Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015...
Transcript of Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015...
![Page 1: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/1.jpg)
April 13, 2015Eric Williams, PE
2015 North Carolina Spring ConferenceNC AWWA-WEA
Replacing an Existing Elevated
Storage Tank on the Same Site
![Page 2: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/2.jpg)
Existing Facilities
Maintenance Issues
Tank Alternatives
Challenges
![Page 3: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/3.jpg)
Bid Challenges
Tank Construction
Tank Demolition
Construction Costs
![Page 4: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/4.jpg)
Project Location
![Page 5: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/5.jpg)
Project Location
![Page 6: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/6.jpg)
01 Existing Facilities
![Page 7: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/7.jpg)
2 Inch -12 Inch Water Lines
Materials Including PVC, Ductile Iron and Asbestos Cement
3 Master Meters
2 Elevated Storage Tanks
Existing Facilities
![Page 8: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/8.jpg)
Constructed in 1998
Capacity – 250,000 Gallons
Style – Single Pedestal
Contractor – Brown Steel Contractors
West End Elevated Storage Tank
![Page 9: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/9.jpg)
Constructed in 1973
Capacity – 200,000 Gallons
Style – Leg
Overflow Elevation – Approximately
2.2 Feet Lower than West End Tank
Contractor – Brown Steel Contractors
East End Elevated Storage Tank
![Page 10: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/10.jpg)
02 Maintenance Issues
![Page 11: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/11.jpg)
Tank in Need of Painting
Repainting would Require Complete Shrouding
Drip Line of Tank Extended Over 2 Adjacent Properties
East End Storage Tank Maintenance Issues
![Page 12: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/12.jpg)
03 Tank Alternatives
![Page 13: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/13.jpg)
Repaint and Repair Existing Tank
oCosts were Estimated at $500,000-$600,000 (Lead Based Paint)
oTank Would Still Be 40+ Years Old
Build a New Tank
oCan Increase Capacity
oCan Match West End Overflow Elevation
oCan Match Tank Style
oFuture Maintenance Less Costly
East End Storage Tank Alternatives
![Page 14: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/14.jpg)
04 Challenges
![Page 15: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/15.jpg)
New Tank Construction
Close Proximity of Homes
Pile Installation
Painting
Telecommunications Facilities
Demolition of Existing Tank
Resort/Vacation Destination –
Construction Schedule
Restrictions
Challenges
![Page 16: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/16.jpg)
Challenges - Tank Site
![Page 17: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/17.jpg)
05 Bid Challenges
![Page 18: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/18.jpg)
Planned to Bid Tank Construction and Tank Demolition Separately
Only One Bid Received on Bid Day
Only One Bid Received on the Rescheduled Bid Day
Bid not Submitted by a Tank Contractor – A. C. Schultes
Bid Received Exceeded Budget
Able to Negotiate a Lower Price
Negotiations Included Adding Tank Demolition
Bid Challenges
![Page 19: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/19.jpg)
06 Tank Construction
![Page 20: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/20.jpg)
Water Line Installation
12-Inch Water Line
Design was to Cut In New Tee
Existing Isolation Valve Would not
Hold
Tank Construction
![Page 21: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/21.jpg)
Foundation Installation
Driven 12-Inch Steel H Piles
Minimum Depth Required - 40 Feet
Monitored Vibration at Adjacent Homes
Noise Restrictions (8:00 am – 8:00 pm)
Pile Cap – 4 Feet Thick by 2.5 Feet
Wide
24 – 2” Anchor Bolts by 3 Feet 4 Inches
Long (To Extend 7 Inches Above
Concrete)
Tank Construction
![Page 22: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/22.jpg)
Structure by Caldwell Tanks
Challenges
oClose Proximity of Homes
oTotal Site – Less than ½ Acre
oStorage Space for Steel
Components
oExisting Tank
oTelecommunications Structures
Tank Construction
![Page 23: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/23.jpg)
Structure
Single Pedestal
Complaints/Damage to
Private Property
Tank Construction
![Page 24: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/24.jpg)
Painting
Shrouding Required –
Tightly Woven Nylon
Windy Conditions –
15 mph Maximum
Summer Season
Restrictions
Tank Construction
![Page 25: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/25.jpg)
Shrouding
Outriggers
Extensive Cabling
Equipment at Base of Tank for Raising and
Lowering Shroud
Tank Construction
![Page 26: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/26.jpg)
Paint by Tnemec
Interior (Dry) – 2 Coat System
o Shop Prime – 5.0 mils Series N-140 Epoxy
o Stripe Coat – 5.0 mils Series N-140 Epoxy – For all Seams
and Abraded Areas
o Finish Coat – 5.0 mils Series N-140 Epoxy – Stripe Coat
then Full Coat
Interior (Wet) – 3 Coat System
o Shop Prime – 3.0 mils Series 94 Hydro-Zinc
o Stripe Coat – 3.0 mils Series 94 Hydro-Zinc – For all
Seams and Abraded Areas
o Finish Coat –
• 5.0 mils Series N-140 Epoxy – Stripe Coat to all Weld Seams,
Edges, Corners, Bolts and Nuts – Tank White
• 5.0 mils Series N140 Epoxy – Beige Color
• 5.0 mils Series N140 Epoxy – Tank White
Tank Construction
![Page 27: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/27.jpg)
Paint by Tnemec
Exterior – 4 Coat System
o Shop Prime – 3.0 mils Series
94 Zinc Rich Polyurethane
o Stripe Coat – 3.0 mils Series
94 – For all Seams and
Abraded Areas
o Finish Coat – 3 Separate
Coats
• 3.0 mils Series N69 Hi-Build
Epoxy
• 2.0 mils Series 73 Endura Shield
(Polyurethane Enamel)
• 2.5 mils Series 700 Hydroflon
Tank Construction
![Page 28: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/28.jpg)
Standby Generator for SCADA
Electrical and SCADA Equipment
Discharge Headwall Structure
Altitude Valve
Tank ConstructionTank Components
![Page 29: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/29.jpg)
Telecommunication Vendors
ATMC/AT&T
Verizon
Town
Communication
Antenna
SCADA Antenna
Tank Construction
Verizon ATMC/AT&T
![Page 30: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/30.jpg)
Telecommunications
Cabling in Tank
Cabling Continues Through
Access Tube
Tank Construction
![Page 31: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/31.jpg)
07 Tank Demolition
![Page 32: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/32.jpg)
Protect
Telecommunications
Structures
Protect Brand New
Tank
Loading of Steel
Components
Tank Demolition
![Page 33: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/33.jpg)
No Complaints or Damage
During Demolition
Three Days from Start to
Finish
Tank Demolition
![Page 34: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/34.jpg)
Valve Vault
Other Structures
Tank Demolition
![Page 35: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/35.jpg)
08 Construction Costs
![Page 36: Replacing an Existing Elevated Storage Tank on the Same Site...April 13, 2015 Eric Williams, PE 2015 North Carolina Spring Conference NC AWWA-WEA Replacing an Existing Elevated Storage](https://reader033.fdocuments.us/reader033/viewer/2022052007/601af1761040410fb86604d5/html5/thumbnails/36.jpg)
Original Budget - $1,400,000
As Bid Without Demolition - $1,574,618
After Negotiations with Demolition -
$1,498,600
Final Cost after Change Orders -
$1,475,038.75
Approximately $35,000 Paid by
Telecommunications Vendors
Construction Costs