Replacing the Stormwater Fee City Council Workshop May 8, 2012.

8
Replacing the Stormwater Fee City Council Workshop May 8, 2012

Transcript of Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Page 1: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Replacing the Stormwater Fee

City Council WorkshopMay 8, 2012

Page 2: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Original Ordinance was going to be Challenged because it did not meet criteria for a Fee

New Ordinance attempted to address legal and technical requirements in the Eyes of a Judge, Lawyers, and Engineers through a complex process with billing adjustments, credits, refunds, appeals, etc.

New Ordinance is Unfair in many ways to Property Owners Never Been Billed Some Bills Go Up, Some Go Down Golf Courses Others (Town Center, Bankrupt Projects, Areas Outside Service

Area, Schools, Agricultural Exemptions)

Stormwater Ordinance Issues

Page 3: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Stormwater Gross

Billings

Loan* Other Total

FY 2010 $6.5 M $8.0 M - $14.5 M

FY 2011 $5.8 M $1.2 M - $7.0 M

FY 2012 $4.9 M - $2.6 M $7.5 M

*Total Loan Proceeds 2009-2011 = $11 Million

Revenue History

Page 4: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Revenues for FY2012 - $7.5M

Stormwa-ter Fees; $4,900,00

0

Property Taxes (0.45

mills); $1,686,100

Infrastructure Surtax; $885,000

Page 5: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Fund Stormwater through Combination of Revenue Sources consistent with Auditor Recommendations to Diversify Revenue Sources

Replace Stormwater Fee with Combination of Electric Franchise Fee / Public Service Tax and Ad Valorem Taxes

Allocation of Funding Sources To Be Determined through Upcoming Budget Process

City Council Direction

Page 6: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Budget 2013 Revenues - $7.5M

Electric Fran-chise Fee/

Public Service

Tax

$4,700,000

Property Taxes (?

mills)

$1,686,100

Infra-structure

Tax ?$885,000

Other Sources ? $200,000

Page 7: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Stormwater Fee Utility Franchise Fee + Utility Tax

RevenueGenerated

$4.9 Million $4.7 Million

Charge $8/ERU/Month 6% Fee + 2% Tax

% Non-Residential 19% 26%

Cost to Typical Homeowner (Month)

$8.00 $7.68*(Fee $6.36, Tax $1.32)

Cost to Typical Homeowner (Year)

$96.00 $92.16

*Based on Average Bill ($106.12 Total Bill, Usage Portion $66.00)

Replacing Stormwater Fee

Page 8: Replacing the Stormwater Fee City Council Workshop May 8, 2012.

Stormwater Fee Terminated October 1, 2012 Electric Franchise Fee Agreement

6% Franchise Fee Effective October 1, 2012

Public Service Tax 2% Public Service Tax Effective October 1, 2012

Allocation of Other Funding Sources To Be Determined during Annual Budget Process

Next Steps