EXECUTIVE SUMMARY School Sanitation Infrastructure Programme require construction of sanitation facilities.
• ACTIVITIES OF THE PROJECT EARTHWORKS • Excavation of pit trenches • Backfilling • Compaction • CONCRETE FORMWORK & REINFORCEMENT • Base concrete & slab • MASONRY • Brickworks for pit lining using (Mampara) • Brickworks for super structure (Face Brick) • WATERPROOFING • Damp proofing of walls using 375 micron embossed damp proof course (1 layer) • Damp proofing of under surface beds using 250 micron embossed damp proof course (1 layer) • Damp proofing of floors & walls using approved black epoxy coating (2 coats)
• ROOF COVERINGS • Install IBR profiled roof sheets (corrugated) lined with timber kapa & fixed to timber purlins • CARPENTRY & JOINERY • carpentry and joinery on roofs, eaves, verges and doors Fascia’s and barge boards • Wrought meranti doors hung to steel frames • METALWORKS IN-SITU FINISHES • Install aluminium windows & doors • PLUMBING & DRAINAGE • Install PVC pipe and fittings to urinal tank • Install concrete wash basin • GLAZING • Glazing on Glass • PAINTWORK • Apply to the specified requirements: Paint on fibre cement o paint on wood o paint on metal
Limpopo Schools School Name Emis Number Circuit District
Ngwanabahlalerwa Secondary 921230504
Moletlane Lebowakgomo Education District
Nthabalala Primary 931340104
Sekgosese Noth Vhembe Education District
Rehlahlwa Primary 907111832
Vaalwater Waterberg Education District
Tshikhovhokhovho Primary 993306201
Dzondo Vhembe Education District
Tshilapfene Primary 930350897
Tshinane Vhembe Education District
Ncheleleng Secondary 922251754 Vlaakfontein Polokwane Education District
Tibanefontein Primary 922251679 Vlaakfontein Polokwane Education District
Watervaal Secondary 931332523 Soutpansberg East Vhembe ED