Report on Embankment Distress Remedial Work Submit

download Report on Embankment Distress Remedial Work Submit

of 14

Transcript of Report on Embankment Distress Remedial Work Submit

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    1/14

    1.0 GENERAL DESCRIPTION OF PROJECT

    1.1 General

    Jabatan Kerja Raya Negeri Perak intend to construct the road (JKR R3 Standard

    single carriageway) connecting Alor Pongsu and Bukit Merah, Perak. The approximatelength of the road is about 7.0 km. The proposed road would bring social benefic to the

    local community by establishing a local road network for subsequent integration into the

    state transportation system.

    2.0 EMBANKMENT DISTRESS

    2.1 Introduction

    During the construction of the road embankment along the stretch of the road

    there are several occurrence of embankment distress. The first occurrence happened at

    CH4100-CH4250 on 3 August 2010 and then the second happened at CH100-CH240 on

    12 November 2010. The third occurrence happened on 2 December 2010 at CH260-

    CH400, and the last occurrence happened at CH2720-CH2860.

    2.1.1 CH4100-CH4250

    Figure 1 Cracks propagated from the centerline towards the right hand side of the carriageway

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    2/14

    The embankment fill heights between CH4100 and CH4250 are less than 2.0m.

    The fill height ranges from less than 0.5m to about 1.5m above the original ground. The

    prescribed ground treatment at the area was removal of 1.5m thick unsuitable material

    and replaced with suitable fill and sand in the ratio of 70:30. Non-woven geotextile

    Polyfelt TS40 has been prescribed as separator.

    2.1.2 CH100-CH240

    The embankment fill heights between CH100 and CH240 are in the range of 1.5m

    to 3.1m above the existing ground level. The prescribed ground treatment was Partial

    Removal and Replacement of 1.5m unsuitable material, and surcharge. Surcharge fill

    height was 1.0m high and the surcharge period was 3 to 6 months. Basal reinforcementwith woven geotextile Polyfelt PEC100 was specified in the drawing.

    Figure 2 Cracks have propagated from the edge of carriageway towards the embankment toe

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    3/14

    2.1.3 CH260-CH400

    The embankment fill heights between CH260 and CH400 are in the range of 1.5m

    to 3.1m above the existing ground level. The prescribed ground treatment was Partial

    Removal and Replacement of 1.5m unsuitable material, and surcharge. Surcharge fill

    height was 1.0m high and the surcharge period was 3 to 6 months. Basal reinforcement

    with woven geotextile Polyfelt PEC100 was specified in the drawing.

    Figure 3 Cracks propagated at the centerline towards the right and left hand side of the

    carriageway

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    4/14

    2.1.4 CH2680-CH2760

    The embankment fill heights between CH2680 and CH2760 are in the range of

    1.5m to 3.1m above the existing ground level. The prescribed ground treatment at thearea was removal of 1.5m thick unsuitable material and replaced with suitable fill and

    sand in the ratio of 70:30. Non-woven geotextile Polyfelt TS40 has been prescribed as

    separator.

    3.0 EMBANKMENT DISTRESS REMEDIAL METHOD

    3.1 Recommendation by Consultant

    It is proposed that the following remedial action be carried out to the embankment

    distress/ failure areas.

    Remove the loose fill material

    Reconstruct the slope with 2 layers of reinforced geotextile (woven

    geotextile) Tencate/ Polyfelt PEC200 (or equivalent)

    Figure 4 Cracks propagated from the left hand side of the carriageway towards the right hand side

    of the carriageway

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    5/14

    Surcharge period of 3 month with rod settlement gauge installed to

    monitor the progress of settlement

    A filling rate restriction of 0.5m per week

    The proposed remedial works is presented in Appendix B.

    APPENDIX 1 Proposed Remedial Work

    2 LAYERS OF POLYFELT PEC200 (OR

    TYPICAL SECTION FOR REMEDIAL WORK USING GEOTEXTILE

    DETAIL 'A'

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    6/14

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    7/14

    4.0 EMBANKMENT DISTRESS REMEDIAL WORK

    4.1 Embankment Distress Remedial Work Method Statement

    4.1.1 Joint Survey

    A joint survey first conducted by contractors site engineer and JKR

    representative to determine the existing reduces level of the distress embankment

    before an excavation works starts.

    4.1.2 Excavation and Backfilling Work

    The excavation of the distress embankment has been determined to specificrequirement. The depth of the excavation is 2.5m from the top of the existing

    embankment. The width of the excavation is 11.0m from the centerline to both left

    and right hand side of the proposed carriage way.

    The loose soil of the excavation is dumped nearby. When there are sufficient

    excavation areas for laying reinforced geotextile, one layer of reinforced

    geotextile PEC200 then spread on the ground. The step then repeated, the end of

    two reinforced geotextile sheets will be sewn 3 times using electric powered hand

    sawing machine. This will ensure no puncture between the reinforced geotextile.

    Figure 5 Excavation and backfilling works

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    8/14

    The loose soil excavated and dumped before, then be used as the filling

    material. The soil will be dumped on the reinforce geotextile which has been lain

    earlier and will be spread and leveled to the whole area using tractor/backhoe. The

    thickness of the soil spread is ensured not exceeding 0.6m. During this process,

    rod settlement gauge installed at the desired position.

    Figure 6 Sewing process

    Figure 7 Spreading and leveling soil

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    9/14

    4.1.3 Soil Compaction Work

    Soil compaction is the method of mechanically increasing the density of soil.

    If performed improperly, settlement of the soil could occur and resultingembankment failure. In order to achieved the desired strength to carry the

    intended embankment loading, the soil that spread and leveled before has been

    properly compacted using vibratory smooth drum roller. Besides that well

    compacted soil may reduce water seepage and provide stability.

    Vibratory force uses a mechanism, engine-driven to create a downward force

    in addition to the machine's static weight. The vibrating mechanism is the rotating

    eccentric weight or piston/spring combination. The compactors deliver a rapid

    sequence of blows (impacts) to the surface, thereby affecting the top layers as wellas deeper layers. Vibration moves through the material, setting particles in motion

    and moving them closer together for the highest density possible.

    Figure 8 Compaction work using vibratory smooth drum roller

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    10/14

    4.1.4 Constructing Second Layer of Fill Material

    Once completed, the process continued with second layer of fill material. The

    reinforced geotextile sheet laid before then folded onto the soil that has been

    compacted.

    Then another layer of reinforced geotextile PEC200 spread on the compacted

    soil. The step then repeated, the end of two reinforced geotextile sheets will be

    sewn 3 times using electric powered hand sawing machine. This will ensure no

    puncture between the reinforced geotextile.

    The soil then fill onto the reinforced geotextile layer that sewn before. The

    step is almost the same as the previous backfilling method. The loose soil from theexcavation before reused as the backfilling material. Since the quantity of soil is

    inadequate, imported soil from nearby borrow pit required. The soil is transferred

    using lorries. The soil then spread and leveled to the whole area using

    tractor/backhoe. The thickness of the soil spread is ensured not exceeding 0.6m.

    Figure 9 Reinforced geotextile that be folded onto the compacted soil

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    11/14

    Figure 10 Backfilling earth to form second fills layer

    Figure 11 Imported soil from nearby borrow pit

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    12/14

    Soil compaction process is continuously done after the soil is spread and

    leveled. The step is almost the same as the previous compaction work.

    Figure 12 Continuously soil compaction process

    Figure 13 2nd layer of reinforced geotextile be folded and backfilling with soil

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    13/14

    4.1.5 Constructing Third, Fourth and Fifth Layer of Fill Material

    The construction of third, fourth and fifth layer of fill material is a repetitive

    sequence of constructing second layer fills material, the different when backfilling

    soil to form third layer is that there is no more reinforced geotextile laid on theground. After the second layer reinforced geotextile be folded the loose soil can be

    dumped on it. Since the quantity of soil is inadequate, imported soil from nearby

    borrow pit required. The soil is transferred using lorry. The soil then spread and

    leveled to the whole area using tractor/backhoe. The thickness of the soil spread is

    ensured not exceeding 0.6m. Then extensively compaction process did to the fill

    material layer. The steps are repeated to the fourth and fifth layer.

    4.1.6 Constructing SurchargeThe construction of surcharge load is also a repetitive process of layer fourth

    and fifth. The filling earth for the surcharge is divided into two layers. There is

    restriction for filling rate of 0.5m per week. During the construction of the first

    surcharge level, the soil is spread and level not exceeding 0.5m, the soil then

    compacted using vibratory smooth drum roller. The process is repeated during the

    construction of second layer surcharge load.

    Figure 14 Compaction work on surcharge load

  • 8/2/2019 Report on Embankment Distress Remedial Work Submit

    14/14