REPUBLIC OF IRAQ · 2018. 2. 20. · Old pipe drawings Project Description This Subproject consist...

69
REPUBLIC OF IRAQ Ministry of Construction, Housing, Municipalities and Public Works Emergency Operation Development Projects (EODP) (P155732) Environmental and Social Management Checklist for Implementation of Transmission Pipeline 300 mm and Rehabilitation of Al- Zargania Low Lift Station - Diyala Governorate W10B December 5 , 2017

Transcript of REPUBLIC OF IRAQ · 2018. 2. 20. · Old pipe drawings Project Description This Subproject consist...

  • REPUBLIC OF IRAQ

    Ministry of Construction, Housing, Municipalities

    and

    Public Works

    Emergency Operation Development Projects (EODP)

    (P155732)

    Environmental and Social Management Checklist

    for

    Implementation of Transmission Pipeline 300 mm and Rehabilitation of Al-

    Zargania Low Lift Station - Diyala Governorate – W10B

    December 5 , 2017

  • 2 / 69

    IRAQ: Emergency Operation for Development Project

    PART A: General Project and Site Information

    INSTITUTIONAL & ADMINISTRATIVE

    Country IRAQ

    Project title Implementation Transmission Pipeline 300 mm and Rehabilitation of Al-Zargania low lift station - Al-Aazeem

    district- Diyala Governorate – W10B

    Institutional

    arrangements

    Project Owner: MMPW

    Person in Charge: SMO

    Name: Eng. Salih Jabbar Abbas

    Title: PMT Director

    Contact: [email protected]

    Local Counterpart(s): Diyala Governorate

    Person in Charge: Diyala Water Directorate

    Name: Murtada Jasim Hammod

    Title: Diyala Water Director

    Contact: [email protected]

    Environmental Resident Engineer

  • 3 / 69

    and Social

    Management

    Implementation

    arrangements

    Name: To be set later

    Contact:

    PMT Supervision:

    Name:

    Title: follow up engineer

    Contact:

    Local Site Supervision:

    Name:

    Title:

    Directorate: To be set later

    Contact:

    Local Counterpart Supervision:

    Contractor:

    Safeguard Supervision

    Name: To be set later

    Title:

    Contact:

  • 4 / 69

    PROJECT LOCATION & SITE DESCRIPTION

    Project

    Location

    The project is located in the town of Al-Azim (Al-Adhim) (34° 0'30.39"N, 44°22'27.79"E), Diyala Governorate, approximately 100 km north of the capital city of Baghdad. The town is situated on the bank of the Al-Azim River.

    Map below shows the project location.

  • 5 / 69

    Figure 1: Project Location

  • 6 / 69

  • 7 / 69

  • 8 / 69

  • 9 / 69

    Google map of the transmission pipeline

    The predominant land use in the vicinity of the project and in the area adjacent to it is rural residential and the

    surrounding land is vacant.

  • 10 / 69

    Old pipe drawings

    Project

    Description

    This Subproject consist of supply, implementation new pipeline instead of the old one which will be implemented

    beside the existing pipes which transport the raw water from the lift station to the booster station ( as shown in Fig.

    below and rehabilitation low lift station

    For the low lift station The main objective of the subproject is the rehabilitation of the facilities

    Low lift station consists of the following parts:

    low lifting pumps.

  • 11 / 69

    Electric transformer.

    Generator.

    Main electrical board.

    Cables.

    Hydrophone system.

    Site Google

    Map

  • 12 / 69

    Figure 2: Project Site and Adjacent Areas

    Current

    condition of the

    facility

    At present the unit is not operational due to the damage during the combat operations in the area. The damage can be

    described as severe and

    includes the following:

    Structural damage to the existing

    operational facilities;

    Damage to electrical network;

    Damage to mechanical parts: rusted

    and broken pipes;

    destroyed network

  • 13 / 69

    connections, destroyed sanitary facilities.

    Figure 3: Damage to

    the Facilities

    Current

    Alternatives

    At present the population relies on the water delivered by water tankers for drinking purposes which imposes

    additional financial burden on the community, as well as severe limitations on the water provision.

    For irrigation, in areas close to the river bank, the water is pumped directly from the river.

    Project

    Duration

    The expected project duration is 9 months.

    Table 1: Duration of Construction Activities

    # Activity Duration (man days)

    1 Cleaning of the site 75

    2 Rehabilitation of pumps 60

    3 Installation of pipes` 200

    4 Casting and installation of manholes 100

    Proposed

    Project

    Activities

    The project scope comprises of the following components:

    Civil Works:

    Cleaning of the site;

    Installation of transmission lines and network connections.

    Rehabilitation of pumps.

    Casting and installation of new manholes.

  • 14 / 69

    Electrical and mechanical works:

    The works above include supply, installation, operation and testing of the pumps and the fittings

    Land

    Acquisition

    The project comprises the rehabilitation of the existing facilities with no additional structures to be constructed and

    the new pipeline will be implemented beside the old pipelines within the roadblocks, Therefore, the project will not

    require any permanent land acquisition.

    The construction camp is envisioned to be located within the perimeter of the compact unit; therefore, the project

    will not require the temporary land acquisition.

    Contactor’s

    Camp

    The existing building comprises rooms as offices for the engineers and operators and others for the guards.

    The Contractor's main camp, will contain, the operational center, with prefabricated offices and parking areas for

    administration and technical staff. This will also include areas with sheds for materials testing storage, maintenance

    and equipment cleaning. The need for residential accommodation is likely to be relatively minor, except for security

    personnel and operators which they woks in 3 shifts, 3 persons for each shift.

    It is to point out that the sub project run by three shifts, each shift is setup of two operators and one guard

    The total number of personnel including technical, administrative staff and skilled and unskilled labor is expected

    not to exceed 45 persons on daily bases. The employed personnel will be mostly from the neighborhood areas and

    Iraqi nationals.

    The construction camp should have independent sources of water and electricity, and the septic tank for the working

    teams effluent disposal.

    PROJECT BASELIN CONDITIONS

    Description of

    Geographic

    Conditions

    The terrain is characterized as flat to gently rolling plains, hills, and mountains. In the project area the elevations are

    ranging between 300-550 m asl. The maximum elevation is 543.5 m asl and the minimum elevation is 313.9 m asl.

    The surrounding land use is characterized as rural residential, with the predominance of the flood irrigated

  • 15 / 69

    agriculture and limited rain-fed agriculture mostly of cereals.

    Description of

    Physical

    Conditions

    The climate in the project area is characterized as Mid-steppe and desert climate. The average temperature is 22.2°C.

    The warmest month, on average, is July with an average temperature of 35°C. The coolest month on average is

    January, with an average temperature of 9.4°C. The average amount of precipitation per year is 348 mm. The

    predominant wind direction is Northeast in the months November through to April, and predominantly north-west in

    the months May-October. The mean average wind speed is 10-12 km/h with the wind gusts reaching up to 26-28

    km/h.

    The predominant wind direction is Northeast in the months November through to April, and predominantly north-

    west in the months May-October. The mean average wind speed is 10-12 km/h with the wind gusts reaching up to

    26-28 km/h.

    The main sources of the air pollution is dust generated by moving of vehicles on unpaved surfaces.

    The area is rural residential and noise is limited to the passenger vehicle movement.

    Description of

    Geological

    Conditions

    Stratigraphically, the project area is dominated by geological formations ranging from Middle Miocene to

    Quaternary. In the project location the geological formation is composed of thin-bedded, black bituminous

    limestone, dolomitic limestone and black papery shale with streaks of thin black chert.

    Tectonically Iraq is located in a relatively active seismic zone at the northeastern boundaries of the Arabian Plate.

    Seismic zoning of Iraq is divided into four zones. The project area is located in the minor damage zone with the

    seismic activity of IV on Richter scale.

    Description of

    Hydrogeology

    Conditions

    According to the hydro-geological classification of Iraq, the project area is located in the Low Fold hydro-geological

    zone. The Low Fold zone is filled by sedimentary formations that range in age from Late Miocene to Recent: Fatha,

    Injana, Mukdadiyah and Bai Hassan, and Quaternary cover. These formations represent the main aquifers in this

    zone. The general trend of the groundwater movement is mainly from north and northwest towards south and

    southeast.

    Generally, the salinity of the groundwater increases from north to south. It increases from the recharge sources at the

    high land areas (less than 1000 mg/l), towards the discharge areas along the Mesopotamia Zone and Al-Jazira Zone

    (more than 10000 mg/l). Groundwater quality is mainly bicarbonate at the recharge areas, and becomes sulphatic at

    the discharge areas. The groundwater quality in the project area is slightly brackish with the salinity of 1000-3000

  • 16 / 69

    ppm. The groundwater depth in the project area ranges from 20-30 m below surface.

    At present there is no information available about the wells in the project area.

    Description of

    Surface water

    The project is located in close proximity to Adhaim Dam is a multi-purpose embankment dam on the Al Uzaym

    (Adhaim) River 133 km northeast of Baghdad, Iraq. The purpose of the dam is flood control, hydro-power and

    irrigation. The dam was completed in 2000 with only the embankment, spillway and intake. The power station and

    irrigation outlets are unfinished. When complete, the power station will have a 27 MW installed capacity and the

    irrigation outlet will be able to discharge 73 m3/s. The surface water is characterized as intermittent run-off streams

    mostly filled with water in winter rainy season and dry in summer. The majority of these streams discharge the water

    into Tigris River with the contribution to the river flow negligible (0.2 MCM on average for the year 2008). The area

    consists of potentially fertile soils characterized as heavy alluvial soils, with some organic content and a high

    proportion of clays. The soil classification is approximately 75% silty loam, the rest are silty clay loam and clay soil.

    The river bed is composed of fine sand, silt and clays with rather high sedimentation load.

    Description of

    Ecology

    Conditions

    The project area is located in the Mesopotamian shrub desert terrestrial eco-region1 considered as a transitional zone

    between the Syrian Desert and steppe region further north. This terrestrial eco-zone is categorized as vulnerable and

    due to the security concerns have received little focused study.

    Vegetation reflects the Mesopotamian province of the Irano-Turanian eco-region and is characterized by the

    dominance of the drought-tolerant low shrubs with a variety of grasses and legumes.

    Large mammals that are associated with this ecoregion include: Red fox (Vulpes vulpes); wildcats (Felis silvestris);

    Greater Horseshoe Bat (Rhinolophus ferrumequinum). Other mammalian species include: Long-eared hedgehog

    (Hemiechinus auritus), Asian house shrew (Suncus murinus), Euphrates jerboa (Allactaga euphratica), black rat

    (Rattus rattus).

    Reptilian and amphibians associated with this eco-region include: Green Toad (Bufo viridis), Green Frog

    (Pelophylax ridibunda), Keeled Rock Gecko (Cyrtopodion scaber). Persian Gecko (Asaccus elisae), Snake-eyed

    lizard (Ophisops elegans), Desert monitor (Varanus griseus).

    1 National Report on Biodiversity in Iraq, July 2010

    https://en.wikipedia.org/wiki/Embankment_damhttps://en.wikipedia.org/wiki/Baghdad,_Iraq

  • 17 / 69

    The area of the project is located in a general area identified as a fly-way route for migratory birds from Eastern

    Europe and West Siberia to Mesopotamia and Africa.

    The riparian vegetation predominantly comprises reeds and rushes. The fauna of the freshwater eco-systems is

    dominated by cyprinids, approximately 75% of the eco-region’s species and native fauna is represented by genus

    Barbus considered as economically important species.

    The project area does not contain any globally important habitats or ecosystems. There are no Nature Reserves or

    other legally protected areas in the vicinity of the project or in a close proximity. No conservation practices are

    exercised in the project area apart from the control of hunting to the extent they are controlled and monitored

    throughout the country.

    Description of

    Physical

    Cultural

    Resources

    Diyala Governorate has an important historical value as it witnessed the succession of Great Sumerian, Akadian,

    Assyrian and Babylonian and Persian empires. Also, the governorate is located on the Silk Road connecting Iraq

    with the East. There are no known sites of historical and archeological importance within the immediate vicinity of

    the project, however, caution should be exercised in excavation.

    Description of

    Socio-

    Economic

    Context

    Population: Diyala Governorate - 1,133,627 (3.6% of total population of Iraq). Population of Aazeem approximately

    20,000. The population is predominantly urban - 74.5% and the gender division is 49.4% male and 50.6% female.

    The main economic activities - agriculture, livestock raising, and poultry farming.

    In 2011, 10.3% of the population lived below the poverty line of US$ 2.5 per day, which is lower than the national

    level (11.5%).

    The overall unemployment rate is 15% above the national rate of 11.3%. 40.5% of the labor force is employed in the

    services sector, while 18.7% works in the building and construction sector, 12.9% works in the wholesale and retail

    trade, restaurant or hotels, and 10% works in the agriculture, forestry, and fishing sector.

    The literacy rate is 84.2% which is higher than the national average. In 2011, enrolment in primary education was

    90.3% for females and 94.2% for males.

    In Diyala, the proportion of the population with sustainable access to an improved water source is 74.8%, which is

    the lowest in the country but slightly higher than its value in 2006 (72.5%). 71.7% of the population relies on the

    public network as first source of drinking water, while 11.9% relies on a stream, river, or a lake, and 11.7% relies on

  • 18 / 69

    a water tanker or vehicle.

    Access to the public sewage system is also lower than average in Diyala, with only 0,8% of the governorate’s

    population primarily relying on it of effluent disposal.

    The power cuts are frequent in Diyala, with almost 60% of the governorate’s inhabitants to rely on a secondary

    power source besides the public network like private or shared generators to fulfill its power needs.

    23.8% of the population in Diyala has home domestic waste collection services, while 4.6% relies on public

    containers, and 70.6% of residents burn, bury, or dispose of domestic waste in open areas. In Khanaqin more than

    30% of the population is provided with waste collection services.

    Public hospitals are the health facilities most used by people in case of illness of a household member 37.6%,

    followed by clinics or private medical complexes 36.5%, and clinics or governmental health centers 22.3%. Since the

    beginning of the armed conflict, the area witnessed a sharp decline in provision of the healthcare services. According

    to the available information, less than 10% of healthcare facilities are functional at present.

    Two main Iraqi Highways cross the project area:

    Highway 4: from Kirkuk to Sadiya, passes through Sulaimaniyah to Darbinadikhan and Jalula;

    Highway 5: from Baquba to Qasr-el-Shirin in Iran, passes through Muqdadiyah, Sadiya and Khanaqin.

    LEGISLATION & POLICIES

    National &

    Local

    Legislation and

    World Bank

    Policies that

    Apply to the

    Project

    The applicable national legislation is as following:

    The Law for the Protection and Improvement of Environment No. 27, 2009;

    Forests and Woodlands Law No. 30 of 2009;

    Protection of Wild Animals and Birds No. 21 of 1979;

    Regulating Exploitation and Protection of Aquatic Life No. 46 of 1976;

    Ministry of Water Resources Law No. 50 of 2008;

    Public Health Law No. 89 of 1981, amended by Resolution No.54 of 2001;

  • 19 / 69

    Iraqi Drinking Water Standard No. (417)-2001;

    Regulation for the Provision of Water Resources, No. 2, 2001;

    Regulation for the Protection of Rivers No. 25, 1967;

    Law No. 27 of 1999 concerning the establishment of the General Authority for Water and Sewage;

    Instructions No. 2 of 2014 on Environmental Protection from Municipal Waste;

    Directive No. (67) of 1986 Regulating the Debris Collection Areas;

    Clean Air Act No. 1 of 2004;

    Noise Prevention Law No. 21 of 1966;

    Directive No. 4 of 1993 concerning occupational health, protection of workers against vibration;

    Instructions No. 3/1985 Concerning Occupational Safety;

    Law No. 6 of 1988 concerning the National Commission for Occupational Hygiene and Safety;

    Law No. 55 of 2002 for The Antiquities & Heritage of Iraq;

    Acquisition Law No.12. of 1981

    At present, there is no national Building Code in Iraq and the most commonly used are the ACI 318 codes.

    The main WB safeguard policies are:

    OP/BP 4.01 Environmental Assessment

    OP/BP 4.11 Physical Cultural Resources

    BP 17.50 Disclosure Policies

    OP 4.12 Operational Policies.

    Since there is no impact on cultural sites and no involuntary taking of land, therefore, OP 4.11 and OP 4.12 do not

    apply for this project.

    The EHS Guidelines applicable to the project are:

    Environmental, Health, and Safety General Guidelines

  • 20 / 69

    EHS Guidelines for Water and Sanitation

    When host country regulations differ from the levels and measures presented in the EHS Guidelines, projects will be

    required to achieve whichever is more stringent.

    In case of the difference between the National Legislation and WB Safeguard Guidelines, it has been agreed that the

    WB instructions will prevail over the national legislation provisions.

    Air quality standard and the drinking water standard are presented in Annex 1.

    PUBLIC CONSULTATION

    Public

    Consultation

    Process

    Due to the security concerns, it is not possible to conduct the public consultation meeting with the affected parties,

    therefore, interviews were held with the residents and local authorities’ representatives on individual basis. There are

    no active local NGOs currently in the area.

    The PMT team has conducted individual interviews with the residents of the area passing by the project site on 28

    December, 2016. Accordingly, a questionnaire was prepared in order to cover the key environmental and social

    aspects related to the project. The questionnaire was then addressed to the local individuals in the surrounding

    community randomly to have their opinions and thoughts regarding the rehabilitation activities. The questionnaire

    was also conducted with women to take their opinions freely. The total number of people interviewed 4 men and 3

    women. Please refer to annex 2 below for more details. During the interview the team presented the description of

    the project and discussed the issues of concern of the stakeholders. The main results of the discussion are:

    1. All questioned local stakeholders agreed that the Rehabilitation activities will have a strong positive impact

    from the social perspectives on the local residents.

    2. No claims from any local population were recorded or alleged regarding the ownership of the land where the

    rehabilitation activities to take place; all agreed that is governmental land property.

    3. No vegetation covers, crops, plants, trees…etc. will be removed in order to execute the rehabilitation

    activities.

    4. No infrastructure will be affected negatively due the reconstruction activities.

    5. No deportation, dislocation of any of the local community.

    6. Information about a grievance mechanism was introduced to interviewed individuals and a translated GRM form was also provided. All interviewed people were informed that they can submit their complaint to either

    site engineer, or to community leader or to PMT during construction.

  • 21 / 69

    GRIEVANCE REDRESS MECHANISEM (GRM)

    GRM Process

    Bank procedures require that Grievance Redress Mechanisms (GRMs) be established and operational prior to

    commencement of the project, and that they continue to operate for one year following completion of the works for

    third party settlement of disputes. This GRM should take into account the availability of judicial recourse as well as

    traditional and community dispute resolution mechanisms.

    The project grievance redressed system should be developed in consultation with communities, which might include

    the following for written complaints:

    1. First, the affected person sends his/her grievance in writing to the communities’/community leaders. The

    grievance note should be signed and dated by the aggrieved person. Where the affected person is unable to

    write, s/he should obtain assistance from the community to write the note and mark the letter with his/her

    thumbprint. The community should respond within 14 days.

    2. Second, if the aggrieved person does not receive a response or is not satisfied with the solution provided by

    the community, s/he lodges her or his grievance to PMT which should respond within 14 days.

    3. Third, if the aggrieved person is not satisfied with the solution of PMT, s/he can go to the court.

    In any case, the PMT must maintain records of grievances and complaints, including minutes of discussions,

    recommendations and resolutions made. During interview, participants were informed that they can submit their

    complaint to either site engineer, or to community leader or to PMT during rehabilitation. The contact information of

    the designated GRM personnel will be posted at the project site for any complaint and redress. Also, the community

    leaders’ information (mobile phone number) and PMT contact information (office and mobile phone numbers) will

    be available before implementation starts and will be posted at the entrance of the project site.

    . The contacts at the Ministry are:

    Contact Information for GRM

    # Name Job Title Phone Number E-mail

  • 22 / 69

    1 Fouad Abed Jameel Engineer, Ministry +9647701019701 [email protected]

    2 Saba Qasem Engineer, Ministry +9647813011556 [email protected]

    INSTITUTIONAL CAPACITY BUILDING

    Will there be

    any capacity

    building?

    [ ] N or [X ]Y

  • 23 / 69

    PART B: safeguards SCREENING AND Triggers (as indicated in the ESMF)

    ENVIRONMENTAL /SOCIAL SCREENING FOR SAFEGUARDS TRIGGERS

    Will the site

    activity

    include/involve

    any of the

    following??

    Activity/ Typology Status Triggered Actions

    1. Reconstruction of linear infrastructure, such as roads or transmission lines

    [X] Yes [] No If “Yes”, see Section A in the ESMF

    2. Reconstruction of private homes, housing estates, public buildings, or facilities and installations for public services

    (e.g. substations, water treatment plants, pumping stations

    or similar)

    [] Yes [X] No If “Yes”, see Section A in the ESMF

    3. Reconstruction of / impacts on surface drainage system [ ] Yes [ X] No If “Yes”, see Section B in the ESMF

    4. Activities in Historic building(s) and districts [ ] Yes [X ] No If “Yes”, see Section C in the ESMF

    5. Required acquisition of land2 or temporary / permanent impacts on livelihoods

    [ ] Yes [ X] No If “Yes”, see Section D in the ESMF

    6. Handling or presence of hazardous or toxic materials3 [ X] Yes [ ] No If “Yes”, see Section E in the ESMF

    7. Impacts on forests and/or protected areas [ ] Yes [ X] No If “Yes”, see Section F in the ESMF

    8. Risk of unexploded ordinance (UXO) [X ] Yes [ ] No If “Yes”, see Section G in the ESMF

    9. Traffic and Pedestrian Safety [ ] Yes [X ] No If “Yes”, see Section H in the ESMF

    2 Land acquisitions includes displacement of people, change of livelihood encroachment on private property this is to land that is purchased/transferred and affects people who are

    living and/or squatters and/or operate a business (kiosks) on land that is being acquired. 3 Toxic / hazardous material includes but is not limited to asbestos, toxic paints, noxious solvents, removal of lead paint, etc.

  • 24 / 69

    PART C: Mitigation measures

    ACTIVITY PARAMETER MITIGATION MEASURES CHECKLIST

    0. General Conditions Notification and Worker

    Safety

    a) The local construction and environment inspectorates and communities have been notified of

    upcoming activities

    b) The public has been notified of the works through appropriate notification in the media and/or at

    publicly accessible sites (including the site of the works)

    c) All legally required permits have been acquired for construction and/or rehabilitation

    d) The Contractor formally agrees that all work will be carried out in a safe and disciplined manner

    designed to minimize impacts on neighboring residents and environment.

    e) Workers’ PPE will comply with international good practice (always hardhats, as needed masks and

    safety glasses, harnesses and safety boots)

    f) Appropriate signposting of the sites will inform workers of key rules and regulations to follow.

    A. General Rehabilitation

    and /or Reconstruction

    Activities

    Air Quality (a) During excavation works dust control measures shall be employed, e.g. by spraying and moistening

    the ground

    (b) Demolition debris, excavated soil and aggregates shall be kept in controlled area and sprayed with

    water mist to reduce debris dust

    (c) During pneumatic drilling or breaking of pavement and foundations dust shall be suppressed by

    ongoing water spraying and/or installing dust screen enclosures at site

    (d) The surrounding environment (sidewalks, roads) shall be kept free of soil and debris to minimize dust

    (e) There will be no open burning of construction / waste material at the site

    (f) All machinery will comply with Iraqi emission regulations, shall well maintained and serviced and

    there will be no excessive idling of construction vehicles at sites

    Noise (a) Construction noise will be limited to restricted times agreed to in the permit

    (b) During operations the engine covers of generators, air compressors and other powered mechanical

    equipment shall be closed, and equipment placed as far away from residential areas as possible

    Water Quality (a) The site will establish appropriate erosion and sediment control measures such as e.g. hay bales and /

    or silt fences to prevent sediment from moving off site and causing excessive turbidity in canalization

    and nearby streams and rivers

    (b) Sewage from construction offices and rest areas will be collected and transferred by trucks to the

  • 25 / 69

    nearest sewage treatment plant

    Waste management (a) Waste collection and disposal pathways and sites will be identified for all major waste types expected

    from excavation, demolition and construction activities.

    (b) Mineral construction and demolition wastes will be separated from general refuse, organic, liquid and

    chemical wastes by on-site sorting and stored in appropriate containers.

    (c) Construction waste will be collected and disposed properly by licensed collectors

    (d) The records of waste disposal will be maintained as proof for proper management as designed.

    (e) Whenever feasible Contractor will reuse and recycle appropriate and viable materials (except when

    containing asbestos)

    B. Impacts on surface

    drainage system

    Water Quality (a) Drainage systems will be reconstructed according to good engineering practice.

    (b) Storm water drainage systems will be designed and constructed as not to silt, pollute, block or

    otherwise negatively impact natural streams, rivers, ponds and lakes; including during construction

    activities

    (c) There will be procedures in place for prevention of and rapid response to accidental spills of fuels,

    lubricants and other toxic or noxious substances, and for their recovery and appropriate disposal

    (d) Construction vehicles and machinery will be washed only in designated areas where runoff will not

    pollute natural surface water bodies There will be no unregulated extraction of groundwater, nor

    uncontrolled discharge of process waters, cement slurries, or any other contaminated waters into the

    ground or adjacent streams or rivers; the Contractor will obtain all necessary licenses and permits for

    water extraction and regulated discharge into the public wastewater system.

  • 26 / 69

    Environmental and Social Management and Monitoring Plan

    Construction Phase

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation

    measures Monitoring

    0 General

    Conditions

    (f) The local construction and environment inspectorates and communities have been notified of upcoming activities

    (g) The public has been notified of the works through appropriate notification in the media and/or at publicly

    accessible sites (including the site of the works)

    (h) All legally required permits have been acquired for construction and/or rehabilitation

    (i) The Contractor formally agrees that all work will be carried out in a safe and disciplined manner designed to minimize

    impacts on neighboring residents and environment.

    (j) Workers’ PPE will comply with international good practice (always hardhats, as needed masks and safety glasses,

    harnesses and safety boots)

    (k) There is posted material indicating the nearest police station and hospital (with accident and emergency facilities).

    (l) The contractor must take reasonable steps to prevent unauthorized people accessing the site.

    (m) Training on handling of UXO/ERW (n) Avoid the burning of materials on site. (o) Provide a first aid kits in different places of the work site

    with the appropriate number of materials given the number

    of workers on site. The locations of the first aid kits will be

    provided to all workers.

    (p) Providing extinguishers on work site. (q) If work involving the use of flammable materials is being

    carried out, stop people smoking and do not allow other

    work activities involving potential ignition sources to take

    place nearby.

    (r) Providing site boundaries by installing suitable physical boundaries (barriers, tape or fence).

    (s) Marking excavation holes with physical boundaries (barriers, tape or fence)

    (t) The contractor should put up barriers or covers in the area of openings and excavations.

    (u) Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over.

    Bi-monthly: record of

    all the licenses and

    permits obtained;

    Compliance with the

    HSE requirements

    Contractor Resident

    engineer

    No additional cost No additional cost

  • 27 / 69

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation

    measures Monitoring

    (v) Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris.

    (w) Everyone who works on any site must have access to adequate toilet and washing facilities, a place for preparing

    and consuming refreshments, and an area for storing and

    drying clothing and personal protective equipment (PPE).

    (x) Contractor to ensure PPE (personal protective equipment) is used by all workers on site.

    (y) Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is adequate

    space for new materials to be stored in secured covered

    areas to avoid damage, theft, and to protect these items

    from weather conditions.

    (z) Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General

    Requirements for Scaffolds §1926.451”

    (aa) Appropriate signposting of the sites will inform workers of key rules and regulations to follow.

    1

    Generation,

    storage, disposal

    of construction

    and domestic

    waste

    (bb) Waste collection and disposal pathways and sites will be identified for all major waste types expected from

    excavation, demolition and construction activities.

    (cc) Mineral construction and demolition wastes will be separated from general refuse, organic, liquid and chemical

    wastes by on-site sorting and stored in appropriate

    containers.

    (dd) Construction waste will be collected and disposed properly by licensed collectors

    (ee) The records of waste disposal will be maintained as proof for proper management as designed.

    (ff) Whenever feasible Contractor will reuse and recycle appropriate and viable materials (except when containing

    asbestos)

    Weekly site inspections

    and verifying the

    records on waste

    disposal

    Contractor Resident

    engineer

    No additional cost No additional cost

    2 Deterioration of

    air quality

    (g) During excavation works dust control measures shall be employed, e.g. by spraying and moistening the ground

    (h) Demolition debris, excavated soil and aggregates shall be kept in controlled area and sprayed with water mist to

    reduce debris dust

    (i) During pneumatic drilling or breaking of pavement and foundations dust shall be suppressed by ongoing water

    Air quality parameters:

    PM10, PM2.5, SO2,

    NOx, CO, Ozone and

    HC

    Contractor Resident

    engineer

    Additional cost of

    water

    2000

    Testing done by

    accredited

    laboratories.

    Additional cost

    2000 US $

  • 28 / 69

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation

    measures Monitoring

    spraying and/or installing dust screen enclosures at site

    (j) The surrounding environment (sidewalks, roads) shall be kept free of soil and debris to minimize dust

    (k) There will be no open burning of construction / waste material at the site

    (l) All machinery will comply with Iraqi emission regulations, shall well maintained and serviced and there will be no

    excessive idling of construction vehicles at sites

    Compliance with dust

    abatement measures

    3 Increased level of

    noise

    (c) Construction noise will be limited to restricted times agreed to in the permit

    (d) During operations the engine covers of generators, air compressors and other powered mechanical equipment shall

    be closed, and equipment placed as far away from

    residential areas as possible

    Weekly site inspection:

    Compliance with the time

    limitations;

    Switching off the equipment not in

    use;

    Use of protective gear

    Contractor Resident

    engineer

    No additional cost No additional cost

    4

    Disruption of the

    runoff water and

    drainage systems

    (e) Drainage / canalization systems will be reconstructed according to good engineering practice, including

    appropriate dimensions, sedimentation basins, and

    connection to treatment facilities as required

    (f) Storm water drainage systems will be designed and constructed as not to silt, pollute, block or otherwise

    negatively impact natural streams, rivers, ponds and lakes;

    including during construction activities

    (g) There will be procedures in place for prevention of and rapid response to accidental spills of fuels, lubricants and

    other toxic or noxious substances, and for their recovery

    and appropriate disposal

    (h) Construction vehicles and machinery will be washed only in designated areas where runoff will not pollute natural

    surface water bodies

    (i) There will be no unregulated extraction of groundwater, nor uncontrolled discharge of process waters, cement slurries,

    or any other contaminated waters into the ground or

    adjacent streams or rivers;

    (j) the Contractor will obtain all necessary licenses and permits

    Weekly site inspection

    during rainy season;

    Bi-weekly site

    inspection during dry

    seasons:

    debris accumulation in

    water drainage

    areas;

    Alteration of water courses;

    Signs of spillage of hazardous

    materials

    Contractor Resident

    engineer

    additional cost:

    contingency water

    testing by

    accredited

    laboratories 1000

    US $

    No additional cost

  • 29 / 69

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation

    measures Monitoring

    for water extraction and regulated discharge into the public

    wastewater system.

    5

    Deterioration of

    groundwater

    quality

    a) The site will establish appropriate erosion and sediment control measures such as e.g. hay bales and /

    or silt fences to prevent sediment from moving off site

    and causing excessive turbidity in canalization and

    nearby streams and rivers

    b) Sewage from construction offices and rest areas will be collected and transferred by trucks to the nearest

    sewage treatment plant

    Weekly site inspection

    during rainy season;

    Bi-weekly site

    inspection during dry

    seasons

    Water testing: in case

    of accidental spills of

    hazardous materials

    Contractor Resident

    engineer

    No additional cost Testing done by

    accredited

    laboratories.

    Additional cost

    3000 US $

    6 Damage to fauna,

    flora

    (a) A survey and an inventory shall be made of large trees in the vicinity of the construction activity, large trees shall be

    marked and cordoned off with fencing, their root system

    protected, and any damage to the trees avoided

    (b) There will be no unlicensed borrow pits, quarries or waste dumps in adjacent areas, especially not in protected areas.

    Bi-weekly site

    inspections:

    Degree of habitat disruption due to

    construction

    activities

    Degree of workers’ perception of

    necessity of habitat

    conservation

    Site restoration after work completion

    Contractor Resident

    engineer

    No additional cost No additional cost

    7 Disruption of

    traffic

    (a) In compliance with national regulations the Contractor will insure that the construction site is properly secured and

    construction related traffic regulated.

    (b) The site will be clearly visible and the public warned of all potential hazards by signposting and barriers / fencing

    (c) Traffic management system and staff training, especially for site access and near-site heavy traffic. Provision of safe

    passages and crossings for pedestrians where construction

    traffic interferes.

    (d) Ensuring safe and continuous access to all adjacent office facilities, shops and residences during construction

    Monthly site

    surveillance for the

    presence of

    fencing/barriers and

    warning signs, and

    traffic speed limitations

    Contractor Resident

    engineer

    No additional cost No additional cost

  • 30 / 69

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation

    measures Monitoring

    8

    Deterioration of

    health & safety

    conditions

    (a) Provide adequate signage to prevent accidental falling into open areas

    (b) Fencing of the work areas (c) Deployment of HSE procedures for the construction

    personnel (Annex 3)

    Inspection and photo

    evidence

    Maintaining records of

    injuries and accidents

    with cause and location

    Contractor Resident

    engineer

    No additional cost No additional cost

    9 Social Impacts

    (a) Reducing impacts on the community through community and neighbour engagement.

    (b) In cases of where there are minority communities speaking a different language in the area or working on site, notices

    are printed in the common local language.

    (c) Provide the proper GRM for handling complaints

    Bi-weekly monitoring

    of response to

    complaints

    Contractor Resident

    engineer

    No additional cost No additional cost

    Expected additional mitigation costs: USD8450

    Expected monitoring costs: USD 5 250 per year

  • 31 / 69

    PART D: Monitoring Plan

    Table (1) Summary of ESMP during Rehabilitation Phase

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation measures Monitoring

    1

    Generation,

    storage, disposal

    of construction

    and domestic

    waste

    (a) Use of non-toxic paints for repairs of the

    buildings;

    (b) Storage of hazardous materials used for repairs in

    sealed containers;

    (c) Disposal of waste to authorized disposal sites;

    (d) Avoid disposal of effluent into the river

    Monthly

    surveillance;

    Maintaining

    records of

    quantities of waste

    and location of its

    disposal

    Operator Diyala Water

    Directorate

    No additional costs No additional cost

    2 Deterioration of

    air quality

    (a) Water spraying for dust control in maintenance

    areas;

    (b) Draining of ponds to prevent stagnation;

    (c) Timely disposal of effluent from sanitary facilities

    in office buildings;

    (d) Timely disposal of domestic waste

    Once a year testing

    during the dry

    season:

    Air quality

    Parameters:

    PM10, PM2.5,

    SO2, NOx, CO,

    Ozone and HC

    Operator Diyala Water

    Directorate

    No additional costs 2000 US $ for air quality

    monitoring

    3 Increased level of

    noise

    (a) Advance warning to public ahead of planned

    maintenance and repair activities;

    (b) Restriction on working hours to 8.00-19.00 during

    working days and avoidance of works during

    holidays unless needed on emergency basis

    Ensure the noise

    levels are within

    the acceptable

    limits during

    maintenance and

    repairs

    Operator Diyala Water

    Directorate

    No additional costs No additional costs

    4

    Deterioration of

    groundwater

    quality

    (a) Timely and adequate disposal of debris generated

    by maintenance activities and solid and liquid

    waste from office building;

    Water quality in

    case of accidental

    spills of hazardous

    materials:

    pH, Turbidity,

    Electrical

    Conductivity (EC),

    Color, Total

    Suspended Solids

    (TSS), Total

    Dissolved Solids

    (TDS), Chemical

    Operator Diyala Water

    Directorate

    No additional costs 500 for water testing

  • 32 / 69

    No. Potential Impacts Mitigation Measures Monitoring

    Responsibility Additional Cost in USD

    Implementation Monitoring Mitigation measures Monitoring

    Oxygen Demand

    (COD), Biological

    Oxygen Demand

    (BOD),

    Polychlorinated

    Biphenyls (PCBs)

    5 Damage to fauna,

    flora

    (a) Adequate waste disposal;

    (b) Draining of ponds;

    (c) Re-vegetation with the plants native to the area

    Monthly

    inspection:

    Condition of the manholes

    and ditches;

    Level of re-vegetation;

    Absence of ponds

    Operator Diyala Water

    Directorate

    No additional costs No additional costs

    6

    Drinking water

    quality issues

    during operation

    (a) Regular checking for the condition of the storm water and sewerage networks for the presence of

    leaking;

    (b) Adequate waste disposal; (c) Timely draining of ponds to avoid breeding of

    insects

    Water quality

    testing as per

    requirements of the

    law

    Operator Diyala Water

    Directorate

    No additional costs No additional costs

    Expected additional mitigation costs: USD No additional costs

    Expected monitoring costs: USD 2 500

  • 33 / 69

    Annexes:

    Annex 1:

    Drinking Water Quality Standard:

    Characteristic Maximum Allowable Limit

    Natural Characteristics

    Color 10 units

    Turbidity (NTU) 5 units

    Smell acceptable

    Taste acceptable

    pH value 6.5-8.5

    Chemical Characteristics (mg/L)

    Arsenic 0.01

    Cadmium 0.003

    Chrome 0.05

    Cyanide 0.02

    Fluoride 1

    Lead 0.01

    Mercury 0.001

    Nitrate (NO3) 50

    Nitrite (NO2) 3

    Selenium 0.01

    Aluminium 0.2

    Chloride (Cl) 250

    Copper 1

    Total Hardness (as CaCO3) 500

    Iron 0.3

    Manganese 0.1

    Sodium 200

    T.D.S 1000

    Sulphate (SO4) 250

    Zinc 3

    Calcium 50

    Magnesium 50

    Barium 0.7

    Nickel 0.02

    Dissolved H.C 0.01

    Carbon-chloroform Extracted 0.3

    Industrial Detergents 0.3

    Phenolic compounds 0.002

    Biological Characteristics

  • 34 / 69

    Characteristic Maximum Allowable Limit

    Coliform (100 ml after 24hr at 35oC)

  • 35 / 69

    Indicative Values for Sanitary Sewage Discharge by EHS Guidelines

    Pollutants Units Guideline Value

    pH pH 6 – 9

    BOD mg/l 30

    COD mg/l 125

    Total nitrogen mg/l 10

    Total phosphorus mg/l 2

    Oil and grease mg/l 10

    Total suspended solids mg/l 50

    Total coliform

    bacteria

    MPNb / 100

    ml 400a

  • 36 / 69

    Maximum Contaminant Level by EHS Guidelines

    (Possible contaminations and their effects on the human health)

    Contaminant MCL or

    TT(mg/L)

    Potential Health Effects from Long-

    Term Exposure Above the MCL (unless

    specified as short-term)

    Sources of

    Contaminant in

    Drinking Water

    Cryptosporidium TT3 Gastrointestinal illness (such as diarrhea,

    vomiting, and cramps)

    Human and animal

    fecal waste

    Giardia lamblia TT3 Gastrointestinal illness (such as diarrhea, vomiting, and cramps)

    Human and animal

    fecal waste

    Heterotrophic plate

    count (HPC) TT

    HPC has no health effects; it is an analytic

    method used to measure the variety of

    bacteria that are common in water. The

    lower the concentration of bacteria in

    drinking water, the better maintained the

    water system is.

    HPC measures a range

    of bacteria that are

    naturally present in the

    environment

    Legionella TT Legionnaire's Disease, a type of pneumonia Found naturally in

    water; multiplies in

    heating systems

    Total Coliforms

    (including fecal

    coliform and E.

    Coli)

    5.0% Not a health threat in itself; it is used to

    indicate whether other potentially harmful

    bacteria may be present5

    Coliforms are naturally

    present in the

    environment; as well as

    feces; fecal coliforms

    and E. coli only come

    from human and

    animal fecal waste.

    Turbidity TT

    Turbidity is a measure of the cloudiness of

    water. It is used to indicate water quality

    and filtration effectiveness (such as whether

    disease-causing organisms are present).

    Higher turbidity levels are often associated

    with higher levels of disease-causing

    microorganisms such as viruses, parasites

    and some bacteria. These organisms can

    cause symptoms such as nausea, cramps,

    diarrhea, and associated headaches.

    Soil runoff

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#threehttps://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#threehttps://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#five

  • 37 / 69

    Contaminant MCL or

    TT(mg/L)

    Potential Health Effects from Long-

    Term Exposure Above the MCL (unless

    specified as short-term)

    Sources of

    Contaminant in

    Drinking Water

    Viruses (enteric) TT Gastrointestinal illness (such as diarrhea, vomiting, and cramps)

    Human and animal

    fecal waste

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    Bromate 0.010 Increased risk of cancer

    Byproduct

    of drinking

    water

    disinfection

    Chlorite 1.0

    Anemia; infants and

    young children: nervous

    system effects

    Byproduct

    of drinking

    water

    disinfection

    Haloacetic acids (HAA5) 0.060 Increased risk of cancer

    Byproduct

    of drinking

    water

    disinfection

    Total Trihalomethanes (TTHMs) ========-->-->

    0.080

    Liver, kidney or central

    nervous system problems;

    increased risk of cancer

    Byproduct

    of drinking

    water

    disinfection

    Chloramines (as Cl2) MRDL=4.0 Eye/nose irritation;

    stomach discomfort,

    Water

    additive

  • 38 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    anemia used to

    control

    microbes

    Chlorine (as Cl2) MRDL=4.0 Eye/nose irritation;

    stomach discomfort

    Water

    additive

    used to

    control

    microbes

    Chlorine dioxide (as ClO2) MRDL=0.8

    Anemia; infants and

    young children:

    nervous system effects

    Water

    additive

    used to

    control

    microbes

    Antimony 0.006

    Increase in blood

    cholesterol; decrease in

    blood sugar

    Discharge

    from

    petroleum

    refineries;

    fire

    retardants;

    ceramics;

    electronics;

    solder

    Arsenic

    Quick reference guide

    Consumer fact sheet

    0.010 as of

    01/23/06

    Skin damage or

    problems with

    circulatory systems, and

    may have increased risk

    of getting cancer

    Erosion of

    natural

    deposits;

    runoff from

    orchards,

    runoff from

    glass and

    electronics

    https://safewater.zendesk.com/hc/en-us/sections/202366568https://www.epa.gov/dwreginfo/chemical-contaminant-ruleshttp://nepis.epa.gov/Exe/ZyPDF.cgi?Dockey=300065YM.txthttp://nepis.epa.gov/Exe/ZyPDF.cgi?Dockey=60000E1E.txt

  • 39 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    production

    wastes

    Asbestos (fiber > 10

    micrometers) 7 MFL

    Increased risk of

    developing benign

    intestinal polyps

    Decay of

    asbestos

    cement in

    water

    mains;

    erosion of

    natural

    deposits

    Barium 2 Increase in blood

    pressure

    Discharge

    of drilling

    wastes;

    discharge

    from metal

    refineries;

    erosion of

    natural

    deposits

    Beryllium 0.004 Intestinal lesions

    Discharge

    from metal

    refineries

    and coal-

    burning

    factories;

    discharge

    from

    electrical,

    aerospace,

    and

    defense

    industries

    https://safewater.zendesk.com/hc/en-us/sections/202366548https://safewater.zendesk.com/hc/en-us/sections/202366548https://safewater.zendesk.com/hc/en-us/sections/202346507https://safewater.zendesk.com/hc/en-us/sections/202366528

  • 40 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    Cadmium 0.005 Kidney damage

    Corrosion

    of

    galvanized

    pipes;

    erosion of

    natural

    deposits;

    discharge

    from metal

    refineries;

    runoff from

    waste

    batteries

    and paints

    Chromium (total) 0.1 Allergic dermatitis

    Discharge

    from steel

    and pulp

    mills;

    erosion of

    natural

    deposits

    Copper TT7; Action

    Level=1.3

    Short term exposure:

    Gastrointestinal distress

    Long term exposure:

    Liver or kidney damage

    People with Wilson's

    Disease should consult

    their personal doctor if

    the amount of copper in

    their water exceeds the

    action level

    Corrosion

    of

    household

    plumbing

    systems;

    erosion of

    natural

    deposits

    https://safewater.zendesk.com/hc/en-us/sections/202366508https://safewater.zendesk.com/hc/en-us/sections/202366458https://safewater.zendesk.com/hc/en-us/sections/202346427https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#seven

  • 41 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    Cyanide (as free cyanide) 0.2 Nerve damage or

    thyroid problems

    Discharge

    from

    steel/metal

    factories;

    discharge

    from

    plastic and

    fertilizer

    factories

    Fluoride 4.0

    Bone disease (pain and

    tenderness of the

    bones); Children may

    get mottled teeth

    Water

    additive

    which

    promotes

    strong

    teeth;

    erosion of

    natural

    deposits;

    discharge

    from

    fertilizer

    and

    aluminum

    factories

    Lead

    Quick reference guide

    Rule information

    TT7; Action

    Level=0.015

    Infants and children:

    Delays in physical or

    mental development;

    children could show

    slight deficits in

    attention span and

    learning abilities

    Adults: Kidney

    problems; high blood

    Corrosion

    of

    household

    plumbing

    systems;

    erosion of

    natural

    deposits

    https://safewater.zendesk.com/hc/en-us/sections/202366438https://safewater.zendesk.com/hc/en-us/sections/202346337https://www.epa.gov/ground-water-and-drinking-water/basic-information-about-lead-drinking-waterhttp://nepis.epa.gov/Exe/ZyPDF.cgi?Dockey=60001N8P.txthttps://www.epa.gov/dwreginfo/lead-and-copper-rulehttps://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#seven

  • 42 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    pressure

    Mercury (inorganic) 0.002 Kidney damage

    Erosion of

    natural

    deposits;

    discharge

    from

    refineries

    and

    factories;

    runoff from

    landfills

    and

    croplands

    Nitrate (measured as Nitrogen) 10

    Infants below the age of

    six months who drink

    water containing nitrate

    in excess of the MCL

    could become seriously

    ill and, if untreated,

    may die. Symptoms

    include shortness of

    breath and blue-baby

    syndrome.

    Runoff

    from

    fertilizer

    use;

    leaking

    from septic

    tanks,

    sewage;

    erosion of

    natural

    deposits

    Nitrite (measured as Nitrogen) 1

    Infants below the age of

    six months who drink

    water containing nitrite

    in excess of the MCL

    could become seriously

    ill and, if untreated,

    may die. Symptoms

    include shortness of

    breath and blue-baby

    Runoff

    from

    fertilizer

    use;

    leaking

    from septic

    tanks,

    sewage;

    erosion of

    https://safewater.zendesk.com/hc/en-us/sections/202366308https://safewater.zendesk.com/hc/en-us/sections/202346267https://safewater.zendesk.com/hc/en-us/sections/202346257

  • 43 / 69

    Contaminant MCL or TT(mg/L)

    Potential Health Effects

    from Long-Term

    Exposure Above the MCL

    (unless specified as short-

    term)

    Sources of

    Contaminant

    in Drinking

    Water

    syndrome. natural

    deposits

    Selenium 0.05

    Hair or fingernail loss;

    numbness in fingers or

    toes; circulatory

    problems

    Discharge

    from

    petroleum

    refineries;

    erosion of

    natural

    deposits;

    discharge

    from mines

    Thallium 0.002

    Hair loss; changes in

    blood; kidney, intestine,

    or liver problems

    Leaching

    from ore-

    processing

    sites;

    discharge

    from

    electronics,

    glass, and

    drug

    factories

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    https://safewater.zendesk.com/hc/en-us/sections/202346227https://safewater.zendesk.com/hc/en-us/sections/202346197https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#one

  • 44 / 69

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    Benzene 0.005

    Anemia; decrease in blood

    platelets; increased risk of

    cancer

    Discharge from factories;

    leaching from gas storage

    tanks and landfills

    Benzo(a)pyrene

    (PAHs) 0.0002

    Reproductive difficulties;

    increased risk of cancer

    Leaching from linings of

    water storage tanks and

    distribution lines

    Carbon tetrachloride 0.005 Liver problems; increased

    risk of cancer

    Discharge from chemical

    plants and other industrial

    activities

    Chlordane 0.002

    Liver or nervous system

    problems; increased risk of

    cancer

    Residue of banned

    termiticide

    Chlorobenzene 0.1 Liver or kidney problems

    Discharge from chemical

    and agricultural chemical

    factories

    2,4-D 0.07 Kidney, liver, or adrenal

    gland problems

    Runoff from herbicide

    used on row crops

    1,2-Dibromo-3-

    chloropropane

    (DBCP)

    0.0002 Reproductive difficulties;

    increased risk of cancer

    Runoff/leaching from soil

    fumigant used on

    soybeans, cotton,

    pineapples, and orchards

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#onehttps://safewater.zendesk.com/hc/en-us/sections/202346547https://safewater.zendesk.com/hc/en-us/sections/202346547https://safewater.zendesk.com/hc/en-us/sections/202346547

  • 45 / 69

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    o-Dichlorobenzene 0.6 Liver, kidney, or circulatory

    system problems

    Discharge from industrial

    chemical factories

    p-Dichlorobenzene 0.075

    Anemia; liver, kidney or

    spleen damage; changes in

    blood

    Discharge from industrial

    chemical factories

    1,2-Dichloroethane 0.005 Increased risk of cancer Discharge from industrial

    chemical factories

    1,1-Dichloroethylene 0.007 Liver problems Discharge from industrial

    chemical factories

    cis-1,2-

    Dichloroethylene 0.07 Liver problems

    Discharge from industrial

    chemical factories

    trans-1,2-

    Dichloroethylene 0.1 Liver problems

    Discharge from industrial

    chemical factories

    Dichloromethane 0.005 Liver problems; increased

    risk of cancer

    Discharge from drug and

    chemical factories

    1,2-Dichloropropane 0.005 Increased risk of cancer Discharge from industrial

    chemical factories

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#one

  • 46 / 69

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    Di(2-ethylhexyl)

    adipate 0.4

    Weight loss, liver problems,

    or possible reproductive

    difficulties.

    Discharge from chemical

    factories

    Di(2-ethylhexyl)

    phthalate 0.006

    Reproductive difficulties;

    liver problems; increased

    risk of cancer

    Discharge from rubber

    and chemical factories

    Dioxin (2,3,7,8-

    TCDD) 0.00000003

    Reproductive difficulties;

    increased risk of cancer

    Emissions from waste

    incineration and other

    combustion; discharge

    from chemical factories

    Endrin 0.002 Liver problems Residue of banned

    insecticide

    Epichlorohydrin TT8

    Increased cancer risk, and

    over a long period of time,

    stomach problems

    Discharge from industrial

    chemical factories; an

    impurity of some water

    treatment chemicals

    Ethylbenzene 0.7 Liver or kidneys problems Discharge from petroleum

    refineries

    Ethylene dibromide 0.00005

    Problems with liver,

    stomach, reproductive

    system, or kidneys;

    increased risk of cancer

    Discharge from petroleum

    refineries

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#onehttps://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#eight

  • 47 / 69

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    Glyphosate 0.7 Kidney problems;

    reproductive difficulties Runoff from herbicide use

    Heptachlor 0.0004 Liver damage; increased risk

    of cancer

    Residue of banned

    termiticide

    Heptachlor epoxide 0.0002 Liver damage; increased risk

    of cancer Breakdown of heptachlor

    Hexachlorobenzene 0.001

    Liver or kidney problems;

    reproductive difficulties;

    increased risk of cancer

    Discharge from metal

    refineries and agricultural

    chemical factories

    Lindane 0.0002 Liver or kidney problems

    Runoff/leaching from

    insecticide used on cattle,

    lumber, gardens

    Methoxychlor 0.04 Reproductive difficulties

    Runoff/leaching from

    insecticide used on fruits,

    vegetables, alfalfa,

    livestock

    Polychlorinated

    biphenyls (PCBs) 0.0005

    Skin changes; thymus gland

    problems; immune

    deficiencies; reproductive or

    nervous system difficulties;

    increased risk of cancer

    Runoff from landfills;

    discharge of waste

    chemicals

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#onehttps://safewater.zendesk.com/hc/en-us/sections/202346277https://safewater.zendesk.com/hc/en-us/sections/202366298https://safewater.zendesk.com/hc/en-us/sections/202366248https://safewater.zendesk.com/hc/en-us/sections/202366248

  • 48 / 69

    Contaminant MCL or

    TT1(mg/L)

    Potential Health Effects from

    Long-Term Exposure Above

    the MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    Tetrachloroethylene 0.005 Liver problems; increased

    risk of cancer

    Discharge from factories

    and dry cleaners

    Toluene 1 Nervous system, kidney, or

    liver problems

    Discharge from petroleum

    factories

    Trichloroethylene 0.005 Liver problems; increased

    risk of cancer

    Discharge from metal

    degreasing sites and other

    factories

    Vinyl chloride 0.002 Increased risk of cancer

    Leaching from PVC

    pipes; discharge from

    plastic factories

    Xylenes (total) 10 Nervous system damage

    Discharge from petroleum

    factories; discharge from

    chemical factories

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#one

  • 49 / 69

    Contaminant MCL or

    TT1(mg/L)2

    Potential Health Effects

    from Long-Term

    Exposure Above the

    MCL (unless specified as

    short-term)

    Sources of Contaminant in

    Drinking Water

    Alpha particles

    15 picocuries

    per Liter

    (pCi/L)

    Increased risk of cancer

    Erosion of natural deposits of

    certain minerals that are

    radioactive and may emit a form

    of radiation known as alpha

    radiation

    Beta particles and

    photon emitters

    4 millirems per

    year Increased risk of cancer

    Decay of natural and man-made

    deposits of

    certain minerals that are

    radioactive and may emit forms

    of radiation known as photons

    and beta radiation

    Radium 226 and

    Radium 228

    (combined)

    5 pCi/L Increased risk of cancer Erosion of natural deposits

    Uranium 30 ug/L as of

    12/08/03

    Increased risk of cancer,

    kidney toxicity Erosion of natural deposits

    https://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#onehttps://www.epa.gov/ground-water-and-drinking-water/table-regulated-drinking-water-contaminants#two

  • 50 / 69

    Annex 2: Public Consultations

    Questionnaire Form in English:

    Name of the project:

    Location of the project:

    Name of the respondent:

    Occupation of the respondent:

    Date of visit:

    1 In your opinion, would the rehabilitation of water/sanitation facilities have positive impact

    on the residents of the area?

    yes no

    2 Are there any claims on private land ownership in the project area? yes no

    3 Would there be any damages to income generating crops, trees, and vegetation due to the

    rehabilitation activities?

    yes no

    4 Would there be any losses of income of local residents due to the rehabilitation activities? yes no

    5 Would there be any damages whether permanent or temporary which would affect the

    livelihood of the residents due to the rehabilitation activities?

    yes no

    6 Would the rehabilitation activities require relocation of the residents of the area, whether

    permanent or temporary?

    yes no

    7 Is there any usage by local residents of the facilities or land of the facilities by the local

    residents?

    yes no

    8 In your opinion, would there be any negative social impacts due to the rehabilitation

    activities?

    yes no

    9 Would there be any changes to the demographics or social structure in the project area

    induced by the rehabilitation activities?

    yes no

    10 Would there be any damages to the structures or houses induced by the rehabilitation

    activities?

    yes no

    11 Would there be any disturbance to traffic during the rehabilitation activities? yes no

    12 Is there any need for warning and directional signage during the rehabilitation activities? yes no

    Name and signature of the interviewer:

  • 51 / 69

  • 52 / 69

    Photos of Interviews

  • 53 / 69

    Arabic Questionnaire with Responses

  • 54 / 69

  • 55 / 69

  • 56 / 69

  • 57 / 69

  • 58 / 69

  • 59 / 69

  • 60 / 69

    Responses to the Questionnaire in English

    +

    Na

    me

    of

    the R

    esp

    on

    den

    t

    Occ

    up

    ati

    on

    Gen

    der

    In y

    ou

    r o

    pin

    ion

    , w

    ou

    ld t

    he

    reh

    ab

    ilit

    ati

    on

    of

    wa

    ter/

    san

    ita

    tio

    n f

    aci

    liti

    es

    hav

    e p

    osi

    tive i

    mp

    act

    on

    the r

    esi

    den

    ts o

    f th

    e a

    rea

    ?

    Are t

    her

    e a

    ny

    cla

    ims

    on

    priv

    ate

    la

    nd

    ow

    ner

    ship

    in

    the p

    ro

    ject

    are

    a?

    Wo

    uld

    th

    ere

    be

    an

    y d

    am

    ag

    es

    to i

    nco

    me g

    en

    era

    tin

    g

    cro

    ps,

    tre

    es,

    an

    d v

    egeta

    tio

    n d

    ue t

    o t

    he

    reh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Wo

    uld

    th

    ere

    be

    an

    y l

    oss

    es

    of

    incom

    e o

    f lo

    cal

    resi

    den

    ts d

    ue t

    o t

    he

    reh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Wo

    uld

    th

    ere

    be

    an

    y d

    am

    ag

    es

    wh

    eth

    er p

    erm

    an

    en

    t

    or t

    em

    po

    rary

    wh

    ich

    wo

    uld

    aff

    ect

    the l

    iveli

    hoo

    d o

    f

    the r

    esi

    den

    ts d

    ue

    to t

    he r

    eh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Wo

    uld

    th

    e r

    eh

    ab

    ilit

    ati

    on

    acti

    vit

    ies

    req

    uir

    e

    relo

    cati

    on

    of

    the r

    esi

    den

    ts o

    f th

    e area

    , w

    heth

    er

    perm

    an

    en

    t o

    r te

    mp

    ora

    ry?

    Is t

    here

    an

    y u

    sag

    e b

    y l

    ocal

    resi

    den

    ts o

    f th

    e fa

    cili

    ties

    or l

    an

    d o

    f th

    e f

    acil

    itie

    s b

    y t

    he

    loca

    l resi

    den

    ts?

    In y

    ou

    r o

    pin

    ion

    , w

    ou

    ld t

    her

    e b

    e a

    ny n

    ega

    tiv

    e so

    cia

    l

    imp

    acts

    du

    e to

    th

    e r

    eh

    ab

    ilit

    ati

    on

    act

    ivit

    ies?

    Wo

    uld

    th

    ere

    be

    an

    y c

    ha

    ng

    es

    to t

    he

    dem

    ogra

    ph

    ics

    or s

    ocia

    l st

    ru

    ctu

    re i

    n t

    he p

    roje

    ct

    are

    a i

    nd

    uced

    by

    the r

    eh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Wo

    uld

    th

    ere

    be

    an

    y d

    am

    ag

    es

    to t

    he

    stru

    ctu

    res

    or

    ho

    use

    s in

    du

    ced

    by t

    he r

    eh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Wo

    uld

    th

    ere

    be

    an

    y d

    istu

    rb

    an

    ce t

    o t

    ra

    ffic

    du

    rin

    g

    the r

    eh

    ab

    ilit

    ati

    on

    acti

    vit

    ies?

    Is t

    here

    an

    y n

    eed

    fo

    r w

    arn

    ing a

    nd

    dir

    ecti

    on

    al

    sig

    na

    ge d

    uri

    ng t

    he r

    eh

    ab

    ilit

    ati

    on

    act

    ivit

    ies?

    Recom

    men

    da

    tio

    ns

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    Yes

    NO

    1 Sumeyya Nateq Wali

    Housewife Female X X X X X X X X X X X X

    2 Abdul Jalil Mohamed Alwan

    Freelancer Male X X X X X X X X X X X X

    3 Murtadha Kareem Taher

    Freelancer Male X X X X X X X X X X X X

    4 Ali Ameer GAtea Freelancer Male X X X X X X X X X X X X

    5 Wafaa Hussoun Teacher Female X X X X X X X X X X X X

    6 Majeeda Hadi Al-obaidy

    Housewife Female X X X X X X X X X X X X

    7 Saad Humaidy M. Freelancer Male X X X X X X X X X X X X

  • 61 / 69

    Annex 3: List of Mitigation Measures during Rehabilitation Phase

    General Conditions

    (a) The local construction and environment inspectorates and communities have been notified of upcoming activities (b) The public has been notified of the works through appropriate notification in the media and/or at publicly accessible sites

    (including the site of the works)

    (c) All legally required permits have been acquired for construction and/or rehabilitation (d) The Contractor formally agrees that all work will be carried out in a safe and disciplined manner designed to minimize

    impacts on neighboring residents and environment.

    (e) Workers’ PPE will comply with international good practice (always hardhats, as needed masks and safety glasses, harnesses and safety boots)

    (f) There is posted material indicating the nearest police station and hospital (with accident and emergency facilities). (g) The contractor must take reasonable steps to prevent unauthorized people accessing the site. (h) Training on handling of UXO/ERW (i) Avoid the burning of materials on site. (j) Provide a first aid kits in different places of the work site with the appropriate number of materials given the number of

    workers on site. The locations of the first aid kits will be provided to all workers.

    (k) Providing extinguishers on work site. (l) If work involving the use of flammable materials is being carried out, stop people smoking and do not allow other work

    activities involving potential ignition sources to take place nearby.

    (m) Providing site boundaries by installing suitable physical boundaries (barriers, tape or fence). (n) Marking excavation holes with physical boundaries (barriers, tape or fence) (o) The contractor should put up barriers or covers in the area of openings and excavations. (p) Store building materials (such as pipes, manhole rings, and cement bags) so that they cannot topple or roll over. (q) Keep walkways and stairways free of tripping hazards such as trailing cables, building materials, and debris. (r) Everyone who works on any site must have access to adequate toilet and washing facilities, a place for preparing and

    consuming refreshments, and an area for storing and drying clothing and personal protective equipment (PPE).

    (s) Contractor to ensure PPE (personal protective equipment) is used by all workers on site. (t) Materials and equipment are tidily stacked, protected and covered where necessary. Additionally, there is adequate space for

    new materials to be stored in secured covered areas to avoid damage, theft, and to protect these items from weather

    conditions.

    (u) Scaffolding for work in elevated areas such as ceiling painting should comply with the OSHA “General Requirements for Scaffolds §1926.451”

    (v) Appropriate signposting of the sites will inform workers of key rules and regulations to follow.

    Generation, storage, disposal of construction and domestic waste

    (a) Waste collection and disposal pathways and sites will be identified for all major waste types expected from excavation, demolition and construction activities.

    (b) Mineral construction and demolition wastes will be separated from general refuse, organic, liquid and chemical wastes by on-site sorting and stored in appropriate containers.

    (c) Construction waste will be collected and disposed properly by licensed collectors (d) The records of waste disposal will be maintained as proof for proper management as designed. (e) Whenever feasible Contractor will reuse and recycle appropriate and viable materials (except when containing asbestos)

    Deterioration of air quality

    (a) During excavation works dust control measures shall be employed, e.g. by spraying and moistening the ground (b) Demolition debris, excavated soil and aggregates shall be kept in controlled area and sprayed with water mist to reduce

    debris dust

    (c) During pneumatic drilling or breaking of pavement and foundations dust shall be suppressed by ongoing water spraying and/or installing dust screen enclosures at site

    (d) The surrounding environment (sidewalks, roads) shall be kept free of soil and debris to minimize dust (e) There will be no open burning of construction / waste material at the site (f) All machinery will comply with Iraqi emission regulations, shall well maintained and serviced and there will be no

    excessive idling of construction vehicles at sites

    Increased level of noise

  • 62 / 69

    (a) Construction noise will be limited to restricted times agreed to in the permit (b) During operations the engine covers of generators, air compressors and other powered mechanical equipment shall be

    closed, and equipment placed as far away from residential areas as possible

    Disruption of the runoff water and drainage systems

    (a) Drainage / canalization systems will be reconstructed according to good engineering practice, including appropriate dimensions, sedimentation basins, and connection to treatment facilities as required

    (b) Storm water drainage systems will be designed and constructed as not to silt, pollute, block or otherwise negatively impact natural streams, rivers, ponds and lakes; including during construction activities

    (c) There will be procedures in place for prevention of and rapid response to accidental spills of fuels, lubricants and other toxic or noxious substances, and for their recovery and appropriate disposal

    (d) Construction vehicles and machinery will be washed only in designated areas where runoff will not pollute natural surface water bodies

    (e) The site will establish appropriate erosion and sediment control measures such as e.g. hay bales and / or silt fences to prevent sediment from moving off site and causing excessive turbidity in canalization and nearby streams and rivers

    Deterioration of groundwater quality

    (a) Sewage from construction offices and rest areas will be collected and transferred by trucks to the nearest sewage treatment plant

    (b) There will be no unregulated extraction of groundwater, nor uncontrolled discharge of process waters, cement slurries, or any other contaminated waters into the ground or adjacent streams or rivers;

    (c) the Contractor will obtain all necessary licenses and permits for water extraction and regulated discharge into the public wastewater system.

    Damage to fauna, flora

    (a) Adjacent wetlands and streams shall be protected from site run-off and siltation with appropriate measures (b) There will be no unlicensed borrow pits, quarries or waste dumps in adjacent areas; (c) Monitor the construction crew and provide punitive measures for illegal hunting and/or fishing; (d) Provide the crew with fuel for cooking to avoid burning of natural materials; (e) Apply waste management plan (f) Provide regular dredging around the cofferdams for the intake structure to ensure sufficient depth and avoid creation of

    whirlpools around the cofferdam which will cause increased turbidity of the water.

    Disruption of traffic

    (a) In compliance with national regulations the Contractor will insure that the construction site is properly secured and construction related traffic regulated.

    (b) The site will be clearly visible and the public warned of all potential hazards by signposting and barriers / fencing (c) Traffic management system and staff training, especially for site access and near-site heavy traffic. Provision of safe

    passages and crossings for pedestrians where construction traffic interferes.

    (d) Adjustment of working hours to local traffic patterns, e.g. avoiding major transport activities during rush hours or times of livestock movement

    (e) If required, active traffic management by trained and visible staff at the site for safe passage for the public (f) Ensuring safe and continuous access to all adjacent office facilities, shops and residences during construction

    Deterioration of health & safety conditions

    (a) Provide adequate signage to prevent accidental falling into open areas (b) Fencing of the work areas (c) Provision of safe crossing rumps over the excavated trenches for residence access and for livestock crossing; (d) Keep walkways free of tripping hazards such as trailing cables, building materials, and debris. (e) Deployment of HSE procedures for the construction personnel as described in point: General Conditions.

    Social Impacts

    (a) Reducing impacts on the community through community and neighbour engagement. (b) In cases of where there are minority communities speaking a different language in the area or working on site, notices are in

    the common local language.

  • 63 / 69

    (c) Provide the proper GRM for handling complaints

    Physical cultural resources:

    Chance find procedures will be used as follows:

    Stop the construction activities in the area of the chance find;

    Delineate the discovered site or area;

    Secure the site to prevent any damage or loss of removable objects. In cases of removable antiquities or sensitive remains, a night guard shall be present until the responsible local

    authorities and the Ministry of Culture take over;

    Notify the supervisory Engineer who in turn will notify the responsible local authorities and the Ministry of Culture immediately (within 24 hours or less);

    Responsible local authorities and the Ministry of Culture would be in charge of protecting and preserving the site before deciding on subsequent appropriate procedures. This would require a

    preliminary evaluation of the findings to be performed by the archeologists from the Department

    of Antiquities and the Ministry of Culture (within 72 hours). The significance and importance of

    the findings should be assessed according to the various criteria relevant to cultural heritage;

    those include the aesthetic, historic, scientific or research, social and economic values;

    Decisions on how to handle the finding shall be taken by the responsible authorities from DA and the Ministry of Culture. This could include changes in the layout (such as when finding an

    irremovable remain of cultural or archeological importance) conservation, preservation,

    restoration and salvage;

    Implementation for the authority decision concerning the management of the finding shall be communicated in writing by the Ministry of Culture; and

    Construction work could resume only after permission is given from the responsible local authorities and the Ministry of Culture concerning safeguard of the heritage.

    These procedures must be referred to as standard provisions in construction contracts, when applicable.

    During project supervision, the Site Engineer shall monitor the above regulations relating to the treatment

    of any chance find encountered are observed.

    Monitoring Obligations of the Contractor:

    Generation, storage, disposal of construction and domestic waste:

    Weekly site insp