Report Part 3
Transcript of Report Part 3
-
8/11/2019 Report Part 3
1/17
Envireau I4/ater
6
DISPOSAL
METHOD
The
proposal
at
the Ebberston
Moor
Field is
to
inject
produced
waters
to
the
Triassic
Shenuood
Sandstone
formation
rather
than injection
to the Permian
Kirkham Abbey
Formation.
6.1
EngineeringMethod
Water
injection
to
the
Shenvood Sandstone
will
be through
a well completed
through
the
injection
zone
either
with
a
perforated
cemented
liner
or
into
open
hole.
The injection
zone
may
target the full
thickness
of
the
sandstone,
depending
on the
exact nature
ofthe
sandstone
formation
encountered.
6.2
IniectionPressures
lnjection
will
be achieved
by
low
pressure
injection
from surface;
the hydrostatic
pressure
of the water
column
will
assist
the water
injection
with
only limited
additional
pressure
added from
pumping.
No
high
pressure
injection
is
foreseen
since
the
injectivity of
the
injection well should
be
sufficient
to
provide
the
required
rates
of
injection.
During
the life
of
the injection well,
accumulation
of fines
may lead
to
a higher
driving
pressure
being
required
to maintain
injection
rates however,
injection
pressure
will
be designed
to
be
below
fracturing
pressure.
6.3
Injection
Rates
and Volumes
The
proposed
rates
and
volumes
of injection
for
the
initial development
phase
of the
Ebberston
Moor Field
are
presented
in
Table
8 below.
Table
8 Proposed
lnjection
Rates
&
Volumes
Assuming
that
the
totalvolumes
(for
both
phases)
are
injected
into
sandstone with
a
porosity
of L0 ;
and the
water
forms
a
spherical
bubble,
the
radius
of the
bubble for the
total volume
would
be in
the order of
240m
(480m
diameter).
lf
it
is
assumed
that
the
porosity
is L ,
then the
radius
increases
to 520m
(1040m
diameter).
The
act of
injection
will result
in displacement
of
the
formation
water,
with
a
theoretical
zone
of influence in
the
region
of
1km.
The effects
of the
displacement will
be
controlled
by
the elastic
storage
of the formation.
Assuming
this
to
be
1
x
LO-s m3/m3
then head
effects would
be
expected
to
propagate
up
to 5200m
from
the injection
point.
Given
the fact
that the
injection
well
at
EB-A
is 40
km from
the outcrop
where the
Sherwood Sandstone
contains
usefulgroundwater,
then
no
effect will
be
seen
in
the outcrop
area.
6.4
Iniection Water
Composition
and
Iniection
Additives
The
disposal
water
at
Ebberston
Moor
may
contain
small
quantities
of
the chemical
additives detailed
in Section
5.3 and
will
have a
resultant
composition
similar
to
that
presented
in Section
5.4.
Ref:
P:\Third Energt
Ebberston
Moor
(1484)\Reporting\Report
v7.6
Rev:
I0/02/2014 2:45
PM
Up
to
1900
.BB
million
.25
hase
1 &
2
1900
.47 million
.00
hase
2
1600 increasing
to
1900
during
the final
year
.41million
.25
hase
1
Average
Daily Injection
(m3/day)
otal Injection
Volume
(m3)
uration
(years)
evelopment
Phase
Page 25
of4l
-
8/11/2019 Report Part 3
2/17
Envireau
llater
7 CONCEPTUAL MODEL
The conceptual
model
presented
below
relates
to this
risk
assessment, as opposed
to
the
full hydrogeological
situation
from
surface
to
depth. lt
has
therefore,
by
necessity been simplified when compared
to
the
geology.
The
conceptual
model is
illustrated on Figure 13
a,b,c)
and
the
principalcomponents
of the conceptual
modelare:
o
The
vertical hydrostratigraphic units
-
namely:
o The
geology
above the Oxford Clay
Layer
1)
o
The
geology
from
the
base
of
the
Mercia Mudstone to the Oxford
Clay
Layer
2)
o
The Sherwood Sandstone
Layer
3)
o The
Zechstein
Permian)
/
Carboniferous
Layer
4)
The lateralvariation
in
geology,
controlled
by
dip and east
west faulting.
a
Recharge
to the
Sherwood Sandstone
formation
is
limited to the outcrop
and
subcrop areas in Vale of
York
/
Mowbray.
Recharge
to the
geology
above the Oxford Clay
is limited
to
the outcrop
on
the
North
Yorkshire
Moors.
Hydraulic
properties
of
the
layers have
been
defined by
literature search, but broadly Layer 1 can be
taken
as
having
useful
hydraulic
conductivity and storage;
Layer
2 is
poorly
permeable very
low hydraulic
conductivity) and has
limited
useful storage;
Layer
3
has
useful
hydraulic conductivity and storage; and
Layer
4 has limited hydraulic conductivity and
storage,
and
poorly
permeable
clay and
mudstone
horizons effectively hydraulically
separate
the
Permian
Layer
4)
from
the overlying
Triassic
water
bearing
formation.
Differences
in water
quality
between the water
bearing
formations have been defined by
literature
search and confirmed
in
the
case
of
Layer 4,
from
sampling and
analysis at Knapton.
The change
in
salinity of the
formation
water in
the Sherwood
Sandstone
is
illustrated by
an
arbitrary line
on
Figure 13c.
This
line
denotes a
change from what we
describe
as
groundwater
to
formation water.
The line
has
been located
based on
the
literature
search
and can be conceptualised
as
an isochlor
a
line
of equal
salinity
[or
more
accurately chloride concentrationl).
When combined,
the
various
aspects
of the
conceptual model produce
a
system
with
no
transfer
of
water
vertically between
the
permeable
Layers
1
and 3, either upward
or
downward.
This
is
achieved
by
the
low
permeability
and thickness of Layer 2 and low vertical hydraulic conductivity of
Layer
4. The effectiveness of the
hydraulic separation is
demonstrated
by
the
marked difference in
water
quality
between
Layers 1
and
3, where
the sandstone
is
at depth.
The
quality
of the
sandstone water at depth demonstrates
that
circulation of recharge
into the
Sherwood
Sandstone
is limited
to near the
outcrop/subcrop
areas,
with
very little deep
circulation occurring.
Evidence
published
in
the
literature
from
isotope and ionic ratio
analysis
Section
3.4.3.2 and 5.5) indicates
that the
NaCl
in
the sandstone
water
is
mineral rather
than sea water based.
The significant
down dip
distance
of the
EB-A site
effectively
isolates
it
volumetrically
from
the aquifer
zone.
Ref P:\Third Energ
Ebberston
Moor
l
484)\Reporting\Report v7.6
Rev: I0/02/2014 2:45 PM
o
Page
26
of4l
-
8/11/2019 Report Part 3
3/17
Envireou Water
8 RISKASSESSMENT
This assessment
considers
the dispsal of
produced
waters
only and does not consider
the
risks
associated
with
the
physicalconstruction
phase
of an
injection
well into the
Shenrood
Sandstone
formation.
8.1
AssessmentMethodologr
DEFRI(s
GL
lll
contains
generic guidelines
for
the assessment and
management
of
environmental risks.
GL
lll
outlines a staged approach
to risk assessment
and
the
document
is
intended
to
guide
regulatory
staff in
Government
and
its
agencies,
as
well
as
those
carrying
out assessments, to reach
a
decision on
managing
environmental risk.
A
hydrogeological
risk
assessment for the
proposed
disposal
of
produced
waters
to the Shenrood
Sandstone
formation
at
Ebberston
Moor
has been
carried
out
in
accordance
with
GL
lll
using
the
Source-Pathway-Receptor
(S-P-R)
methodology
described
in the
Environment Agenqy s
Hl Environmental
Risk
Assessment
framework
-
Annex
J
(Groundwater).
Where
S-P-R
linkages
have been identified,
the
sensitivity of
the
receptor,
magnitude
of
impact
and significance
of
effect has
been
considered
in
order to
assess
potential
risks.
8.1.1
ReceptorSensitivity
The
sensitivity of
water resource
receptors
is
based on their status and considered resource value,
as
described in
Table
9 below.
Table 9
Receptor Sensitivity
A
water resource
desated
or directly linked
to a
SSSI.
hincipal aquifer
providing
potable
water to a
small
population
A
river
desated as being of Good
status
or
with a target
of
Good
status
orpotential underthe
WFD
A
water
body
used
for
national
sporting
events
such as regatts or
sailing events
EC designated
Cyprinid fishery
a
a
a
aater
resource
with a high
quality
and rarity
at
a
national
or
regional
level and limited
potential
for
substitution.
High
A
water resource
making up a vital
component of
an SAC
or
SPA
underthe EC Habitats Directive
A
water
body achieving
a status
of
High
status
or
potential
under the
WFD
Princal
aquifer
providing
potable
water to a large
population
EC
designated Satrnonid fishery
a
a
a
ater
resource
with an
importance
and
rarity
at an
intemational
level
with
limited
potential
for
substitution.
VeryHigh
Ref P)Thrd Energt
Ebberston
Moor
(1484)\Reporting\Report
v7.6
Rev: 10/02/2014
2:45
PM
Page 27
of4l
-
8/11/2019 Report Part 3
4/17
Erwreau Water
A
non
'main'
river or steafri or
other water
body without significant
ecological habitat
a
ater
resotrce with
a
low
qual
and
rarity
at
a local
scale.
[w
o
Secondary aquifer
providing
potable
water to a small
population
o
An
aquifer
providing
abstaction
water for
agricultural
and industial
rse
Water
resource with
a
high
qualrty
and
rarity at a
local
scale;
or
Water resource
with
a
medium
qualrty
and
rarity at a
regional
or
national
scale.
Medium
8.1,2
Magnihrdeoflmpact
The
magitude
of a
potential
impact
on a
receptor
depends
on
the
nature
and
eltent of the
proposed
development, and
is
independent
of the sensitivity of the
wter
resource,
as
described
in
Table
10.
Table 10
Magnitude
of lmpact
Physical
impact to
a
water
resource,
but no
sigrificant
reductior/
increase in
quality,
productivity
or
biodivers
No
significant
impact
on the economic value
ofthe
feature
No
increase in floodrisk
a
a
esul in an impact
on attibute
but
of
insignificant magnitude
to
affect
use
and/or integity.
VeryLow
Measurable
changes
in
attibutg but of
limited
size and/orproportion
esulg
in minor
impact to
attibutes.
Iw
Loss /gain in
productivity
of
a
fishery.
Conibution
/
reduction
of
a significant
proportion
of
the effluent in a
receiving river, but insufficient to change its
WFD
classification
Reduction
/
incree in the economic value
ofthe
feature
a
a
esuls in
impact
on
integrity
of
attibute or
loss
.of
part
of
attibute.
Medium
lss
ofEU desated
Salmonid fishery
Change
in
WFD
clsification
ofawaterbody
Compromise employment source
Ioss offlood
storage/increased
flood
risk
Pollution of
potable
source of
abstaction
a
a
a
a
esults in a major change to
atibutes.
Hieh
ffi
MIE
Ref,
P:lThird Energ
Ebberston
Moor
(l
4 4)lReportingt'Report v7.6
Rar
10/02/20142:45 PM
Page 28
of4l
-
8/11/2019 Report Part 3
5/17
Envireau
ll ater
8.1.3 Significance
of
Effect
The significance
of the
potential
effect is
derived
by
combining
the
assessments
of
both
the sensitivity of
the
water
resource
and
the
magnitude
of
the
impact in
a simple
matrix,
as
presented
in Table 11
below. Effects which
are assessed
to
be major or moderate
are considered
to
be
significanf
whilst
those
that
are minor
or
negligible
are
not significant.
Table
11
Significance
of Effect
8.2 Hazardldentication
The
conceptual model
presented
in
Section
7
suggests
that
injection
of
produced
water
containing
small
quantities
of
hydrocarbons
and additives
to the
Shenruood
Sandstone
formation
represents
a
potential
hazard, as
summarised
in
Table
12
below.
Table
12
Source-Pathway-Receptor
Linkage
(lnjection
of
Produced
Water
to
Shennood
Sandstone)
Negligible
egligible
inoroderate4inor
Neglible
inor
oderate/I4inor
oderate
Minor
oderate4inoroderateajor4oderate
Moderate/lr4inor
oderate
ajor/lvloderate
ajor
Yes
he Shenvood
Sandstone
aquifer at
outcrop
(wholesome,
lowsalin
groundwater)
Migration
ofproduced
water from
the
point
of
injection
through the
Shenrood
Sandstone
formation
to the
outcrop
area
Yes
roundwater
bearing
formations above the
Li
and any
public
or
private
water
supplies
targeting
them;
surface
waters
Failure
ofwell
casing
and migration
of
produced
water
through
groundwater
Injection well
targeting
Shenpood Sandstone
formation
at
Ebberston
Moor
@B-A
wellsitQ
Produced
water
containing
hydrocarbons and
i4jection additives
Ref,
P
lThird
Energ
Ebberston
Moor
(l
484)\Reporting\Report v7.6
Rev: 10/022014 2:45
PM
Page 29 of4l
-
8/11/2019 Report Part 3
6/17
Envireau
llater
The two
S-P-R
linkages
above
are
also
shown
in
the
risk
assessment
summary
in
Table
13, which
shows that
whilst
there
is
a
potential
pathway
between
the
injection
well
and
groundwater
receptors,
the
likelihood of occurrence
is
low and
negligible respectively
because:
Approximately 750m
of
low
permeability
formations
provide
a
vertical separation between the
point
of
injection and the
nearest
groundwater
supplies.
The lateral distance between
the
point
of
injection and the feather edge of
the
Triassic
Sandstone
where
the formation
provides potable
water
is
in
excess
of
40km. Significant
geological
faulting
between the
injection
point
and the outcrop
area will
limit lateral
movement. lnjection
displacement
of formation
water
over
the
lifetime of
the
scheme
is in the region of
lkm, with
pressure
effects
limited to
less
than
5.2km.
Consequently,
the
only
plausible
S-P-R
linkage
would be due to a
failure
of
the injection well
casing
due to
inadequate construction and migration
of
produced
waters
into
groundwater
and surface
water systems local to
the
EB-A
wellsite.
8.3
ReceptorSensitivity
Table
12
shows the
potential
receptors
to
the
produced
water
hazard will
be
local to
the EB-A
wellsite
and
comprise
the
formations
containing
groundwater
above
the
Lias that
might
be targeted
for
public
or
private
water suppliet or
which
may
provide
base flow
to streams
and
rivers.
The sensitivity of the
identified
receptors
is
considered
in the
risk assessment summary
in
Table 13. The most
significant
groundwater
receptor is
the
Principal Corallian
aquifer,
which is assessed as
having a very high
sensitivity. The Secondary aquifers
that
exist between the Corallian
and the
Lias
are
assessed
as having a
medium
sensitivity.
Groundwater
from the
Principal and Secondary
aquifer systems
may be utilised
for
water
supply
and
is
also likely
to
support
base
flow
to a
number
of surface
water features
(streams
and rivers). For the
purpose
of
this
assessment,
the
sensitivity of those
receptors is conservatively
considered
to
be
the
same
as
that of the
aquifer
systems themselves.
8.4
Magnitudeof
Impact
The magnitude of the
impact
on the
identified
receptors
is considered in
the
risk
assessment
summary
in Table
13.
lf
produced
water
entered either
the
Principal Corallian aquifer
or any of the Secondary aquifer
systemg
the
magnitude
of the mpact would be high.
8.5
Signicance
of Effect
The
signifcance of effect
is
also considered
in the risk assessment
summary in Table
13. Based
on the
methodology
presented
in Section 8.1,
it
follows
that
there could
be a major effect if
produced
water entered
the
Principal Corallian aquifer and a
moderate effect if Secondary
aquifer systems
were
affected.
Ref P:\Third
Energt
Ebberston
Moor
(1484)\Reporting\Report
v7.6
Rev: I0/02D014 2:45 PM
a
a
Page
j0
of4l
-
8/11/2019 Report Part 3
7/17
Envireau
ll ater
8.5.1
EmbeddedMitigation
Construction
of
the injection
well
will
be controlled
by
The
Offshore
lnstallations
and Wells
(Design
and
Construction,
etc.) Regulations
1996,
which
in
summary
places
obligations on
the welt-operator
to:
Regulation
13:
Ensure
that
a
well
is
designed,
modified,
commissioned,
constructed,
equipped,
operated,
maintained,
suspended
and
abandoned
such
that
there
is no
unplanned escape
offluids
from
the well
and
that the
risks
to the
health
and safety
of
person
from it
or anything in
i or
in strata
to
which
it
is connected,
are
as low
as is
reasonably
practicable.
Regulation
18:
To make
and
put
into
effect
arrangements
in
writing for independent
examination
by a
competent
person
before
the
design of the well
is commenced.
This
independent
examination
is intended
to
provide
the Well-Operator
that the
well is
designed
and
constructed
properly
and is
maintained
adequately.
Specific
emphasis is
given
to
the impartiality
and
independence
of those
responsible
for
carrying
out
independent
examinations.
The
regulations
ensure
the
protection
of
the
environment
and
persons
through
careful
design. Following
a
number
of
internal
reviews,
the
operations
are reviewed
by
an
independent
competent
third
party.
This
process
ensures
that the
well
is
designed and
planned
to the highest
standards.
As
shown in
the
risk
summary
table
in
Table
13,
for
the
purpose
of
this
assessment
it is
assumed that
the injection
well will
be
constructed
in
accordance
with
standard
best
practice
and
these
regulatory
requirements.
Consequently,
the aquifer
systems
above
the
Lias
will
be cased,
grouted
and
sealed before
the well
is
progressed
into the
Shenruood
Sandstone
where
saline
formation water will
be
encountered.
.
8.5.2
AdditionalMitigation
The injection
pressures
required
to
achieve successful
injection
of
produced
water
nto
the Shenood
Sandstone
will be low
and
it
is
envisaged
that
the
hydrostatic
head
of
the
produced
water
column
will
provide
a sufficient
driving force.
lnjection
pressures
will
be controlled
to
ensure
they
do not
exceed
the fracturing
pressure
of the formation,
which
will
provide
additional
mitigation.
Consequentl
as shown in
the risk
assessment
summary
table
in Table
13, the
resultant
significance
of
effect is considered
to
be
negligible.
Ref P
)Third Energt
Ebberston
Moor
(l
484)\Reporting\Report
v7.6
Rev:
10/02/2014
2:45
PM
Page
3l
of4l
-
8/11/2019 Report Part 3
8/17
I
ErnireauWater
Table
13
tnjection of
Pnoduced
Water- RiskAssessmentsummary
Ref: P
:llhird
hergt
Ebberstot Mot
(
484)lReponng@pol
v7.6
Rev: 10/022014
2:45
PM
hoduced
wEr
iecion
well
Mgration
of
produced
vafr
to
the
oJtqtop
afea
Faihne of
well
*iog; migrion
of
produced
wafr
lbrough
groundwer
Sheruood
Sandstone
aquifer
(
outcrop)
Secondary
aquifers
Principal
Corallian
aquifer
Yes
Yes
Yes
Negligible
VeryIow
Verylow
VeryHigh
High
Verl'High
High
Medirm
High
Major
Moderate
l fajor
D
or
ge
an
lo
inj
pa
Be
we
re,
H
H
@
ru
@
@
w
w
r4
fi
-
8/11/2019 Report Part 3
9/17
Envireau
lTater
9
ALTERNATIVETECHNOTOGIES
9,1 BestAvailableTechnique
The
water
disposal
technology
described in
this
assessment
is
unique,
in
that it
involves
the
injection
of
produced
water into
a
geological
formation
at a higher stratigraphic level
than the
producing
unit. As
such,
it is
important
that
the technology
is
checked
to
ensure
that
it
is
the
Best
Available Technique
(BAT).
As a unique technology
its
status wth respect
to
BAT has
been
derived using an approach based
on that described by the Nuclear lndustry
Safety Directors Forum
document
titled
'Best
Available Techniques
(BAT)
for the Management
of the Generation
and
Disposal
of
Radioactive
Wastes
-
A
Nuclear
lndustry Code of Practice',
published
in
December 2010.
This
document
provides
a robust overview
of the
definition of
BAT, in
an
industry where risk
management is
paramount.
ldentification
and
implementation
of
BAT implies a balanced
judgement
of
the
benefit derived from a measure
and
the
cost
or
effort of
its
introduction.
There
is
no single
'right
way'
to
identifo
BAT;
although
it
is
accepted
that
all studies
will be based
on
information,
verified where
practicable,
and documented
for transparency. BAT may
be established by reference
to
previous
studies, or
as
an independent
comparison of detriments
and benefits. The
general
rule
is
that the level of
effort
expended
to
identifu
and implement BAT should
be
proportionate
to
the
scale of
the
issue
to be resolved. ln
many cases, studies
will
be
constrained by one
or
more
factors, depending
upon the assessment
context. A number of
assumptions may also be required,
particularly
where long timescales
are considered.
lt is important
that the
process,
and
any
underpinning constraints
or
assumptions, must be
documented and
justified.
Overall,
the following
principles
should also be taken into
account:
o
sustainabledevelopment;
o
waste
hierarchy and waste
form;
o
the
precautionary
principle;
and
the
proximity principle.
This chapter
sets out and documents
the
identification,and
justification
of
the
BAT for the disposal
of
produced
water at Ebberston
Moor.
9.2 TechnologyOptions
The following
technology options have
been considered:
o
lnjection
of
produced
water into
the
hyper
saline Sherwood Sandstone formation;
o
lnstalling
an injection well at Ebberston
Moor to target the Kirkham Abbey
production
formation;
.
o
lnstalling
an
injection well
at Ebberston Moor
to
target
the deeper Carboniferous
strata;
o
lnstalling a
pipeline
to transport
produced
water
back
to
KG from where it would
be transported
out to
the existing injection
well
in
the
Vale
of
Pickering;
and
o
Disposalvia municipal
sewage
treatment
works
and discharge to
surface
water.
Ref:
PlThird
Energt Ebberston Moor
(1484)\Reporting\Report
v7.6
Rev: 10/02/2014
2:45 PM
Page 33 of4l
-
8/11/2019 Report Part 3
10/17
Envireau
llater
The
following
sections describe the
key
components
of the options
wth
respect
to
a
scoring matri
which
is
presented
as
Table
13.
The
scoring
matrx
is discussed
in detail
in
Section
9.3.
9.2.1.
Iniectionto Sherwood Sandstone
Formation
(Base
Case)
The
proposed disposal
route
is
to
the
Sherwood Sandstone
formation. This
route
has
the following
primary
benefits:
o
Engineering
practicality
as
the technique
is
a
proven,
wellestablished
technique offshore;
o
While a
high cost option,
the
less deep
injection level means
that
wellconstructon is
lower;
o
Low
environmental
risk
(see
above);
o
Low sustainability score, based on
low energy
use;
and
o
Low
precautionary
principalscore
based
on
robust
risk analysis.
This route
has
the
following
primary
dis-benefits:
o
Moderateregulatoracceptability.
9,2.2
Iniectionto
Production
Formation
(IGF)
-
Ebberston
Moor
The
current
injection
of
produced
water
in
the Vale
of
Pickering
field
results
in
recirculation
of
fluids from the
injection well,
whereby
the fluid
travels through
the
fracture network
within the KAF to
the
production
well.
This
results
in 'watering-offl
whereby
high liquid rates are
produced
from
the
production
well,
resulting
in further
processing
of
fluids at surface and
lower
overall
gas
recovery
rates,
thus
limiting
the
commercial
viability of the
Ebberston
Moor
Field.
lt is
a
condition
of the licence issued to
Third
Energy
by
the
UK Government
(DECC)
that
recovery of hydrocarbons
must
be maximised.
lf a new injection
well is
installed within the
boundaries of
the
Ebberston
Moor
field,
then it
is
fully
expected
that
the
same
historic
issues
relating
to
recirculation of
fluids will be observed.
This
leads
to a
high Production
lmpact
score.
lf
a
KAF
injection
well
was
constructed
at
Ebberston Moor,
then
it would most
likely be constructed
as
far away
from
the
production
well
as
possible.
Assuming an injection
well was constructed
on the furthest
boundary of
the
gas
field, this
would mean a
produced
water
pipeline
of around
10km
in
length
would
be
required
to transport
produced
water
from the
production
site to the disposal
site.
The deeper
injection
well
(relative
to
the
base case)
increases
the cost
score.
As an
accepted
and
permitted
disposal
route, this
option has a
low regulator
acceptability
icore.
The
produced
water
pipeline
increases the environmental
risk
score
(see
g.2.41.
9.2.3
Iniection
to
sub Permian Strata
-
Ebberston
Moor
lnjection
into
the
sub-Permian
Strata
oses
engineering
challenges,
primarily
due
to the
low
permeability
(injeaivity)
of
these formations.
Below
the
limestones
of
the
Permian,
the
strata become dominated
by clay
rock
(shale)
and indurated sandstone.
lnjection into these
formations is
unlikely
to
be
possible
at
low
pressures
and
is.
Ref
P:\Third
Energt
Ebberston
Moor
(1484)Weporting\Report
v7.6
Rev:
10/022014 2:45
PM
Page
j4
of4l
-
8/11/2019 Report Part 3
11/17
Envireau
Water
likely
to require
pressures
that
signfcantly
increase
the risk
of fracturing.
lf this
were
to
occur, while
it
would
not
be likely
to
increase
the
environmental
risk,
it would
increase
the
production
ris(
via movement
of water
back
to
the
production
horizon.
Costs increase
over the
base
case
due
to the increased
depth
of injection.
As an
accepted
and
permitted
disposal
route,
this option has
a low regulator
acceptability
score.
9.2.4
Injection
to
Production
Formation
(KAF)
-
Vale
of
pickering
lf the
existing
injection
well in
the
Vale
of
Pickering
is used
as a disposal
route for
produced
waters
originating
from
production
wells
at
Ebberston
Moor,
this will further
diminish
the
productivity
of the
existing
wells in
the
Vale
of Pickering,
thus limiting
the
commercial
viability
of the
Vale
of
Pickering
Fields. tt
is
a
condition
of the
licence
issued
to Third
Energy
by
the
UK
Government
(DECC)
that
recovery
of hydrocarbons
must be
maximised.
ln
order to
utilise existing
injection
wells
in the Vale
of Pickering,
a
pipeline
will
need
to
be installed
to
transport
produced water
from
Ebberston Moor
to
KGS.
The
pipeline
would
be
around L0km in length
and
would
follow
a
relatively
direct
route,
subject
to
landowner
agreement.
The
construction
of a
pipeline
for
produced
water would
introduce
a number
or
environmental
risks,
as
presented
in
Table
14
below.
The risks
illustrated
in
Table
i.0
represent
the situation
after
taking
appropriate
mitigation
measures.
lt
is
not
the
intention
of
this
report
to
undertake
a
detailed
risk
analysis
of
pipeline
construction,
but
to
recognise
that
risks
remain
after construction,
and
during
the operation
of
a
pipeline.
Table 14
water
Related
Risks
Associated
with
a
produced
water
pipeline
The most
significant
risk
associated
with
a
produced
water
pipelines
is
the
potential
for
disturbance
and
pollution
of
the
hghly
sensitive Scarborough
SpZ.
Figure
1.2
illustrates
the
extent
to which
pipelines
could infringe
on
the
Scarborough
SPZ. Approximately
3km
of
the
pipeline
to
Knapton
would
cross
the
SPZ,
whilst
a
pipeline
to
an injection
well
in
the
Ebberston
Moor
Field
(located
as
far
as
possible
from
production
wells)
would
cross up
to
10km
of
the
SPZ. Conversely,
an injection well
targeting
the
Sherwood
Sandstone
would
be constructed
at
the same
site
as the
production
well
(EB-A)
and
would
therefore
totally
remove
the
need
for
a
produced
water
pipeline
crossing
the
SPZ.
Based
on this,
the
environmental
risk
score
has
been increased
for the
pipeline
options.
Ref P:\Third
Energt Ebberston
Moor
(14]4)Weporting\Report
v7.6
Rev:
I0/02/2014
2:45 PM
Moderate
oderate
igh
ipeline
leakage
and
pollution
of DTWPAs
and
SPZs
Low
ow
igh
ollution
disturbance
of
DTWPAs
and
SPZs
during
pipeline
construction
Low
ow
igh
isturbance
of wetland
ecosystems
Riskikelihood
onsequence
azard
Page
35 of4l
-
8/11/2019 Report Part 3
12/17
Envireau
Water
9.3 ScoringMatrix
Table 15
presents
a scoring matrix which
evaluates
the
BAT
criteria. The matrix
looks
at
each
of
the
criteria
presented
in
Section
9.1
together with
other
important factors. The only aspect
that
is missing is
"waste hierarchy
&
waste form".
The
waste hierarchy
is
summarised in
the
embedded figure below.
Prefened Environmentl
Opton
Use BATto ensure
wasteis not
generated
unnecessadly
Waslecreatcd:
UseBATto ensure
waste discharges are
minimised
Liquld
Waste
discharged:
UseBATto
minimise impads
Least Prefened
Environmental Opton
Within
the context of the
produced
water,
the
water has
to be
produced.
lt
is
a
part
of the
process
of extracting
gas.
The high
salinity of the water means
that
it
has no
practical
re-use
or options
for
recycling, other than in
th
development of new
gas
wells, which isn't
the intention within the context of this
proposal.
Energy recovery is not
applicable in this case and
therefore disposal is the only option. Size reduction is not applicable.
Table 15
provides
a
relative
scoring system
that
has
been adjusted by a simple
weighting.
Cost has been reduced
in significance, as while it is important
it is not an overriding factor. The most important factors
are environmental
risk and
production
impact.
The
former
because
this
is
what
is being
protected
and
the
latter
because
loss in
production
will result in failure
of the company
and
goes
against the
requirements
of the
DECC
licence conditions.
The matrix has been designed
so
that a low number
gives
the best option.
9.4
Summary
The scoring matrix identifies in a
systematic
way
that the Sherwood Sandstone formation disposal route is BAT
Given that the overall disposal is
low
risk
(Section
8)
Envireau
Water consider that this
qualitative
BAT assessment
is appropriate and meets the requirements
of the BAT
guidelines
referenced above.
Ref P:\Thrd Energt Ebberston Moor
(1484)\ReportingWeport
v7.6
Rev: 10/02/2014 3:37 PM
Reduce lmpact
through Chemical
and Phyrical Form
Gas
Solid
I
;,,
Rgg.t--$9
r--t;
-.
.: .i.': r':,i..
-.:
Re-use
Reduce
Avoid
Page
36
of4l
-
8/11/2019 Report Part 3
13/17
ErwireauWater
Tablel5
BATScodngMatrix
VoP
=Vale
of
Pckerng
EM=Ebberston Mr
Ref, P:\Ihrd herg Ebberxtot
Mr
(14&l)lReportinglRept
v7.6
Rar 10/022014 3:37
PM
Discharge
to
xce
watr
Pline to VoP
and
inject o KAF
Injection
into
srb Permian
Str
@M
site)
Injection into I(AF
@M
si)
Discharge
to
uface
uater
fnjection into
Shntrood
Smdstone
Pline
o
VoP
ad
tuect
to
KAF
Injection into srb
Permian Stn
(EM
site)
iectionintoKAF@M)
Injection ino Sherwood
Sdstone
3
5
I
J
3
3
5
8
J
3
5
5
3.5
5
2.5
t0
IE
l0
7
l0
5
l5
7.5
1.5
7.5
1.5
10
5
I
5
I
0
l5
6
15
0
0
t0
4
10
0
8
J
I
I
I
J
I
I
I
I
0
5
I
I
I
l0
5
I
I
I
-
8/11/2019 Report Part 3
14/17
Envireau lVater
10
fusTrFrcATIoN
FoR
IN|ECTION
TO THE SHERWOOD
SANDSTONE
Based
on
the
risk assessment
provided
in Section 8 and the
BAT
analysis
in Section 9,
the
alternative
methods
of
water
disposal
involve technologies
which will:
o
Reduce
productivity
and the rates
ofgas
recovery
o
Limit the commercial
viability
of
gas production
from
the Ebberston
Moor
Field
o
lntroduce significant environmental
risk
By
comparison,
the
proposed
method of water disposal by
injection to the
Sherwood Sandstone
will:
o
Maximise
productivity
and
the
rates of
gas
recovery
o
Maximise
the commercialviability
of gas
production from
the
Ebberston
Moor
Field
o
Minimise environmental
risl most significantly
because
there
is no
requirement
for
a
pipeline
to
transport
produced
water
across
the
Scarborough
SPZ
It
is
therefore
considered
that
in this
particular
casd,
the disposal
of
produced
water to the
Sherwood Sandstone
represents
both
the
BAT
and
the BPEO.
Ref P:\Third
Energt
Ebberston
Moor
1484)\Reportng\Report
v7.6
Rev:
10/02/20142:45
PM
Page
j8
of4l
-
8/11/2019 Report Part 3
15/17
Envireau
ll'ater
LI
SUMMARY
CONCLUSION
The
technical
analysis
and
risk
assessment
presented
above
demonstrates
that fundamentally
and crucially,
there
is
no
(or
essentially
no)
environmental
risk
associated
with
properly
designed and
managed
disposal.
This
is
based
on
clear hydraulic
and
geochemical
separation
of the
water
bearing formations
of the
Trassic
and
the
aquifers of
the
shallow groundwater
system
of
the
Upper
Jurassic.
The
conceptual hydrogeological model underpinning this
assessment
has
been
discussed
and agreed
in
principle
with
the
local
Environment
Agency
Groundwater
Contaminated
Land
team.
Comparison
of
the North
Sea
salinity
with
the
main
constituents
of the
produced
water
from
the
KAF
and the
Shenvood
Sandstone
formation
water
show
that the
KAF
water
is
approximately
two
times
more
saline than
the
Shenood
Sandstone
formation
water.
However,
this
is
within
the
context
of
both waters
having
total
dissolved
solids
concentration
(TDS)
n
excess of
18Q000mg/1.
Both
waters
show significant
amounts
of
naturally
occurring
hydrocarbons,
with
the
produced
water
showing
more,
as
would
be
expected.
The
produced
water
and
Shenruood
Sandstone
formation
water
are 10 and
5 times more
saline
than
the
North
Sea,
respectively.
On
this
basis,
and
in
line
with
UKIAG guidance
the
Shenvood
Sandstone
formation
water
has
no resource value.
Therefore
the formation
water,
into which
disposalwilltake place
can
be
defined
as:
o
Permanentlyunsuitable
o
Deep
and isolated
o
Of
no resource
value
On this
basis the
WFD,
GWDD
and
UK
regulations
which cascade
from
them,
allow disposal.
The design and management
of the
disposal
well
(borehole)
will
utilise standard oil
and
gas
field
practices
wh
respect
to
casing
setting
and
grouting,
curing and
testing
to
ensure
full
protection
of
the
shallow
aquifers
and
groundwater
system.
Envireau
Water
03
December20LS
Ref
P:\Third
Energt
Ebberston
Moor
(1484)\Reporting\Report
v7.6
Rev: 10/022014
2:45
PM
Page
39
of4l
-
8/11/2019 Report Part 3
16/17
Envireau
Water
L2 BIBLIOGRAPHY
The
following
documents have been used
as
reference
material
in
the compilation of this technical
assessment
(Bolded
titles
referto the relevant Regulations, Directives,
Guidelines and UKAG documents):
Allen,
D. J.,
et
al
(L9971,
The
physical
properties
of
major
aquifers
in
England
and
Wales.
BGS
Tech.
Rep.
WD/97
/34.
Environment
Agency
R D
publc.
8.
Application of Groundwater
Standards
to
Regulation
-
UK
Technical
Advisory Group on the Water Framework
Directive,
Application of GroundwaterStandards
to
Regulation, March 2011.
Best
Available
Techniques
(BAT)
for the
Management
of
the
Generation
and
Disposal
of Radioactive Wastes
-
A
Nuclear
lndustry Code of
Practice. Nuclear
lndustry
Safety
Directors
Forum. lssue
1
December 2010.
Bottrell,
S.H.,
et
al
(2006)
Combined isotopic and
modelling
approach
to determining
the
source
of
saline
groundwaters
in the Selby Sheruood
Sandstone aquifer,
UK.
Geological Society, London, Special Publications,
v263 pp325-338.
Bricker,
S.
H.,
et
al
(2012)
Effects
of CO2 injection
on
shallow
groundwater
resources:
A hypothetical
case study
in
the Sherwood Sandstone aquifer, UK. lnternationalJournal
of Greenhouse Gas Control 11,
pp337-348.
British GeologicalSurvey
(BGS)
1:50
000 scale sheets:
E027
-
Durham
E032
-
Barnard
Castle
E033
-
Stockton
E034
-
Guisborough
E035
-
Whitby
Scalby
(includes
part
of
E044)
E041-
Richmond
8042
-
Northallerton
E043
-
Egton
E051-
Masham
E052
-
Thirsk
E053
-
Pickering
E054
-
Scarborough
E055
-
Flamborough
and
Bridlington
(includes
part
of
E065)
E062
-
Harrogate
E063
-
York
E064
-
Great
Driffield
E070
-
Leeds
E071
-
Selby
8072
-
Beverley
E073
-
Hornsea
E078
-
Wakefield
8079
-
Goole
E080
-
Kingston upon Hull
Defining
Reporting
on Groundwater
Bodies
-
UK Technical Advisory
Group
on
the Water Framework
Directive
V 6.2L1
Mar
2011.
Final 300312.
Downing,
R.4.,
et
al
(1985) Cleethorpes
No.
1
Geothermal Well
-
a
preliminary
assessment
of the
resource,
lnvestigation
into
the
Geothermal Potentialof
the UK
British
Geological Survey.
Ref,
P:\Third Energt
Ebberston
Moor
(1484)\Reportng\Report
v7.6
Rev:
10/02/20142:45
PM
Page
40
of4l
-
8/11/2019 Report Part 3
17/17
Envireau lil'ater
Environment
Agency,
The
Refining
of
the
Scarborough Source
Protection
Zone
Delineation
in
the Corallian
Limestone
Aquifer, Environment
Agency
Report, 2012.
Environmental
Permitting
(England
and Wales)
Regulations 2010.
European
Water Framework
Directive
-
DIRECTIVE
2cff,/6O/EC
OF THE EUROPEAN PARLIAMENT
AND
OF
THE
COUNCIL of
23
October 2000 establishing
a
framework
for
Community
action in the field of water
policy.
Official
Journal
of the
European
Communities.
Gale,
1.N.,
et
al
(1983).
The
post
Carboniferous rocks
of
the
East
Yorkshire
and Lincolnshire
Basin,
lnvestigation
of
the Geothermal Potentialof
the
U British
Geologicalsurvey.
Green Leaves lll
-
Guidelines
for
Environmental
Risk
Assessment
and
Management:
Green Leaves lll.
Revised
Departmental
Guidance Prepared
by
Defra
and the Collaborative
Centre of Excellence
in
Understanding
and
Managing
Natural
and
Environmental
Risks, Cranfield
University, November 2011.
Groundwater
Daughter Directive
-
DIRECflVE
2006/t].8/EC
OF THE
EUROPEAN
PARLIAMENT
AND
OF
THE
COUNCIL
of
12
December 2006
on the
protection
of
groundwater
against
pollution
and
deterioration.
Official
Journalof
the
European Union.
Groundwater
Directive
-
Council Directive
8O/68/EEC of
17
December
1979
on
the
protection
of
groundwater
against
pollution
caused
by
certain
dangerous substances.
OfficialJournal
of the
European
Communities.
Groundwater Protection:
Principles
and Practice
(GP3),
Version
1,
Environment Agency,
November 2012.
Groundwater
Regulations
-
Groundwater
(England
and Wales) Regulations 2009.
H1
Environmental
Risk
Assessment
framework
-
Annex
J
(Groundwater).
Environment Agency, 20L0.
Hem 1985,
Study and
lnterpretation
of
the
Chemical
Characteristics
of
Natural
Water.
USGS
Water
Supply Paper
2254.
Jones,
H.
K.,
et
al
(2000),
The
physical
properties
of minor aquifers
in
England
and
Wales. BGS
Tech.
Rep.
WD/00/04. Environment
Agency
R D
publc.
68.
tandfilf
Directive
-
Council Directive
1999/3L/EC
of
26
April
1999
on the
landfill of waste.
Official Journal
of
the
European
Communities.
The
Royal
Belgian
lnstitute of
Natural
Sciences
(www.naturalsciences.be)
Scottish Environment
Protection Agency,
Position
Statement WAT-PS-10-01, Assigning
groundwater
assessment
criteria for
pollutant
inputs, Version
2.t,
JuneZOLL
Shand,
P.,
et al
(2002)
Baseline
Report
Series
1: The
Permo-Triassic Sandstones
of
the
Vale
of
Yorl
British
Geological
Survey
Commissioned Report
No.
CR/02/102N.
United States Environmental
Protection
Agency,
National Primary Drinking
Water Regulations,
EPA
816-F-09-@4,
May 2009.
World
Health Organisation,
Guidelines
for
Drinking
Water
Quality,
Fourth
Edition, 2011.
Ref P:\Third Energt
Ebberston
Moor
(1484)\Reporting\Report
v7.6
Rev:
10/02/2014
2:45 PM
Page4l of4l