Report on Project Management of a particular project

16
Project Management Presentation ON Design of low cost wearable leg exoskeleton system for physically impaired people By Texas Instruments

description

Project Management Presentation on Design of low cost wearable leg exoskeleton system for physically impaired people By Texas Instruments

Transcript of Report on Project Management of a particular project

Page 1: Report on Project Management of a particular project

Project Management PresentationON

Design of low cost wearable leg exoskeleton system for physically impaired

peopleBy Texas Instruments

Page 2: Report on Project Management of a particular project

(Exoskeleton System)

Page 3: Report on Project Management of a particular project

Motivation

• Design a low cost exoskeleton system to help physically impaired people.

• Available Models too Expensive to be availed by an average Indian.

Page 4: Report on Project Management of a particular project

Project Phases

Page 5: Report on Project Management of a particular project

Project Lifecycle

Page 6: Report on Project Management of a particular project

Project Planning

Members:• PROJECT MANAGER• TECHNICAL MANAGER• RELATIONS MANAGER• TECHNICAL ENGINEERS (2)

Page 7: Report on Project Management of a particular project

Project Tools

• Work Break Down StructureDecomposition into different sections which better illustrates the role of each in the performance, schedule & budget analysis.

• Responsibility matrixFormat which shows work package for a functional position

Page 8: Report on Project Management of a particular project

Work Breakdown Structure

Page 9: Report on Project Management of a particular project

Responsibility Matrix

Page 10: Report on Project Management of a particular project

Budgeting and Cost EstimationComponent Name of

ManufacturerPrice per

ComponentNo. of

Components

Total cost of Component

TI Supplied/Purchased

1.MSP-430G2553 Texas Instruments $9.99 1 $9.99 *TI Supplied

2MSP-430G2253 Texas Instruments $9.99 1 $9.99 Purchased

3.OPT101 Photo-diode Texas Instruments Free Sample 1 - TI Supplied

4.Aluminum Sheet Local Manufacturer Rs. 150 per metre 1 Metre Rs.150 Purchased

5.Servo Motors Vigor Precision Ltd. Rs. 466 3 Rs.1400 Purchased

6.Springs Local Manufacturer Rs. 30 3 Rs.90 Purchased

7.L-Strips Local Manufacturer Rs. 1 9 Rs.9 Purchased

8.Straps Local Manufacturer Rs.30 per metre 1 Metre Rs.30 Purchased

9.Aluminum Rods Local Manufacturer Rs. 10 3 Rs. 30 Purchased

10.Manufacturing cost - - - Rs.1000 -

Total Cost of all ComponentsOther expenses (transportation + shipping + documentation)

Rs. 3961 Rs.6339

TOTAL Rs.10,300

Page 11: Report on Project Management of a particular project

Tasks

• A=abstract preparation• B=permission from college• C=hardware arrangement• D=interim report• E=hardware architecture• F=sensors interfacing with microcontroller• G=servomotor interfacing• H=writing technical paper• I=video demonstration

Page 12: Report on Project Management of a particular project

Scheduling

Critical path=b ,c ,d ,e ,g ,h , iCritical time=106 days

Page 13: Report on Project Management of a particular project

Activity Diagrams

AOA

AON

Page 14: Report on Project Management of a particular project

Table for ES, EF, LS, LF, SLACK

Page 15: Report on Project Management of a particular project

Project Crashing

Completion in 100 days crash A and I both by 3 days.So, total increment in cost if we want to do the project in 100 days is:= (100+100)*3 =Rs.600

Page 16: Report on Project Management of a particular project

Risks Involved

• Attempt to reduce project cost from 60Lakh to 6Lakh.

• Any wrong doing in project will directly affect human life.

• Lack of market for these medical devices in India.