability to display information on multiple monitors
Automatic Zoom and Tracking
Perimeter Intrusion Detection
Object Speed Calculation
Load balancing
Image Integrity Checking Feature
Smart search
Security
Logging
Compatibility : Compatible with All brands of Network Video Products running
Firmware,
Software Support : Up to 64 Cameras, compatible for future expansion of minimum
Video compression: H.264 (MPEG-4 Part 10/AVC), MJPEG.
Resolutions : Up to 1920 x1080
Camera live view : Live view up to 16/25 cameras simultaneously in 4, 6, 9,
16/25-split Views, full screen 4, 9, 16-split view single camera
pop- up User defined split views
Live sequence mode: Multiple camera sequence (Patrolling)
Audio : Full duplex real time audio support
PTZ support : Control of PTZ cameras and preset positions using mouse or
joystick
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 175
Alarm recording : Events triggering by motion detection, external input
Alarm recording : From 1 image per minute up to 25fps per camera
Frame rate : Configurable pre-and post alarm buffering
Alarm notification: Visual indication, pop-up live image, e-mail and event log
Motion detection : Advanced motion detection with exclude filter for image areas of
no Interest. Different day and night settings Camera-based motion detection, option to
save on bandwidth “No motion” detection
Scheduled recording : Recording can be scheduled per camera, be set for
continuous ,motion detection, scheduled upload, per
weekday or Specific dates
Recording : Warning on deleted or altered images in recorded events
Tampering
Archiving : Recordings can be moved daily to remote storage
Playback : Controllable speed or frame by frame
Synchronized : Playback of video synchronized in time from up to 4 video
sources
Playback : Simultaneously
Search for recording : Search for recording based on date, time, or Motion
Search for motion in continuous recordings
Video clip export : Exports signal MPEG images to file, Printer or e-Mail
Exports video sequences in AVI or ASF format
System alarm : Notification in event log and via e-mail for alarm, no signal
from Camera, full hard disk and archiving failure
Input/output control : Advanced control panel for cameras digital input/outputs
Remote access : Web client for remote viewing and playback
Security : Multiple user access levels with password protection local or
Windows Domain users (Active directory)
Logs : All events, filter by day/night camera. Audit log-filter by ay,ca
mera Event and user
Installation : Auto search and detection of cameras
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 176
Minimum system : Windows server, Internet requirements Explorer 6.0 or
later, DirectX 9.0c or later (for MPEG-4) TCP/IP support
Internet information Services (IIS)- for Web client
Microsoft, NET Runtime environment
Support protocols : IPv4/v6, HTTP, HTTPS, SSL/TLS, QoS Layer 3 DiffServ, FTP,
SMTP, Bonjour, UPnP, SNMPv1/v2c/v3 (MIB-II), DNS, DynDNS, NTP, RTSP, RTP, TCP,
UDP, IGMP, RTCP, ICMP, DHCP, ARP, SOCKS
Preferred Make: Axis/Mindtree/Milestone/Videotec/ Dvtel/Bosch/ Pelco/Panasonic/
SIQURA/VIVOTEK
Specification of LED TV display
Features
Smart energy saving
Motion eco sensor
2D to 3D source convert
3D to 2 D source convert
3D Depth & Image control
Dual core CPU
DLNA built in
Network file browser
Internal memory recording
External HDD recording
Full Web browser
Display
1. Display screen size : 86 Inches
2. Display type : Full HD 3D Smart LED LCD
3. Display design : Cinema screen design.
4. Display resolution : 3840 x 2160 UHD
5. Back light module : Ultra slim LED
6. Pixel control : Micro lens array
7. Motion control index (Hz) : 800 (120 Hz)
Video
8. Video system : PAL
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 177
9. Video processing : Triple Engine
10. Resolution upscale : Basic
11. Color enhancer : Dynamic
12. Aspect ratio : 16:9,just scan,original,4:3
13. Noise reduction : 3 D MPEG
Audio
14. DTS decoder : Built In
15. Dolby Digital decoder : Built in
16. Speaker system : 2 way 3 speaker (2.1)
17. Audio output : > 20 watts
18. Sound optimization : Normal, Wall mount, Stand mount
19. Surround sound : Built in virtual surround plus
20. Sound sync : Optical
Connectivity
21. Wi-FI : Built in
22. Wi-Fi : Direct
23. Full Web Browser : Built in
24. DNLA : Built in
25. NFC tagging : Built in
26. USB : 3 no’s of USB 3.0/2.0
27. HDMI 1.4 : 4
28. RF In : 1
29. Video RCA composite : 1x RCA (F)
30. Component video : 3 x RCA(F)
31. Digital audio out : Optical
32. LAN connectivity : 1 RJ45
33. Head phone out : 3.5 mm stereo socket
Power
34. Power supply : 100-240 V ac ,50-60 Hz
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 178
Accessories
35. Mounting Kit : Wall mounting
Preferred Make: Sony/LG/Panasonic/ Samsung
48 core Fiber Optic Splicing Patch panel
Features:
Wall mounting
Compact and adequate space for fiber organizing
Provision for cable clamping and strain relief
Management for excess length of pigtail
Loaded with duplex couplers
Removable hinged door with lock & key arrangement
Powder coated
IP 65 category
Specifications
Material : Mild steel
Thickness : 1.6mm
Finish : 50 Micron powder coating
Slack Management up to 5 meters
No. of trays : 4
No. of fibers : 12 per tray × 4 No’s
Cable glands : 4 nos.
Preferred Make: 3M/R&M/MOLEX/ FDI
Surge Protectors Device (SPD) for CCTV system
Surge Protector Device (SPD) for power line for 230 V AC line
Working voltage : 230 Volts AC, 50 Hz
Maximum continuous
Operating voltage : 25 % above nominal voltage
Limiting voltage : < 800 Volts
Maximum continuous
Operating current : 15 Amp
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 179
Nominal discharge current : 18 kA peak current (8/20 µsec wave form)
Maximum attenuation : 55 dB
Maximum leakage current : < 0.3 mA at working voltage
Lines protected : L,N,E
Mounting type : Din rail mountable
Terminal : 2.5 Sqmm
Compliance : IEC 61000-4-5, level 4.
Surge Protector Device (SPD) for Ethernet twisted pair lines
Input connector : RJ45
Output connector : RJ45
Input signal type : Ethernet twisted pair 100 Base T
No. of Input wires : 8 wire
Maximum bandwidth : >155 MHz
Insertion loss : 0.1 dB @144 Khz
Limiting voltage : 12 Volts (10/350 kA)
Working voltage : 6 Volts DC
Maximum discharge current : 5 kA peak current (8/20 µsec wave form)
Mounting : Plug in type
EMC compliance : BS EN 61000-6-2:1999, BS EN 60950:1992
Surge Protectors Device (SPD) for power line to video cameras
Working voltage : 24 Volts AC, 50 Hz
Maximum continuous
Operating voltage : 34 Volts AC, 50 Hz
Limiting voltage : < 800 Volts
Maximum continuous
Operating current : 20 Amp
Nominal discharge current : 0.7 kA peak current (8/20 µsec wave form)
Maximum attenuation : 70 dB
Impulse energy absorption : 420 Joules
Fuse rating : 10 Amp
Maximum leakage current : < 0.3 mA at working voltage
Mounting type : Din rail mountable
Terminal : 2.5 Sqmm
Compliance : IEC 61000-4-5, level 4.
Surge Protector Device (SPD) for RS485 line
Input connector : Terminal screw
Output connector : Terminal screw
Input signal type : RS 485
Input wires : 2 wire
Maximum bandwidth : 50 MHz
Limiting voltage : 10 Volts (6kV/ 3kA)
Working voltage : 5 Volts DC
Maximum discharge current : 10 kA peak current (8/20 µsec wave form)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 180
Mounting : DIN rail
EMC compliance : BS EN 61000-6-2:1999, BS EN
Preferred Make: OBO/MTL/Emerson/Schneider
Intercommunication System
Matrix intercom System
Matrix Capabilities
Maximum Expansion Cards : 4
Maximum CPU Cards : 2 (included)
Maximum Power Supply Units : 2 (included)
Maximum Fiber Expansion Cards : 2
Maximum RJ-45 Ports per Matrix : 64
Maximum Timeslots : 512
Matrix Performance
Sample Rate : 48 kHz
Resolution : 24 bit
Frequency Response
at 48 kHz sampling : 30 Hz - 22 kHz ± 3 dBu
Crosstalk
(Adjacent channel) : <-70 dBu
Nominal Level : 0 dBu
Matrix headroom : +18 dBu
Distortion : <0.05 %, @ 0 dBu, 300 Hz to 10 kHz;
<0.1 %, @ 0 dBu,100 Hz to 20 kHz
Off Noise : <-70 dBu (20 Hz - 22 kHz)
On Noise : <-65 dBu (20 Hz - 22 kHz)
Key Response, Intra-System : <40 ms for audio route
Linked Systems : <60 ms for audio Between matrices
Environmental
Operating Temperature : 0°C - 40°C
Humidity: : 90% non-condensing
Interface frame card for Matrix (wireless controller)
Maximum cards per frame : 4
Wireless device per card : 50 at 1.9GHz, 40 at 2.4GHz,
Audio Pass band : 100Hz – 7 kHz
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 181
G.722 Codec : 16 kHz sample rate (@64kb/s)
Connectivity : CAT5
Maximum Active Antenna Support: 10 per card
Power (combined cards) : +3.3V, 3.5A; +5V, 0.7A; +12V, 0.05A
Environmental
Operating Temperature : 0°C - +40°C
Operating Humidity : 40 – 90%, non-condensing
Dimensions
Front Card : 6RU H x 11.8in D (6RU H x 300mm D)
Rear Card : 6RU H x 2.3in D (6RU H x 58mm D)
Specification for Control panel
Front panel controls & Connectors
Talk / Listen buttons : 35
Function buttons : 4
Answerback buttons : 1
Clear buttons : 1
Volume controls : 2
Headset connector : 1
Panel mike connector : 1 locking ¼” phone jack
Rear panel Connectors
To Matrix : RJ-45
DB-15F
Expansion : RJ-45
Power : 3 pin EIA connector
Headset Audio:
Earphone Impedance : from 50Ω
Output Power : 0.5W into 50 Ω for <1% distortion
Loudspeaker Audio:
Frequency response : 40Hz – 20 kHz +/- 3 dB
Panel Microphone Input
Type : Electret
Level : -40 dBu
Impedance : 200Ω +/- 10%
Headset Microphone Input:
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 182
Type : Dynamic
Level : - 55 to 0 dBu
Power supply:
Voltage : 90/240 VAC +/- 10%
Frequency : 50 – 60 Hz
Specification for wireless receiver (walky- talky)
Audio Bandwidth: 100Hz-7.1KHz (G.722)
No. of Full-Duplex Audio Paths:
Up to 5 with individual level control (2 pairs)
2 controls and a main volume
Mode of Operation: Full-duplex on all routes
Level/Talk Controls: 4 pushbuttons, a reply button and 2 rotary controls
Enter/Answer-Back Button : 1
Radio Frequency Spectrum : 2.4 GHZ
Auto-roaming technology
RF Output:
200mW Burst, 17mW average**
Range:
Up to 1475ft (450m) to Wireless system in good
Conditions, 800 feet typical
Battery:
Li-Ion Battery (BAT60) or 3 AA cells
Battery Charging:
Drop-in charger (AC60) or local USB
Battery Life:
18+ hours with Li-Ion – also accepts
3 x Alkaline AA cells
Headset Connector:
4-pin male, Clear-Com standard
Microphone Type:
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 183
Electret and Dynamic, selectable
Microphone Level and Headset Limiter:
Selectable from menu
Headset Limiter:
Selectable from menu
Environmental:
IP-65 water and dust resistance -67°F
to +158°F (-55°C to +70°C)
Base Station Specification
Base-to-handset Frequency Response : 100 Hz-7.1 kHz.
No. of handset per Base Station : 20
No. of Transceiver/ Antennas Supported by Base, Basic Base: 10
No. of Active Antenna Ports : 2
PC Programming Port : LAN and DB9 (Serial)
Relay Port : DB9
Party line : Intercom A and Intercom B (each):
Four-Wire/Matrix Connection : 4 RJ-45
Program Input : XLR-3F, transformer isolated, line-level input
Stage Announce Output : XLR-3M, transformer isolated, line-level output
Front-Panel Headset : 4-pin male connector
Antenna Splitter Technical Specifications
No. of Antennas : 5
No. of Splitters per Base : 2
Connection between Base and Splitter : CAT5 or better cable with RJ-45
Connection between Splitter and Antennas: CAT5 or better cable with RJ-45
Powering of Splitter : Locally powered via supplied
External power supply
Active Antenna Technical Specification
Wireless device Supported per Active Antenna : 5
Active Antenna Transmission Range : Up to 1475ft (450m) to device in good
conditions, 800 feet typical
Active Antenna Output : 200mW burst, 80mW average*
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 184
Maximum Distance, Base to Antenna ViaTransceiver Port : 3,200ft (1,000m) on 4-pair
CAT5 or better cable
Maximum Distance, Antenna Powered by Base: 975ft (300m) on CAT5 or better cable
Local Powering : 24VDC power supply
Connection to Base : RJ-45
Mounting Integral screw mounts or Standard microphone mounting
Specification for Interface frames
Plug in Module capacity : 10
Rear panel connectors : (2) 10 pin
To Matrix frame : RJ-45
Interface I/O : DB9-M
Specification for Interface Modules to Matrix:
Frequency response : 100 Hz – 15 KHz + 0/-3 dB
Impedance :> 10 KΩ
Audio Level : -10 to -15 dBv nominal
Call Signal level : 4 – 11 VDC
Nulling Capability :
Line length : 0 – 4000 feet
Line Impedance : 120 – 350 Ω
Depth of Null : >30 dB 200Hz – 8 kHz
Nulling tone : Via 1/8” phone jack
Preferred Make: Clearcomm/Bosch/Phi Audiocomm/
TIMING SYSTEM
GPS /IRNSS based network time server
GPS receiver:
Band : L1 1575.42 MHz
Code : C/A
No of channels : 8 channel
Time base : TCXO
Time to lock : < 5 minutes
Stratum level : level 1
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 185
Antenna:
Impedance : 50 OHM
Connector : TNC jack on rear panel
LNA & filter : Integrated +35 dB LNA and band pass filter for out of
bound Interface rejection
ENVIRONMENT : Rugged all weather housing capable of operation over -40
to +85 C
Cable length : 100 feet
Accuracy:
GPS/IRNSS receiver : < 30 nanoseconds to GPS (< 100 ns to UTC) when locked
Hold over accuracy : 10 millisecond /day
NTP time stamping : < 10 microseconds while supporting 2,00,000 clients (typical)
NTP client LAN Sync : 2 millisecond (typical)
Supported protocols: -SNTP, NTP v2, v3, v4, MD5 authentication and
Broadcast/multicast mode and auto key.
- SSH server with secure copy utility, SCP.
- SNMP v1, V2c, V3 with enterprise MIB.
- HTTPS (web interface)
- Time & Daytime server
- TELNET client/server
- FTP & DHCP clients
- IPv4 & IPv4/IPv6 hybrid
- SYSLOG
- PTP/IEEE-1588 (optional)
Software : Free NTP Client software
Network I/O:
Rear panel : RJ-45 jack
Speed : 10/100 Base-T Ethernet
Serial port I/O : RS -232 on 9 pin jack on rear panel
System status : Sync LED; Network LED; Alarm LED
Alphanumeric Display /keypads:
Display : 16 x 280 dot matrix
Keypad : Enter, Back, Edit, Left, Up, Down, Help
Outputs
NTP time : 10/100 Base-T Ethernet
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 186
Time code output : 1 Vrms into 50 Ohms, 1 KHZ carrier
Format : User selectable format: IRIG-B120, IRIG-B12 and IRIG- B123
1PPS output : TTL pulse
Pulse width : Selectable 20 microseconds, 1 milisec, 100 milisec, 500
milisec
Accuracy : < 30 nanoseconds to GPS (< 100 ns to UTC) when locked
Stability : TDEV < 20 nanosecond,
Firmware Upgrades : Field upgradable at free of charge
Power : 90-264 VAC, 47-63 Hz
Mechanical : 19 “rack mountable
Environmental:
Temperature operating : 0 to 50 Deg C,
Humidity : 0-95 %, non-condensing
Compliance : CE, FCC
Network Time Display units
Display size : 4 inches
Number of Display digits : 6
NETWORK PROTOCOLS : NTP, SNTP, DHCP, TCP/IP, UDP
MODULE CONNECTION : 10/100 Base-T Ethernet
Network connector : RJ-45
Synchronization input : NTP
Control : Telnet for IP configuration, 12/24
Hour format, status Reporting, SNTP server address,
Daylight savings time
Mount : Wall mountable
Power : 90-264 VAC, 47-63 Hz
Environmental:
Temperature operating : 0 to 50 Deg C,
Humidity : 0-95 %, non-condensing
Compliance : CE, FCC
Time Distribution Amplifier
Input Specifications
Connection : 50Ω BNC Socket.
Frequency Range : 2Hz to 15MHz Sine Wave, Square Wave, Time code or Fibre
Optic
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 187
Input Coupling : AC/DC selectable
Input Amplitude : 1Vrms nominal or 0.5Vpp to 5Vpp
Input Impedance : 50Ω, 75Ω or 10k Ω selectable
Output Specifications
Connection : 10 Independent buffered outputs from an input channel.
Dual Input option with automatic selection of a second input
The output connections are available via 75Ω BNC Sockets.
Frequency Range : 2Hz to 15MHz (AC coupled) or place internal jumper to select
DC Coupling throughout
Output Amplitude : 1 Vrms into 75Ω load standard (+13dBm)
2 Vrms into 75Ω maximum (+19dBm)
Output impedance : 75Ω
Isolation : >70dB
Delay : <30ns
Harmonic Distortion : < –30 dBc.
Non Harmonic Distortion : < –60 dB.
Output Protection : Open/short circuit, over current an over temperature
Internal 10MHz Band-pass filter.
Phase Noise at 1Hz : -120 dBc
(Single-Sideband) 10Hz : -140 dBc
100Hz : -150 dBc
1kHz : -150 dBc
10kHz : -150 dBc
100kHz: -150 dBc
General
Status Indicators: Primary Power On.
LED indicator for each of 10 outputs present
Individual input present indicators for dual input options
Status relay contact c/o for any failure
Power: 110V or 220 VAC 45-65Hz at 10VA
EMC: CE Compliant
Physical: 19 inch 1U/2U high rack-mount
Environment
Operating Temperature : 0°C to +45°C.
Storage Temperature: -20°C to +60°C.
Humidity: Up to 95% RH (Non condensing)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 188
Video Time Inserter
Description Specified
1. Time data input : Modified IRIG-B count down time
2. Time input level : 1 – 6 V p-p
3. Video input : PAL composite video of 1 v p-p into 75 ohms
4. Number of video Channel : 4 nos.
5. Video output : PAL composite video of 1 v p-p into 75 ohms
per channel.
6. Time display on video : Hours, minutes, seconds, milliseconds
(mmm), countdown sign and Hold
(HH:MM:SS: mmm)
7. Display control : Individual potentiometer controls for
a. Height
b. Width
c. Horizontal position
d. Vertical position
8. Display indication : UTC/CDT, Hold, UP/Down
9. Video Display selection : Selectable black on white background or white
10. Front panel display : Time code in (HH:MM:SS), sign, CDT/UTC
11. Front panel control : Power on, CDT/UTC,Normal video/inverted video
12. Mechanical : 19 “rack mountable
13. Power : 230 V AC, 50 Hz
Count Down Time Code Generator
Time Base : Oven Controlled Crystal Oscillator
Time Base Stability : 1 PPM or better
Time Output : 1.Standard IRIG-B modified to provide sign (Count up/down);
Hold/Run function and BCD Seconds; Minutes and Hours
HH:MM:SS: mmm
2.Parallel BCD outputs for HH:MM:SS: mmm for driving
Up to 2 meters length
3. RS 422/RS 485
4. RS 232 output
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 189
5. TCP/IP Interface (RJ 45)
Time set ability : from - 99:59:000
Time resolution
RS232 output : 10 mili second
RS 485/ 422 output: 10 mili second
TCP/IP output : 10 mili second
UDP packet format
1 2 3 4 5 6 7 8 9 10 11 12 13
$ H H M M S S m m m U/D R/H CS
TCP/IP Protocol : Unicast & Multicast address
TCP/IP port speed : 100/10 base T
RS232 speed : 115200 baud /s
Carrier Frequency : 1 KHz sine wave
Amplitude : 0-10 VP-P into 600 ohms
No. of modulated O/P:6 nos. of isolated outputs
Modulation ratio : Adjustable 2:1 to 4:1
Front Panel Display : Six Decimal Digits: 7 segments LED (1” size)
Display indicating HH:MM:SS, Sign and Hold
Controls
Front panel : Power ON/OFF, Time Preset through Thumb Wheel
Switch (from - 99:59:00), Start/Stop, Count up/down, Hold/Run,
Enter Push Button, Enter Lock with Key.
Rear Panel : Parallel BCD time output in format
(HH:MM:SS: mmm)
IRIGB-Modulated time code output,
RS-485/RS-232 output
Hold/Run : Internal (Front panel control) and external Remote control for
Individually HOLD and RUN
IP address : User Selectable
Power supply : 230V AC ±10%, 50Hz
Mounting : 19” rack Mountable, 2 U heights
Preferred Make: EndRun /Time Freq Solutions/Spectracom/Meinberg/
Symmetricom
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 190
ARMOURED UTP Ethernet cable
CAT6 CLASS-E UTP cable
Frequency Range : 250 MHz
Attenuation : 36 dB at 250 MHz
NEXT : 33.1 dB
Power sum NEXT : 30.2 dB
ACR : 2.9 dB
Power sum ACR : 5.8 dB
ELFEXT : 15.3 dB
Power Sum ELFEXT : 12.3 dB
Return Loss : 8 dB
Propagation delay : 546 n Sec
Delay Slow : 50 n Sec
Standards : EIA/TIA 568 A
ARMOURING : Corrugated Steel
Preferred Make: Molex/D-Link/3M/R&M
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 191
Table 1 Aux
Auxiliary System Requirements S.No Item Description Qty(nos.) Remarks
1 IP CCTV system (Ex proof) PTZ 02 2 IP CCTV system (Ex proof ) Fixed 02 3 IP CCTV system (Non Ex proof ) PTZ 04 4 Network video recorder with 12 TB HDD
and display, DVD writer, keyboard and mouse
1 each
5 LED Display : 86 inch 01 6 LED Display : 55inch 02 7 Non Explosion proof Intercom System &
Speakers (wired) 05
8 Wireless transreceiver 10 9 Explosion proof Intercom System &
Explosion proof Speaker (wired) 02
10 Countdown time code generator 01 11 Video time inserter 01 12 Time display unit 02 13 Control keyboard for Video Management
System 01
14 File Server 01 15 36 core Fiber Optic Armored cable 800m 16 48 core Fiber Optic Splicing Patch panel
(LIU) 1
17 Armoured CAT6 cable 1500m 18 Surge Protector Device (SPD) for power
line for 230 V AC line 01
19 Surge Protector Device (SPD) for Ethernet twisted pair lines
01
20 H264 Decoder 04 21 Layer 2 network switch with combo SFP
port / RJ45 02
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 192
ANNEXURE –F
(T & E Sheet format)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 193
SECTION/DIVISION NAME
MEASUREMENT CHAIN TEST REPORT Type Parameter
Location Legend
TRANSMITTER DETAILS
Transmitter Make Constants
Transmitter Model No A0
Serial No A1
Measurement Range Calibration Range
Calibration Date
CALIBRATION EQUIPMENT
Calibration Equipment
FIELD WIRING DETAILS
JB No JB incoming cable tag
JB outgoing cable tag
JB incoming ferrule tag JB outgoing ferrule tag
INSTRUMENTATION RACK WIRING DETAILS
Rack tag
Field connector tag CS connector
TIB make TIB model no
TIB ch.no TIB serial no
TIB input pin details TIB output pin details
CONTROL SYSTEM WIRING DETAILS
CS type Gain
Offset
Incoming connector no Connector pin no
CS card/Slot no/Sl no
MEASUREMENT CHAIN CHECKING
Insulation resistance check
ELECTRICAL CHAIN CHECKING
Simulator Input Obtained Value Expected Value Error
mA (bar) (bar) % FSO
4
8
10
14
16
20
Theoretically Estimated measurement chain accuracy Electrical chain accuracy
Chain Calibration Date
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 194
TESTED BY VERIFIED BY CLEARED BY
SECTION/DIVISION NAME
EP VALVE COMMAND CHAIN TEST REPORT
TAG
LOCATION
DESCRIPTION
VALVE DETAILS SOLENOID VALVE DETAILS
MAKE SOV MAKE
MODEL NO. MODEL NO.
VALVE SIZE SL.NO.
SUPPLY PRESSURE (bar)
JB & CUBICLE DETAILS JB & CUBICLE DETAILS
SOV CUBICLE&JB NO. SOV JB END FERRULE
MARSHALLING JB NO. MARSHALLING JB FERRULE
STATUS JB NO. STATUS JB FERRULE
RELAY DETAILS RELAY WIRING DETAILS
MAKE RACK NO.
MODEL NO. RELAY NO.
SL.NO. FIELD END TB NO.
STATUS TIB DETAILS STATUS TIB WIRING DETAILS
MAKE& MODEL NO. RACK NO.
SL.NO. TIB NO.
PLC IO DETAILS PLC IO DETAILS
IO CARD NO. SLOT
STATION CHANNEL
TEST DETAILS
COMMAND ISSUE OFF STATUS
CMD ACK COIL RESISTANCE ()
ON STATUS COIL VOLTAGE (DC VOLT)
INSULATION RESISTANCE INSULATION RESISTANCE
SOV COIL RACK - STATUS JB CABLE
RACK - MJB CABLE STATUS JB - PROXIMITY SWITCH CABLE
MJB - SOV CABLE
MIMIC DISPLAY VERIFICATION RESPONSE TIME (sec)
COMMAND ISSUE ON TIME
CMD ACK&STATUS OFF TIME
SEALING & EARTHING CHECK OF FIELD OBSERVATIONS
SOV CUBICLE SOV BACK EMF DIODE CHECK
MARSHALLING& STATUS JB
CHAIN CALIBRATED ON:
TESTED BY VERIFIED BY CLEARED BY
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 195
SECTION/DIVISION NAME
CONTROL VAVE COMMAND CHAIN TEST REPORT
TAG NO.
PROCESS PARAMETER
DESCRIPTION
VALVE DETAILS
MAKE MODEL NO. SERIAL NO.
FIELD JB NO.: CMD PIN NO. FB PIN NO.
POSITIONER DETAILS
MAKE MODEL NO. SERIAL NO.
POSITIONER SETTINGS
GAIN CL INT TIME CL SET TIME CL
GAIN OP IN TIME OP SET TIME OP
CONTROL GAP
TIB DETAILS MAKE MODEL NO. FIELD TB NO. SL.NO.
COMMAND
FEEDBACK
PLC IO CARD DETAILS SLOT CHANNEL
COMMAND
POSITION FEEDBACK (M)
TEST DETAILS
CONTROLLER CONSTANTS KP KI KD
INSULATION RESISTANCE(G) COMMAND LOOP FEEDBACK
LOOP
RACK - FJB CABLE
FJB - CONTROL VALVE CABLE
OPENING COMMAND (%)
CURRENT TO
POSITIONER
(mA)
PHYSICAL OPENING (%) CURRENT FROM
POSITIONER (mA)
POSITION
FEEDBAC
K (%)
MIMIC DISPLAY
RESPONSE TIME (sec)
ON TIME (0-100%)
OFF TIME (100-0%)
FIELD OBSERVATIONS
SEALING CHECK OF FIELD JB
EARTHING CHECK OF FIELD JB
T& E DATE
TESTED BY VERIFIED BY CLEARED BY
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 196
ANNEXURE-G
(Process & Instrumentation Diagrams and Layout)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 197
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 198
ANNEXURE H
(Price Format)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 199
Price Format
Sl.No Items Unit Qty. Unit Rate Total cost
1 Pressure Transmitters with
manifolds
Nos
50
2 Temperature transmitter
Nos 28
3 Solenoid dual coil including
plunger unit
Nos
100
4
Isolation Barrier (IB)
TIB for transmitters.
Nos
150
TIB for status
Nos
120
TIB for Control valve command Nos
10
TIB for Control valve feed back
Nos 10
ZB for Transducer Excitation
Nos 20
ZB for Transducer Sense
Nos 20
ZB for Transducer output
Nos 20
TIB for Transducer current
Excitation
Nos 10
Zener Barrier for RTD
Nos 20
High Freq. TIB for Transducer
output
Nos 12
5 Voltage isolator
Nos 90
6 Pulse isolator
Nos 10
7 Hall effect sensor
Nos 32
8 Relays
Nos 200
9 Flow Totalizer for turbine FM
Nos 07
10 Proximity sensor
Nos 190
11
Power supply
24V±20%,20A (SMPS R)
Nos 10
24V±10%, 10A(SMPS R)
Nos 10
0-72V, 10A(SMPS R)
Nos 02
0-100 V, 10A(SMPS R)
Nos 02
±15V, 5A(Linear S)
Nos 02
24V±10%, 10A(linear S)
Nos 08
24V±10%, 20A(linear S)
Nos 04
12 PTFE cables
6 core shielded cable (22AWG)
m 500
32 core shielded cable (22AWG)
m 100
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 200
64 core shielded cable (22AWG)
m 200
96 core shielded cable (22AWG) m 1000
13
PVC armoured cables
2 core armoured PVC cable
m 3000
4 core armoured PVC cable
m 3500
6 core armoured PVC cable
m 1000
10 Core armoured PVC Cable
m 11000
PVC un-armoured cables
32 Core un-armoured PVC Cable
m 1000
64 Core un-armoured PVC Cable
m 1500
96 Core un-armoured PVC Cable
m 1500
14
PTFE cables
18AWG Single core wire (Red &
black)
m 2000
22AWG Single core wire (red,
black, Green, orange, blue &
white)
m 10000
24AWG Single core wire (red,
black, Green, orange, blue &
white)
m 750
15
T/C Extension Cable
Single pair T/C extension cable
m 2000
32 core T/C extension cable
m 800
16
Power cable
1.5 sq.mm m 1000
2.5 sq.mm m 650
17
Earth cable
2.5 sq.mm
m 1000
4 sq.mm m 300
18
Indicators , Switches &Keys
Indicators Nos 50
Authorization keys Nos 20
Switches with Indicators Nos 50
19 Industrial standard Connectors
(108 pin) Set 100
20 7 pin Circular Connectors Set 50
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 201
21 32 pin Circular Connectors Set 10
22 Miniature K-Type TC connector Set 150
23
Terminal block (2.5 sq.mm)
Terminal Blocks- No. of levels:1 ;
No of terminals:2 Nos 18000
Terminal Blocks- No. of levels:2 ;
No of terminals:4 with short link Nos 200
Terminal Blocks- No. of levels:2 ;
No of terminals:4 with cross link
Nos 100
Terminal Blocks- No. of levels:1 ;
No of terminals:2 with diode in
series
Nos 200
Terminal Blocks- No. of levels:1 ;
No of terminals:2 with diode in
parallel
Nos
200
Terminal block – Powering (Red,
Yellow and Blue)
Nos
500
24
Junction boxes
Type I : 600x400x225 Nos 10
Type II : 300x300x165 Nos 02
25
Compression fittings & SS tubes
12.7mm SS tube; Wall thickness:
1.6mm Mtrs. 200
8 mm SS tube Mtrs. 800
12.7mm SS tube union Nos. 100
12.7mm SS tube Tee Nos. 25
8 mm SS tube union Nos. 150
8 mm SS tube Tee Nos. 50
Bulk head union for 8mm tube Nos. 150
½” NPT SS Plug Nos. 100
¼” NPT SS Plug Nos. 100
26
Cable trays
Perforated MS Cable Trays- width:
50mm; Height: 12mm; Thickness:
1.6mm
m 2500
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 202
Perforated MS Cable Trays- width:
100mm; Height: 25mm; Thickness:
2.0 mm
m 1500
Perforated MS Cable Trays- width:
150mm; Height: 25mm; Thickness:
2.0 mm
m 1500
Perforated MS Cable Trays- width:
300mm; Height: 50mm; Thickness:
2.0 mm
m 1000
Ladder MS Cable Trays- width:
300mm; Height: 75mm; Thickness:
2.0 mm
m 600
Ladder MS Cable Trays- width:
600mm; Height: 75mm; Thickness:
2.0 mm
m 1500
27
Structural materials supply &
fabrication (various sizes of L-
angle& channel and 2“MS pipe
etc.)
kg 10000
28 Canopy Sq.m. 15
29
Instrumentation (600mm
W)Racks with accessories
Nos. 12
Instrumentation (1200mm
W)Racks with accessories
Nos. 02
30
Cable glands Suitable for the cable given below
(Nickel coated Brass Type)
2 core armoured PVC Nos 250
4 core armoured PVC Nos 300
6 core armoured PVC Nos 50
10 core armoured PVC Nos 120
32 core un-armoured PVC Nos 5
64 core un-armoured PVC Nos 15
96 core un-armoured PVC Nos 15
32 core PTFE Nos 05
64 core PTFE Nos 10
96 core PTFE Nos 50
2 core TC cable Nos 100
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 203
32 core TC cable Nos 10
31 Cable entry Plate Nos 20
32 Connector Mounting Plate Nos 25
33
Metal conduits, Metal flexible
hoses suitable for conduit, 4/3/2
way metal junction box suitable
for conduit bends, elbows, Tees
and couplers of required
quantities.
lot 1
34 Operator chair Nos. 30
35 CCTV system Details as per
table 1 Aux @
page 191
36 Inter communication system
37 Timing system
38
Harnessing Materials
Lasing tie
Mtrs. 5000
50mm cable tie (Pack of 1000
nos.)
packs 100
100mm cable tie (Pack of 1000
nos.)
packs 100
150mm cable tie (Pack of 1000
nos.)
packs 100
200mm cable tie (Pack of 1000
nos.)
packs 100
250mm cable tie (Pack of 1000
nos.)
packs 100
300mm cable tie (Pack of 1000
nos.)
packs 100
400mm cable tie (Pack of 1000
nos.)
packs 25
500mm cable tie (Pack of 1000
nos.)
packs 25
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 204
ANNEXURE-I
(Terms and Conditions)
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 205
TERMS & CONDITIONS
1.1. ENTIRE AGREEMENT
1.1.1. The Contract to be entered into shall convey the final agreement
between the Department and the Vendor on the terms and
conditions.
1.1.2. In the event of conflicts between general conditions of Contract and
the specification furnished by the Department, the latter will take
precedence.
1.2. MODIFICATIONS TO THE CONTRACT
This Contract may be amended or modified only in writing signed by
both the parties or their duly authorized agents or representatives by
a change order issued by the Department and accepted by the
Vendor, pursuant to the terms stated therein.
1.3. CANCELLATION OF CONTRACT
1.3.1. The Department will have the right, at any time, to cancel the
Contract either wholly or in part by giving written notice. The Vendor
shall undertake to observe the instructions of the Department as to
the winding up of the Contract both on his own part and on the part
of his sub-vendors.
1.3.2. In the case of cancellation of the Contract by the Department without
any fault of the Vendor, the Vendor shall forthwith take the necessary
steps to implement the Department’s instructions. The period to be
allowed to implement shall be fixed by the Department after
consultation with Vendor and, in general, shall not exceed 2 months.
1.3.3. The ownership of all materials, part and unfinished work paid for by
the Department under the provisions of this Section shall be vested in
or transferred to the Department as soon as they have been paid for.
1.4. VENDOR’S DEFAULT LIABILITY
1.4.1. The Department shall reserve the right to terminate the work in the
circumstances detailed hereunder:
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 206
a. If the Vendor fails to rectify or replace any defective system/ sub-
system/ equipment within a period of 60 days after the
Department having given a notice to the Vendor to rectify or
replace the said defective system/ subsystem/ equipment or the
Vendor delays, suspends or is unable to complete the system/
subsystem/ equipment by the date mutually agreed upon
b. If the vendor commits breach of any of the terms and conditions
of the Contract.
c. If the Government of India decides to terminate the Contract in
public interest.
1.4.2. When the Vendor makes themselves liable for action under the
circumstances mentioned above, the Department will have power to
forfeit the bank guarantee of Vendor and the Vendor shall have no
claim for damages whatsoever on such forfeiture.
1.4.3. The work remaining to be completed at the time of termination of the
Contract shall be got executed through any other Vendor, in which
case the expenses, which may be incurred in excess of sums, which
would have been paid to the original Vendor, had the whole work
been executed by them, shall be borne by the original Vendor and
shall be recovered from them.
1.5. CHANGES AND MODIFICATIONS TO SPECIFICATIONS AND
QUALITATIVE REQUIREMENTS
1.5.1. The Department shall reserve the right at any time to modify the
qualitative requirements, specifications, patents or drawings related
to the work covered by the Contract. The Vendor shall inform to the
Department within 30 days, of any objections they have to the
modifications required.
1.5.2. The Department may also accept the modification proposed by the
Vendor on his own initiative or on behalf of sub-vendors or as a result
of detailed engineering review.
1.5.3. When a modification or other change is so authorized, the Vendor
shall proceed with action in accordance with the Department’s
direction. They shall moreover, as soon as possible after the receipt of
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 207
such directions, submit to the Department a firm and detailed
estimate showing any decrease or increase in the cost entailed by the
modifications and any effect its introduction will have on the delivery
schedule.
Any amendment to the Contract which may be necessary in this
respect will be established within a reasonable time in the form of
amendment to Contract, to be signed by both the parties. If the
parties do not agree on the amendments to the Contract, in particular
regarding prices, responsibility, delivery schedule etc, dispute shall be
submitted to arbitration.
1.6. SUB-CONTRACTING
The Vendor shall not assign or sub-contract the work or any part of
the work without the written approval of the Department. In the
event of approval of sub-vendors, the detailed specifications and
drawings of sub-contracted items shall be approved by the
Department. All the works carried-out by such sub-vendors shall also
be scrutinized, inspected and approved by the Department. However
the responsibility of such sub-contracted systems shall lie with the
Vendor. Any delay in carrying out the work by the sub-vendor which
affects the overall schedule of the work does not absolve the Vendor
from payment of compensation for the delays. All terms and
conditions applicable to the Vendor shall also be applicable to sub-
vendor.
1.7. COMPLIANCE WITH STANDARDS
All the materials supplied or used shall be of new and first quality and
manufactured and tested in accordance with the latest editions of the
relevant Indian/ International standards. Wherever imported
components are used, they shall be manufactured in accordance with
the relevant standards published in the country of manufacture after
allowing for specific aspects under Indian conditions such as tropical
climate, etc. Any material or work, where no specific standard is
applicable, shall be fabricated as per the instructions and directions of
the Department.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 208
All the electrical equipments used shall conform to the latest Indian
Electricity rules as regards safety, earthing and other essential
provisions specified therein for installation and operation of electrical
parts.
1.8. SECRECY
The technical information, drawings, specification and other related
documents forming part of enquiry or Contract are the property of
the Department and shall not be used for any other purpose, except
for execution of the Contract. All rights, including the rights in the
event of grant of a patent and registration of designs are reserved.
The technical information, drawings, specifications, records and other
documents shall not be copied, transcribed, traced or reproduced in
any other form or otherwise in whole and/ or duplicated, modified
and/or disclosed to a third party and/or not misused in any other
form whatsoever without the Department’s consent in writing except
to the extent required for the execution of the work. This technical
information, drawings, specifications, records and other documents
shall be returned to the Department with all approved copies and
duplicates, if any, immediately after they have been used for the
agreed purpose.
1.9. INSPECTION OF WORK
1.9.1. The Department or any person appointed by it shall have access and
right to inspect the work, or any part thereof, at all times and places
during the progress of the work. The inspection and supervision is for
the purposes of assuring the Department that the plans and
specifications are being properly executed and while the Department
and its representative(s) will extend to the Vendor all desired
assistance in interpreting the plans and specifications, such assistance
shall not relieve the Vendor of any responsibility for the work. Any
work which is proved faulty shall be corrected by the Vendor without
delay. The fact that faulty work or work which is not in accordance
with plan and specifications was not pointed out by the Department
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 209
will not relieve the Vendor from correcting such work as directed by
the Department without additional compensation.
1.9.2. The Department’s representatives shall at all reasonable times have
free access to the works and/ or to the workshops, factories or other
places where materials are being prepared or fabricated for the work
and also to any place where the materials are lying or from where
they are being obtained, and the Vendor shall give every facility to
the Department’s representatives for inspection and test of the
materials and workmanship even to the extent of discontinuing
portions of the work temporarily or of uncovering or taking down
portions of finished work.
1.9.3. The Department has no obligations to discover defects patents or
otherwise and it shall be the sole responsibility of the Vendor. The
inspection and clearance for dispatch by Department’s
representatives shall not absolve the Vendor’s obligations and duties
under terms and conditions herein.
1.10. CO-ORDINATION WITH OTHER VENDORS AND INTERFACING OF THE
WORKS
The Vendor shall extend all co-operation to other Vendors of the
Department to perform their works at site simultaneously. The
Vendor shall so arrange their activities so as to ensure smooth and
timely execution of the project, minimize interference with the works
of the other Vendors and allow the other Vendors to use the facilities
engaged by them for erection activities. For this purpose, the Vendor
shall plan such works and indicate such interfaces in an interface
schedule. They shall not be entitled to any extra payment on this
account.
1.11. FORCE MAJEURE
If at any time during the execution of the Contract, the performance
in whole or in part by either party of any obligation under the work is
prevented or delayed by reasons of any war, hostility, acts of the
public enemy/terrorist, civil commotion, sabotage, fire, flood, earth
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 210
quake, epidemics, quarantine restrictions, strikes, lock-outs, or acts of
God (hereinafter referred as Eventualities) and if notice is given by
either party to the other within 21 days from the date of occurrence
thereof, neither party shall for such eventuality be entitled to
terminate the work nor shall any party have any claim for damages
against the other in respect of such non-performance or delay in
performance. The performance under the work shall be resumed as
soon as practicable after such eventualities have come to an end and
the decision of the Department whether the performance has been
resumed or not shall be final and conclusive.
Provided further that if the performance in whole or in part of any
obligation under the work is prevented or delayed by such eventuality
for a period of exceeding 60 days, the Department may at their option
terminate the Contract provided also if the work is terminated under
this clause, the Department will be at liberty to take over from the
Vendor at a price fixed by the Department which shall be final. All
unused, un-damaged acceptable materials, bought-out components
lying in stores in course of erection and commissioning in the
possession of the Vendor at the time of such termination of such
portion thereof as the Department may deem fit excepting such
material, bought-out components lying in stores as the Vendor may
with the concurrence of the Department elect to retain.
1.12. INDEMNITY TO DEPARTMENT AGAINST INFRINGEMENT OF LABOUR
LAWS
The Vendor shall indemnify the Department against any action, claim
or proceedings relating to infringement of all or any of the prevailing
labour laws of India like Workmen’s Compensation Act 1923, Work
Labour (Regulation and Abolition), Central Rules 1971, Employees
Liability Act 1938, Industrial Disputes Act 1947, Employees Provident
Funds and Miscellaneous Act 1952 as amended from time to time
during erection and commissioning at Department’s site.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 211
1.13. PATENT RIGHTS
The Vendor shall fully indemnify the Department against any action,
claim or proceedings relating to infringements or use of any patent or
any design or any alleged patent or design rights and shall pay any
royalty which may be payable in respect of any claims made under or
any action brought against the Department. In respect of such
matters as aforesaid, the Vendor shall be set at liberty, at their own
expense, to settle any dispute or to conduct any litigation that may
arise there-from. The Vendor shall not be liable to indemnify the
Department on the infringement of the patent or design or any
alleged patent or design right which is the direct result of an order
passed by the Department.
1.14. ARBITRATION
Except matters in respect of which the decision of the Department is
final as specified in the Contract, any dispute, disagreement or
question arising out of or relating to or in consequence of the work or
fulfillment or the validity of the enforcement thereof which cannot be
settled mutually, shall within 30 days from the date that either party
informs the other in writing that such dispute or disagreement exists,
be referred to arbitration. The Arbitrator shall be a serving Law Officer
of the rank of Joint Secretary to the Government of India from a panel
of names as laid down in the Government of India, Bureau of Public
enterprises Circular and as modified from time to time. The
performance under this work shall continue during the arbitration
proceedings and no payment due or payable by the Department will
be withheld unless any such payment is or forms part of the subject
matter of the arbitration proceedings.
1.15. ASSIGNMENT
The work shall be binding upon the successors and the assignees of
the parties hereto. It shall not be assigned in whole or in part by
either party without prior written consent of the other. If the Vendor
becomes insolvent or being a firm or a company whether
incorporated or not is dissolved or goes into bankruptcy or is caused
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 212
to be wound up except for re-construction purposes or carried on its
business under a receiver, the representatives in law of estate of the
Vendor or any such receiver, liquidator or any person in whom the
agreement may be vested shall forthwith give notice thereof in
writing to the Department and shall remain liable for the successful
performance of the Vendor or the successors of their obligations
under this Contract under any circumstances.
1.16. JURISDICTION AND APPLICABLE LAW
The work shall be governed by the laws of India for the time being in
the force. The courts of the Tirunelveli, Tamil Nadu state only shall
have jurisdiction to deal with and decide any legal matters or dispute
whatsoever arising out of the work.
1.17. EXECUTION OF WORK
The specifications of the work are intended to describe and provide
for a complete finished system. It is to be understood and agreed by
the Vendor that the work described shall be complete in every detail,
even though every item necessarily involved is not particularly
mentioned. The Vendor shall be required to provide all labour,
materials and equipments necessary for the completion of the work
described and shall not avail themselves of any manifesting
unintentional error, omission or inconsistency that may exist. The
Vendor shall carry out and complete the work in every respect in
accordance with the Contract and the directions and to the
satisfaction of the Department.
1.18. RIGHTS OF THE DEPARTMENT
1.18.1. RIGHT TO ILLUSTRATE AND EXPLAIN PLANS
a. The various parts of the Contract are intended to be
complementary to each other but if any discrepancies appear or
any misunderstanding arises, the explanation of the Department
will be final and binding.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 213
b. The corrections of any errors or omissions of specifications may
be made by the Department, when such correction is necessary
to bring out clearly the intention which is indicated by a
reasonable interpretation of the specifications as a whole.
c. Wherever in the specifications which are a part of the work or
which may be furnished to the Vendor for directing the work,
the terms and descriptions of various qualities of workmanship,
materials, structures, processes, plant or other features of the
work are described in general terms, the meaning of fulfillment
of which must depend upon individual judgments, then in all
such cases, the question shall be decided by the Department and
said material shall be furnished, said work shall be done and said
structure or feature shall be constructed, furnished or carried out
in full and in accordance with their interpretation of the same
and to their full satisfaction and approval, provided such
interpretation is not in direct conflict with the specifications or
generally accepted good practice.
1.18.2. RIGHT TO DIRECT WORK
a. The Department will have the right to direct the manner in which
all work under this Contract shall be done, in so far as it may be
necessary to secure the safe and proper progress and the
specified quality of the work and all work shall be done and all
material shall be furnished to the satisfaction and approval of the
Department.
b. Whenever, in the opinion of the Department, the Vendor has
made marked departure from the schedule of completion laid
down in the Contract or when untoward circumstances force
departure from the said schedule, the Department in order to
assure compliance with the schedule and the provisions of the
work, shall direct the order, pace and method of doing the work,
which shall be adhered to by the Vendor.
c. If, in the judgment of the Department, it becomes necessary at
any time to accelerate the overall execution of the work, the
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 214
Vendor when ordered and directed by the Department will cease
the work at any particular point and transfer their men to such
other point or points and execute such portion of their works, as
may be required, to enable others to hasten and properly engage
and carry on their work, as directed by the Department.
d. The work by the Vendor at the site beyond normal working hours
(08:45 to 17:15 hr) on working days and any time on holidays
(including Saturdays and Sundays) shall be permitted only with
prior approval of the Department. The Department may also
direct the Vendor to operate extra shifts over and above normal
day shift to ensure completion of the work on schedule if, in the
opinion of the Department, such work is required.
1.19. VENDOR’S FUNCTIONS
1.19.1 The Vendor shall provide everything necessary for proper execution
of the work according to the intent and meaning of the
specifications whether the same may or may not be particularly
shown or described therein, provided that the same can reasonably
be inferred there-from and if the Vendor finds any discrepancy
there-in, they shall immediately and in writing refer the same to the
Department whose decision shall be final and binding on the
Vendor.
1.19.2 In the execution of the work, no person other than the Vendor, or
their duly appointed representatives, their sub-vendors, and their
workmen, shall be allowed to work at the site except by special
permission, in writing by the Department.
1.19.3 The Vendor shall proceed with the work to be performed under this
Contract and each and every part and detail thereof, in the best and
most workmen-like manner by engaging qualified, careful and
efficient workers and to the several parts thereof at such time and in
such order as the Department directs and finish such work in strict
conformance with the drawings and/or specifications and any
changes, modifications thereof made by the Department.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 215
1.19.4 The Vendor’s personnel shall not be permitted to reside inside the
Department’s premises after the work. The Vendor shall arrange for
transportation, accommodation, food, health care, communication,
etc. for their personnel.
1.19.5 In respect of observance of local rules, administrative orders, working
hours and the like, the Vendor and their personnel shall co-operate
with the Department.
1.20. SUPPLY OF TOOLS, AND OTHER MATERIALS
1.20.1. For full completion of the work, the party shall, at their own expense,
furnish all erection tools, power tools, cables, wiring tools, test
instruments, and all associated protective equipments, appliances,
materials required to accomplish the work under the contract unless
otherwise provided for. Adequacy of such tools shall be subject to
final determination of the Department.
1.20.2. The party shall not dispose, transport or withdraw any tools,
equipments and materials provided by them for the contract without
taking prior written approval from the Department and the
Department at all times shall have right to refuse permission for
disposal, transport or withdrawal of tools, equipment and material if
in their opinion, the same will adversely affect the efficient
completion of the work.
1.20.3. The Vendor shall also furnish all necessary expendable devices like
anchors, grinding and abrasive wheels, plugs, hacksaw blades, taps,
dies, drills, reamers, chisels, files, carborundum stones, wire brushes,
necessary scaffolding, ladders, wooden planks, timbers, sleepers, and
consumable materials like oxygen, acetylene, argon, lubricating oils,
greases, cleaning fluids, cylinder oil, graphite powder and flakes,
fasteners, gaskets, temporary supports, stainless steel shims or
various thicknesses as required, cotton waste, PTFE tapes and all
other miscellaneous supplies of every kind required for carrying out
the work under the contract.
1.21. PROTECTION OF WORK
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 216
1.21.1. The Department will not be responsible or held liable for any damage
to person or property consequent upon the use, misuse or failure of
any fabrication tools and equipment used by the Contractor or any of
their sub-contractors.
1.21.2. The Contractor shall effectively protect all the works from action of
weather and from damages or defacement and shall cover finished
parts where required for their thorough protection.
1.21.3. The Contractor shall cover the work by a Contractor’s all-risk
policy during the currency of the contract.
1.22. SITE PERSONNEL
The party shall identify a Site Supervisor and he/ she shall be
personally present to supervise the work under the contract. The Site
Supervisor shall have full technical capability and complete
administrative and financial powers to expeditiously and efficiently
execute the work under the contract. Any written orders or
instructions which the Department may give to the party’s Site
Supervisor shall be deemed to have been given to the party.
1.23. FIRST AID
The Vendor may have access to the Departments’ qualified first aid
personnel and ambulance in case of accidents, subject to the
availability of the same. However, the Vendor shall make his own
medical and transport arrangements to take care of his employees in
case of accident. The Vendor shall provide a first aid kit at the work
site to meet the requirements of minor injuries.
1.24. REPORTING
The Vendor must report the following information to the
Department by the end of every week during the work at Department’s
site.
a) Progress achieved
b) Expected dates for completion of individual works
c) Any actual or likely delay in the execution of work
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 217
1.25. WORKING AND SAFETY REGULATIONS
The Vendor shall observe all statutory and legal requirements
enforced by Central and State Government applicable to the work as
well as any local regulations applying to the site issued by Department
or any other authority. Particular attention is drawn to the following;
a) In case of accident, the Department shall be informed in writing
forthwith. The Vendor shall strictly follow the regulations laid
down by the Factory Inspector, Central and State Government
authorities in this regard.
b) Compliance with all electricity regulations.
1.26. ELECTRICAL SAFETY REGULATIONS
In no circumstances will the Vendor interfere with fuses and electrical
equipment belonging to the Department or other Vendors. Before
the Vendor connects any electrical appliance to any plug or socket
belonging to other Vendor or Department, he will
a) Satisfy Department that the appliances are in good working
condition
b) Inform the Department of the maximum current rating, voltage
and phase of the appliance
c) Obtain permission of the Department detailing the sockets, to
which the appliance may be connected
1.27. POWER
Electricity will be supplied at free of cost. Contractor must provide
power supply distributor with isolator for taking power for his
equipments. Contractor should obtain Electrical safety clearance from
CMG/IPRC and safety clearance from safety division before starting
the work.
1.28. WATER
Free supply of water will be made available by the Department.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 218
1.29. CLEAN-UP OF WORK SITE
The party shall not store or place the equipment, materials or
erection equipment on the drive ways and streets and shall take care
that their work in no way restricts or impedes traffic or passage of
men and material. All waste materials are to be disposed off safely to
the location specified by the department
1.30. SAFETY AND RELIABILITY
1.31. Since the systems are highly complex in nature, the philosophy and
criteria to be adopted shall be highly safety-and-reliability-oriented for
their systematic and proper functioning. The designs of the sub-
systems, components, equipments to be carried out by the Contractor
shall specifically address essential safety provisions both in-built and
external. Reliability is a prime factor, which has to be embedded in the
process of realization of the systems. To ensure that the sub-system
design, development, selection of equipment, components, material,
etc are in compliance with the standard engineering practices, it is
necessary to follow established design codes and standards.
1.32. QUALITY ASSURANCE
The reliability of Instrumentation is a combination of specification of
the equipments/ components, serviceability and maintenance of the
same, which are meant to serve and provide effective and timely
operation, which includes trouble-free performance of systems and
sub-systems to the intended specifications.
The Contractor must look for the quality factors individually attributed
to engineering developments, selection of equipments and
components, test and acceptance procedures followed, repetitive
performance achieved, risk analysis carried out, etc. each and every
module must be manufactured and tested to international Quality
Control standards. The test certificates shall be provided to
Department.
The quality assurance is an unified approach that attempts to control
the quality right from design stage to commissioning stage, which
includes the checking of the adequacy of the equipments/ components
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 219
for materials, fabrication, installation, testing. It is the combined
responsibility of the Contractor and the Department to ensure that all
possible failure modes are exercised and validated during FAT.
1.33. PURCHASE OF MATERIALS
The selection of equipment's, components, materials, etc. with
appropriate and suitable specifications shall be the responsibility of the
Vendor, as overall performance of the system rests with the Vendor.
Accordingly, the selection and purchase tasks shall be handled by the
Vendor immediately after the approval of Detailed Engineering
documents by the Department.
The criteria for selection of particular product and the reasoning
involved therein shall be submitted to the Department for necessary
approval. However Department’s decision will be final.
The Department will provide necessary end-use certificate for obtaining
the required license for import of items if requested by the Contactor.
In keeping with the terms of the Contract, the Vendor shall undertake
the responsibility for handling, packaging and transportation involved
to the accepted level of any sub-systems/ equipment covered by the
work in the Contract.
1.34. GATEPASS
For Vendor’s equipment, tools, materials, etc. which are to be taken
out from IPRC, Mahendragiri campus after completion of work, proper
entry shall be made at the main gate duly endorsed by CISF. The
Department shall issue necessary gate passes for taking out the
Vendor’s materials, as and when required and after completion of
work.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 220
2 INSTRUCTIONS TO BIDDERS
The proposals are invited as sealed quotations on behalf of the
President of India by the Head, Purchase & Stores, IPRC, Mahendragiri,
from reputed Vendors of high competence for the following work for
IPRC, Mahendragiri, Tirunelveli District, Tamil Nadu State, India.
2.1 PRE BID MEETING
Within 2 weeks from date of floating of tender, it is proposed to brief all
interested bidders on the requirements of this RFP at IPRC,
Mahendragiri and the exact date will be intimated after tendering.
Bidders interested to participate in the pre-bid meeting shall
communicate their willingness in writing to Head, Purchase & Stores
immediately on receipt of this document. Tender of a firm which has
not attended the pre-bid meeting shall be considered for
disqualification.
2.2 SCOPE OF WORK
The scope of the work includes Detailed Engineering, Procurement,
erection & commissioning , test & Evaluation and documentation for
Bulk storage Facilities as per the specification given in this document.
The bidder is required to submit quotation for the entire works
mentioned herein. The incomplete quotations shall be summarily
rejected. The deviation, if any, in the bidder’s proposal with respect to
this document shall be explicitly mentioned in the schedule of
deviations to be provided in the quotation. If the bidder does not
mention any deviation, it shall be construed by the Department that
the bidder agrees to comply with each and every aspect of this
document.
2.3 EXECUTION PERIOD
The proposed work contract is to cater to the requirements of
procurement, installation and commissioning of instrumentation
system for New Test facility at IPRC, Mahendragiri. The contract shall be
valid for a period of 7 months from the date of award of contract. The
execution schedule shall be as given below.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 221
Sl. No Scope of work Period Responsibility
1 Detailed engineering and
acceptance by Department
after the P O
1.5 months Vendor
2 Equipment and material
supply after the sl no.1 1 month Vendor
3 Erection and commissioning
after the supply 3 months Vendor
4 Test and Evaluation &
documentation 1.5 month Vendor
2.4 COMPENSATION FOR DELAY
If the contractor fails to complete execution of the contract or fails to
meet delivery specified in the contract or any extension thereof, the
Department will recover from the Contractor as Liquidated Damages
(LD) a sum of 0.5% for the undelivered portion of the order value per
week subject to a maximum of 10%.
2.5 SECURITY DEPOSIT
The supplier / contractor shall provide bank guarantee for an amount
equivalent to 10% of the total order value towards security deposit for
the due performance of the contract (MSME firms are not exempted)
2.6 PERFORMANCE BANK GUARANTEE
If Performance Bank Guarantee for 10% of the order value shall be
submitted prior to final payment of the order and the same shall be
valid for 60 days beyond the warranty period.
2.7 DELIVERY TERM
All equipments/materials to be supplied by contractor shall be
delivered at IPRC, Mahendragiri. The party shall be responsible for
further transportation of items to erection site. Further responsibility
of handling and storage of all items lies with the vendor.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 222
2.8 LANGUAGES AND MEASURES
All documents pertaining to the Contract including specifications,
schedules, notices, correspondence, operating and maintenance
instructions, drawings or any other writings shall be written in
ENGLISH Language only.
2.9 DOCUMENTS
All operating, maintenance and technical manuals, drawings and
diagrams in English Language relevant to the systems/components
shall be supplied by the Contractor.
2.10 GUARANTEE
a) The “Defect Liability Period” shall be 12 months from the date of
successful completion of commissioning of instrumentation system.
The work shall not be considered as completed until the Department
has certified in writing that they have been actually accepted and
the Defect liability period shall commence from the date of such
certificate.
b) The equipments& material supplied by the vendor shall carry a
guarantee for a period of 12 months from the date of
commissioning, against any material defect, design defect,
manufacturing defect and/or failure of equipment to perform, as
stipulated.
c) In case any defect in the work due to bad materials, and/ or bad
workmanship develop in the work before the expiry of the period,
the Contractor, on notification by the Department, shall rectify or
remedy the defects at their own cost and shall make their own
arrangements to provide materials, labour, equipment and any
other appliances required in this regard.
d) The equipments, or components repaired or replaced by the
Contractor shall be guaranteed for a period of 12 months from the
date of repairs or replacement.
e) The Contractor shall furnish performance guarantee in the form of
bank guarantee at 10 % of the total contract value and shall be valid
for a period of sixty days, beyond the date of completion of all terms
and conditions/expire date of warranty period. If any defect is
noticed by the Department during the defect liability period and
Contractor fails to rectify or remedy the defects, the Department
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 223
will have the right to get this done by other agencies and recover
the cost incurred, as determined by the Department, which shall be
final and binding, by recovery from the amounts due to the
Contractor and/ or by enforcing bank guarantee.
2.11 INSURANCE
The contractor should take all necessary steps including the necessary
insurance cover till the system are dispatched & delivered at
purchaser’s site.
2.12 PACKING
The contractor shall pack all the equipments, materials and its
accessories and make the identification names at the top of each
pack. Proper packing shall be done so as to ensure that the items are
not damaged during transportation.
2.13 FORM OF QUOTATION
The quotation shall be submitted in two part,
a. Part - I Technical and commercial
b. Part - II Price
If any Tenderer includes, price of any nature in Part-I (Techno-
commercial) of the tender such offer will be rejected without any
notice to the tenderer.
The first shall contain the technical and commercial aspects shall
be opened first. The price quotation and the revision in prices thereof
if any submitted subsequently based on authorization from the
Department, shall be opened only after the evaluation of the
technical and commercial quotation.
All documents (including the drawings) issued in this tender
enquiry shall be returned along with the quotation. The bidder not
quoting for this enquiry shall return the tender documents (including
the drawings) to the Head Purchase & Stores, IPRC, Mahendragiri
within 15 days from due date of opening.
All corrections shall be attested by initials of the bidder with date.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 224
The Department reserves the right to reject any or all quotations in
whole or part without assigning reasons thereof.
2.14 PRICES
The bidder shall quote firm and fixed prices valid during the
execution of the Contract till commissioning and final acceptance of
the systems to the satisfaction of the Department. The prices shall
include all taxes, levies like octroi, duties, taxes, royalties, permits
charges, etc. levied by any central, state, local or other Governmental
authority, which the Vendor is required to pay in any country as well
as in India with reference to fabrication, purchase, transportation up
to the delivery point stated in this document.
The bidder shall provide the individual item wise break-up prices
as given in Annexure-B price format.
2.15 PAYMENT
Milestone payments: Milestone payment will be considered as
follows:
1. 80% of supply price shall be released after receipt and
acceptance of all items at Department site.
2. 10% of supply price shall be released after satisfactory
completion of commissioning of entire system (including
Testing & Evaluation& documentation).
3. Final 10 % of supply price shall be released upon completion of
all activities and on submission of bank guarantee of 10% of
order value.
2.16 VALIDITY: The quoted price should be valid for a period of 6 months
from the date of opening of the technical and commercial quotation.
2.17 QUANTITY VARIATION OF ITEM
The exact quantity and the list of items required for commissioning
the facility will be finalized during detailed engineering and 10%
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 225
quantity variation shall be permitted for supply and erection part of
contract.
2.18 BIDDER’S PROFILE
The bidder shall elaborately bring out in their quotation their company
profile, which shall be commensurate with the level demanded for the
execution of the work specified in this document. Vendors not meeting any of
the criteria will not be considered
1. Vendor should have similar experience and installations in major
industries/ISRO centres/ Defence/ Nuclear.
2. Financial soundness, specifying the annual turn-over, annual income tax
paid, name of the banker, etc.
3. Previous experience in the execution of projects of the nature and
quantum on par with those specified in this document.
4. Experience of having successfully completed similar works during last 5
years ending 31st
March 2018. Purchase order to be enclosed.
I. Three similar Supply and commissioning works costing not less
than each Rs. 1.0 Crore.
II. Two similar completed works costing not less than each
Rs. 2.0 Crore.
III. One similar completed works costing not less than
Rs. 3.0 Crore.
5. Adequate & suitably qualified and experienced in-house personnel at
all levels such as managerial, supervisory and tradesmen level and in
the area of design, development, fabrication, commissioning field
instrumentation, and procurement to execute the works given in this
RFP. The educational qualification, expertise and experience of the key
staff shall also be submitted.
6. Adequate facilities such as equipments, machineries, tools and other
infrastructures to carry out fabrication and field commissioning
7. Should be preferred to have ISO Certification.
8. Documentary evidence for successful completion of projects obtained
from the customer may be provided.
REQUEST FOR PROPOSAL (RFP) ON NEW TEST FACILITY INSTRUMENTATION SYSTEM
Page 226
9. Detailed design document, chain diagrams, component specs,
calibration details with manufacturer’s catalog, and technical
documents (operational manuals, detailed technical manuals, service
and maintenance manuals) of all sub-systems should be supplied to
IPRC by the Party along with equipment supply
10. The Detailed engineering document prepared by the vendor shall be as
per ISRO Standard. These copies should also be provided in softcopy
version.