REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I....

172
LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT PREPARED FOR: CUMBERLAND COUNTY TECHNICAL EDUCATION CENTER 601 BRIDGETON AVENUE BRIDGETON, NJ 08302 ATTN: MR. GENE MERCOLI BUSINESS ADMINISTRATOR PREPARED BY: CONCORD ENGINEERING GROUP 520 S. BURNT MILL ROAD VOORHEES, NJ 08043 TELEPHONE: (856) 427-0200 FACSIMILE: (856) 427-6529 WWW.CEG-INC.NET CEG CONTACT: PATRICK MULLEN, P.E. LEAD MECHANICAL ENGINEER EMAIL: PMULLEN@CEG-INC.NET REPORT ISSUANCE: FINAL, APRIL 6, 2011 PROJECT NO: 9C10093

Transcript of REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I....

Page 1: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

LOCAL GOVERNMENT ENERGY AUDIT PROGRAM: ENERGY AUDIT REPORT

PREPARED FOR: CUMBERLAND COUNTY TECHNICAL EDUCATION CENTER

601 BRIDGETON AVENUE BRIDGETON, NJ 08302 ATTN: MR. GENE MERCOLI BUSINESS ADMINISTRATOR

PREPARED BY: CONCORD ENGINEERING GROUP

520 S. BURNT MILL ROAD VOORHEES, NJ 08043 TELEPHONE: (856) 427-0200 FACSIMILE: (856) 427-6529 WWW.CEG-INC.NET

CEG CONTACT: PATRICK MULLEN, P.E.

LEAD MECHANICAL ENGINEER EMAIL: [email protected]

REPORT ISSUANCE: FINAL, APRIL 6, 2011

PROJECT NO: 9C10093

Page 2: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 1 of 89

TABLE OF CONTENTS

I.  EXECUTIVE SUMMARY ................................................................................................. 3 

II.  INTRODUCTION ............................................................................................................. 11 

III.  METHOD OF ANALYSIS................................................................................................ 13 

IV.  HISTORIC ENERGY CONSUMPTION/COST ............................................................... 15 

A. ENERGY USAGE / TARIFFS .................................................................................................. 15

B. ENERGY USE INDEX (EUI) .................................................................................................. 19

C. EPA ENERGY BENCHMARKING SYSTEM ............................................................................. 22

V.  FACILITY DESCRIPTION .............................................................................................. 24 

VI.  MAJOR EQUIPMENT LIST ............................................................................................ 29 

VII.  ENERGY CONSERVATION MEASURES ..................................................................... 30 

VIII.  RENEWABLE/DISTRIBUTED ENERGY MEASURES ................................................ 72 

IX.  ENERGY PURCHASING AND PROCUREMENT STRATEGY .................................. 80 

X.  INSTALLATION FUNDING OPTIONS.......................................................................... 85 

XI.  ADDITIONAL RECOMMENDATIONS ......................................................................... 88 

Appendix A – ECM Cost & Savings Breakdown

Appendix B – New Jersey Smart Start® Program Incentives

Appendix C – Portfolio Manager “Statement of Energy Performance”

Appendix D – Major Equipment List

Appendix E – Investment Grade Lighting Audit

Appendix F – Renewable / Distributed Energy Measures Calculations

Appendix G – Energy Calculations - Energy Recovery

Appendix H – Energy Calculations – Envelope Upgrade

Page 3: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 2 of 89

REPORT DISCLAIMER

The information contained within this report, including any attachment(s), is intended solely for use by the named addressee(s). If you are not the intended recipient, or a person designated as responsible for delivering such messages to the intended recipient, you are not authorized to disclose, copy, distribute or retain this report, in whole or in part, without written authorization from Concord Engineering Group, Inc., 520 S. Burnt Mill Road, Voorhees, NJ 08043.

This report may contain proprietary, confidential or privileged information. If you have received this report in error, please notify the sender immediately. Thank you for your anticipated cooperation.

Page 4: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 3 of 89

I. EXECUTIVE SUMMARY

This report presents the findings of the energy audit conducted for:

Cumberland County Technical Education Center 601 Bridgeton Avenue Bridgeton, NJ 08302 Municipal Contact Person: Gene Mercoli, Business Administrator

Facility Contact Person: Shane Davenport, Facilities Manager This audit is performed in connection with the New Jersey Clean Energy - Local Government Energy Audit Program. The energy audit is conducted to promote the mission of the office of Clean Energy, which is to use innovation and technology to solve energy and environmental problems in a way that improves the State’s economy. This can be achieved through the wiser and more efficient use of energy. The annual energy costs at this facility are as follows: The potential annual energy cost savings for each energy conservation measure (ECM) and renewable energy measure (REM) are shown below in Table 1. Be aware that the ECM’s and REM’s are not additive because of the interrelation of some of the measures. This audit is consistent with an ASHRAE level 2 audit. The cost and savings for each measure is ± 20%. The evaluations are based on engineering estimations and industry standard calculation methods. More detailed analyses would require engineering simulation models, hard equipment specifications, and contractor bid pricing.

Electricity $ 222,578

Natural Gas $ 121,978

Total $ 334,556

Page 5: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 4 of 89

Table 1 Financial Summary Table

ENERGY CONSERVATION MEASURES (ECM's)

ECM #1 Indoor Heating & Ventilation Units Upgrade

$39,862 $242 164.7 -90.9%

ECM #2 Roof Top Heating & Ventilation Units Upgrade

$385,853 $3,575 107.9 -86.1%

ECM #3 Packaged Cool/Heat RTU Upgrade

$39,223 $1,109 35.4 -57.6%

ECM #4 Condensing Unit Upgrade $14,848 $2,590 5.7 161.7%

ECM #5 Multi-deck RTU Upgrade with Energy Recovery

$1,607,623 $41,684 38.6 -61.1%

ECM #6 Premium Efficient Motor Upgrade

$15,990 $295 54.2 -66.8%

ECM #7 Dishwasher & Booster Water Heater Upgrade

$11,660 $1,025 11.4 5.5%

ECM #8 Building Envelope Upgrade - Base Bid

$924,300 $9,679 95.5 -73.8%

ECM #8.1 Building Envelope Upgrade - Alternate Bid

$1,039,300 $13,769 75.5 -66.9%

ECM #9 DDC Controls / Retro Commissioning

$265,186 $15,246 17.4 -13.8%

ECM #10 Lighting Upgrade - General $39,154 $11,914 3.3 356.4%

ECM #11 Lighting Controls $32,910 $8,690 3.8 296.1%

ECM #12 CRT Monitor Replacement $600 $147 4.1 268.6%

REM #1 Solar PV System 293.02 kW DC

$2,637,180 $181,130 14.6 71.7%

Notes: A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.

ANNUAL SAVINGSB

RENEWABLE ENERGY MEASURES (REM's)

ECM NO. DESCRIPTION

NET INSTALLATION

COST

ANNUAL SAVINGS

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

ECM NO. DESCRIPTION

SIMPLE PAYBACK

(Yrs)

SIMPLE LIFETIME

ROI

NET INSTALLATION

COSTA

The estimated demand and energy savings for each ECM and REM is shown below in Table 2. The descriptions in this table correspond to the ECM’s and REM’s listed in Table 1.

Page 6: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 5 of 89

Table 2 Estimated Energy Savings Summary Table

ECM #1 Indoor Heating & Ventilation Units Upgrade

0.2 804.5 12.5

ECM #2 Roof Top Heating & Ventilation Units Upgrade

1.8 9,330.3 81.3

ECM #3 Packaged Cool/Heat RTU Upgrade

4.4 3,949.0 373.7

ECM #4 Condensing Unit Upgrade 5.9 16,602.6 0.0

ECM #5 Multi-deck RTU Upgrade with Energy Recovery

0.0 97,664.0 20,036.5

ECM #6 Premium Efficient Motor Upgrade

1.9 1,890.8 0.0

ECM #7 Dishwasher & Booster Water Heater Upgrade

8.0 4,643.0 0.0

ECM #8 Building Envelope Upgrade - Base Bid

9.1 8,202.0 6,363.3

ECM #8.1 Building Envelope Upgrade - Alternate Bid

14.6 13,104.0 8,882.3

ECM #9 DDC Controls / Retro Commissioning

0.0 88,668.5 1,071.3

ECM #10 Lighting Upgrade - General 25.1 76,077.0 0.0

ECM #11 Lighting Controls 21.6 55,706.0 0.0

ECM #12 CRT Monitor Replacement 0.0 945.0 0.0

REM #1 Solar PV System 293.02 kW DC

237.3 357,965.0 0.0

ECM NO. DESCRIPTION

ANNUAL UTILITY REDUCTION

ECM NO. DESCRIPTION

ANNUAL UTILITY REDUCTION

NATURAL GAS (THERMS)

RENEWABLE ENERGY MEASURES (REM's)

ENERGY CONSERVATION MEASURES (ECM's)

ELECTRIC DEMAND

(KW)

ELECTRIC DEMAND

(KW)

ELECTRIC CONSUMPTION

(KWH)

NATURAL GAS (THERMS)

ELECTRIC CONSUMPTION

(KWH)

Page 7: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 6 of 89

Concord Engineering Group (CEG) recommends proceeding with the implementation of all ECM’s that provide a calculated simple payback at or under ten (10) years. The following Energy Conservation Measures are recommended for the facility:

• ECM #4: Condensing Unit Upgrade

• ECM #10: Lighting Upgrade - General

• ECM #11: Lighting Controls

• ECM #12: CRT Monitor Replacement

Although ECMs #7 and #9 do not provide paybacks in less than 10 years, it is recommended to proceed with them. The installation of a dishwasher and electric booster heater as suggested in ECM #7 (or equal) for the Culinary Arts & Hospitality kitchen is recommended since the existing dishwasher and electric booster heating units are past their expected lifespan and will have a considerable energy and water reduction. It is recommended to proceed with Retro-commissioning in the near term and DDC controls for the long term as suggested in ECM #9 (or equal). This will allow energy savings in the near term using the equipment and controls already in place. The long term plan would connect heating, ventilation and air conditioning equipment to the DDC control system to provide the benefits of DDC control and reduce the energy consumption.

As part of ECM#9, based on the review of the facility’s energy bills and discussions with the CCTEC personnel, the energy audit team recommends Retro-Commissioning of this facility to meet the following objectives:

• Bring existing HVAC equipment to its proper operational state including air and water distribution systems

• Reduce energy use and energy costs • Improve indoor air quality • Verify the installation and performance of identified system upgrades • Address overall building energy use and demand and identify areas of highest energy use

and demand • Identify the location of the most comfort problems or trouble spots in the building • Review current O&M practices

Through the implementation of a Retro-Commissioning Plan, the Cumberland County Technical Education Center will be able to continue with their vision of reducing energy usage and operating efficient facilities. Indicated in the next section is the “Combined Project Approach” detailing a recommended packaging of energy conservation measures that provides a suitable payback as compared to implementation cost and resulting energy cost savings.

Page 8: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 7 of 89

Combined Project Approach: Although individual projects with a simple payback of 10 years and less are considered financially self sustaining, it is important to consider how multiple projects can be combined together. When ECMs are aggregated into a single project, the lower cost ECMs provides valuable savings to offset the higher cost ECMs.

The Energy Savings Improvement Program (ESIP) allows for financing of any combination of energy efficiency projects into one large project. The term of the financing must be under 15 years and the savings provides the revenue for the financing cost. The combination of all projects into one large energy efficiency project provides Cumberland County Technical Education Center with the opportunity to implement ECM #4, #7, #9, #10, #11 and #12 as identified within this report with an overall simple payback of 9.2 years. This option allows Cumberland County Technical Education Center to implement much needed infrastructure improvements such as new air conditioning condensing unit, dishwasher and booster water heater, DDC controls and Retro commissioning, high efficiency lighting, lighting controls and to upgrade the remaining CRT computer monitors to the more efficient LCD monitor for the facility. The program financing allows for the implementation with no upfront cost for Cumberland County Technical Education Center. Implementation of an ESIP provides significant benefits and should be strongly considered for Cumberland County Technical Education Center. The total Entity Project Summary table below shows the savings, costs, incentive programs and paybacks for all ECMs at Cumberland County Technical Education Center that can be combined and will have a payback in less than 15 years.

It is pertinent to note that if the CCTEC has available capital funds, these projects would be highly recommended for implementation and would not require the use of the ESIP legislation.

Page 9: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 8 of 89

Table 3 ESIP -Total Entity Project Summary

ECM #4 Condensing Unit Upgrade $2,590 $15,835 $988 $14,848 5.7

ECM #7 Dishwasher & Booster Water Heater Upgrade

$1,025 $11,660 $0 $11,660 11.4

ECM #9 DDC Controls / Retro Commissioning

$15,246 $265,186 $0 $265,186 17.4

ECM #10 Lighting Upgrade - General $11,914 $42,754 $3,600 $39,154 3.3

ECM #11 Lighting Controls $8,690 $34,800 $1,890 $32,910 3.8

ECM #12 CRT Monitor Replacement $147 $600 $0 $600 4.1

Total Entity Project $39,613 $370,835 $6,478 $364,358 9.2

Total CCTEC Energy Costs: $344,556Est. Total CCTEC Energy Savings: $39,613

Overall CCTEC Percent Reduction: 11.5%

* Rebates / Incentives represent an estimate for the potential incentives (not guarenteed for the ECM specified.)** Customer cost is based on maximum incentive available (Smart Start )

ECM #

ENERGY SAVINGS IMPROVEMENT PROGRAM - POTENTIAL ENERGY EFFICIENCY PROJECT

REBATES, INCENTIVES*

FACILITY ENERGY EFFICIENCY PROJECTS

ANNUAL ENERGY

SAVINGS ($)

PROJECT COST ($)

CUSTOMER COST **

SIMPLE PAYBACK

Implementation of all ECMs identified within the ESIP – Entity Total Project Summary table represents a total annual savings of approximately $39,613 for Cumberland County Technical Education Center. The description of each ECM is shown later in this report.

Page 10: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 9 of 89

Capital Improvement Energy Conservation Measures: The ECMs that have much longer paybacks are considered capital improvement ECMs. These ECMs typically have high installation costs that are more difficult to justify the savings based solely on the energy savings associated with the improvement. Despite the long paybacks, these ECMs in many cases provide valuable and much needed infrastructure improvements for the facility. These ECMs include HVAC equipment upgrades, electric motor upgrades and building envelope improvements. The savings identified for the following ECMs provides additional incentive for Cumberland County Technical Education Center’s capital improvement projects.

Although ECM #1 does not provide a payback less than 10 years, it is recommended to proceed with the installation of efficient rooftop heating and ventilation units as suggested in ECM #1 (or equal) for the Gymnasium addition and East wing, since the existing rooftop heating and ventilation units are past their expected lifespan.

Although ECM #2 does not provide a payback less than 10 years, it is recommended to proceed with the installation of efficient rooftop units as suggested in ECM #2 (or equal) for the Main Building, since the existing rooftop units are past their expected lifespan.

Although ECM #3 does not provide a payback less than 10 years, it is recommended to proceed with the installation of efficient packaged cooling/heating rooftop units as suggested in ECM #3 (or equal) for the Board Office and South wing, since the existing packaged rooftop units are past their expected lifespan.

Although ECM #5 does not provide a payback less than 10 years, it is recommended to proceed with the installation of an efficient rooftop unit as suggested in ECM #5 (or equal) for the Main Building, since the existing rooftop units are past their expected lifespan and will have a considerable energy reduction.

ECM #6 does not provide a payback less than 10 years. The shop air compressor and paint booth fan motors are recommended for replacement. It is recommended when these motors are replaced, they should be replaced with premium efficient motors as suggested in ECM #6 (or equal) as they will provide a notable energy savings.

Although ECMs #8 and #8.1 do not provide a payback less than 10 years, it is recommended to proceed with the installation of new FRP doors, panels and windows as suggested in ECM #8.1 (or equal) for the CCTEC building envelope, since the existing known asbestos will be abated and there will be a notable energy reduction.

Page 11: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 10 of 89

Other Considerations:

In addition to the ECMs, there are maintenance and operational measures that can provide significant energy savings and immediate benefit. The ECMs listed above represent investments that can be made to the facility which are justified by the savings seen overtime. However, the maintenance items and small operational improvements below are typically achievable with on site staff or maintenance contractors and in turn have the potential to provide substantial operational savings compared to the costs associated. The following are recommendations which should be considered a priority in achieving an energy efficient building:

1. Chemically clean the condenser and evaporator coils periodically to optimize efficiency.

Poorly maintained heat transfer surfaces can reduce efficiency 5-10%. 2. Maintain all weather stripping on entrance doors. 3. Clean all light fixtures to maximize light output. 4. Provide more frequent air filter changes to decrease overall system power usage and maintain

better IAQ. Renewable Energy Measures (REMs) were also reviewed for implementation at the Cumberland County Technical Education Center. CEG utilized a roof and parking lot canopy mounted solar array to house a substantial PV system. The recommended 293.0 kW PV system will produce approximately 357,965 kWh of electricity annually and will reduce the schools electrical consumption from the grid by 25.05%. The system’s calculated simple payback of 14.56 years is past the standard 10 year simple payback threshold; however, with alternative funding this payback could be lessened. CEG recommends the Owner review all funding options before deciding to not implement this renewable energy measure. Overall Assessment: Overall, the Cumberland County Technical Education Center appears to be operating at a higher efficiency level compared to other schools in the region. With the implementation of the above recommended measures the Education Center will realize further energy savings at the Cumberland County Technical Education Center.

Page 12: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 11 of 89

II. INTRODUCTION

The comprehensive energy audit covers the 120,543 square foot Cumberland County Technical Education Center Building, which includes the following spaces: Electrical Technology, Carpentry, Plumbing and HVAC Technology, Construction Trades, Automotive Servicing Technology, Auto Collision Repair Technology, Welding Technology, Cafeteria, Culinary Arts & Hospitality Kitchen, Health Occupations Dental, Cosmetology, Internet Technology, Digital Graphics, academic classrooms, atrium, offices, Conference Center, restrooms, Gymnasium, locker rooms, storage rooms and Maintenance areas. Electrical and natural gas utility information is collected and analyzed for one full year’s energy use of the building. The utility information allows for analysis of the building’s operational characteristics; calculate energy benchmarks for comparison to industry averages, estimated savings potential, and baseline usage/cost to monitor the effectiveness of implemented measures. A computer spreadsheet is used to calculate benchmarks and to graph utility information (see the utility profiles below). The Energy Use Index (EUI) is established for the building. Energy Use Index (EUI) is expressed in British Thermal Units/square foot/year (BTU/ft2/yr), which is used to compare energy consumption to similar building types or to track consumption from year to year in the same building. The EUI is calculated by converting the annual consumption of all energy sources to BTU’s and dividing by the area (gross square footage) of the building. Blueprints (where available) are utilized to verify the gross area of the facility. The EUI is a good indicator of the relative potential for energy savings. A low EUI indicates less potential for energy savings, while a high EUI indicates poor building performance therefore a high potential for energy savings. Existing building architectural and engineering drawings (where available) are utilized for additional background information. The building envelope, lighting systems, HVAC equipment, and controls information gathered from building drawings allow for a more accurate and detailed review of the building. The information is compared to the energy usage profiles developed from utility data. Through the review of the architectural and engineering drawings a building profile can be defined that documents building age, type, usage, major energy consuming equipment or systems, etc. The preliminary audit information is gathered in preparation for the site survey. The site survey provides critical information in deciphering where energy is spent and opportunities exist within a facility. The entire site is surveyed to inventory the following to gain an understanding of how each facility operates:

• Building envelope (roof, windows, etc.) • Heating, ventilation, and air conditioning equipment (HVAC) • Lighting systems and controls • Facility-specific equipment

Page 13: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 12 of 89

The building site visit is performed to survey all major building components and systems. The site visit includes detailed inspection of energy consuming components. Summary of building occupancy schedules, operating and maintenance practices, and energy management programs provided by the building manager are collected along with the system and components to determine a more accurate impact on energy consumption.

Page 14: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 13 of 89

III. METHOD OF ANALYSIS

Post site visit work includes evaluation of the information gathered, researching possible conservation opportunities, organizing the audit into a comprehensive report, and making recommendations on HVAC, lighting and building envelope improvements. Data collected is processed using energy engineering calculations to anticipate energy usage for each of the proposed energy conservation measures (ECMs). The actual building’s energy usage is entered directly from the utility bills provided by the owner. The anticipated energy usage is compared to the historical data to determine energy savings for the proposed ECMs. It is pertinent to note, that the savings noted in this report are not additive. The savings for each recommendation is calculated as standalone energy conservation measures. Implementation of more than one ECM may in some cases affect the savings of each ECM. The savings may in some cases be relatively higher if an individual ECM is implemented in lieu of multiple recommended ECMs. For example implementing reduced operating schedules for inefficient lighting will result in a greater relative savings. Implementing reduced operating schedules for newly installed efficient lighting will result in a lower relative savings, because there is less energy to be saved. If multiple ECM’s are recommended to be implemented, the combined savings is calculated and identified appropriately. ECMs are determined by identifying the building’s unique properties and deciphering the most beneficial energy saving measures available that meet the specific needs of the facility. The building construction type, function, operational schedule, existing conditions, and foreseen future plans are critical in the evaluation and final recommendations. Energy savings are calculated base on industry standard methods and engineering estimations. Energy consumption is calculated based on manufacturer’s cataloged information when new equipment is proposed. Cost savings are calculated based on the actual historical energy costs for the facility. Installation costs include labor and equipment costs to estimate the full up-front investment required to implement a change. Costs are derived from Means Cost Data, industry publications, and local contractors and equipment suppliers. The NJ Smart Start Building® program incentives savings (where applicable) are included for the appropriate ECM’s and subtracted from the installed cost. Maintenance savings are calculated where applicable and added to the energy savings for each ECM. The life-time for each ECM is estimated based on the typical life of the equipment being replaced or altered. The costs and savings are applied and a simple payback, simple lifetime savings, and simple return on investment are calculated. See below for calculation methods:

Page 15: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 14 of 89

ECM Calculation Equations:

⎟⎟⎠

⎞⎜⎜⎝

⎛=

SavingsYearlyCostNetPaybackSimple

( )LifetimeECMSavingsYearlySavingsLifetimeSimple ×=

CostNetCostNetSavingsLifetimeSimpleROILifetimeSimple )( −

=

( )LifetimeECMSavingseMaintenancYearlySavingseMaintenancLifetime ×=

( )∑=

⎟⎟⎠

⎞⎜⎜⎝

+=

N

0nnIRR1PeriodofFlowCashReturnofRateInternal

( )∑=

⎟⎟⎠

⎞⎜⎜⎝

+=

N

0nnDR1PeriodofFlowCashValuePresentNet

Net Present Value calculations based on Interest Rate of 3%.

Page 16: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 15 of 89

IV. HISTORIC ENERGY CONSUMPTION/COST A. Energy Usage / Tariffs The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. The facility has one natural gas meter and five electric meters: the school, irrigation pump, sign, service for the house project and a rented area light for the house project. The electric power consumption is primarily the school building. The natural gas and electric data was provided as a summary total with a sample bill from each meter which provided an electric demand of 408 kW for the school. The electric usage profile represents the actual electrical usage for the facility. The demand profile is an estimated profile using the provided 408 kW as an assumed peak demand. Atlantic City Electric (ACE) provides electricity to the facility under their Annual General Service and Monthly General service rate structures. A Third Part Supplier (TPS) was not contracted during the period of the supplied energy data. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The gas usage profile shows the actual natural gas energy usage for the facility. South Jersey Gas provides natural gas to the facility under the Basic General Supply Service (Firm Transportation) rate structure. Woodruff Energy, a Third Part Supplier (TPS), was contracted during the period of the supplied energy data. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy. The facility has miscellaneous equipment used in a classroom setting for learning and troubleshooting. The equipment utilizes natural gas, propane, oil and electricity. One Gallon of #2 oil is equivalent to 140,000 BTUs of energy. One Gallon of propane is equivalent to 91,600 BTUs of energy. The equipment runs a minimal amount of time and does not have a significant impact on facility operation energy utilization. Therefore, this miscellaneous energy usage is ignored in this report. The overall cost for utilities is calculated by dividing the total cost by the total usage. Based on the utility history provided, the average cost for utilities at this facility is as follows: Description Average

Electricity 15.6¢ / kWh Natural Gas $1.32 / Therm

Page 17: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 16 of 89

Table 4 Electricity Billing Data

Utility Provider:

Rate:

Meter No:

Customer ID No:

Third Party Utility Provider:

TPS Meter / Acct No: N/AMONTH OF USE CONSUMPTION TOTAL BILL

Dec-09 110,656 $16,097 Jan-10 102,914 $14,842 Feb-10 106,685 $15,293 Mar-10 112,343 $16,279 Apr-10 116,230 $16,922 May-10 144,780 $23,175 Jun-10 150,762 $25,587 Jul-10 132,602 $22,562

Aug-10 131,630 $23,375 Sep-10 126,063 $19,863 Oct-10 95,172 $14,134 Nov-10 99,291 $14,448 Totals 1,429,128 408.9 Max $222,578

AVERAGE DEMAND 354.3 KW averageAVERAGE RATE $0.156 $/kWh

405.8

Monthly General Service, Annual General Service+Private Street Lighting, Monthly General Service, Street/Private Lighting, Monthly General Service

82890472, 82890387, 105748403, Street Light, 105738749

286.5

323.1322.8338.3400.7

None

ELECTRIC USAGE SUMMARY

0329 9959 9981, 0329 9959 9999, 1137 2849 9949, 1137 2849 9980, 1137 2849 9998

Atlantic City Electric

387.4

333.6389.9

DEMAND315.4

408.9339.8

Page 18: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 17 of 89

Figure 1 Electricity Usage Profile

Page 19: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 18 of 89

Table 5 Natural Gas Billing Data

Utility Provider: South Jersey GasRate: BGSS Firm Transportation

Meter No: 0222200Account Number:: 3 14 11 0029 05

Third Party Utility Provider: Woodruff EnergyTPS Meter No:

MONTH OF USE CONSUMPTION (THERMS) TOTAL BILL

Dec-09 21,803.21 $27,537.52Jan-10 19,073.50 $24,175.88Feb-10 13,296.96 $17,045.13Mar-10 6,607.44 $8,852.66Apr-10 4,149.08 $5,730.91May-10 1,439.20 $2,451.01Jun-10 608.29 $1,447.13Jul-10 471.96 $1,191.74

Aug-10 1,095.68 $2,031.56Sep-10 2,482.92 $3,914.93Oct-10 6,560.00 $8,863.73Nov-10 14,510.08 $18,735.94

TOTALS 92,098.32 $121,978.14

AVERAGE RATE: $1.32 $/THERM

NATURAL GAS USAGE SUMMARY

Page 20: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 19 of 89

Figure 2 Natural Gas Usage Profile

Page 21: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 20 of 89

B. Energy Use Index (EUI) Energy Use Index (EUI) is a measure of a building’s annual energy utilization per square foot of building. This calculation is completed by converting all utility usage consumed by a building for one year, to British Thermal Units (BTU) and dividing this number by the building square footage. EUI is a good measure of a building’s energy use and is utilized regularly for comparison of energy performance for similar building types. The Oak Ridge National Laboratory (ORNL) Buildings Technology Center under a contract with the U.S. Department of Energy maintains a Benchmarking Building Energy Performance Program. The ORNL website determines how a building’s energy use compares with similar facilities throughout the U.S. and in a specific region or state. Source use differs from site usage when comparing a building’s energy consumption with the national average. Site energy use is the energy consumed by the building at the building site only. Source energy use includes the site energy use as well as all of the losses to create and distribute the energy to the building. Source energy represents the total amount of raw fuel that is required to operate the building. It incorporates all transmission, delivery, and production losses, which allows for a complete assessment of energy efficiency in a building. The type of utility purchased has a substantial impact on the source energy use of a building. The EPA has determined that source energy is the most comparable unit for evaluation purposes and overall global impact. Both the site and source EUI ratings for the building are provided to understand and compare the differences in energy use. The site and source EUI for this facility is calculated as follows:

FootageSquareBuildingkBtuinUsageGaskBtuinUsageElectricEUISiteBuilding )( +

=

FootageSquareBuildingRatioSSXkBtuinUsageGasRatioSSXkBtuinUsageElectricEUISourceBuilding )( +

=

Page 22: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 21 of 89

Table 6 Facility Energy Use Index (EUI) Calculation

kWh Therms Gallons kBtu kBtu

ELECTRIC 1,429,128.0 4,879,043 3.340 16,296,004

NATURAL GAS 92,098.3 9,209,832 1.047 9,642,694

FUEL OIL 0.0 0 1.010 0

PROPANE 0.0 0 1.010 0

TOTAL 14,088,875 25,938,698

BUILDING AREA 120,543 SQUARE FEET

BUILDING SITE EUI 116.88 kBtu/SF/YRBUILDING SOURCE EUI 215.18 kBtu/SF/YR

ENERGY USE INTENSITY CALCULATION

ENERGY TYPESITE-

SOURCE RATIO

BUILDING USESITE

ENERGYSOURCE ENERGY

*Site - Source Ratio data is provided by the Energy Star Performance Rating Methodology for Incorporating Source Energy Use document issued Dec 2007.

As a comparison, data has been gathered by the US Department of Energy (DOE) for various facilities cataloguing the standard site and source energy utilization. This data has been published in the 2003 Commercial Building Energy Consumption Survey and is noted as follows for facilities of this type:

Education (College-University Campus level)

120 280 0.452 54.24 126.56

Food Service (Restaurant/Cafeteria)

302 612 0.099 29.898 60.588

Health Care: Outpatient (Clinic/Other Outpatient Health)

84 219 0.18 15.12 39.42

Service (Vehicle Repair) 77 150 0.269 20.713 40.35

1.000 119.97 266.92Historical Utility Usage EUI 116.88 215.18Facility Comparison, % Better or (% worse) 2.6% 19.4%

Facility TypeSite Energy (kBtu/SF)

Source Energy (kBtu/SF)

Area % CCTEC

Calculated Average Source Energy

(kBtu/SF)

Calculated Average Site

Energy (kBtu/SF)

Based on the information compiled for the studied facility and compared to the national average, the site energy usage is approximately 2.6 % lower and the source energy usage is 19.4% lower than the baseline data.

Page 23: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 22 of 89

C. EPA Energy Benchmarking System The United States Environmental Protection Agency (EPA) in an effort to promote energy management has created a system for benchmarking energy use amongst various end users. The benchmarking tool utilized for this analysis is entitled Portfolio Manager. The Portfolio Manager tool allows tracking and assessment of energy consumption via the template forms located on the ENERGY STAR website (www.energystar.gov). The importance of benchmarking for local government municipalities is becoming more important as utility costs continue to increase and emphasis is being placed on carbon reduction, greenhouse gas emissions and other environmental impacts. Based on information gathered from the ENERGY STAR website, Government agencies spend more than $10 billion a year on energy to provide public services and meet constituent needs. Furthermore, energy use in commercial buildings and industrial facilities is responsible for more than 50 percent of U.S. carbon dioxide emissions. It is vital that local government municipalities assess facility energy usage, benchmark energy usage utilizing Portfolio Manager, set priorities and goals to lessen energy usage and move forward with priorities and goals. In accordance with the Local Government Energy Audit Program, CEG has created an ENERGY STAR account for the municipality to access and monitoring the facility’s yearly energy usage as it compares to facilities of similar type. The login page for the account can be accessed at the following web address; the username and password are also listed below:

https://www.energystar.gov/istar/pmpam/index.cfm?fuseaction=login.login User Name: cumberlandcountytec Password: lgeaceg2010 Security Question: What city were you born in? Security Answer: “bridgeton” The utility bills and other information gathered during the energy audit process are entered into the Portfolio Manager. The following is a summary of the results for the facility:

Table 7 ENERGY STAR Performance Rating

ENERGY STAR PERFORMANCE RATING

FACILITY DESCRIPTION

ENERGY PERFORMANCE

RATING

NATIONAL AVERAGE

CCTEC N/A -

Refer to Statement of Energy Performance Appendix for the detailed energy summary. This facility type falls under the College/University (campus level) category. This facility cannot be

Page 24: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 23 of 89

rated since more than 10% of the facility spaces fall under the “other” sub-category (other than the energy star defined building space types).

Page 25: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 24 of 89

V. FACILITY DESCRIPTION

The 120,543 SF Technical Education Center is a one story facility comprised of the following spaces: Electrical Technology, Carpentry, Plumbing and HVAC Technology, Construction Trades, Automotive Servicing Technology, Auto Collision Repair Technology, Welding Technology, Cafeteria, Culinary Arts & Hospitality Kitchen, Health Occupations Dental, Cosmetology, Internet Technology, Digital Graphics, academic classrooms, atrium, offices, Conference Center, restrooms, Gymnasium, locker rooms, storage rooms and Maintenance areas.

The typical hours of operation for this facility are Monday through Friday between 7:00 am and 10:00 pm. The school is occupied with 600 day students, 400 evening students, and 70 staff from 7:00 am through 10:00 pm. There are 3 day maintenance staff 7:00 am to 3:30 pm and 4 staff on the cleaning crew 3:30 pm to 11:00 pm Monday through Friday. The building is closed Monday through Friday 11:00 pm to 7:00am and all weekends.

The main building’s exterior walls are brick and block construction with minimum insulation typical of the time period. The original building’s wings are metal buildings with minimum insulation typical of the time period. The amount of insulation within the wall is unknown. The windows throughout the facility are in fair to poor condition and appear to be maintained. Typical windows throughout the facility are 1” clear tempered structural glass with steel tube frame. The existing metal doors are hollow and not insulated. The insulating panels in the window frame assemblies are metal and are known to have 1” asbestos insulation. Blinds are utilized in some of the rooms in the facility per occupant comfort but most rooms do not have blinds. The blinds are valuable because they help to reduce heat loss in the winter and reduce solar heat in the summer. The roof on the main building is an EPDM covering on 1 ½” rigid insulation board and 1 ½” metal decking. The amount of insulation below the roofing is unknown. The roofs on the wings are Standing seam metal roof and have approximately three inches of fiberglass batt insulation with a vapor barrier. The building was built in 1970 with a Gymnasium wing addition in 1982.

The main roof is scheduled for re-roofing this year. It will have new EPDM with some areas reusing existing insulation and some areas receiving new insulation and new EPDM.

The Gymnasium addition is a steel frame building having block wall construction with minimum insulation typical of the time period. The amount of insulation within the wall is unknown. The windows in the Gym addition are in good condition and appear to be maintained. Typical windows in the addition are double pane, ¼” clear glass with metal frame. The existing metal doors are hollow and not insulated. Blinds are utilized in some of the rooms in the facility per occupant comfort but most rooms do not have blinds. The blinds are valuable because they help to reduce heat loss in the winter and reduce solar heat in the summer. The roof on the addition is standing seam metal roof and has six inches of R-19 fiberglass batt insulation and an R-5 insulation board with facing.

The exterior man doors and asbestos insulated metal panels are scheduled for replacement this summer. They will be replaced with fiberglass reinforced plastic (FRP) doors with 1” insulated low-E glass and 1” insulated FRP panels. A bid alternate would replace the existing windows with low-E 1” insulated glass in addition to the base bid.

Page 26: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 25 of 89

HVAC Systems

The main building is served by four MSI roof top multi deck air handling units with natural gas heat and direct expansion (DX) cooling with R-22 refrigerant. These units each have 500 MBH to 540 MBH natural gas input heating capacity and were 75% efficient when they were new. These units have a cooling capacity ranging from 262 MBH to 268 MBH (22 Tons nominal cooling, each). These units have a 5.3 EER. The multi deck unit maintains heating and cooling deck temperatures so a set of discharge dampers will modulate to maintain thermostat set point. The duct system is constant volume. This sequence was modified in the 1980’s to prevent mechanical cooling when a zone required heating. That modification would improve the system efficiency but lacks good control.

The MSI Multi deck systems are scheduled for replacement. The design documents for this indicate the MSI units being replaced with three AAON model RN-060 with DX cooling capacities ranging from 285.6 MBH to 592 MBH and full modulating natural gas heating capacities ranging from 270 MBH to 540 MBH. The units will be variable air volume (VAV) supply air with an energy recovery wheel. The existing duct systems will be replaced with a new duct system and VAV terminals with hot water reheat. VAV terminals are scheduled as Enviro-Tec model SDR. The Atrium is scheduled to have a fan powered VAV, Enviro-Tec model CFRWC. The project will include new DDC control for the control of the new roof top units.

The project includes the installation of a new AERCO water boiler model MLX-909 with 909 MBH natural gas input and 781-835 MBH output. There will be a boiler in-line circulation pump B&G model 2x2x7, 56 gpm at 12 feet head, 3/4hp. There will be a system circulation pump B&G model 1 1/2BC 76 gpm at 60 feet head, 3 hp.

There will be a total capacity of 12.5 kW new electric baseboard heat. The baseboard heaters will serve Nursing, Cosmetology, Adult Cosmetology, Internet Technology and Health Occupations.

The gymnasium addition has four roof top units. The Trane unit serving the Girls locker room is heating only with 200 MBH natural gas input. It is past its ASHRAE expected service life and should be replaced with a more efficient heat and ventilation unit. A Trane model YSC048 serves the Business office having 4 Tons of nominal cooling capacity and 80 MBH of natural gas input capacity. It is in good condition and has ten years of ASHRAE expected service life remaining. The Trane model YCD091 serves the Board Office having 7.5 Tons of nominal cooling capacity and 205 MBH of natural gas input capacity. It is in fair condition and has one year of ASHRAE expected service life remaining. The Trane model GRNC020 is a heating only unit providing ventilation and has 300 MBH natural gas input heating capacity. The unit is past its ASHRAE expected service life and should be replaced with a more efficient heat and ventilation unit.

The gymnasium addition has three indoor horizontal air handling units with a natural gas duct furnace. There are two units serving the Gym having 400 MBH natural gas input and one unit serving the Boy’s locker room having 175 MBH natural gas input. These units had 76% combustion efficiency when they were new. The three units are 13 years past the ASHRAE expected useful service life and should be replaced with high efficiency units.

Page 27: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 26 of 89

The gymnasium addition has a cabinet heat and ventilation unit serving the Health classroom. It has an electric heating capacity of 5.8 kW, is in fair condition and is 13 years past the ASHRAE expected useful service life. This unit can be maintained or replaced in kind as needed.

The East wing has six roof top units. Three units are Sterling model PV-300-B heating and ventilating roof top units having 300 MBH natural gas input heating capacity and had 76% combustion efficiency when they were new. The three units are 4 years past the ASHRAE expected useful service life and should be replaced with high efficiency units. The Trane model GRAA25 is a heating and ventilation rooftop unit having 250 MBH natural gas input and had 80% combustion efficiency when it was new. The unit has one year of expected ASHRAE useful service life remaining. The Trane model YSC120 is a nominal 10 Ton cooling capacity and 250 MBH natural gas input capacity roof top unit. The unit is two years old and in good condition. The Trane model TTA150 12.5 nominal Ton cooling capacity condensing unit is in fair condition with one year of ASHRAE useful service life remaining.

The South Wing has seven roof top units. One Trane model YCD121 is a nominal 10 ton cooling and 250 MBH natural gas input unit that is two years past its ASHRAE expected useful service life and should be replaced. There are three Sterling model PV-300-B and three model PV-400-B roof top heating and ventilation units with 300 MBH and 400 MBH natural gas input capacity, respectively. These six units are four years past the ASHRAE expected useful service life and should be replaced.

The West Wing has eight roof top units. Four units are Sterling model PV-300-B with 300 MBH natural gas input heating capacity. These units are three years past the ASHRAE expected useful service life and should be replaced. There are three Sterling model PV-250-B with 250 MBH natural gas input heating capacity. These units are three years past the ASHRAE expected useful service life and should be replaced. There is one Trane model YSC120 that has 10 ton nominal cooling capacity and has 250 MBH natural gas input heating capacity. The unit is two years old and in good condition.

There is a Sterling model PV-250-B, serial number 1806-91-4 on the roof with 250 MBH natural gas input heating capacity. The unit is five years past the ASHRAE expected useful service life and should be replaced.

There is a York International Heat Pump model B3CH060 on the main building roof. The unit has a 5 ton nominal cooling capacity and heating capacity of 59 MBH at 47⁰F outdoor temperature. The unit is in fair condition and has three years of ASHRAE expected useful service life remaining.

There are electric cabinet heaters at corridor entry/exits. Maintenance staff stated that the power to these heaters have been turned off for a few years as the building is comfortable enough and deemed not required.

There are electric unit heaters in various, remote locations throughout the building. They range from 3 to 5.8 kW electric heating capacity and are controlled by local thermostats. They are at or past their ASHRAE expected useful service life and are in fair condition. Replacing these units

Page 28: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 27 of 89

in kind would not provide any energy savings. Therefore, these units can be maintained/replaced as needed as a maintenance project.

There is a ductless split system in the Nurse’s Office and Maintenance office with capacities of 1 ½ and 1 Ton nominal cooling. These units are in good condition and have a few years of service life remaining.

The Culinary Arts & Hospitality Kitchen has four 11 ½ foot long hoods. They are configured in a 22 foot long back to back island over the cooking equipment. On the roof there are two Greenheck non-recirculating direct fired make up air units. One unit is model DG-115-H20-BD with 351.1 MBH natural gas input. The other unit is model DGX-115-H22-DB with 405.1 MBH natural gas input. These units have remaining service life and should be maintained. There are two exhaust fans, Greenheck model CUBE-240-20-S having a 2 hp motor and model CUBE-200-30-S having a 3 hp motor. The fans were installed in 2004, are in good condition and should be maintained.

There is one Weil McLain model 478 series 1, dual fuel water boiler. The boiler can operate on #2 oil or natural gas. The boiler serves the greenhouse, is in good to fair condition and has 14 years of ASHRAE expected useful service life remaining.

Exhaust System

Air is exhausted from the toilet rooms through the roof exhausters. The exhaust systems run 24/7.

There are local exhaust systems for dust collection in Carpentry, Automotive service and Auto Collision repair and Welding Technology. The fans are controlled locally and are operated as needed.

HVAC System Controls

The HVAC systems within the facility are controlled manually via electronic local thermostats. There is a Johnson Metasys DDC system that can control the occupancy and set points for the wings but is used basically to monitor the systems. The wings are served primarily by heating and ventilation units. The units have individual room thermostats that are controlled by the DDC system. There is an electronic control panel that controls the gym addition. The panel has occupied/unoccupied and automatic control modes by means of time clocks. The maintenance staff stated that these systems run 100%, 24/7 and don’t know if the controls work.

The project to replace the Multi deck units will include a DDC system to control the units in that project. It is unknown if the two DDC systems will be tied together. The assumption is that they will not be tied together.

Page 29: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 28 of 89

Domestic Hot Water

Domestic hot water for the building is provided by two water tube boilers A.O. Smith model GW-55-200 with 500 MBH natural gas input each. The domestic hot water is drawn through each boiler and pumped into an A.O Smith storage tank (model GWT-500ASV0N100001) by fractional horsepower pumps. The system hot water recirculation pump is a fractional horsepower pump. The circulation pump is controlled by an aqua stat. The domestic hot water piping insulation appeared to be in good condition.

Lighting The majority of the interior lighting throughout the Cumberland County Technical Education Center building is provided by fluorescent fixtures with older generation, 700 series 32W T8 lamps and electronic ballasts. The kitchen hood, restroom and some exit signs are lit with incandescent lamps. The Atrium lighting is provided by compact fluorescent lamps. Finally, the exterior of the Cumberland County Technical Education Center is illuminated with 400W Mercury Vapor post mounted area lights and 175 watt mercury vapor wall packs.

Page 30: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 29 of 89

VI. MAJOR EQUIPMENT LIST

The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.

Refer to the Major Equipment List Appendix for this facility.

Page 31: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 30 of 89

VII. ENERGY CONSERVATION MEASURES Description: The Gym addition has two (2) gas fired heat and ventilation (H&V) units which provide heat to the Gymnasium and one (1) H&V unit that serves the Boy’s Locker room. There are two (2) Trane Model GDNC040/HBAC and one (1) Trane model GDNC/HBAC200 that are twenty-eight (28) years old in fair to poor condition. The current units have a combustion efficiency of 76% but the age of these unit heaters in conjunction with radiation losses has brought the efficiency down to approximately 71%. These units have surpasses their ASHRAE expected useful service life. The existing electric fan motors equal to or greater than one horsepower ranged from 78 to 93% efficient. The improved efficiency of the NEMA premium efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate 40-80 hours per week, even small increases in efficiency can yield substantial energy and dollar savings. This energy conservation measure will replace three (3) gas fired units serving the Gym and Boy’s Locker room. The existing units will be replaced with higher energy efficient units with capacity typical of the existing units. This energy conservation measure would replace all motors equal to or greater than 1 HP with NEMA Premium® Efficient Motors. Calculations are based on the following equipment: two (2) Trane model GGBA50PAA, 400 MBH input and one (1) Trane model GGBA20PAA, 200 MBH input with both models having 80% combustion efficiency or equivalent. Energy Savings Calculations: Existing Gas Fired Unit: Replacement Trane Gas Fired Unit: Rated Capacity = 400 MBh Max Input Rated Capacity = 400 MBh Max Input Combustion Efficiency = 76% Combustion Efficiency = 80% Age & Radiation Losses = 5% Radiation Losses = 0.5% Thermal Efficiency = 71% Thermal Efficiency = 79.5% Motor HP = 2 HP Motor HP = 2 HP Motor Efficiency = 80.8 % Motor Efficiency = 85.6 % Existing Gas Fired Unit: Replacement Trane Gas Fired Unit: Rated Capacity = 175 MBh Max Input Rated Capacity = 200 MBh Max Input Combustion Efficiency = 76% Combustion Efficiency = 80% Age & Radiation Losses = 5% Radiation Losses = 0.5% Thermal Efficiency = 71% Thermal Efficiency = 79.5% Motor HP = 1/2 HP Motor HP = 1/2 HP

Page 32: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 31 of 89

Operating Data: The estimated usage is calculated as: Est. Annual Usage = (Equip. conn. MBH / All conn. Equip. MBH) x Utility Annual gas Usage, Therms/yr. = ((400+400+175) MBH / 767,286 MBH) x 92,098.32 Therms/yr. = 117.03 Therms/yr.

( ))./.(1 newEffUHoldEffUHnConsumptioFuelSavingsEnergyHeating −×= Heating Energy Savings = 117.03 Therms x (1-(71% / 79.5%)) = 12.51 Therms Total Heating Cost savings Heating Energy Cost Savings = Annual Energy Savings x $/Therm Heating Energy Cost Savings = (12.51 Therms) x $1.32/Therm = $16.51/ yr. Existing: A 2 HP system fan Motor with the following characteristics: Existing Motor Efficiency = 80.8% Annual Hours of Operations = 5180 hrs 1 HP = 0.746 Watt Load Factor = 75% Cost of electricity = $0.156 / kWh Existing 2HP Motor Operating Cost = {0.746 Watt/HP x Motor HP x Load Factor x Hours of Operation x Cost of Electricity] ÷ Motor Efficiency = 2 x [0.746 x 2 x 0.75 x 5,180 x 0.156] ÷ 0.808 = $2,238 / Year New NEMA Premium Motor Efficiency = 85.6% New NEMA Premium Efficiency Motor Operating Cost = 2 x {0.746 x 2 x 0.75 x 5,180 x 0.156} ÷ 0.856 = $2,113 / Year Electrical Savings = $2,238 - $2,113 = $126 / Year Total annual savings = Gas Savings + Electrical Savings = $16.51/ yr. + $125.50 / Year = $142 / yr. Installed cost of two (2) Trane model GGBA50PAA, 400 MBH input and one (1) Trane model GGBA20PAA, 200 MBH input natural gas fired burner and installation is $39,970.

Page 33: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 32 of 89

There is no incentive for gas fired furnaces less than 92% AFUE. The incentive for an ODP Premium efficient 2 hp motor is $54 / motor. Annual maintenance savings is estimated to be $100 per year. Simple Payback = net cost / savings Simple Payback = $39,850 / ($142 + $100) = 164.6 years

ECM INPUTS EXISTING PROPOSED SAVINGSTotal Heat Input (MBH) 975 1,000

Combustion Efficiency (%) 76% 80.0%

Age & Radiation Losses (%) 5.0% 0.5%

Thermal Efficiency (%) 71.0% 79.5%

Nat Gas Heat Value (BTU/Therm) 100,000 100,000Heating Degree Days (HDD) 5,180 5,180

Total Motor HP (1hp or greater) 4 4

Fan Motor Hrs per year (Hrs/yr) 5,180 5,180

Motor Efficiency % 80.8% 85.6%

Blgd. Equip connected (MBH) 767,286.0 767,311.0 (25)

Historical Gas Usage (Therms) 92,098.3 -

Nat Gas Cost ($/Therm) $1.320 $1.320

Electric Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGSAnnual Heat Energy (Therms) 117.03 104.52 12.51

Nat Gas Energy Cost ($) $154 $138 $17

Annual Electric Usage (kWh) 14,348 13,543 805

Electric Cost ($) $2,238 $2,113 $126

Total ($) $2,393 $2,251 $142

ECM #1 INDOOR HEAT & VENTILATION UNIT UPGRADE

ENERGY SAVINGS CALCULATIONS

COMMENTS: HDD65 source www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W,39.37N); Station ID: KMIV; Before proceding with this ECM, consult with a professional engineer and the gas company as the connected load will increase.

Page 34: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 33 of 89

Energy Savings Summary:

Installation Cost ($): $39,970

NJ Smart Start Equipment Incentive ($): $108

Net Installation Cost ($): $39,862

Maintenance Savings ($/Yr): $100

Energy Savings ($/Yr): $142

Total Yearly Savings ($/Yr): $242

Estimated ECM Lifetime (Yr): 15

Simple Payback 164.7

Simple Lifetime ROI -90.9%

Simple Lifetime Maintenance Savings $1,500

Simple Lifetime Savings $3,630Internal Rate of Return (IRR) -21%Net Present Value (NPV) ($36,972.73)

ECM #1 - ENERGY SAVINGS SUMMARY

Page 35: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 34 of 89

ECM #2: Roof Top H&V Unit Upgrade

Description: The building has twenty (20) roof top gas fired heat and ventilation (H&V) units which provide heat to various spaces in the wings. The units are inefficient compared to today’s standard and can be replaced with more efficient units. The existing units have a combustion efficiency ranging from 75% to 80% (75.45% weighted average) but the age of these unit heaters in conjunction with radiation losses has brought the efficiency down to approximately 70.45%. These units have surpasses their ASHRAE expected useful service life. The existing electric fan motors equal to or greater than one horsepower ranged from 78 to 93% efficient. The improved efficiency of the NEMA premium efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate 40-80 hours per week, even small increases in efficiency can yield substantial energy and dollar savings. This energy conservation measure will replace twenty (20) gas fired units serving the Wings. These units are identified in APPENDIX D – Major Equipment List. The existing units will be replaced with higher combustion efficient units with capacity typical of the existing units. This energy conservation measure would replace all motors equal to or greater than 1 HP with NEMA Premium® Efficient Motors. Calculations are based on the equipment listed in the Proposed Equipment table below. Energy Savings Calculations: EXISTING EQUIPMENT SUMMARY GAS USAGE

TotalInputMBH

Trane GRNC120 1 200 77 200 0.00026 24.0Trane GRNC020 1 300 77 300 0.00039 36.0

Sterling PV-300-B 10 300 75 3000 0.00391 360.1Sterling PV-400-B 3 400 75 1200 0.00156 144.0Sterling PV-250-B 4 250 75 1000 0.00130 120.0Trane GRAA25 1 250 80 250 0.00033 30.0

Total connected input (MBH) = 5,950.0 0.00775 714.2Total Building Equipment connected input (MBH) = 767,286.0

Total Annual Usage (Therms) = 92,098.3

% of Connected Bldg Load

Estimated Annual Usage, ThermsMake Model Qty. Eff., %

Heating Input, MBH

Page 36: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 35 of 89

PROPOSED EQUIPMENT

Trane GRAA200 1 26.6 70.45 79.5 23.6 3.0Trane GRAA250 5 166.2 70.45 79.5 147.3 18.9

Sterling GRAA300 11 438.9 70.45 79.5 388.9 50.0Sterling GRAA400 3 159.6 70.45 79.5 141.4 18.2

791.3 701.2 90.1

New Thermal Eff., %

Estimated Annual Savings

ThermsMake Model Qty.

Total Annual Usage

Avg. EXIST. Thermal Eff.,

%

Estimated Annual Usage,

Therms

Operating Data: The furnaces, water heaters and boilers used in the classroom are used a negligible amount of time and are considered negligible. The estimated usage is calculated as:

( ))./.(1 newEffAvgoldAvgEffnConsumptioFuelSavingsEnergyHeating −×= Heating Energy Savings = 791.3 Therms x (1-(70.45% / 79.5%)) = 90.1 Therms Total Heating Cost savings Heating Energy Cost Savings = Annual Energy Savings x $/Therm Heating Energy Cost Savings = (90.1 Therms) x $1.32/Therm = $119/ yr. Motor Data: A 2 HP system fan Motor with the following characteristics: Existing Motor Efficiency = 80.8% New Motor Efficiency = 86.5% Annual Hours of Operations = 5180 hrs 1 HP = 0.746 Watt Load Factor = 75% Cost of electricity = $0.156 / kWh Existing 2HP Motor Operating Cost = {0.746 Watt/HP x Motor HP x Load Factor x Hours of Operation x Cost of Electricity] ÷ Motor Efficiency = 3 x [0.746 x 2 x 0.75 x 5,180 x 0.156] ÷ 0.808 = $3,357.3 / Year New NEMA Premium Efficiency Motor Operating Cost = 3 x {0.746 x 2 x 0.75 x 5,180 x 0.156} ÷ 0.865 = $3,136.1 / Year Electrical Savings = $3,357.33 - $3,136.10 = $221.2 / Year

Page 37: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 36 of 89

A summary of motor calculations is in the table below on a per motor basis.

Proposed Manufacturer

Proposed Model Qty.

Estimated Motor HP

Existing Motor

Efficiency

NEMA Premium Efficiency

kW Savings

kWh Savings

Cost Savings

Trane GRAA200 1 1 76.7% 85.5% 0.08 389 $60.7Trane GRAA250 5 1.5 79.1% 86.5% 0.45 2,351 $366.7

Sterling GRAA300 11 1.5 79.1% 86.5% 1.00 5,172 $806.8Sterling GRAA400 3 2 80.8% 86.5% 0.27 1,418 $221.2

1.80 9,330 $1,455.5

NEMA Premium Efficient Motor Replacement

Total Savings The installed cost of twenty (20) units listed above and installation is $386,780. This cost includes removal of old units, installation of new units, overhead, profit and engineering costs. The incentive for premium efficient fan motors is calculated in the table below.

Motor HP QTYIncentive per

Motor Cost Savings

1 1 $45 $451.5 5 $45 $2251.5 11 $45 $4952 3 $54 $162

$927

NEMA Premium Efficient Motor Incentive

Total Savings Annual maintenance savings is assumed to be $100 per year per unit. Simple Payback = net cost / savings Simple Payback = ($386,780-$927) / ($1,456+$119 + (20x$100) = 107.9 years

Page 38: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 37 of 89

ECM INPUTS EXISTING PROPOSED SAVINGSTotal Heat Input (MBH) 5,950 5,950

Combustion Efficiency (%) 75% 80.0%

Age & Radiation Losses (%) 5.0% 0.5%

Thermal Efficiency (%) 70.5% 79.5%

Nat Gas Heat Value (BTU/Therm) 100,000 100,000Heating Degree Days (HDD) 5,180 5,180

Total Motor HP (1hp or greater) 31 31

Fan Motor Hrs per year (Hrs/yr) 5,180 5,180

Weighted Average Motor Efficiency % 79.3% 86.4%

Blgd. Equip connected (MBH) 767,286.0 767,286.0

Historical Gas Usage (Therms) 92,098.3 -

Nat Gas Cost ($/Therm) $1.320 $1.320

Electric Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGSAnnual Heat Energy (Therms) 714.2 632.9 81.3

Nat Gas Energy Cost ($) $943 $835 $107

Annual Electric Usage (kWh) 113,317 103,987 9,330

Electric Cost ($) $17,677 $16,222 1,456

Total ($) $18,620 $17,057 $1,563

ECM #2 ROOF TOP HEAT & VENTILATION UNIT UPGRADE

ENERGY SAVINGS CALCULATIONS

COMMENTS: HDD65 source www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W,39.37N); Station ID: KMIV; Before proceding with this ECM, consult with a professional engineer and the gas company as the connected load will increase.

Page 39: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 38 of 89

Energy Savings Summary:

Installation Cost ($): $386,780

NJ Smart Start Equipment Incentive ($): $927

Net Installation Cost ($): $385,853

Maintenance Savings ($/Yr): $2,000

Energy Savings ($/Yr): $1,575

Total Yearly Savings ($/Yr): $3,575

Estimated ECM Lifetime (Yr): 15

Simple Payback 107.9

Simple Lifetime ROI -86.1%

Simple Lifetime Maintenance Savings $30,000

Simple Lifetime Savings $53,618Internal Rate of Return (IRR) -18%Net Present Value (NPV) ($343,180.85)

ECM #2 - ENERGY SAVINGS SUMMARY

Page 40: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 39 of 89

ECM #3: Packaged Cool/Heat Rooftop Unit Upgrade Description: The Cumberland County Technical Education Center Building has two (2) packaged, direct expansion cooling-natural gas heat packaged rooftop units (RTUs). The unit’s cooling efficiencies are as shown below. The existing units have a combustion efficiency of 80.5% when new. Due to the age of these unit heaters in conjunction with radiation losses has brought the efficiency down to approximately 75.5%. One unit is at the end of its ASHRAE expected useful service life and the other is past its expected service life. The units are in poor condition and in need of replacement. The efficiencies of the existing units are below today’s standards for cooling efficiency. The proposed units are high efficiency one-for-one replacements of the existing units. The owner should have a professional engineer verify heating and cooling loads prior to moving forward with this ECM. This ECM includes installation of two (2) high efficient packaged rooftop units. The ECM calculations are based on Trane Packaged Rooftop Units or equivalent. Means Costworks software is used to estimate demolition and labor costs for a generic rooftop AC unit replacement. Full Load Cooling Hrs = 900 hrs/yr. Average Cost of Electricity = $0.156/kWh

Energy Savings Calculations: Cooling Savings for 10 Ton Unit Replacement:

( ).11

1000

000,12HrsLoadFull

EEREERkWhWh

hrTonBtuTonsCooling

ngsEnergySaviNEWOLD

×⎟⎟⎠

⎞⎜⎜⎝

⎛−×

⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛×

=

( )

kWh

hours

WBtu

WBtu

kWhWh

hrTonBtuTons

ngsEnergySavi

160,2

9005.12

1

10

1

1000

000,1210

=

×⎟⎟⎟⎟

⎜⎜⎜⎜

⎟⎠⎞

⎜⎝⎛

−⎟⎠⎞

⎜⎝⎛

×⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛×

=

Tag

Cooling Capacity (Tons)

Exist. Cooling

EER

Proposed Cooling

EERHV-5 7.5 10.1 13.00RTU 10 10 12.50

Page 41: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 40 of 89

( )CoolingofHrs

kWhSavingsEnergySavingsDemand =

( ) KWHrskWhSavingsDemand 4.2

.900160,2

==

337$$156.0160,2 =⎟⎠⎞

⎜⎝⎛×=

kWhkWhSavingsCostCooling

The calculations are carried out for the rest of the units and the results are tabulated in the below table.

TagCooling

Capacity (Tons)

Energy Savings (kWh)

Demand Savings

(kW)

Gas Savings, therms

Total Energy

Cost Saved

HV-5 7.5 1,789 1.99 0.17 $279.31RTU 10 2,160 2.40 0.21 $337.23

Total 17.5 3,949 4.39 0.37 $616.54 From the NJ Smart Start® Program appendix, the packaged unit replacement falls under the category “Electric Unitary HVAC” and warrants an incentive based on efficiency (EER) at or above 11.5. The program incentives are calculated as follows:

( )IncentiveTonTonsCoolingIncentive /$StartSmart ×=® Central DX AC Systems

<5.4 tons, minimum 14.0 SEER, $92/ton >5.4 tons to 11.25 tons, minimum 11.5 EER, $73/ton >11.25 tons to 20 tons, minimum 11.5 EER, $79/ton

TagCooling Capacity (Tons)

Incentives

HV-5 7.5 $548RTU 10 $730

$1,278Total

Page 42: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 41 of 89

Energy Savings Summary:

Installation Cost ($): $40,500

NJ Smart Start Equipment Incentive ($): $1,278

Net Installation Cost ($): $39,223

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $617

Total Yearly Savings ($/Yr): $617

Estimated ECM Lifetime (Yr): 15

Simple Payback 63.6

Simple Lifetime ROI -76.4%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $9,248Internal Rate of Return (IRR) -14%Net Present Value (NPV) ($31,862.26)

ECM #3 - ENERGY SAVINGS SUMMARY

Page 43: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 42 of 89

ECM #4: Condenser Unit Upgrade Description: There is a 12.5 Ton nominal Trane model TTAA150 condensing unit on the East Wing. It is connected to a Trane model GRAA25 air handling unit that serves the Tiger Den (Restaurant Careers). The system that has a cooling capacity of 150,000 BTUH and is at the end of its ASHRAE expected useful service life. The condensing unit is in poor condition and very inefficient (EER=8). This ECM would replace the existing rooftop condensing unit with a higher-efficiency Trane Model TTA150 or equal with an efficiency of EER=11.7. Energy Savings Calculations: Cooling Assumptions: Total Cooling Capacity = 12.5 Tons Existing Unit Efficiency = 8 EER New Unit Efficiency = 11.7 EER Average Cost of Electricity = $0.156/kWh Average Annual Hours @ Full Load = 2,800 Hours Cooling Savings Calculation:

( ).11

1000

000,12HrsCooling

EEREERkWhWh

hrTonBtuTonsCooling

ngsEnergySaviNEWOLD

×⎟⎟⎠

⎞⎜⎜⎝

⎛−×

⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛×

=

( )

kWh

hours

WBtu

WBtu

kWhWh

hrTonBtuTons

ngsEnergySavi

6.602,16

800,27.11

1

8

1

1000

000,125.12

=

×

⎟⎟⎟⎟⎟

⎜⎜⎜⎜⎜

⎟⎠⎞

⎜⎝⎛

−⎟⎠⎞

⎜⎝⎛

×⎟⎠⎞

⎜⎝⎛

⎟⎟⎠

⎞⎜⎜⎝

⎛×

=

( )CoolingofHrs

kWhSavingsEnergySavingsDemand =

Page 44: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 43 of 89

( ) kWHrs

kWhSavingsDemand 9.5.800,2

6.602,16==

Total Annual Energy Cost Savings = 16,602.6 kWh x $0.156/kWh = $2,590 per year

( ) ( ) 988$79$5.12/79$StartSmart =×=×=® TonTonsofNumberIncentive The total installed cost of a 12.5-Ton condenser rooftop unit with an ambient kit is $15,835. Energy Savings Summary:

Installation Cost ($): $15,835

NJ Smart Start Equipment Incentive ($): $988

Net Installation Cost ($): $14,848

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $2,590

Total Yearly Savings ($/Yr): $2,590

Estimated ECM Lifetime (Yr): 15

Simple Payback 5.7

Simple Lifetime ROI 161.7%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $38,850Internal Rate of Return (IRR) 15%Net Present Value (NPV) $16,071.75

ECM #4 - ENERGY SAVINGS SUMMARY

Page 45: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 44 of 89

ECM #5 Multi-deck RTU Upgrade with Energy Recovery Description: The Cumberland County Technical Education Center Main building is heated and cooling by four large MSI multi-deck air handling units. The units provide heating with natural gas furnace with 75% combustion efficiency. Each of the four units provide direct expansion cooling using R-22 refrigerant with capacities ranging from 262 MBH to 268 MBH. The unit efficiencies are calculated at 5.1 to 5.3 EER. The multi-deck unit maintains heating and cooling deck temperatures so a set of discharge dampers will modulate to maintain thermostat set point. The duct system is constant volume. This sequence was modified in the 1980’s to prevent mechanical cooling when a zone required heating. That modification would improve the system efficiency but lacks good control. Even with the modification to the operation sequence, the heating and cooling efficiencies are very inefficient compared to today’s standards. The units are forty-one years old, in poor condition and should be replaced. The existing units were installed using 0.5 CFM per square foot for outside air volume. Today’s requirements for outside air have changed and the owner should consult with a professional engineer for that analysis. To save cost on the significant energy required to condition outside air, an energy recovery unit can provide the ventilation required for the unit and space while capturing the heat otherwise exhausted from the building. An energy recovery unit also provides valuable energy savings in the cooling season by pre-cooling the outside air to the unit’s cooling coils with the cool room air otherwise exhausted. This ECM includes removing the four roof top MSI multi-deck units, ductwork and controls; the installation of three heating and cooling roof top units with air-to-air energy recovery, ductwork, variable air volume terminal boxes with hot water reheat, boilers, pumps, piping, valves and appurtenances, and DDC controls. The basis for this ECM is the AAON RN series units with air-to-air energy recovery and two Aerco MLX-909 boilers. It is recommended to perform airflow measurements of the existing equipment to verify the O.A. quantities prior to implementation of this ECM. It is also recommended to have a professional engineer provide further review of the equipment selection and load analysis prior to implementing this ECM. The equations used in the energy savings calculations are listed below. The input data and calculation results are in the tables in the APPENDIX G – ENERGY RECOVERY ENERGY CALCULATIONS appendix.

Page 46: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 45 of 89

Energy Savings Calculations: Heating Energy Savings: Total heating capacity is calculated with the equation below.

Heating Load,BTUHr 1.08 Airflow CFM O. A. % Indoor °F Outdoor °F

Occ Ventilation Heating Energy

Occ Heating Load

ΔT Eff V Occ. HDD °F NonSetback Hrs 1Energy Rec. Eff. %

Unocc Ventilation Heating Energy

Unocc Heating Load

ΔT Eff V Unocc. HDD °F Setback Hrs 1Energy Rec. Eff. %

Where:

HDD = number of Heating Degree Days as Specified Base Temperature ∆T= Design temperature difference, º F Eff = Efficiency of Energy Utilization V = Heating value of fuel, BTU/kWh (3,413 Btu = 1 kWh)

Heating Cost Savings Energy Savings Therms Cost of Gas $

Therm

Savings for DDC control of new system is estimated at 10% of the heating and cooling costs for building area served by these units. 10% Savings on Heating Calculations

Heat load is approximately equivalent to the heat provided by the existing units:

Building heat load = ((3x 500 kbtu/hr) + 540 kbtu/hr) x 75% efficient = 1530 kbtu/hr

Building heat load = Ventilation Load + Skin Load

Skin Load = Building Heat Load – Ventilation Load

( ) ( ) ⎟⎠⎞

⎜⎝⎛××°

×××⎟⎠⎞

⎜⎝⎛

=

ThermkBtuValueHeatFuelEfficiencyFDifferenceTempDesign

FactorCorrectionHrsDaysDegHeatHr

kBtuLoadSkinHeatSkinLoadEst

%

24.

Page 47: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 46 of 89

The existing Therms used with the 75% RTU units is:

( ) ( )

( )( )Therms

ThermkBtuF

HrsHDDHr

kBtu

SkinLoadGasUsageEst 18.697,10100%7555

6.024959,577.1015530,1. =

⎟⎠⎞

⎜⎝⎛××°

×××⎟⎠⎞

⎜⎝⎛−

=

The boiler heat is used at the VAV coils to treat the skin load. The therms needed with the 87%

efficient boiler is:

( ) ( )

( )( )Therms

ThermkBtuF

HrsHDDHr

kBtu

SkinLoadeNewGasUsag 71.221,9100%8755

6.024959,577.1015530,1. =

⎟⎠⎞

⎜⎝⎛××°

×××⎟⎠⎞

⎜⎝⎛−

=

The Boiler efficiency savings for the skin load portion is:

( ) ( )ThermsSkinLoadHeatThermsSkinLoadHeateSkinLoadNewGasUsag .(. −=

( ) )(47.475,1)(71.922118.697,10. ThermsThermsThermseSkinLoadNewGasUsag =−=

The 10% savings for using DDC control for the skin load portion is:

( ) ( ) ⎟⎠⎞

⎜⎝⎛×−=Therm

CostGasAveThermsSkinLoadHeatThermsSkinLoadHeatdSavingsDDCSkinLoa $)).(.(.

( ) )(17.9221.071.221,9%10.. ThermsThermsSkinLoadHeatdSavingsDDCSkinLoa =×=×=

The Total skin load savings is:

( ) ⎟⎠⎞

⎜⎝⎛×+=Therm

CostGasAveThermsdDDCSkinLoaSkinLoadeHeatNewGasUsagvingsSkinLoadSa $)..(.

( ) 85.164,3$$32.1)17.922)(47.1475(. =⎟⎠⎞

⎜⎝⎛×+=Therm

ThermsThermsvingsSkinLoadSa

Heating energy savings calculations are summarized in the table below.

Page 48: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 47 of 89

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTSNo O.A.

Preconditioning

Total O.A. Energy

Recovery Wheel

Total AHU Airflow (CFM) 34,000 35,500

Occ. O.A. Percentage (%) 50% 47%

Unocc. O.A. Percentage (%) 5% 5%

Occ. Temp Diff (°F) 55 55

Unocc. Temp Diff (°F) 65 65

Heating Degree Days (68°F) 5,959 5,959

Heating Degree Days (60°F) 4,027 4,027

Hours of setback per day (ave) 0 9

RTU Heating System Efficiency (%) 75% 80%

Heating Fuel Value 100,000 100,000

Boiler Efficiency (%) N/A 87%

Average Energy Recovery Sys Efficiency 0% 57.8%Demand Control Ventilation Savings (10% of Ventilation)

0% 10%

Occ O.A. Heating Load (Btu/Hr) 1,015,770 409,216

Unocc O.A. Heating Load (Btu/Hr) 119,340 52,604

Occ O.A. Heating Energy (Therms) 23,799 5,618 18,181

Unocc O.A. Heating Energy (Therms) 0 543 (543)Skin_Load (BTU/Hr)= Total_Load-Ventilation_Load

514,230 514,230

DDC Controls - Skin load Savings (Therms) 10,697 8,300 2,398

Additional Equip Load (10.45 kW), kWh 0 46,704 (46,704)Elec Cost ($/kWh) $0.156 $0.156Gas Cost ($/Therm) $1.32 $1.32

ECM RESULTS EXISTING PROPOSED SAVINGS

Total Additional Electric Energy (kWh) 0 46,704 (46,704)

Additional Electric Energy Cost ($) $0.000 $7,286 ($7,286)

Total Heating Energy (Therms) 34,496 14,460 20,037

Heating Energy Cost ($) $45,535 $19,087 $26,448

Total Heating Energy Cost ($) $45,535 $26,373 $19,162

ENERGY RECOVERY HEATING ENERGY SUMMARY

ENERGY SAVINGS SUMMARY

COMMENTS: Degree Days based on Milville Airport,NJ.

Page 49: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 48 of 89

Cooling Energy Savings: Cooling Energy savings are based on the energy required to condition outside air during occupied hours only. The cooling energy required for minimal outside air at unoccupied hours are negligible and therefore not included in this calculation. Enthalpy difference is based on design cooling day (95°F DB, 78°F WB), and average room conditions (75°F, 50% RH).

Cooling Load BTUHr 4.5 Airflow CFM O. A. % Enthalpy Diff

Cooling Energy kWh

Cooling Capacity,BTUHr

1EER

Full Load Hrs

1000 WkWh

1 Energy Rec. Eff. %

Cooling Cost Savings Energy Savings, kWh Cost of Electricity $

kWh

DDC savings 10% Savings on Cooling Calculations:

Cooling load is approximately equivalent to the cooling provided by the existing units:

Building cooling load = Ventilation Load + Skin Load

Skin Load = Building Cooling Load – Ventilation Load

Skin Load = 1259.78 kbtu/hr – 808 kbtu/hr = 451.78 kbtu/hr

( ) ( )

⎟⎠⎞

⎜⎝⎛×⎟

⎠⎞

⎜⎝⎛

×⎟⎟⎠

⎞⎜⎜⎝

⎛×

×=

kWhWh

WhBtuRatioEfficiencyEnergyAve

HrsCoolingLoadFullHrhrkbtu

BtuhrkbtuLoadCoolSkinLoadCoolEst

1000

./

000,1/.

( ) ( ) ( )kWh

kWhWh

WhBtu

HrsHrhrkbtu

BtuhrkbtuSkinLoadCoolEst 726,79

10001.5

.900/

000,1/781.451. =

⎟⎠⎞

⎜⎝⎛×⎟

⎠⎞

⎜⎝⎛

×⎟⎟⎠

⎞⎜⎜⎝

⎛×

×=

( ) ⎟⎠⎞

⎜⎝⎛××=

kWhCostElecAveSavingskWhSkinLoadCoolnLoadSavingsSki $%10.

Page 50: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 49 of 89

( ) 73.243,1$$156.0%10726,79. =⎟⎠⎞

⎜⎝⎛××=

kWhkWhvingsSkinLoadSa

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTSNo O.A.

Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 34,000 35,500

Occ. O.A. Percentage (%) 50% 47%

Occ. Enthalpy Diff (°F) 11 11

Unocc. Enthalpy Diff (°F) 0 0

Full Load Cooling Hrs 900 900

Cooling System Efficiency (EER) 5.1 10.5

Average Energy Recovery Sys Efficiency 0% 55.2%

O.A. Cooling Load (Btu/Hr) 807,999 361,660 Skin_Load (BTU/Hr) 451,781 451,781 DDC Controls - 10% Savings (kWh) 79,726 34,852 44,874

Additional Equip Load (10.45 kW), kWh 0 9,405 (9,405)

Elec Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

Total Cooling Energy (kWh) 219,624 75,256 144,368

Cooling Energy Cost ($) $34,261 $11,740 $22,521

ENERGY RECOVERY COOLING ENERGY SUMMARY

ENERGY SAVINGS SUMMARY

COMMENTS: Degree Days based on Millville Airport,NJ. ; Add'l Equip: VAV fan, Boiler, Pump1, Pump2 and DDC controls

Page 51: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 50 of 89

Cost Installation cost of the installation of three heating only roof top units with air-to-air energy recovery, ductwork, variable air volume terminal boxes with hot water reheat, boilers, pumps, valves and appurtenances, and DDC controls, and misc construction requirements, is estimated to be $1,607,600 ($965,000 Materials) It is pertinent to note that electric demand savings were unable to be estimated. Also, incentives for the installation of the DDC system are not currently available and maintenance savings could not be adequately calculated because information was not available to baseline the savings.

Energy Savings Summary:

Installation Cost ($): $1,607,623

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $1,607,623

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $41,684

Total Yearly Savings ($/Yr): $41,684

Estimated ECM Lifetime (Yr): 15

Simple Payback 38.6

Simple Lifetime ROI -61.1%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $625,257Internal Rate of Return (IRR) -10%Net Present Value (NPV) ($1,110,004.51)

ECM #5 - ENERGY SAVINGS SUMMARY

Page 52: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 51 of 89

ECM #6: NEMA Premium Efficient Motor Upgrade Description: Replacing the old electric motors with new efficient motor is a simple change that can provide substantial savings. The Shop air compressor motor and the paint booth motor are past their ASHRAE expected useful service life and should be replaced. Existing electric motors equal to or greater than one horsepower ranged from 78 to 93% efficient. The improved efficiency of the NEMA premium efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate 40-80 hours per week, even small increases in efficiency can yield substantial energy and dollar savings. This energy conservation measure would replace all motors equal to or greater than 1 HP with NEMA Premium® Efficient Motors. NEMA Premium® is the most efficient motor designation in the marketplace today. Using MotorMaster+, Version 4, the energy & cost savings were calculated for the fan/pump motors in this facility that are greater than or equal to 1 HP. Energy Savings Calculations:

Existing: A 25 HP system air compressor Motor with the following characteristics: Existing Motor Efficiency = 88.5% 1 HP = 0.746 Watt Load Factor = 75% Cost of electricity = $0.156 / kWh Annual Hours of Operations = (20min/60min/hr)x15hr/dayx5days/wkx52wks/yr Annual Hours of Operations = 1300hrs/yr Existing 25HP Motor Operating Cost = {0.746 Watt/HP x Motor HP x Load Factor x Hours of Operation x Cost of Electricity] ÷ Motor Efficiency = [0.746 x 25 x 0.75 x 1,300 x 0.156] ÷ 0.885 = $3,205.27 / Year New NEMA Premium Motor Efficiency = 93.6% New NEMA Premium Efficiency Motor Operating Cost = {0.746 x 25 x 0.75 x 1,300 x 0.156} ÷ 0.936 = $3030.63 / Year Savings = $3,205.28 - $3,030.63 = $174.65/ Year Installed Cost of a 25 HP NEMA Premium® Efficiency Motor = $4,060.

Page 53: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 52 of 89

This motor does not qualify for an incentive because the operation hours are less than 2000 hour per year. Simple Payback = $4,060 / $167 = 24.3 Years kWh saved = $167 / $0.149/kWh = 1120.8 kWh kW saved = 1120.8 kWh /1,300 hrs./yr. = 0.86 kW

Equipment Tag

Motor HP

Hours / Year

Existing Efficiency

NEMA Premium

Efficiency

kW Savings

kWh Savings

Air Comp 25 1300 88.5% 93.6% 0.86 1,120Paint Booth 40 750 90.2% 94.1% 1.03 771

1.9 1,891

NEMA Premium Efficient Motor Replacement

Total Savings The following table outlines the motor replacement plan for this facility:

Motor HP QTY

ENCL.TYPE

No. of POLEs

INSTALLED Cost **

TOTAL COST

TOTAL SAVINGS

Simple Payback

25 1 TEFC 4-Pole $4,060 $4,060 $174.65 23.240 1 XPFC 4-Pole $11,930 $11,930 $120.31 99.2

$15,990 $295 54.2Totals:

MOTOR REPLACEMENT PLAN

** Net Cost after the SmartStart Buildings® incentive is applied.

Page 54: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 53 of 89

Energy Savings Summary:

Installation Cost ($): $15,990

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $15,990

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $295

Total Yearly Savings ($/Yr): $295

Estimated ECM Lifetime (Yr): 18

Simple Payback 54.2

Simple Lifetime ROI -66.8%

Simple Lifetime Maintenance Savings 0

Simple Lifetime Savings $5,309Internal Rate of Return (IRR) -10%Net Present Value (NPV) ($11,933.27)

ECM #6 - ENERGY SAVINGS SUMMARY

Page 55: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 54 of 89

ECM #7: Dishwasher & Booster Heater Upgrade Description: The original dishwasher was a Hobart model AM9T2. It has been upgraded with Hobart AM14 controls. The dishwasher was originally installed in 1970 and upgraded in the 1980s. The existing booster water heater is a Hatco model C-12 and is twenty eight years old and in fair to poor condition. Both the dishwasher and booster water heater are past their useful service life and should be replaced. Since this equipment was installed, there have been improvements made in the washing technology that results in about a 50% water savings. The reduced water requirements translates to less water heating, less water treating and less chemicals that will be used and dumped down the drain. There have been improvements in electric motor technologies. Existing electric motors equal to or greater than one horsepower ranged from 76.7% to 86.5% efficient. The improved efficiency of the NEMA premium efficient motors is primarily due to better designs with use of better materials to reduce losses. Replacing an electric water heater with a natural gas water heater would provide an estimated fuel savings of $895 / year. However, there are several obstacles with this particular location. First, there is a very large premium cost for the natural gas fired booster water heater. The Hatco model PMG-60 has a $5,490 list price premium over the Model C-12 electric heater. Second, the gas unit is larger than the electric unit so additional floor space would be used. There are three possible locations within 20 feet of the dishwasher that could be utilized. Third, a new gas vent would need to be installed and extended up through the roof. Fourth, a natural gas line would need to be extended for the new gas unit. Existing drawings show a 1” valve and cap for future booster heater located within 20 feet of the water heater possible locations. Fifth, the CCTEC staff indicated a possible gas supply pressure problem. Currently all of the gas using kitchen equipment cannot be used at the same time or the stove will shut down to just standing pilot lights. It is recommended that CCTEC have the gas company investigate the gas pressure at the meter and at the kitchen. Last, in a discussion with a kitchen equipment consultant and sales representative at Urie Associates, they strongly advise against the use of any gas booster heater. This advice is based on thirty-plus years of experience and their experience is the gas booster heaters need frequent service and is much more costly for maintenance in addition to aggravation of owners with down time. Therefore, CEG will recommend using an electric booster heater for this ECM. This energy conservation measure would replace the dishwasher and booster water heater. This ECM will use the Hobart model AM15+BUILDUP dishwasher and Hatco model C-9 electric booster water heater for the basis of this ECM or approved equal. The existing dishwasher has a 1 HP motor and the new unit will have a 2 hp motor. Energy Savings Calculations: Existing: A 1 HP system motor with the following characteristics: Existing Motor Efficiency = 76.7% 1 HP = 0.746 Watt

Page 56: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 55 of 89

Load Factor = 75% Cost of electricity = $0.156 / kWh Annual Hours of Operations = (25 loads / 65 load capacity) x 6hr/day x 5days/wk x 50wks/yr Annual Hours of Operations = 577 hrs/yr Existing 1HP Motor Operating Cost = {0.746 Watt/HP x Motor HP x Load Factor x Hours of Operation x Cost of Electricity] ÷ Motor Efficiency = [0.746 x 1 x 0.75 x 577 x 0.156] ÷ 0.767 = $65.66 / Year New 2 HP NEMA Premium Motor Efficiency = 86.5% New NEMA Premium Efficiency Motor Operating Cost = {0.746 x 2 x 0.75 x 577 x 0.156} ÷ 0.865 = $116.44 / Year Savings = $65.66 - $116.44= $-50.78 / Year (increase due to equipment hp)

Equipment Tag

Existing Motor

HP

New Motor

HP

Existing Efficiency

NEMA Premium Efficiency

kW Savings

kWh Savings

Cost Savings

Dishwasher 1 2 76.7% 86.5% -0.56 -325 -$50.8-0.6 -325 -$51

NEMA Premium Efficient Motor Replacement

Total Savings * Net increase due to increased equipment hp. Existing Water Usage= 150 load/day x 1.5 gal/load = 225 gallons / day Existing Water Usage= 225 gallons / day x 5 days/wk x 50 wk/yr = 56,250 gal./yr. Proposed Water Usage= 150 load/day x 0.74 gal/load = 111 gallons / day Proposed Water Usage= 111 gallons / day x 5 days/wk x 50 wk/yr = 27,750 gal./yr. Water savings = 56,250 – 27,750 = 28,500 gal./yr. savings The cost of treating the water the dishwasher uses will be reduced: Cost of Domestic water treatment per year is $5800. Annual Building Water Usage = (2700 gpd x 5 day/wk x 38 wks) + (600 gpd x 5 day/wk x 12 wks) Annual Building Water Usage = 549,000 gal./yr 28,500 gal/yr. saved x ($5800 /yr / 549,000 gal./yr) = $301/year saved domestic water treatment The water heating requirement is: Exist. power required = Temp. Rise x 8.33 lbs/gallon x gallons/yr. / (3413 btuh/kw x 98% efficient)

Page 57: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 56 of 89

Exist. power required = 70⁰F x 8.33 lbs/gallon x 56,250 gal./yr. / ( 3344.74 btu/kw) Exist. power required = 9,806.3 kWh/year New power required = Temp. Rise x Water weight x gallons/yr. / (3413 btuh/kw x98% efficient) New power required = 70⁰F x 8.33 lbs/gallon x 27,750 gal./yr. / ( 3344.74 btu/kw) New power required = 4,837.8 kWh/year Water Heating Power Saved = 9,806.3 kWh/year - 4,837.8 kWh/year = 4,968.5 kWh / year Water Heating Cost Saved = 4,968.5 kWh / year x $0.156/kWh = $775.09 / year Total Annual Power Saved (kWh/yr) = Heating power + Motor power Total Annual Power Saved (kWh/yr) = 4,968.5 kWh/yr + (-325.5 kWh/yr) = 4,643.0 kWh/yr Total Annual Electric Cost Saved ($/yr) = 4643.0 kWh/yr x $0.156/kWh = $724.31/yr Total Annual Cost Saved ($/yr) = $724.31/yr + $301/year = $1,025.31/year kW saved = 4,643 kWh / 577 hrs./yr. = 8.0 kW Installed Cost of dishwasher and booster water heater is $11,660. This motor does not qualify for an incentive because the operation hours are less than 2000 hour per year. Simple Payback = $11,660 / $1,025.31 = 11.4 Years

Page 58: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 57 of 89

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS Existing Unit Ventilator New Unit Ventilator

-

Dishwasher Model Hobart AM9T2 / AM14 Hobart AM-15+BUILDUP

-

DishwasherFial Rinse Water Usage (Gal/rinse) 1.5 0.74 0.76

Temperature Rise (⁰F) 70.0 70.0 -

Loads/Day 150 150 -

Dishwashing (Hours / Day) 6 6 -

Dishwashing (Days / Week) 5 5 -

Dishwashing (Weeks / Year) 50 50 -

Dishwasher Motor HP 1 2 -

Water Usage (Gallons / Day) 225 111 114

Maximum Water Usage (Gallons / Hour) 68 48.1 19.4

Annual Water Usage (Gallons / year) 56,250 27,750 28,500

Heating capacity required (kW) 11.8 8.4 -

Booster Heater Model Hatco C-12 Hatco C-9 -

Booster Heater Power Demand (kW) 12.0 9.0 3.0

Average Heating Power Consumption (kWh/day) 39.23 19.35 19.87

Domestic Water Treatment $594 $293 $301

Elec Cost ($/kWh) $0.156 $0.156 -

ECM RESULTS EXISTING PROPOSED SAVINGS

Annual Heating Power Consumption (kWh/year) 9,806.3 4,837.8 4,968.5

Annual Pump Motor Power Consumption (kWh/yr) 420.8 746.3 -325.5

Total Annual Power Consumption (kWh / yr) 10,227.1 5,584.1 4,643.0

Demand (kW) 17.7 9.7 8.0

Electric Heating Energy Cost ($) 1529.8 754.7 $775

Electric Motor Energy Cost ($) 65.7 116.4 ($51)

Total Annual Electric Energy Cost ($) $1,595 $871 $724

Annual Water Consumption (Gallons / Year) 56,250 27,750 28,500

Water Treatment, Detergent/Sanitizing Cost ($) $594 $293 $301

Total Cost ($) $2,190 $1,164 $1,025

DISHWASHER & BOOSTER HEATER CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS:

Page 59: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 58 of 89

Energy Savings Summary:

Installation Cost ($): $11,660

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $11,660

Maintenance Savings ($/Yr): $301

Energy Savings ($/Yr): $724

Total Yearly Savings ($/Yr): $1,025

Estimated ECM Lifetime (Yr): 12

Simple Payback 11.4

Simple Lifetime ROI 5.5%

Simple Lifetime Maintenance Savings $3,612

Simple Lifetime Savings $12,304Internal Rate of Return (IRR) 1%Net Present Value (NPV) ($1,454.06)

ECM #7 - ENERGY SAVINGS SUMMARY

Page 60: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 59 of 89

ECM #8: Building Envelope Upgrade Description: The windows in the Cumberland County Technical Education Center building are original windows to the 1970 building and 1982 Gymnasium wing addition. The typical windows throughout the facility are 1” clear tempered structural glass with steel tube frame and is assumed to have no thermal breaks. These windows are below today’s standards in insulation value and solar heat reflectivity. The age of the windows and construction methods contribute to the leakage rate of the building. These windows are in fair to poor condition. These factors lead to increased energy use in the cooling and heating season. There is no external architectural shading for the windows except at the school entrance. This ECM includes in the base bid the existing windows to remain and in the bid alternate the replacement of all identified existing windows in the building with 1” tempered structural glass windows with a low emissivity glass. The building has opaque insulating panels in the window walls. The insulating panels in the window frame assemblies are metal and are known to have 1” asbestos insulation. All of these panels are scheduled to be remediated and replaced with 1” insulated fiberglass reinforced plastic (FRP) panels in both the base bid and bid alternate. The bid alternate includes additional window area being replaced with 1” insulated FRP panels. The building has hollow, un-insulated metal doors. These doors are very inefficient. The man doors are scheduled to be replaced with fiberglass reinforced plastic (FRP) doors with 1” insulated low-E glass. The un-insulated metal roll-up doors are scheduled to remain. Building envelope improvements may require a significant investment. Typically, the investment is recovered through energy savings however; the payback is generally quite protracted. For example, in a drafty building, adding insulation or upgrading the windows would improve comfort. Human comfort impacts productivity as uncomfortable or unhappy occupants will have a higher absentee rate and/or will require additional time from maintenance personnel as they search for stopgap solutions to the comfort problem. Energy Savings Calculations: For the following energy savings calculations, we obtained heating and cooling degree days for the Millville Airport from the following: Source: www.degreedays.net (using temperature data from www.wunderground.com) Station: Airport: Millville, NJ, US (75.07W, 39.37N) Station ID: KMIV

The window, panel and door areas were derived from drawings provided by Garrison Architects and photographs of this facility. The equations used in the calculations are listed below. A spread sheet was used to perform the calculations and tabulated. The energy transfer through each wall, window and roof was calculated using the appropriate material area, U-value and temperature

Page 61: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 60 of 89

difference. The sum of all the energy transfer for each part is the total energy transfer. The calculations are located in the APPENDIX F –ENERGY CALCULATION – ENVELOPE UPGRADE appendix.

Energy Transfer Load = Uvalue x Area x Temperature difference

( )

( ) ⎟⎠⎞

⎜⎝⎛×

×⎟⎠⎞

⎜⎝⎛

=

kWhWh

WhBTUEER

yrHrsolingFullLoadCohrBtudCoolingLoa

ngsCoolingEnergySaviOLDAVG 1000

./

.

( ) ⎟⎠⎞

⎜⎝⎛××

×⎟⎟⎠

⎞⎜⎜⎝

⎛×⎟⎟⎠

⎞⎜⎜⎝

⎛ −×⎟⎠⎞

⎜⎝⎛

=

ThermBTUAFUEFDiffDesignTemp

dayhr

yrdayFHDD

hrBtudHeatingLoa

ngsHeatingEnergySavi000,100%°

6.024.

°

( )CoolingofHrs

kWhSavingsEnergySavingsDemand =

Simple payback = Cost/Savings The results of the calculations are summarized in the tables below.

Page 62: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 61 of 89

Base Bid EXISTING PROPOSED SAVINGS

Roof Heat Load, (BTUH) -151,137.9 -127,333.3 23,804.6

Skylight Heat Load, (BTUH) -65,254.8 -65,254.8 0.0

Wall/Window/Panel Heat Load, (BTUH) -882,980.2 -570,057.2 312,923.0

Total Heating Load, (BTUH) -1,099,372.8 -762,645.3 336,727.5

Roof Cooling Load, (BTUH) 54,959.2 46,303.0 8,656.2

Skylight Cooling Load, (BTUH) 23,729.0 23,729.0 0.0

Wall/Window/Panel Cooling Load, (BTUH) 153,264.0 98,127.0 55,137.0

Total Cooling Load, (BTUH) 231,952.3 168,159.0 63,793.3

Weighted Average EER 7.0 7.0

Weighted Average Efficiency (%) 79.9% 79.9%

Nat Gas Heat Value (BTU/Therm) 100,000 100,000

Heating Degree Days (HDD68) 5,767 5,767

Full Load Cooling Hours 900 900

Nat Gas Cost ($/Therm) $1.320 $1.320

Electric Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

Annual Heat Energy (Therms) 20,775.33 14,412.04 6,363.3

Annual Electric Usage (kWh) 29,822 21,620 8,202

Electric Demand (kW) 33.1 24.0 9.1

Nat Gas Energy Cost ($) $27,423.44 $19,023.90 $8,399.54

Electric Cost ($) $4,652.30 $3,372.79 $1,279.51

Total ($) $32,076 $22,397 $9,679

ECM #8 BUILDING ENVELOPE UPGRADE - Base Bid

ENERGY SAVINGS CALCULATIONS

COMMENTS: HDD68 source www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W,39.37N); Station ID: KMIV; Before proceding with this ECM, consult with a professional engineer.

The base bid installation cost is $924,300.

Page 63: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 62 of 89

Alternate Bid EXISTING PROPOSED SAVINGS

Roof Heat Load, (BTUH) -151,137.9 -127,333.3 23,804.6

Skylight Heat Load, (BTUH) -65,254.8 -65,254.8 0.0

Wall/Window/Panel Heat Load, (BTUH) -882,980.2 -436,759.1 446,221.0

Total Heating Load, (BTUH) -1,099,372.8 -629,347.2 470,025.6

Roof Cooling Load, (BTUH) 54,959.2 46,303.0 8,656.2

Skylight Cooling Load, (BTUH) 23,729.0 23,729.0 0.0

Wall/Window/Panel Cooling Load, (BTUH) 153,264.0 59,997.1 93,267.0

Total Cooling Load, (BTUH) 231,952.3 130,029.1 101,923.2

Weighted Average EER 7.0 7.0

Weighted Average Efficiency (%) 79.9% 79.9%

Nat Gas Heat Value (BTU/Therm) 100,000 100,000

Heating Degree Days (HDD68) 5,767 5,767

Full Load Cooling Hours 900 900

Nat Gas Cost ($/Therm) $1.320 $1.320

Electric Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

Annual Heat Energy (Therms) 20,775.33 11,893.05 8,882.3

Annual Electric Usage (kWh) 29,822 16,718 13,104

Electric Demand (kW) 33.1 18.6 14.6

Nat Gas Energy Cost ($) $27,423.44 $15,698.83 $11,724.61

Electric Cost ($) $4,652.30 $2,608.01 $2,044.29

Total ($) $32,076 $18,307 $13,769

ECM #8.1 BUILDING ENVELOPE UPGRADE - Bid Alt.

ENERGY SAVINGS CALCULATIONS

COMMENTS: HDD68 source www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W,39.37N); Station ID: KMIV; Before proceding with this ECM, consult with a professional engineer.

The alternate bid installation cost is $1,039,300.

Page 64: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 63 of 89

There are no Smart Start® incentives for envelope upgrades. Energy Savings Summary:

Installation Cost ($): $924,300

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $924,300

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $9,679

Total Yearly Savings ($/Yr): $9,679

Estimated ECM Lifetime (Yr): 25

Simple Payback 95.5

Simple Lifetime ROI -73.8%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $241,975Internal Rate of Return (IRR) -8%Net Present Value (NPV) ($755,758.14)

ECM #8 - ENERGY SAVINGS SUMMARY - Base Bid

Installation Cost ($): $1,039,300

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $1,039,300

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $13,769

Total Yearly Savings ($/Yr): $13,769

Estimated ECM Lifetime (Yr): 25

Simple Payback 75.5

Simple Lifetime ROI -66.9%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $344,225Internal Rate of Return (IRR) -7%Net Present Value (NPV) ($799,538.37)

ECM #8.1 - ENERGY SAVINGS SUMMARY - Bid Alt.

Page 65: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 64 of 89

ECM #9: DDC Control Description:

The HVAC systems within the facility are controlled manually via electronic local thermostats. There is a Johnson Metasys DDC system that can control the occupancy and set points for the wings but is used basically to monitor the systems. The wings are primarily heating only roof top units that heat and ventilate the wings. The units have individual room thermostats that are controlled by the DDC system. There is an electronic control panel that controls the gym addition. The panel has occupied/unoccupied and automatic control modes by means of time clocks. The maintenance staff stated that these systems run 100%, 24/7 and don’t know if the controls even work.

Air is exhausted from the toilet rooms through the roof exhausters. The exhaust systems run 24/7. There are local exhaust systems for dust collection in Carpentry, Automotive service and Auto Collision repair and Welding Technology. The fans are controlled locally and are operated as needed. The large gang toilet room exhaust fans could be turned off during unoccupied nights and weekends and would save about 4600 hours of run hours per year, per fan. By turning these fans off, it will reduce the required heating and cooling of outside air (ventilation and infiltration).

The typical hours of operation for this facility are Monday through Friday between 7:00 am and 10:00 pm. The school is occupied with 600 day students, 400 evening students, 70 staff from 7:00 am through 10:00 pm. There are 3 day maintenance staff 7:00 am to 3:30 pm and 4 staff on the cleaning crew 3:30 pm to 11:00 pm Monday through Friday. The building is closed Monday through Friday 11:00 pm to 7:00am and all weekends.

There is no thermostat adjustments made and set back/set up functions are not employed. Therefore, a DDC system providing the Owner with full control over the HVAC equipment within the building appears to be an energy saving opportunity. The installation of a Building Automation system with Direct Digital Controls (DDC) wired through an Ethernet backbone and front end controller is the typical solution to gain control over the HVAC systems and to minimize the system energy use. The Cumberland County Technical Education Center already has usable parts of the controls already in place. Another piece is planned to be installed as part of the roof and equipment replacement project that is planned for this year. In the near term, the existing equipment and controls should be re-commissioned to assure that they are operation as close as possible to their original design. The existing controls for the wings and Gymnasium addition should employ the unoccupied function. This should close of the outside air damper and change the fan motors from continuous on to only cycle on demand for heat or cooling. In the un-occupied mode, the temperature set points should be set back 68°F to 58°F for heating and set up 75°F to 85°F for cooling. This functionality can be employed in most of the building without much cost.

Page 66: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 65 of 89

In the long term, all equipment replacement should include for each unit being replaced a unit DDC controller and a tie-in to the existing DDC system front end. The system replacements should include new thermostat controllers for all indoor air-handling systems and the rooftop units, in addition to each piece of equipment being wired back to a front end controller and computer interface. With the communication between the devices and the front end computer interface, the Owner will be able to take advantage of equipment scheduling for occupied and unoccupied periods based on the actual occupancy of the facility. The DDC system will also aid in the response time to service / maintenance issues when the facility is not under normal maintenance supervision, i.e. after-hours and week-ends. The new DDC system has the potential to provide substantial savings by controlling the HVAC systems as a whole and provide operating schedules and features such as space averaging, night set-back, temperature override control, etc. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the referenced report:

• Energy Management and Control System Savings: 5%-15%. Savings resulting from the implementation of this ECM for energy management controls are estimated to be 10% of the total energy cost for the facility. The near term cost for retro-commissioning the existing building systems is $24,100. This includes air flows measurement, minor repair and adjustment. Anything larger than a minor repair is deemed a capitol improvement and would not be included. The long term cost of a partial DDC system to tie-in to the existing DDC system with new field devices, controllers, programming, etc. is approximately $2.00 to $3.00 per SF in accordance with recent Contractor pricing for systems of this magnitude. Savings from the implementation of this ECM will be from the reduced energy consumption currently used by the HVAC system by proper control of schedule and temperatures via the DDC system. Cost of partial DDC System = ($2.00/SF x 120,543 SF) = $241,086 For both the near and long term projects, the cost is $265, 186. Note: Degree Days referenced from www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W, 39.37N); Station ID: KMIV.

Page 67: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 66 of 89

Energy Savings Calculations: 10% Savings on Heating Calculations

( ) ( ) ⎟⎠⎞

⎜⎝⎛××°

×××⎟⎠⎞

⎜⎝⎛

=

ThermkBtuValueHeatFuelEfficiencyFDifferenceTempDesign

FactorCorrectionHrsDaysDegHeatHr

kBtuLoadHeatConsHeatEst

%

24.

( ) ⎟⎠⎞

⎜⎝⎛××=

ThermCostGasAveSavingsThermsConsHeatSavings $%10..

10% Savings on Cooling Calculations:

( ) ⎟⎠⎞

⎜⎝⎛××=

kWhCostElecAveSavingskWhConsCoolSavings $%10..

The calculations are summarized in the table below.

Page 68: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 67 of 89

ECM INPUTS EXISTING PROPOSED SAVINGSBuilding Total Area (Sq.Ft.) 120,543 120,543Lighting Load (w/Sq.Ft.) 1.5 1.5Plug Load (w/Sq.Ft.) 3 3Annual Electrical Consumption (kWh/yr.) 1,429,128 1,429,128Net Annual Mechanical Electrical Consumption (kWh/yr.) 886,685 886,685Heat Load (Btu/Hr) 766,326 766,326Natural Gas Heat Value (BTU/Therm) 100,000 100,000Heating System Efficiency (%) 79.9% 79.9%Heating Degree Days (HDD65) 5,042 5,042Heating Hrs Per Day (Hrs) 24 24Energy Savings 0% 10%Electricity Cost ($/kWh) $0.156 $0.156Natural Gas Cost ($/Therm) $1.320 $1.320

ECM RESULTS EXISTING PROPOSED SAVINGSAnnual Electricity Energy (kWh/yr.) 886,685 798,016 88,668Annual Heat Energy (Therms) 10,713 9,642 1,071Annual Electricity Cost ($) $138,322.78 $124,490.50 $13,832Annual Natural Gas Energy Cost ($) $14,141 $12,727 $1,414Total Annual Savings ($/yr.) $152,464 $137,218 $15,246COMMENTS:

ECM #9 - DDC CONTROLS

ENERGY SAVINGS CALCULATIONS

HDD65 source www.degreedays.net (using temperature data from www.wunderground.com); Station Airport: Millville, NJ, US (75.07W,39.37N); Station ID: KMIV.

It is pertinent to note that electric demand savings were unable to be estimated. Also, incentives for the installation of the DDC system are not currently available and maintenance savings could not be adequately calculated because information was not available to baseline the savings.

Page 69: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 68 of 89

Energy Savings Summary:

Installation Cost ($): $265,186

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $265,186

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $15,246

Total Yearly Savings ($/Yr): $15,246

Estimated ECM Lifetime (Yr): 15

Simple Payback 17.4

Simple Lifetime ROI -13.8%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $228,696Internal Rate of Return (IRR) -2%Net Present Value (NPV) ($83,175.24)

ECM #9 - ENERGY SAVINGS SUMMARY

Page 70: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 69 of 89

ECM #10: Lighting Upgrade – General Description: The majority of the interior lighting throughout the Cumberland County Technical Education Center building is provided with fluorescent fixtures with older generation, 700 series 32W T8 lamps and electronic ballasts. Although 700 series T8 lamps are considered fairly efficient, further energy savings can be achieved by replacing the existing T8 lamps with new generation, 800 series 28W T8 lamps without compromising light output. CEG recommends, re-lamping all of the fixtures with 28W T8 lamps. In addition, the kitchen hood, restroom and some exit signs still have incandescent lamps. It is recommended to retrofit or replace all of the incandescent lights in these areas with compact fluorescent lamps or LED exit signs. This ECM includes re-lamping of the existing fluorescent fixtures with 800 series, 28W T8 lamps. The ECM also includes retrofit of all older fluorescent fixtures with T8 or T5 fluorescent fixtures with electronic ballasts in the building. The new, energy efficient T8 fixtures will provide adequate lighting and will save on electrical costs due to better performance of the lamp and ballasts. This ECM also includes maintenance savings through the reduced number of lamps replaced per year. The expected lamp life of a T8 lamp is approximately 30,000 burn-hours, in comparison to the existing T12 lamps which is approximately 20,000 burn-hours. The facility will need approximately 33% less lamps replaced per year for each one for one fixture replaced. The ECM also includes replacement of any incandescent lamps with compact fluorescent lamps. Compact fluorescent lamps (CFL’s) were designed to be direct replacements for the standard incandescent lamps which are common to table lamps, spot lights, hi-hats, bathroom vanity lighting, etc. The light output of the CFL has been designed to resemble the incandescent lamp. The color rendering index (CRI) of the CFL is much higher than standard fluorescent lighting, and therefore provides a much “truer” light. The CFL is available in a myriad of shapes and sizes depending on the specific application. Typical replacements are: a 13-Watt CFL for a 60-Watt incandescent lamp, an 18-Watt CFL for a 75-Watt incandescent lamp, and a 26-Watt CFL for a 100-Watt incandescent lamp. The CFL is also available for a number of “brightness colors” that is indicated by the Kelvin rating. A 2700K CFL is the “warmest” color available and is closest in color to the incandescent lamp. CFL’s are also available in 3000K, 3500K, and 4100K. The 4100K would be the “brightest” or “coolest” output. A CFL can be chosen to screw right into your existing fixtures, or hardwired into your existing fixtures. Where the existing fixture is controlled by a dimmer switch, the CFL bulb must be compatible with a dimmer switch. In some locations the bulb replacement will need to be tested to make sure the larger base of the CFL will fit into the existing fixture. The energy usage of an incandescent compared to a compact fluorescent approximately 3 to 4 times greater. In addition to the energy savings, compact fluorescent fixtures burn-hours are 8 to 15 times longer than incandescent fixtures ranging from 6,000 to 15,000 burn-hours compared to incandescent fixtures ranging from 750 to 1000 burn-hours. However, the maintenance savings due to reduced lamp replacement is offset by the higher cost of the CFL’s compared to the incandescent lamps. Finally, the exterior of the Cumberland County Technical Education Center is illuminated with 400W Mercury Vapor post mounted area lights. It is recommended to retrofit these fixtures with

Page 71: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 70 of 89

pulse start metal halide lamps and electronic ballasts. Pulse-start MH lamps have a high-voltage ignitor to start the lamp using a series of pulses instead of a starting probe electrode. Pulse start metal halide lamps typically have an increased lumen maintenance levels by up to 33%. This allows utilizing lower wattage lamps while maintaining the minimum lighting levels in the space. The 175 watt mercury vapor wall packs use an older, inefficient technology that should be replace with newer more efficient induction fixture. The induction lamp uses less than half the energy and has a rated life of 100,000 hours compared to the 24,000 hour for the mercury vapor lamp. Energy Savings Calculations: The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building. Rebates and Incentives: There are incentives available from NJ Smart Start® Program for a portion of the retrofits in this ECM. Incentives are calculated as follows: From the Smart Start Incentive appendix, the retrofit of a probe start metal halide with a pulse start system (with a minimum 12% wattage reduction) warrants the following incentive: Pulse Start Metal Halide (for fixtures ≥ 150 watts) = $25 per fixture. SmartStart ® Incentive # of Probe Start Fixtures $25 12 $25 $300 Induction Lighting HID Replacement = $70 per fixture SmartStart ® Incentive 175watt Mercury Vapor Wall Pack $70x30 $2,100 Linear Flourescent 400w HID replacement with T5 = $100 per fixture SmartStart ® Incentive 400w HID replacement $100x12 $1,200 Total Incentive = $300 + $2,100 + $1,200 = $3,600 Replacement and Maintenance Savings: Replacement and Maintenance Savings for Induction fixtures are calculated as follows:

( )lampper$Laborlampper$nt(replacemeyear)perreplacedlampsinreductionSavings +×=

( )( ) ( )( ) $45.54/yrlampper$21lampper$10732.1lampper$21lampper$185.5.Savings/yr =+×−+×=

Page 72: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 71 of 89

Energy Savings Summary:

Installation Cost ($): $42,754

NJ Smart Start Equipment Incentive ($): $3,600

Net Installation Cost ($): $39,154

Maintenance Savings ($/Yr): $46

Energy Savings ($/Yr): $11,868

Total Yearly Savings ($/Yr): $11,914

Estimated ECM Lifetime (Yr): 15

Simple Payback 3.3

Simple Lifetime ROI 356.4%

Simple Lifetime Maintenance Savings $683

Simple Lifetime Savings $178,703Internal Rate of Return (IRR) 30%Net Present Value (NPV) $103,069.07

ECM #10 - ENERGY SAVINGS SUMMARY

Page 73: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 72 of 89

ECM #11: Lighting Controls Upgrade – Occupancy Sensors Description: Some of the lights in the school building are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.

Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:

• Occupancy Sensors for Lighting Control 20% - 28% energy savings.

Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors and daylight sensors (The majority of the savings is expected to be after school hours when rooms are left with lights on) This ECM includes installation of ceiling or switch mount sensors for individual offices, classrooms, large bathrooms, and libraries. Sensors shall be manufactured by Sensorswitch, Watt Stopper or equivalent. The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Energy Savings Calculations:

( )( )kWh/YrEnergyLightControlledSavings%SavingsEnergy ×=

( ) ⎟⎠⎞

⎜⎝⎛×=

kWh$CostElecAvekWhSavingsEnergySavings.

Page 74: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 73 of 89

Cost and Incentives:

Installation cost per dual-technology sensors (Basis: Sensor switch or equivalent) are as follows:

Dual Technology Occupancy Sensor - Remote Mount $250 per installation Dual Technology Occupancy Sensor - Switch Mount $150 per installation Dual Technology Occupancy Sensor with 2 Pole Powerpack Remote mount $300 per installation Cost includes material and labor. From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: Occupancy Sensor Fixture Mounted (existing facility only) = $20 per sensor Occupancy Sensor Remote Mounted (existing facility only) = $35 per sensor

( ) $35)mountceilingof(#20$mountwallof#IncentiveStartSmart ×+×=® ( ) $1,890$35)mountceiling(4220$mountwall21IncentiveStartSmart =×+×=®

Energy Savings Summary:

Installation Cost ($): $34,800

NJ Smart Start Equipment Incentive ($): $1,890

Net Installation Cost ($): $32,910

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $8,690

Total Yearly Savings ($/Yr): $8,690

Estimated ECM Lifetime (Yr): 15

Simple Payback 3.8

Simple Lifetime ROI 296.1%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $130,350Internal Rate of Return (IRR) 26%Net Present Value (NPV) $70,830.66

ECM #11 - ENERGY SAVINGS SUMMARY

Page 75: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 74 of 89

ECM #12: Computer Monitor Replacement Description: The computers throughout the school utilize a mixture of CRT computer monitors and LCD computer monitors. The CRT computer monitors within the offices and classrooms are outdated and have several disadvantages such as; significantly increased energy consumption, uses large amount of desk space, poor picture quality, distortions and flickering image, secular glare problems, high weight, and electromagnetic emissions. Many of these drawbacks are difficult to quantify except for the energy use. CRT monitors use considerably more energy than an alternative flat panel LCD monitor. Replacement of the existing CRT monitors with LCD monitors saves considerable energy as well as provides other ergonomic benefits. Based on the site survey it was noted that there are 187 LCD monitor and 6 CRT monitors. Some of the monitors were left in screen saver mode, which only saves the computer screen from image burn in, however it does not save on energy consumption. The average operating hours for all computers and monitors is estimated based on the site survey observations. Energy consumption of computer monitors is based on averages for power usage of various computer monitors. This ECM includes replacement of all existing CRT monitors with LCD flat panel monitors throughout the facility. Installation costs were neglected for this ECM with the intention that this ECM would be replaced by the school district. The calculations are based on the following operating assumptions: Energy Savings Calculations: No. of CRT Monitors: 6 Operating Weeks per Yr: 42 Hrs per Week: 75 (15 hrs per day estimated average)

( ) ( )

⎟⎠⎞

⎜⎝⎛

××=

KWW

HrsOperationWPowerMonitorComputersofUsageElectric1000

#

( ) ⎟⎠⎞

⎜⎝⎛×=

kWhCostElecAvekWhUsageElectricCostEnergy $

Page 76: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 75 of 89

ECM INPUTS EXISTING PROPOSED SAVINGSECM INPUTS CRT Monitors LCD Monitor

# of Computers 6 6

Monitor Power Cons. (W) 75 25

Operating Hrs per Week 75 75

Operating Weeks per Yr 42 42

Elec Cost ($/kWh) 0.156 0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

Electric Usage (kWh) 1,418 473 945

Energy Cost ($) $221 $74 $147

COMMENTS:

COMPUTER MONITOR CALCULATIONS

ENERGY SAVINGS CALCULATIONS

CRT Monitor consumption based on Dell CRT monitor M/N: CRT-E771MM. Operating hours estimated.

Installation cost of new monitors is estimated based on current pricing for a 17” LCD monitor on the market today. No labor costs were included for replacing the existing monitors with the new monitors. No incentives are available for installation of computer monitors. Net cost per monitor was estimated to be $100. Cost of installation is summarized in the table below.

ECM INPUT # OF UNITS UNIT COST TOTAL COSTCRT MONITORS 6 $100 $600Total 6 $600

COST & SAVINGS SUMMARY

Page 77: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 76 of 89

Energy Savings Summary:

Installation Cost ($): $600

NJ Smart Start Equipment Incentive ($): $0

Net Installation Cost ($): $600

Maintenance Savings ($/Yr): $0

Energy Savings ($/Yr): $147

Total Yearly Savings ($/Yr): $147

Estimated ECM Lifetime (Yr): 15

Simple Payback 4.1

Simple Lifetime ROI 268.6%

Simple Lifetime Maintenance Savings $0

Simple Lifetime Savings $2,211Internal Rate of Return (IRR) 24%Net Present Value (NPV) $1,159.89

ECM #12 - ENERGY SAVINGS SUMMARY

Page 78: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 77 of 89

VIII. RENEWABLE/DISTRIBUTED ENERGY MEASURES Globally, renewable energy has become a priority affecting international and domestic energy policy. The State of New Jersey has taken a proactive approach, and has recently adopted in its Energy Master Plan a goal of 30% renewable energy by 2020. To help reach this goal New Jersey created the Office of Clean Energy under the direction of the Board of Public Utilities and instituted a Renewable Energy Incentive Program to provide additional funding to private and public entities for installing qualified renewable technologies. A renewable energy source can greatly reduce a building’s operating expenses while producing clean environmentally friendly energy. CEG has assessed the feasibility of installing renewable energy measures (REM) for the Cumberland County Technical Education Center utilizing renewable technologies and concluded that there is potential for solar energy generation. The solar photovoltaic system calculation summary will be concluded as REM#1 within this report. Solar Generation Solar energy produces clean energy and reduces a building’s carbon footprint. This is accomplished via photovoltaic panels which are mounted on the Main building roof. Flat roof, as well as sloped areas can be utilized; flat areas will have the panels turned to an optimum solar absorbing angle. (A structural survey of the roof would be necessary before the installation of PV panels is considered). Parking lots can also be utilized for the installation of a solar array. A truss system can be installed that is high enough to park vehicles under the array and no parking lot area is lost. The state of NJ has instituted a program in which one Solar Renewable Energy Certificate (SREC) is given to the Owner for every 1000 kWh of generation. SREC’s can be sold anytime on the market at their current market value. The value of the credit varies upon the current need of the power companies. The average value per credit is around $350, this value was used in our financial calculations. This equates to $0.35 per kWh generated. CEG has reviewed the existing roof area and site of Cumberland County Technical Education Center for the purposes of determining a potential for a photovoltaic system. CEG believes a combination of a roof mounted and a ground mounted parking lot canopy system is best suited for this site. An area total of 20,800 S.F. can be utilized for a PV system as depicted in the Renewable / Distributed Energy Measures Calculation Appendix. Using this square footage it was determined that a system size of 293.02 kilowatts could be installed. A system of this size has an estimated kilowatt hour production of 357,965 KWh annually, reducing the overall utility bill by approximately 25.05% percent. A detailed financial analysis can be found in the Renewable / Distributed Energy Measures Calculation Appendix. This analysis illustrates the payback of the system over a 25 year period. The eventual degradation of the solar panels and the price of accumulated SREC’s are factored into the payback. The proposed photovoltaic array layout is designed based on the specifications for the Sun Power SPR-230 panel. This panel has a “DC” rated full load output of 230 watts, and has a total panel conversion efficiency of 18%. Although panels rated at higher wattages are available through Sun Power and other various manufacturers, in general most manufacturers who produce

Page 79: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 78 of 89

commercially available solar panels produce a similar panel in the 200 to 250 watt range. This provides more manufacturer options to the public entity if they wish to pursue the proposed solar recommendation without losing significant system capacity. The array system capacity was sized on available roof and parking lot space at the existing facility. Estimated solar array generation was then calculated based on the National Renewable Energy Laboratory PVWatts Version 1.0 Calculator. In order to calculate the array generation an appropriate location with solar data on file must be selected. In addition the system DC rated kilowatt (kW) capacity must be inputted, a DC to AC de-rate factor, panel tilt angle, and array azimuth angle. The DC to AC de-rate factor is based on the panel nameplate DC rating, inverter and transformer efficiencies (95%), mismatch factor (98%), diodes and connections (100%), dc and ac wiring(98%, 99%), soiling, (95%), system availability (95%), shading (if applicable), and age(new/100%). The overall DC to AC de-rate factor has been calculated at an overall rating of 81%. The PVWatts Calculator program then calculates estimated system generation based on average monthly solar irradiance and user provided inputs. The monthly energy generation and offset electric costs from the PVWatts calculator is shown in the Renewable/Distributed Energy Measures Calculation Appendix. The proposed solar array is qualified by the New Jersey Board of Public Utilities Net Metering Guidelines as a Class I Renewable Energy Source. These guidelines allow onsite customer generation using renewable energy sources such as solar and wind with a capacity of 2 megawatts (MW) or less. This limits a customer system design capacity to being a net user and not a net generator of electricity on an annual basis. Although these guidelines state that if a customer does net generate (produce more electricity than they use), the customer will be credited those kilowatt-hours generated to be carried over for future usage on a month to month basis. Then, on an annual basis if the customer is a net generator the customer will then be compensated by the utility the average annual PJM Grid LMP price per kilowatt-hour for the over generation. Due to the aforementioned legislation, the customer is at limited risk if they generate more than they use at times throughout the year. With the inefficiency of today’s energy storage systems, such as batteries, the added cost of storage systems is not warranted and was not considered in the proposed design. Direct purchase involves the Technical Education Center paying for 100% of the total project cost upfront via one of the methods noted in the Installation Funding Options section below. Calculations include a utility inflation rate as well as the degradation of the solar panels over time. Based on our calculations the following is the payback period:

Table 8 Financial Summary – Photovoltaic System

FINANCIAL SUMMARY - PHOTOVOLTAIC SYSTEM

PAYMENT TYPE SIMPLE PAYBACK

SIMPLE ROI

INTERNAL RATE OF RETURN

Direct Purchase 14.56 Years 6.87% 5.3% *The solar energy measure is shown for reference in the executive summary Renewable Energy Measure (REM) table

Page 80: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 79 of 89

Given the large amount of capital required by the Technical Education Center to invest in a solar system through a Direct Purchase CEG does not recommend the Technical Education Center pursue this route. It would be more advantageous for the Technical Education Center to solicit Power Purchase Agreement (PPA) Providers who will own, operate, and maintain the system for a period of 15 years. During this time the PPA Provider would sell all of the electric generated by Solar Arrays to the Technical Education Center at a reduced rate compared to their existing electric rate. Wind Generation In addition to the Solar Analysis, CEG also conducted a review of the applicability of wind energy for the facility. Wind energy production is another option available through the Renewable Energy Incentive Program. Wind turbines of various types can be utilized to produce clean energy on a per building basis. Cash incentives are available per kWh of electric usage. Based on CEG’s review of the applicability of wind energy for the facility, it was determined that the average wind speed is not adequate for purchase of a commercial wind turbine. Therefore, wind energy is not a viable option to implement.  

Page 81: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 80 of 89

IX. ENERGY PURCHASING AND PROCUREMENT STRATEGY Load Profile: Load Profile analysis was performed to determine the seasonal energy usage of the facility. Irregularities in the load profile will indicate potential problems within the facility. Consequently based on the profile a recommendation will be made to remedy the irregularity in energy usage. For this report, the facility’s energy consumption data was gathered in table format and plotted in graph form to create the load profile. Refer to The Electric and Natural Gas Usage Profiles included within this report to reference the respective electricity and natural gas usage load profiles. Electricity: The electricity usage profile demonstrates a steady year long load profile for facilities that have occupancy during the summer months. Average usage for all accounts combined is 119,094 kWh with highest usage during May, June, July, August and September. The historical usage profile is beneficial and will allow for more competitive energy prices when shopping for alternative suppliers mainly due to the relatively flat load profile. Third Party Supplier (TPS) electric commodity contracts that offer’s a firm, fixed price for 100% of the facilities electric requirements and are lower than the Atlantic City Electric’s (AECO) BGS-FP default rate are recommended. Natural Gas: The Natural Gas Usage Profile demonstrates a very typical natural gas (heat load) profile. The summer months June and July have very little consumption. This load profile will yield less favorable natural gas pricing when shopping for alternative suppliers. This is because the higher winter month consumption will yield higher pricing which will not be offset by the summer month consumption. Nymex commodity pricing is generally higher in the winter months of November – March and lower in the summer months of April – October. Obtaining a flat load profile, (usage is similar each month), will yield optimum natural gas pricing when shopping for alternative suppliers. Third Party Supplier (TPS) natural gas commodity contracts that offer a product structure to include either 1) a fixed basis rate with a market based Nymex/commodity rate or 2) a fixed basis rate with fixed Nymex/commodity winter rate (Nov – March) and market based Nymex/commodity rate for the summer months (April – October) for 100% of the facilities metered natural gas requirements are both recommended due to current market pricing.

Page 82: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 81 of 89

Tariff Analysis: Electricity: The facilities receive electrical service through Atlantic City Electric (AECO) on AGS-Sec (Annual General Service Secondary), MGS (Monthly General Service) and SPL (Street and Private Lighting. The facilities have not contracted a Third Party Supplier (TPS) to provide electric commodity service. Account# 0329 9959 9999 is noted to have been under a 3rd party contract with TPS, Hess Energy for November and December 2010, however as of Jan 2011 the Supplier provided a letter stating that the account was to be turned back to the utility for BGS-FP supply. For electric supply (generation) service, the client has a choice to either use AECO’s default service rate BGS-FP or contract with a Third Party Supplier (TPS) to supply electric. Each year since 2002, the four New Jersey Electric Distribution Companies (EDCs) - Public Service Gas & Electric Company (PSE&G), Atlantic City Electric Company (ACE), Jersey Central Power & Light Company (JCP&L), and Rockland Electric Company (RECO) - have procured several billion dollars of electric supply to serve their Basic Generation Service (BGS) customers through a statewide auction process held in February. BGS refers to the service of customers who are not served by a third party supplier or competitive retailer. This service is sometimes known as Standard Offer Service, Default Service, or Provider of Last Resort Service. The Auction Process has consisted of two auctions that are held concurrently, one for larger customers on an hourly price plan (BGS-CIEP) and one for smaller commercial and residential customers on a fixed-price plan (BGS-FP). This facility’s rate structure is based on the fixed-price plan (BGS-FP). The utility, Atlantic City Electric will continue to be responsible for maintaining the existing network of wires, pipes and poles that make up the delivery system, which will serve all consumers, regardless of whom they choose to purchase their electricity or natural gas from. AECO’s delivery service rate includes the following charges: Customer Service Charge, Distribution Charge, Market Transition, Transition Bond Charge, Non Utility Generation Charge, Societal Benefits Charge (SBC), Infrastructure Investment Charge, System Control Charge, Regulatory Assets Recovery Charge, and Regional Greenhouse Gas Initiative Charge. Natural Gas: The facilities currently receive natural gas distribution service through South Jersey Gas on rate schedule General Service Gas – Large Volume Firm Transportation (GSGLV-FT) with a Firm Demand of 73mcf/day. Woodruff Energy is the contracted Third Party Supplier (TPS) which provides natural gas commodity supply service. The current contract price for natural gas supply is $5.88/dth for a term of Jan 2011 – Dec 2011. South Jersey Gas provides basic gas supply service (BGSS) to customers who choose not to shop from a Third Party Supplier (TPS) for natural gas commodity. The option is essential to protect

Page 83: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 82 of 89

the reliability of service to consumers as well as protecting consumers if a third party supplier defaults or fails to provide commodity service. Please refer to the link below for a recap of natural gas BGSS charges from South Jersey Gas for rate schedule GSGLV-FT. http://www.southjerseygas.com/108/tariff/bgssrates.pdf The utility, South Jersey Gas is responsible for maintaining the existing network of wires, pipes and poles that make up the delivery system, which will serve all consumers, regardless of whom they choose to purchase their electricity or natural gas from. South Jersey Gas’s delivery service rate includes the following charges: Customer Service Charge, Distribution Charge, Demand Charge, & Balancing Service Charge.

Electric and Natural Gas Commodities Market Overview:

Current electricity and natural gas market pricing has remained relatively stable over the last year. Commodity pricing in 2008 marked historical highs in both natural gas and electricity commodity. Commodity pricing commencing spring of 2009 continuing through 2011, has decreased dramatically over 2008 historic highs and continues to be favorable for locking in long term (2-5 year) contracts with 3rd Party Supplier’s for both natural gas and electricity supply requirements.

It is important to note that both natural gas and electric commodity market prices are moved by supply and demand, political conditions, market technicals and trader sentiment. This market is continuously changing Energy commodity pricing is also correlated to weather forecasts. Because weather forecasts are dependable only in the short-term, prolonged temperature extremes can really cause extreme price swings.

Page 84: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 83 of 89

Short Term Energy Outlook - US Energy Information Administration (1/11/2011):

U.S. Natural Gas Prices. The Henry Hub spot price averaged $4.25 per MMBtu during December, an increase of about 54 cents from November's price of $3.71 per MMBtu. EIA expects the higher forecast production during the first half of 2011 compared with the same period last year, combined with a decline in consumption, to moderate natural gas spot prices. The projected spot price falls to a low of $3.73 per MMBtu in June then rises to $4.61 in December, averaging $4.02 per MMBtu for all of 2011, which is $0.37 per MMBtu lower than the 2010 average and $0.31 per MMBtu lower than in last month's Outlook. In 2012, the spot price rises to an average of $4.50 per MMBtu.

Uncertainty over future natural gas prices is slightly lower this year compared with last year at this time. Natural gas futures for March 2011 delivery (for the 5-day period ending January 6) averaged $4.39 per MMBtu, and the average implied volatility over the same period was 43 percent. This produced lower and upper bounds for the 95-percent confidence interval for March 2011 contracts of $3.21 per MMBtu and $6.02 per MMBtu, respectively. At this time last year, the natural gas March 2010 futures contract averaged $5.73 per MMBtu and implied volatility averaged 57 percent. The corresponding lower and upper limits of the 95-percent confidence interval were $3.88 per MMBtu and $8.47 per MMBtu.

Page 85: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 84 of 89

U.S. Electricity Retail Prices. EIA expects the U.S. retail price for electricity distributed to the residential sector during 2010 to average 11.6 cents per kilowatt-hour, about the same level as in 2009. EIA expects the U.S. residential price to increase only slightly over the forecast period--by 0.6 percent in 2011 and by 1.0 percent in 2012.

Recommendations:

1. CEG recommends an aggregated approach for 3rd party commodity supply procurement strategies for electric and natural gas supply service. Aggregating the usage of all facilities for electricity and natural gas supply service, would allow the facilities to either continue to achieve or achieve a reduction in commodity supply costs. Energy commodities are among the most volatile of all commodities, however at this point and time, energy is extremely competitive and contract terms longer than 12 months are desirable. Contracts due to expire in the near term would continue to yield favorable pricing. It is important to aggregate usage where available and take advantage of these current market prices quickly, before energy increases. Overall, after review of the utility consumption, billing, and current commodity pricing outlook, CEG recommends that the facilities continue to participate in the energy supply aggregation group for natural gas and explore options for utilizing an energy supply aggregation for electricity to include all AGS and MGS accounts. Many aggregation groups utilize the advisement of a 3rd party unbiased Energy Consulting Firm experienced in the aggregation of and procurement of retail electricity and natural gas commodity. It is important to note that the Energy Consulting Firm should incorporate a rational, defensible strategy for purchasing commodity in volatile markets based upon the following:

• Budgets that reflect sound market intelligence • An understanding of historical prices and trends • Awareness of seasonal opportunities (e.g. shoulder months) • Negotiation of fair contractual terms • An aggressive, market based price

2. CEG recommends that the school district consider utilizing a third party utility billing-auditing service to further analyze historical utility invoices such as water, sewer, natural gas and electric for incorrect billings and rate tariff optimization services. This service can be based on a shared savings model with no cost to the school district. The service could provide refunds on potential incorrect billings that may have been passed through by the utilities and paid by the school.

Page 86: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 85 of 89

X. INSTALLATION FUNDING OPTIONS CEG has reviewed various funding options for the facility owner to utilize in subsidizing the costs for installing the energy conservation measures noted within this report. Below are a few alternative funding methods:

i. Energy Savings Improvement Program (ESIP) – Public Law 2009, Chapter 4

authorizes government entities to make energy related improvements to their facilities and par for the costs using the value of energy savings that result from the improvements. The “Energy Savings Improvement Program (ESIP)” law provides a flexible approach that can allow all government agencies in New Jersey to improve and reduce energy usage with minimal expenditure of new financial resources.

ii. Municipal Bonds – Municipal bonds are a bond issued by a city or other local

government, or their agencies. Potential issuers of municipal bonds include cities, counties, redevelopment agencies, school districts, publicly owned airports and seaports, and any other governmental entity (or group of governments) below the state level. Municipal bonds may be general obligations of the issuer or secured by specified revenues. Interest income received by holders of municipal bonds is often exempt from the federal income tax and from the income tax of the state in which they are issued, although municipal bonds issued for certain purposes may not be tax exempt.

iii. Power Purchase Agreement – Public Law 2008, Chapter 3 authorizes contractor

of up to fifteen (15) years for contracts commonly known as “power purchase agreements.” These are programs where the contracting unit (Owner) procures a contract for, in most cases, a third party to install, maintain, and own a renewable energy system. These renewable energy systems are typically solar panels, windmills or other systems that create renewable energy. In exchange for the third party’s work of installing, maintaining and owning the renewable energy system, the contracting unit (Owner) agrees to purchase the power generated by the renewable energy system from the third party at agreed upon energy rates.

iv. Pay For Performance – The New Jersey Smart Start Pay for Performance

program includes incentives based on savings resulted from implemented ECMs. The program is available for all buildings that were audited as part of the NJ Clean Energy’s Local Government Energy Audit Program. The facility’s participation in the program is assisted by an approved program partner. An “Energy Reduction Plan” is created with the facility and approved partner to shown at least 15% reduction in the building’s current energy use. Multiple energy conservation measures implemented together are applicable toward the total savings of at least 15%. No more than 50% of the total energy savings can result from lighting upgrades / changes.

Page 87: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 86 of 89

Total incentive is capped at 50% of the project cost. The program savings is broken down into three benchmarks; Energy Reduction Plan, Project Implementation, and Measurement and Verification. Each step provides additional incentives as the energy reduction project continues. The benchmark incentives are as follows:

1. Energy Reduction Plan – Upon completion of an energy reduction

plan by an approved program partner, the incentive will grant $0.10 per square foot between $5,000 and $50,000, and not to exceed 50% of the facility’s annual energy expense. (Benchmark #1 is not provided in addition to the local government energy audit program incentive.)

2. Project Implementation – Upon installation of the recommended measures along with the “Substantial Completion Construction Report,” the incentive will grant savings per KWH or Therm based on the program’s rates. Minimum saving must be 15%. (Example $0.11 / kWh for 15% savings, $0.12/ kWh for 17% savings, … and $1.10 / Therm for 15% savings, $1.20 / Therm for 17% saving, …) Increased incentives result from projected savings above 15%.

3. Measurement and Verification – Upon verification 12 months after implementation of all recommended measures, that actual savings have been achieved, based on a completed verification report, the incentive will grant additional savings per kWh or Therm based on the program’s rates. Minimum savings must be 15%. (Example $0.07 / kWh for 15% savings, $0.08/ kWh for 17% savings, … and $0.70 / Therm for 15% savings, $0.80 / Therm for 17% saving, …) Increased incentives result from verified savings above 15%.

v. Energy Efficiency and Conservation Block Grants – The EECGB rebate provides supplemental funding up to $50,000 for counties and local government entities to implement energy conservation measures. The EECGB funding is provided through the American Recovery and Reinvestment Act (ARRA). The local government must be among the eligible local government entities listed on the NJ Clean Energy website as follows - http://njcleanenergy.com/commercial-industrial/programs/eecbg-eligible-entities. This program is limited to municipalities and counties that have not already received grants directly through the US department of Energy.

This incentive is provided in addition to the other NJ Clean Energy program funding. This program’s incentive is considered the entity’s capital and therefore can be applied to the LGEA program’s requirements to implement the recommended energy conservation measures totaling at least 25% of the energy audit cost. Additional requirements of this program are as follows:

Page 88: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 87 of 89

1. The entity must utilize additional funding through one or more of

the NJ Clean Energy programs such as Smart Start, Direct Install, and Pay for Performance.

2. The EECBG funding in combination with other NJ Clean Energy programs may not exceed the total cost of the energy conservation measures being implemented.

3. Envelope measures are applicable only if recommended by the LGEA energy audit and if the energy audit was completed within the past 12 months.

4. New construction and previously installed measures are not eligible for the EECBG rebate.

5. Energy conservation measures eligible for the EECBG must fall within the list of approved energy conservation measures. The complete list of eligible measures and other program requirements are included in the “EECBG Complete Application Package.” The application package is available on the NJ Clean Energy website - http://njcleanenergy.com/commercial-industrial/programs/energy-efficiency-and-conservation-block-grants.

CEG recommends the Owner review the use of the above-listed funding options in addition to utilizing their standard method of financing for facilities upgrades in order to fund the proposed energy conservation measures.

Page 89: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 88 of 89

XI. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean Energy but save energy none the less.

A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.

B. Maintain all weather stripping on windows and doors.

C. Clean all light fixtures to maximize light output.

D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ.

E. Confirm that outside air economizers on the rooftop units are functioning properly to take advantage of free cooling and avoid excess outside air during occupied periods.

In addition to the recommendations above, implementing Retro-Commissioning would be beneficial for this facility. Retro-Commissioning is a means to verify your current equipment is operating at its designed efficiency, capacity, airflow, and overall performance. Retro-Commissioning provides valuable insight into systems or components not performing correctly or efficiently. The commissioning process defines the original system design parameters and recommends revisions to the current system operating characteristics.

Page 90: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Cumberland County – Technical Education Center Energy Audit

Concord Engineering Group, Inc. 9C10093 April 6, 2011– FINAL Page 89 of 89

XII. ENERGY AUDIT ASSUMPTIONS The assumptions utilized in this energy audit include but are not limited to following:

A. Cost Estimates noted within this report are based on industry accepted costing data such as RS MeansTM Cost Data, contractor pricing and engineering estimates. All cost estimates for this level of auditing are +/- 20%. Prevailing wage rates for the specified region has been utilized to calculate installation costs. The cost estimates indicated within this audit should be utilized by the owner for prioritizing further project development post the energy audit. Project development would include investment grade auditing and detailed engineering.

B. Energy savings noted within this audit are calculated utilizing industry standard procedures and accepted engineering assumptions. For this level of auditing, energy savings are not guaranteed.

C. Information gathering for each facility is strongly based on interviews with operations personnel. Information dependent on verbal feedback is used for calculation assumptions including but not limited to the following:

a. operating hours b. equipment type c. control strategies d. scheduling

D. Information contained within the major equipment list is based on the existing owner documentation where available (drawings, O&M manuals, etc.). If existing owner documentation is not available, catalog information is utilized to populate the required information.

E. Equipment incentives and energy credits are based on current pricing and status of rebate programs. Rebate availability is dependent on the individual program funding and applicability.

F. Equipment (HVAC, Plumbing, Electrical, & Lighting) noted within an ECM recommendation is strictly noted as a basis for calculation of energy savings. The owner should use this equipment information as a benchmark when pursuing further investment grade project development and detailed engineering for specific energy conservation measures.

G. Solar PV system REM assumes panel locations are acceptable. Before proceeding with the panel locations, a structural engineer must be consulted to determine the adequacy of the structures and whether or not structural modifications would be required.

Utility bill annual averages are utilized for calculation of all energy costs unless otherwise noted. Accuracy of the utility energy usage and costs are based on the information provided. Utility information including usage and costs is estimated where incomplete data is provided.

Page 91: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX A1 of 1

LIFETIME ENERGY SAVINGS

LIFETIME MAINTENANCE

SAVINGSLIFETIME ROI SIMPLE PAYBACK INTERNAL RATE OF

RETURN (IRR)NET PRESENT VALUE

(NPV)

MATERIAL LABOR REBATES, INCENTIVES

NET INSTALLATION

COSTENERGY MAINT. /

SREC TOTAL (Yearly Saving * ECM Lifetime)

(Yearly Maint Svaing * ECM Lifetime)

(Lifetime Savings - Net Cost) / (Net Cost) (Net cost / Yearly Savings)

($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)

ECM #1 Indoor Heating & Ventilation Units Upgrade $32,847 $7,123 $108 $39,862 $142 $100 $242 15 $3,630 $1,500 -90.9% 164.7 -21.25% ($36,972.73)

ECM #2 Roof Top Heating & Ventilation Units Upgrade $291,860 $94,920 $927 $385,853 $1,575 $2,000 $3,575 15 $53,618 $30,000 -86.1% 107.9 -18.31% ($343,180.85)

ECM #3 Packaged Cool/Heat RTU Upgrade $23,140 $17,360 $1,278 $39,223 $617 $0 $617 15 $9,248 $0 -76.4% 63.6 -14.28% ($31,862.26)

ECM #4 Condensing Unit Upgrade $12,375 $3,460 $988 $14,848 $2,590 $0 $2,590 15 $38,850 $0 161.7% 5.7 15.41% $16,071.75

ECM #5 Multi-deck RTU Upgrade with Energy Recovery $884,193 $723,430 $0 $1,607,623 $41,684 $0 $41,684 15 $625,257 $0 -61.1% 38.6 -10.00% ($1,110,004.51)

ECM #6 Premium Efficient Motor Upgrade $15,380 $610 $0 $15,990 $295 $0 $295 18 $5,309 $0 -66.8% 54.2 -9.68% ($11,933.27)

ECM #7 Dishwasher & Booster Water Heater Upgrade $9,935 $1,725 $0 $11,660 $724 $301 $1,025 12 $12,304 $3,612 5.5% 11.4 0.84% ($1,454.06)

ECM #8 Building Envelope Upgrade - Base Bid $924,300 $0 $0 $924,300 $9,679 $0 $9,679 25 $241,975 $0 -73.8% 95.5 -8.44% ($755,758.14)

ECM #8.1 Building Envelope Upgrade - Alternate Bid $1,039,300 $0 $0 $1,039,300 $13,769 $0 $13,769 25 $344,225 $0 -66.9% 75.5 -7% ($799,538.37)

ECM #9 DDC Controls / Retro Commissioning $265,186 $0 $0 $265,186 $15,246 $0 $15,246 15 $228,696 $0 -13.8% 17.4 -1.80% ($83,175.24)

ECM #10 Lighting Upgrade - General $42,754 $0 $3,600 $39,154 $11,868 $46 $11,914 15 $178,703 $683 356.4% 3.3 29.82% $103,069.07

ECM #11 Lighting Controls $34,800 $0 $1,890 $32,910 $8,690 $0 $8,690 15 $130,350 $0 296.1% 3.8 25.53% $70,830.66

ECM #12 CRT Monitor Replacement $600 $0 $0 $600 $147 $0 $147 15 $2,211 $0 268.6% 4.1 23.54% $1,159.89

REM #1 Solar PV System 293.02 kW DC $2,637,180 $0 $0 $2,637,180 $55,843 $125,288 $181,130 25 $4,528,257 $3,132,194 71.7% 14.6 4.68% $516,868.49

Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .

REM RENEWABLE ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

ECM COST & SAVINGS BREAKDOWNCONCORD ENGINEERING GROUP

Cumberland County Technical Education Center

INSTALLATION COST YEARLY SAVINGSECM

LIFETIMEDESCRIPTIONECM NO.

ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY

Page 92: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix B Page 1 of 4

Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508

SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives as of February 15, 2011:

Electric Chillers Water-Cooled Chillers $12 - $170 per ton

Air-Cooled Chillers $8 - $52 per ton Energy Efficiency must comply with ASHRAE 90.1-2007

Gas Cooling Gas Absorption Chillers $185 - $400 per ton

Gas Engine-Driven Chillers Calculated through custom measure path)

Desiccant Systems $1.00 per cfm – gas or electric

Electric Unitary HVAC Unitary AC and Split Systems $73 - $92 per ton

Air-to-Air Heat Pumps $73 - $92 per ton Water-Source Heat Pumps $81 per ton

Packaged Terminal AC & HP $65 per ton Central DX AC Systems $40- $72 per ton

Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat

(Hospitality & Institutional Facility) $75 per thermostat

Energy Efficiency must comply with ASHRAE 90.1-2007

Gas Heating Gas Fired Boilers < 300 MBH $300 per unit

Gas Fired Boilers ≥ 300 - 1500 MBH $1.75 per MBH

Gas Fired Boilers ≥1500 - ≤ 4000 MBH $1.00 per MBH

Gas Fired Boilers > 4000 MBH (Calculated through Custom Measure Path)

Gas Furnaces $300 - $400 per unit, AFUE ≥ 92%

Page 93: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix B Page 2 of 4

Ground Source Heat Pumps

Closed Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20

Energy Efficiency must comply with ASHRAE 90.1-2007

Variable Frequency Drives Variable Air Volume $65 - $155 per hp Chilled-Water Pumps $60 per VFD rated hp

Compressors $5,250 to $12,500 per drive Cooling Towers ≥ 10 hp $60 per VFD rated hp

Natural Gas Water Heating

Gas Water Heaters ≤ 50 gallons, 0.67 energy factor or better $50 per unit

Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH Gas-Fired Booster Water Heaters $17 - $35 per MBH Gas Fired Tankless Water Heaters $300 per unit

Prescriptive Lighting Retro fit of T12 to T-5 or T-8 Lamps

w/Electronic Ballast in Existing Facilities

$10 per fixture (1-4 lamps)

Replacement of T12 with new T-5 or T-8 Lamps w/Electronic Ballast in

Existing Facilities $25 per fixture (1-4 lamps)

Replacement of incandescent with screw-in PAR 38 or PAR 30 (CFL)

bulb $7 per bulb

T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)

Lamp & ballast replacement $10 per fixture

Hard-Wired Compact Fluorescent $25 - $30 per fixture

Metal Halide w/Pulse Start Including Parking Lot $25 per fixture

T-5 and T-8 High Bay Fixtures $16 - $200 per fixture

HID ≥ 100w Retrofit with induction lamp, power coupler and generator

(must be 30% less watts/fixture than HID system)

$50 per fixture

HID ≥ 100w Replacement with new HID ≥ 100w $70 per fixture

Page 94: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix B Page 3 of 4

Prescriptive Lighting - LED

LED New Exit Sign Fixture Existing Facility < 75 kw Existing Facility > 75 kw

$20 per fixture $10 per fixture

LED Display Case Lighting $30 per display case

LED Shelf-Mtd. Display & Task Lights $15 per linear foot

LED Portable Desk Lamp $20 per fixture

LED Wall-wash Lights $30 per fixture

LED Recessed Down Lights $35 per fixture LED Outdoor Pole/Arm-Mounted Area

and Roadway Luminaries $175 per fixture

LED Outdoor Pole/Arm-Mounted Decorative Luminaries $175 per fixture

LED Outdoor Wall-Mounted Area Luminaries $100 per fixture

LED Parking Garage Luminaries $100 per fixture

LED Track or Mono-Point Directional Lighting Fixtures $50 per fixture

LED High-Bay and Low-Bay Fixtures for Commercial & Industrial Bldgs. $150 per fixture

LED High-Bay-Aisle Lighting $150 per fixture

LED Bollard Fixtures $50 per fixture

LED Linear Panels (2x2 Troffers only) $100 per fixture

LED Fuel Pump Canopy $100 per fixture

LED Refrigerator/Freezer case lighting replacement of fluorescent in medium

and low temperature display case

$42 per 5 foot $65 per 6 foot

Page 95: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix B Page 4 of 4

Lighting Controls – Occupancy Sensors

Wall Mounted $20 per control Remote Mounted $35 per control

Daylight Dimmers $25 per fixture Occupancy Controlled hi-low

Fluorescent Controls $25 per fixture controlled

Lighting Controls – HID or Fluorescent Hi-Bay Controls Occupancy hi-low $75 per fixture controlled Daylight Dimming $75 per fixture controlled

Daylight Dimming - office $50 per fixture controlled

Premium Motors Three-Phase Motors $45 - $700 per motor

Fractional HP Motors Electronic Communicated Motors (replacing shaded pole motors in

refrigerator/freezer cases)

$40 per electronic communicated motor

Other Equipment Incentives

Performance Lighting

$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-

2007 for New Construction and Complete Renovation

Custom Electric and Gas Equipment Incentives not prescriptive

Custom Measures

$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year

payback on estimated savings. Minimum required savings of 75,000 KWh or 1,500 Therms and a IRR of at

least 10%. Multi Measures Bonus 15%

Page 96: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

OMB No. 2060-0347

STATEMENT OF ENERGY PERFORMANCECumberland County Technical Education Center

Building ID: 2608044 For 12-month Period Ending: November 30, 20101

Date SEP becomes ineligible: N/A Date SEP Generated: February 18, 2011

FacilityCumberland County Technical EducationCenter601 Bridgeton PikeBridgeton, NJ 08302

Facility OwnerCumberland County Technical EducationCenter601 Bridgeton Avenue Bridgeton, NJ 08302

Primary Contact for this FacilityGene Mercoli601 Bridgeton Avenue Bridgeton, NJ 08302

Year Built: 1970Gross Floor Area (ft2): 120,543

Energy Performance Rating2 (1-100) N/A

Site Energy Use Summary3

Electricity - Grid Purchase(kBtu) 4,876,185 Natural Gas (kBtu)4 9,209,832 Total Energy (kBtu) 14,086,017

Energy Intensity5 Site (kBtu/ft2/yr) Source (kBtu/ft2/yr) N/A Emissions (based on site energy use) Greenhouse Gas Emissions (MtCO2e/year) N/A Electric Distribution Utility N/A National Average Comparison National Average Site EUI 120 National Average Source EUI 280 % Difference from National Average Source EUI Building Type College/University

(Campus-Level)

Stamp of Certifying Professional

Based on the conditions observed at thetime of my visit to this building, I certify that

the information contained within thisstatement is accurate.

Meets Industry Standards6 for Indoor EnvironmentalConditions:Ventilation for Acceptable Indoor Air Quality N/A Acceptable Thermal Environmental Conditions N/A Adequate Illumination N/A

Certifying ProfessionalMichael Fischetti520 South Burnt Mill Road Voorhees, NJ 08043

Notes: 1. Application for the ENERGY STAR must be submitted to EPA within 4 months of the Period Ending date. Award of the ENERGY STAR is not final until approval is received from EPA.2. The EPA Energy Performance Rating is based on total source energy. A rating of 75 is the minimum to be eligible for the ENERGY STAR.3. Values represent energy consumption, annualized to a 12-month period.4. Natural Gas values in units of volume (e.g. cubic feet) are converted to kBtu with adjustments made for elevation based on Facility zip code.5. Values represent energy intensity, annualized to a 12-month period.6. Based on Meeting ASHRAE Standard 62 for ventilation for acceptable indoor air quality, ASHRAE Standard 55 for thermal comfort, and IESNA Lighting Handbook for lighting quality.

The government estimates the average time needed to fill out this form is 6 hours (includes the time for entering energy data, Licensed Professional facility inspection, and notarizing the SEP) andwelcomes suggestions for reducing this level of effort. Send comments (referencing OMB control number) to the Director, Collection Strategies Division, U.S., EPA (2822T), 1200 Pennsylvania Ave.,NW, Washington, D.C. 20460.

EPA Form 5900-16

APPENDIX C

Page 1 of 7

Page 97: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY STAR®

Data Checklistfor Commercial Buildings

In order for a building to qualify for the ENERGY STAR, a Professional Engineer (PE) or a Registered Architect (RA) must validate the accuracy of the data underlyingthe building's energy performance rating. This checklist is designed to provide an at-a-glance summary of a property's physical and operating characteristics, as well asits total energy consumption, to assist the PE or RA in double-checking the information that the building owner or operator has entered into Portfolio Manager.

Please complete and sign this checklist and include it with the stamped, signed Statement of Energy Performance.NOTE: You must check each box to indicate that each value is correct, OR include a note.

CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES

Building Name Cumberland County

Technical Education Center Is this the official building name to be displayed inthe ENERGY STAR Registry of LabeledBuildings?

Type College/University(Campus-Level)

Is this an accurate description of the space inquestion?

Location 601 Bridgeton Pike,Bridgeton, NJ 08302

Is this address accurate and complete? Correctweather normalization requires an accurate zipcode.

Single Structure Single Facility

Does this SEP represent a single structure? SEPscannot be submitted for multiple-buildingcampuses (with the exception of acute care orchildren's hospitals) nor can they be submitted asrepresenting only a portion of a building

Technical Education Center (Other)

CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES

Gross Floor Area 120,543 Sq. Ft.

Does this square footage include all supportingfunctions such as kitchens and break rooms usedby staff, storage areas, administrative areas,elevators, stairwells, atria, vent shafts, etc. Alsonote that existing atriums should only include thebase floor area that it occupies. Interstitial(plenum) space between floors should not beincluded in the total. Finally gross floor area is notthe same as leasable space. Leasable space is asubset of gross floor area.

Number of PCs N/A(Optional) Is this the number of personal computers in thespace?

Weekly operatinghours 75Hours(Optional)

Is this the total number of hours per week that thespace is 75% occupied? This number shouldexclude hours when the facility is occupied only bymaintenance, security, or other support personnel.For facilities with a schedule that varies during theyear, "operating hours/week" refers to the totalweekly hours for the schedule most often followed.

Workers on MainShift 675(Optional)

Is this the number of employees present during themain shift? Note this is not the total number ofemployees or visitors who are in a building duringan entire 24 hour period. For example, if there aretwo daily 8 hour shifts of 100 workers each, theWorkers on Main Shift value is 100.

Page 1 of 5

APPENDIX C

Page 2 of 7

Page 98: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY STAR®

Data Checklistfor Commercial Buildings

Energy ConsumptionPower Generation Plant or Distribution Utility:

Fuel Type: Electricity

Meter: CCTEC Electric1 0329 9959 9981 (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 4.00

10/01/2010 10/31/2010 4.00

09/01/2010 09/30/2010 213.00

08/01/2010 08/31/2010 952.00

07/01/2010 07/31/2010 903.00

06/01/2010 06/30/2010 1,060.00

05/01/2010 05/31/2010 284.00

04/01/2010 04/30/2010 5.00

03/01/2010 03/31/2010 5.00

02/01/2010 02/28/2010 4.00

01/01/2010 01/31/2010 4.00

12/01/2009 12/31/2009 5.00

CCTEC Electric1 0329 9959 9981 Consumption (kWh (thousand Watt-hours)) 3,443.00

CCTEC Electric1 0329 9959 9981 Consumption (kBtu (thousand Btu)) 11,747.52

Meter: CCTEC Electric2 0329 9959 9999 (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 98,170.00

10/01/2010 10/31/2010 94,264.00

09/01/2010 09/30/2010 124,558.00

08/01/2010 08/31/2010 129,360.00

07/01/2010 07/31/2010 130,847.00

06/01/2010 06/30/2010 148,248.00

05/01/2010 05/31/2010 143,445.00

04/01/2010 04/30/2010 115,547.00

03/01/2010 03/31/2010 111,359.00

02/01/2010 02/28/2010 105,960.00

01/01/2010 01/31/2010 102,068.00

12/01/2009 12/31/2009 109,878.00

CCTEC Electric2 0329 9959 9999 Consumption (kWh (thousand Watt-hours)) 1,413,704.00

Page 2 of 5

APPENDIX C

Page 3 of 7

Page 99: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CCTEC Electric2 0329 9959 9999 Consumption (kBtu (thousand Btu)) 4,823,558.05

Meter: CCTEC Electric3 1137 2849 9949 Sign (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 439.00

10/01/2010 10/31/2010 404.00

09/01/2010 09/30/2010 479.00

08/01/2010 08/31/2010 516.00

07/01/2010 07/31/2010 449.00

06/01/2010 06/30/2010 506.00

05/01/2010 05/31/2010 486.00

04/01/2010 04/30/2010 445.00

03/01/2010 03/31/2010 519.00

02/01/2010 02/28/2010 456.00

01/01/2010 01/31/2010 445.00

12/01/2009 12/31/2009 528.00

CCTEC Electric3 1137 2849 9949 Sign Consumption (kWh (thousand Watt-hours)) 5,672.00

CCTEC Electric3 1137 2849 9949 Sign Consumption (kBtu (thousand Btu)) 19,352.86

Meter: CCTEC Electric4 1137 2849 9980 Street Light (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 193.00

10/01/2010 10/31/2010 175.00

09/01/2010 09/30/2010 160.00

08/01/2010 08/31/2010 164.00

07/01/2010 07/31/2010 129.00

06/01/2010 06/30/2010 131.00

05/01/2010 05/31/2010 124.00

04/01/2010 04/30/2010 130.00

03/01/2010 03/31/2010 163.00

02/01/2010 02/28/2010 165.00

01/01/2010 01/31/2010 185.00

12/01/2009 12/31/2009 214.00

CCTEC Electric4 1137 2849 9980 Street Light Consumption (kWh (thousand Watt-hours)) 1,933.00

CCTEC Electric4 1137 2849 9980 Street Light Consumption (kBtu (thousand Btu)) 6,595.40

Meter: CCTEC Electric5 1137 2849 9998 (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 485.00

10/01/2010 10/31/2010 325.00

09/01/2010 09/30/2010 653.00

08/01/2010 08/31/2010 638.00

Page 3 of 5

APPENDIX C

Page 4 of 7

Page 100: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

07/01/2010 07/31/2010 274.00

06/01/2010 06/30/2010 817.00

05/01/2010 05/31/2010 441.00

04/01/2010 04/30/2010 103.00

03/01/2010 03/31/2010 297.00

02/01/2010 02/28/2010 100.00

01/01/2010 01/31/2010 212.00

12/01/2009 12/31/2009 31.00

CCTEC Electric5 1137 2849 9998 Consumption (kWh (thousand Watt-hours)) 4,376.00

CCTEC Electric5 1137 2849 9998 Consumption (kBtu (thousand Btu)) 14,930.91

Meter: CCTEC ElectricTPS Hess ACE 0329 9959 9999 (kWh (thousand Watt-hours))Space(s): Entire Facility

Generation Method: Grid Purchase

Start Date End Date Energy Use (kWh (thousand Watt-hours))

11/01/2010 11/30/2010 0.00

10/01/2010 10/31/2010 0.00

09/01/2010 09/30/2010 0.00

08/01/2010 08/31/2010 0.00

07/01/2010 07/31/2010 0.00

06/01/2010 06/30/2010 0.00

05/01/2010 05/31/2010 0.00

04/01/2010 04/30/2010 0.00

03/01/2010 03/31/2010 0.00

02/01/2010 02/28/2010 0.00

01/01/2010 01/31/2010 0.00

12/01/2009 12/31/2009 0.00

CCTEC ElectricTPS Hess ACE 0329 9959 9999 Consumption (kWh (thousand Watt-hours)) 0.00

CCTEC ElectricTPS Hess ACE 0329 9959 9999 Consumption (kBtu (thousand Btu)) 0.00

Total Electricity (Grid Purchase) Consumption (kBtu (thousand Btu)) 4,876,184.74

Is this the total Electricity (Grid Purchase) consumption at this building including allElectricity meters?

Fuel Type: Natural Gas

Meter: CCTEC Gas (therms)Space(s): Entire Facility

Start Date End Date Energy Use (therms)

11/01/2010 11/30/2010 14,510.08

10/01/2010 10/31/2010 6,560.00

09/01/2010 09/30/2010 2,482.92

08/01/2010 08/31/2010 1,095.68

07/01/2010 07/31/2010 471.96

06/01/2010 06/30/2010 608.29

05/01/2010 05/31/2010 1,439.20

04/01/2010 04/30/2010 4,149.08

03/01/2010 03/31/2010 6,607.44

Page 4 of 5

APPENDIX C

Page 5 of 7

Page 101: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

02/01/2010 02/28/2010 13,296.96

01/01/2010 01/31/2010 19,073.50

12/01/2009 12/31/2009 21,803.21

CCTEC Gas Consumption (therms) 92,098.32

CCTEC Gas Consumption (kBtu (thousand Btu)) 9,209,832.00

Total Natural Gas Consumption (kBtu (thousand Btu)) 9,209,832.00

Is this the total Natural Gas consumption at this building including all Natural Gas meters?

Additional FuelsDo the fuel consumption totals shown above represent the total energy use of this building?Please confirm there are no additional fuels (district energy, generator fuel oil) used in this facility.

On-Site Solar and Wind EnergyDo the fuel consumption totals shown above include all on-site solar and/or wind power located atyour facility? Please confirm that no on-site solar or wind installations have been omitted from thislist. All on-site systems must be reported.

Certifying Professional (When applying for the ENERGY STAR, the Certifying Professional must be the same PE or RA that signed and stamped the SEP.)

Name: _____________________________________________ Date: _____________

Signature: ______________________________________ Signature is required when applying for the ENERGY STAR.

Page 5 of 5

APPENDIX C

Page 6 of 7

Page 102: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

FOR YOUR RECORDS ONLY. DO NOT SUBMIT TO EPA.

Please keep this Facility Summary for your own records; do not submit it to EPA. Only the Statement of Energy Performance(SEP), Data Checklist and Letter of Agreement need to be submitted to EPA when applying for the ENERGY STAR.

FacilityCumberland County Technical EducationCenter601 Bridgeton PikeBridgeton, NJ 08302

Facility OwnerCumberland County Technical EducationCenter601 Bridgeton Avenue Bridgeton, NJ 08302

Primary Contact for this FacilityGene Mercoli601 Bridgeton Avenue Bridgeton, NJ 08302

General InformationCumberland County Technical Education Center

Gross Floor Area Excluding Parking: (ft2) 120,543 Year Built 1970 For 12-month Evaluation Period Ending Date: November 30, 2010

Facility Space Use SummaryTechnical Education Center

Space Type

Other -College/University(Campus-Level)

Gross Floor Area(ft2) 120,543

Number of PCso N/A

Weekly operating hourso 75

Workers on Main Shifto 675

Energy Performance ComparisonEvaluation Periods Comparisons

Performance Metrics Current(Ending Date 11/30/2010)

Baseline(Ending Date 11/30/2009) Rating of 75 Target National Average

Energy Performance Rating N/A N/A 75 N/A N/A

Energy Intensity

Site (kBtu/ft2) N/A 128 0 N/A 120

Source (kBtu/ft2) N/A 233 N/A N/A 280

Energy Cost

$/year $ 323,965.60 $ 385,702.15 N/A N/A N/A

$/ft2/year $ 2.69 $ 3.20 N/A N/A N/A

Greenhouse Gas Emissions

MtCO2e/year N/A N/A N/A N/A N/A

kgCO2e/ft2/year N/A N/A N/A N/A N/A

More than 50% of your building is defined as College/University (Campus-Level). This building is currently ineligible for a rating. Please note the National Averagecolumn represents the CBECS national average data for College/University (Campus-Level). This building uses X% less energy per square foot than the CBECSnational average for College/University (Campus-Level). Notes:o - This attribute is optional.d - A default value has been supplied by Portfolio Manager.

APPENDIX C

Page 7 of 7

Page 103: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 1 of 34

Rooftop / AC UnitsTag AC-1 CU-1 EF

Unit Type Split System Air Handler Condensing Unit Exhaust

Qty 1 1 1

Location Maintenance Office Roof S-24 Automotive

Area Served Maintenance Office Maintenance Office Automotive

Manufacturer Mitsubishi Mitsubishi American Company

Model # MS-A12WA MU-A12WA-1 UVS-135Q

Serial # 8004435 8004082T -

Cooling Type DX, R-410A DX, R-410A -

Cooling Capacity (Tons) 1 1 -

Cooling Efficiency (SEER/EER)

- 13 SEER -

Heating Type - - -

Heating Input (MBH) - - -

Efficiency - -

Fuel 115/1/60 115/1/60 -

Approx Age 2008 2008

ASHRAE Service Life 15 15 15

Remaining Life 12 12

Comments Pic 8220-21 2 hp, Duty Mater E Line

MAJOR EQUIPMENT LISTConcord Engineering Group

Cumberland County Technical Education Center

Page 104: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 2 of 34

Rooftop / AC UnitsTag AC-2 CU-2 -

Unit Type Condensing Unit Hood

Qty 1 1 1

Location Nurse Roof Small Kitchen

Area Served Nurse Nurse Small Kitchen

Manufacturer Mitsubishi Mitsubishi KEES Inc.

Model # MSY-A17NA MUY-A17NA KS-100

Serial # 8001560 7002894T 0366

Cooling Type DX, R-410A DX, R-410A -

Cooling Capacity (Tons) 1.5 1.5 -

Cooling Efficiency (SEER/EER)

- 16 SEER -

Heating Type - - -

Heating Input (MBH) - - -

Efficiency - - -

Fuel 208/230-1-60 208/230-1-60 -

Approx Age 2008 2007 1996

ASHRAE Service Life 15 15 30

Remaining Life 12 11 15

Comments Pic 8220, 8222 Used only when needed.

Page 105: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 3 of 34

Rooftop / AC UnitsTag HV-1 HV-1 HV-2

Unit Type Indoor Duct Furnace Supply Fan Supply Fan

Qty 2 2 1

Location Gym Storage Gym Storage Gym Storage

Area Served Gym Gym Boys Locker Room

Manufacturer Trane Trane Trane

Model # GDNC040EDA2000AG HBAC???FBA0 HBAC200FBA0

Serial # A83DO7215 A83DO72?? A83DO7219

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air - -

Heating Input (MBH) 400 - -

Efficiency 76% - -

Fuel Natural Gas 460/60 460/60

Approx Age 1983 1983 1983

ASHRAE Service Life 15 15 15

Remaining Life (13) (13) (13)

Comments pic 8069, ECM 1 2 hp, pic 8073, ECM 1 1/2 hp, pic 8070, ECM 1

Page 106: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 4 of 34

Rooftop / AC UnitsTag HV-2 UH-1 UH-3

Unit Type Indoor Duct Furnace Unit Heater Unit Heater

Qty 1 1 1

Location Gym Storage Gym Storage Health

Area Served Boys Locker Room Gym Storage Health

Manufacturer Trane Trane Trane

Model # Series GDNC - -

Serial # A83DO72?? - -

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Electric Electric

Heating Input (MBH) 175 3.3 kW 5.8kW

Efficiency 76% 98% 95%

Fuel Natural Gas 277/1/60 480/3/60

Approx Age 1983 1983 1983

ASHRAE Service Life 15 15 15

Remaining Life (13) (13) (13)

Comments ECM 2 Pic 8071 Pic 8079

Page 107: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 5 of 34

Rooftop / AC UnitsTag - - EF-2

Unit Type Hood Hood Kitchen Exhaust

Qty 1 1 1

Location Culinary Arts & Hospitality

Culinary Arts & Hospitality Roof

Area Served Culinary Arts & Hospitality

Culinary Arts & Hospitality

Culinary Arts & Hospitality

Manufacturer GREENHECK GREENHECK GREENHECK

Model # GHCW-11.50-S GHCW-11.50-S CUBE-240-20-S

Serial # 04H16550 04H22415 04H26318

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type - - -

Heating Input (MBH) - - -

Efficiency - - -

Fuel - - -

Approx Age 2004 2004 2004

ASHRAE Service Life 30 30 20

Remaining Life 23 23 13

Comments ITEM KH-1-2A, 150 CFM/FT

ITEM KH-2-2A, 150 CFM/FT

2 hp

Page 108: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 6 of 34

Rooftop / AC UnitsTag - - EF-1

Unit Type Hood Hood Kitchen Exhaust

Qty 1 1 1

Location Culinary Arts & Hospitality

Culinary Arts & Hospitality Roof

Area Served Culinary Arts & Hospitality

Culinary Arts & Hospitality

Culinary Arts & Hospitality

Manufacturer GREENHECK GREENHECK GREENHECK

Model # GHCW-11.50-S GHCW-11.50-S CUBE-200-30-S

Serial # 04H19530 04H17594 04H26304

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type - - -

Heating Input (MBH) - - -

Efficiency - - -

Fuel - - -

Approx Age 2004 2004 2004

ASHRAE Service Life 30 30 20

Remaining Life 23 23 13

Comments ITEM KH-1-1A, 150 CFM/FT

ITEM KH-2-1A, 150 CFM/FT

3 hp

Page 109: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 7 of 34

Rooftop / AC UnitsTag MAU-1 MAU-2A -

Unit Type Make Up Air Make Up Air -

Qty 1 1 -

Location Roof Roof -

Area Served Culinary Arts & Hospitality Hood

Culinary Arts & Hospitality Hood -

Manufacturer Greenheck Greenheck -

Model # DG-115-H20-BD DGX-115-H22-DB -

Serial # 04H23963 04H31113 -

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Non-recirculating Direct Fired

Non-recirculating Direct Fired -

Heating Input (BTU/Hr) 351,100 405,100 -

Efficiency 80% 80% -

Fuel Natural Gas Natural Gas -

Approx Age 2004 2004 -

ASHRAE Service Life 15 15 -

Remaining Life 8 8 -

Comments S/A 5 HP, 460/3/60, 6000 CFM

-

Page 110: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 8 of 34

Rooftop / AC UnitsTag HV-3 HV-1 HV-5 (RTU)

Unit Type Heat & Ventilation Packaged RTU Packaged RTU

Qty 1 1 1

Location Roof Roof Roof

Area Served Girls Locker Business Office Board Office

Manufacturer Trane Trane Trane

Model # GRNC120FHA29C1A YSC048A4RMA2MD YCD091D4HOBE

Serial # A83DO7220 651102587L M371011170

Cooling Type - DX, R-22 DX, R-22

Cooling Capacity (Tons) - 4 8

Cooling Efficiency (SEER/EER)

- 10 SEER 10.1 EER

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 200 80 205

Efficiency 77% 80% 80.5%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1983 2006 1997

ASHRAE Service Life 15 15 15

Remaining Life (13) 10 1

Comments 460/3/60, 540 watts power consumption, Pic 8162-64, ECM 2

460/3/60, Pic 8165-67 460/3/60, Pic 8169, ECM3

Page 111: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 9 of 34

Rooftop / AC UnitsTag HV-4 SF-1 -

Unit Type Heat & Ventilation Supply Fan -

Qty 1 1 -

Location Roof Roof -

Area Served Automotive, ATV & Motorcycle Servicing Resturaunt Carreers -

Manufacturer Trane Cook -

Model # GRNC020FHA29U1A 120 KSPB -

Serial # A83DO7221 289S4689240000019010497 -

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air - -

Heating Input (MBH) 300 - -

Efficiency 77% - -

Fuel Natural Gas 115/1/60 -

Approx Age 1983 1989 -

ASHRAE Service Life 15 20 -

Remaining Life (13) (2) -

Comments 460/3/60, 725 watts power consumption, Pic 8174, ECM 2

1/3 hp, 1725 rpm -

Page 112: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 10 of 34

Rooftop / AC UnitsTag HV HV HV

Unit Type Heat & Ventilation Heat & Ventilation

Qty 1 1 1

Location Roof Roof Roof

Area Served East Wing East Wing East Wing

Manufacturer Sterling Radiator Trane Sterling Radiator

Model # PV-300-B GRAA25PFKB0N1CQ105T0C PV-300-B

Serial # 1808-91-4 A97E37117 1810-91-4

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 300 250 300

Efficiency 75% 80% 75%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1992 1997 1992

ASHRAE Service Life 15 15 15

Remaining Life (4) 1 (4)

Comments Pic 8212, 460/3/60, 875 watts Power Consumption, ECM 2

Pic 8189, ECM 2 Pic 8213, 460/3/60, 875 watts Power Consumption, ECM 2

Page 113: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 11 of 34

Rooftop / AC UnitsTag RTU HV CU

Unit Type Packaged RTU Heat & Ventilation Condensing Unit

Qty 1 1 1

Location Roof Roof Roof

Area Served East Wing East Wing East Wing

Manufacturer Trane Sterling Radiator Trane

Model # YSC120A4RHA3DD PV-300-B TTA150B400BC

Serial # 920101610L 1809-91-4 M2511HLAH

Cooling Type DX, R-22 - DX, R-22

Cooling Capacity (Tons) 10 - 12.5

Cooling Efficiency (SEER/EER)

10.2 EER - 8.0 EER

Heating Type Forced Air Forced Air -

Heating Input (MBH) 250 300 -

Efficiency 80% 75% -

Fuel Natural Gas Natural Gas -

Approx Age 2009 1992 1997

ASHRAE Service Life 15 15 15

Remaining Life 13 (4) 1

Comments 460/3/60, Pic 8192, 8216 Pic 8214-15, 460/3/60, 875 watts Power Consumption, ECM 2

460/3/60, Pic 8195, ECM 4

Page 114: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 12 of 34

Rooftop / AC UnitsTag RMU-1 RMU-2 RTU

Unit Type Multi Deck Multi Deck Packaged RTU

Qty 1 1 1

Location East Wing Roof South Wing Roof South Roof

Area Served NE Main SE Main South Wing

Manufacturer Mechanical Specialties Inc.

Mechanical Specialties Inc. Trane

Model # RMA100NG5C2207BB06A170100BC10

RMA100NG6C2407CB05A170100BC10 YCD121B4H0DB

Serial # 0911-0005 0911-0006 J49100269D

Cooling Type DX, R22 DX, R22 DX, R22

Cooling Capacity (Tons) 22 24 10

Cooling Efficiency (SEER/EER)

5.2 EER 5.1 EER 10 EER

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 500 540 250

Efficiency 75% 75% 80.5%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1970 1970 1994

ASHRAE Service Life 15 15 15

Remaining Life (26) (26) (2)

Comments Pic 8197, 460/3/60, 7.5 hp, MO 51018, ECM 5

Pic 8198, 460/3/60, 7.5 hp, MO 51018, ECM 5

Pic 8201-3, 460/3/60, ECM 3

Page 115: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 13 of 34

Rooftop / AC UnitsTag HV HV HV

Unit Type Heat & Ventilation Heat & Ventilation Heat & Ventilation

Qty 1 1 1

Location Roof Roof Roof

Area Served South Wing South Wing South Wing

Manufacturer Sterling Radiator Sterling Radiator Sterling Radiator

Model # PV-400-B PV-300-B PV-400-B

Serial # 1812-91-4 0184-92-4 1813-91-4

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 400 300 400

Efficiency 75% 75% 75%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1991 1992 1991

ASHRAE Service Life 15 15 15

Remaining Life (5) (4) (5)

Comments Pic 8204, 460/3/60, 1080 watts Power Consumption, ECM 2

Pic 8205, 460/3/60, 875 watts Power Consumption, ECM 2

Pic 8206, 460/3/60, 1080 watts Power Consumption, ECM 2

Page 116: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 14 of 34

Rooftop / AC UnitsTag HV HV HV

Unit Type Heat & Ventilation Heat & Ventilation Heat & Ventilation

Qty 1 1 1

Location Roof Roof Roof

Area Served South Wing South Wing South Wing

Manufacturer Sterling Radiator Sterling Radiator Sterling Radiator

Model # PV-300-B PV-400-B PV-300-B

Serial # 0186-92-4 1811-91-4 0185-92-4

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 300 400 300

Efficiency 75% 75% 75%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1992 1991 1992

ASHRAE Service Life 15 15 15

Remaining Life (4) (5) (4)

Comments Pic 8207, 460/3/60, 875 watts Power Consumption, ECM 2

Pic 8210, 460/3/60, 1080 watts Power Consumption, ECM 2

Pic 8211, 460/3/60, 875 watts Power Consumption, ECM 2

Page 117: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 15 of 34

Rooftop / AC UnitsTag HV HP RMU-3

Unit Type Heat & Ventilation Heat Pump Multi Deck

Qty 1 1 1

Location Roof Roof Roof

Area Served West Wing Computer Room SW Main

Manufacturer Sterling Radiator York International Mechanical Specialties Inc.

Model # PV-250-B B3CH060A46C RMA100NG5C2207CB05A170100BC10

Serial # 1806-91-4 (S)NGH14090732 0911-0007

Cooling Type - DX, R22 DX, R22

Cooling Capacity (Tons) - 5 22

Cooling Efficiency (SEER/EER)

- 10 SEER, 9 EER 5.3 EER

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 250 59 MBH @ 47°F, 17.4 kW

500

Efficiency 75% 7.0 HSPF 75%

Fuel Natural Gas Electric Natural Gas

Approx Age 1991 1999 1970

ASHRAE Service Life 15 15 15

Remaining Life (5) 3 (26)

Comments Pic 8217, 460/3/60, 800 watts Power Consumption, ECM 2

Pic 8218-19 Pic 8223, 460/3/60, 7.5 hp, MO 51018, ECM 5

Page 118: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 16 of 34

Rooftop / AC UnitsTag RMU-4 HV HV

Unit Type Multi Deck Heat & Ventilation Heat & Ventilation

Qty 1 1 1

Location West Roof Roof Roof

Area Served NW Main West Wing West Wing

Manufacturer Mechanical Specialties Inc. Sterling Radiator Sterling Radiator

Model # RMA100NG5C2207BB05A170100BC10 PV-300-B PV-250-B

Serial # 0911-0008 0785-93-4 0790-93-4

Cooling Type DX, R22 - -

Cooling Capacity (Tons) 22 - -

Cooling Efficiency (SEER/EER)

5.3 EER - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 500 300 250

Efficiency 75% 75% 75%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1970 1993 1993

ASHRAE Service Life 15 15 15

Remaining Life (26) (3) (3)

Comments Pic 8224, 460/3/60, 7.5 hp, MO 51018, ECM 5

Pic 8225, 460/3/60, 875 watts Power Consumption, ECM 2

Pic 8226, 460/3/60, 800 watts Power Consumption, ECM 2

Page 119: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 17 of 34

Rooftop / AC UnitsTag HV HV RTU

Unit Type Heat & Ventilation Heat & Ventilation Packaged RTU

Qty 1 1 1

Location Roof Roof Roof

Area Served West Wing West Wing West Wing

Manufacturer Sterling Radiator Sterling Radiator Trane

Model # PV-250-B PV-300-G4N YSC120A4RHA3DD

Serial # 0789-93-4 0787-93-4 920101616L

Cooling Type - - DX, R-22

Cooling Capacity (Tons) - - 10

Cooling Efficiency (SEER/EER)

- - 10.2 EER

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 250 300 250

Efficiency 75% 75% 80%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1993 1993 2009

ASHRAE Service Life 15 15 15

Remaining Life (3) (3) 13

Comments Pic 8227, 460/3/60, 800 watts Power Consumption, ECM 2

Pic 8228, 460/3/60, 875 watts Power Consumption, ECM 2

460/3/60, Pic 8229

Page 120: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 18 of 34

Rooftop / AC UnitsTag HV HV HV

Unit Type Heat & Ventilation Heat & Ventilation Heat & Ventilation

Qty 1 1 1

Location Roof Roof Roof

Area Served West Wing West Wing West Wing

Manufacturer Sterling Radiator Sterling Radiator Sterling Radiator

Model # PV-300-G4N PV-250-B PV-300-G4N

Serial # 0786-93-4 0791-93-4 0788-93-4

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 300 250 300

Efficiency 75% 75% 75%

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 1993 1993 1993

ASHRAE Service Life 15 15 15

Remaining Life (3) (3) (3)

Comments Pic 8230, 460/3/60, 875 watts Power Consumption, ECM 2

Pic 8231, 460/3/60, 800 watts Power Consumption, ECM 2

Pic 8232, 460/3/60, 875 watts Power Consumption, ECM 2

Page 121: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 19 of 34

Rooftop / AC UnitsTag F F F

Unit Type Furnace Furnace Furnace

Qty 1 1 1

Location W-13 Plumbing W-13 Plumbing W-13 Plumbing

Area Served Classroom Classroom Classroom

Manufacturer Carrier Payne Therm Pride

Model # 58MXA060-F-15112 PG8UAA036065 OH5-85

Serial # 2901A17102 3301A66987 V-446382

Cooling Type DX - R22 or R410A - -

Cooling Capacity (Tons) 5 - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 60 66 106.25

Efficiency 93.1% 80.3% 80%

Fuel Natural Gas Natural Gas Oil

Approx Age 2001 2001 1983

ASHRAE Service Life 15 15 15

Remaining Life 5 5 (13)

Comments Classroom Demonstration unit

Classroom Demonstration unit

Classroom Demonstration unit

Page 122: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 20 of 34

Rooftop / AC UnitsTag F CU F

Unit Type Furnace Condensing Unit Furnace

Qty 1 1 1

Location W-13 Plumbing W-13 Plumbing W-13 Plumbing

Area Served Classroom Classroom Classroom

Manufacturer Carrier Corp Heat Controller Hallmark

Model # 58CLA120-10120 HP1024-1A HBD85

Serial # 1903V50874 94D404081 536104

Cooling Type - - -

Cooling Capacity (Tons) - - -

Cooling Efficiency (SEER/EER)

- - -

Heating Type Forced Air Forced Air Forced Air

Heating Input (MBH) 0.85 gph - 105 MBH, 0.75 gph

Efficiency 81% - 81.4%

Fuel #2 Oil 208/230 #2 Oil

Approx Age 2003 1994 1998

ASHRAE Service Life 15 15 15

Remaining Life 7 (2) 2

Comments Becket AFG-F3, Classroom Demonstration unit

Classroom Demonstration unit

Becket AFG, Classroom Demonstration unit

Page 123: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 21 of 34

Rooftop / AC UnitsTag CU CU CU

Unit Type Condensing Unit Condensing Unit Condensing Unit

Qty 1 1 1

Location Grade adjacent to W-13 Plumbing

Grade adjacent to W-13 Plumbing

Grade adjacent to W-13 Plumbing

Area Served Class room W-13 Class room W-13 Class room W-13

Manufacturer Carrier Corp. Goodman Mfg. Corp.

Model # 38TZA030320 PA10JA036-A CKT30-1B

Serial # 2400E07151 2101E29791 9804551015

Cooling Type DX R410A DX R410A DX R22

Cooling Capacity (Tons) 2.5 3.0 2.5

Cooling Efficiency (SEER/EER)

10.6 EER 10 SEER / 9.3 EER 12 SEER / 11 EER

Heating Type - - -

Heating Input (MBH) - - -

Efficiency - - -

Fuel 208/230-1 - 208/230

Approx Age 2000 2000 1998

ASHRAE Service Life 15 15 15

Remaining Life 4 4 2

Comments Classroom Demonstration unit

Classroom Demonstration unit

Classroom Demonstration unit

Page 124: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 22 of 34

Rooftop / AC UnitsTag CU F -

Unit Type Condensing Unit Furnace -

Qty 1 1 -

Location Class room W-13 Class room W-13 -

Area Served Class room W-13 Class room W-13 -

Manufacturer Nordyne Nordyne -

Model # JS5BD-024KB FG7SA 072C-24B -

Serial # JSF090100169 FGD080805547 -

Cooling Type DX R22 - -

Cooling Capacity (Tons) 2.0 - -

Cooling Efficiency (SEER/EER)

13 SEER / 11.5 EER - -

Heating Type - Forced Air -

Heating Input (MBH) - 72 -

Efficiency - 80% -

Fuel - Natural Gas -

Approx Age 2000 2008 -

ASHRAE Service Life 15 15 -

Remaining Life 4 12 -

Comments Classroom Demonstration unit

Classroom Demonstration unit

-

Page 125: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 23 of 34

BoilersTag Boiler Boiler Boiler

Unit Type Water Water Water

Qty 1 1 1

Location W-13 Plumbing W-13 Plumbing W-13 Plumbing

Area Served Classroom Classroom Classroom

Manufacturer Burnham Corp. Axeman-Anderson Weil McLain

Model # P203PVWNI 74P0 WGO-3

Serial # 17423055 - 550201172

Input Capacity (MBH) 62 86.1 0.95 gph

Rated Output Capacity (MBH) 51 - 115

Approx. Efficiency % 82.2% - 85.3%

Fuel Natural Gas Oil #2 Oil

Approx Age 1996 - -

ASHRAE Service Life 30 30 30

Remaining Life 15 - -

Comments (4) Taco 1/25hp zone circulator pumps, Classroom Demonstration unit

Sun Ray Burner Mfg. Corp.Model FC Burner MP-103, Classroom

Beckett GO-3, Classroom Demonstration unit

MAJOR EQUIPMENT LISTConcord Engineering Group

Cumberland County Technical Education Center

Page 126: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 24 of 34

BoilersTag Boiler - -

Unit Type Cast Iron Water boiler - -

Qty 1 - -

Location Greenhouse - -

Area Served Greenhouse - -

Manufacturer Weil McLain - -

Model # 478 series 1 - -

Serial # 67434 - -

Input Capacity (MBH) 3.4 gph Lt oil / 494 MBH - -

Rated Output Capacity (MBH) 400 - -

Approx. Efficiency % 82.2% - -

Fuel Oil / Natural Gas - -

Approx Age 1995 - -

ASHRAE Service Life 30 - -

Remaining Life 14 - -

Comments - -

Page 127: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 25 of 34

Domestic Water HeatersTag WH-1 WH-2 T-1

Unit Type Water Tube Boiler Water Tube Boiler Insulated Tank

Qty 1 1 1

Location Mechanical Room Mechanical Room Mechanical Room

Area Served Building Domestic Water

Building Domestic Water

Building Domestic Water

Manufacturer A. O. Smith A. O. Smith A. O. Smith

Model # GW-500 200 GW-500 200 GWT-500ASV0N100001

Serial # D 03 72879 E-03 73655 SL03-101934-5 SK030000433

Size (Gallons) 10,000

Input Capacity (MBH/KW)

500 MBH 500 MBH -

Recovery (Gal/Hr) -

Efficiency % 83.7% 83.7% -

Fuel Natural Gas Natural Gas Natural Gas

Approx Age 2003 2003 2003

ASHRAE Service Life 30 30 20

Remaining Life 22 22 12

Comments Part No: GW 500 E22N400000 NJ 000043141-07H

Part No: GW 500 E22N100000 NJ 000043140-07H

Item id: 9500007348 NJ 118018-104 SV Cap 2289000BTU/Hr

MAJOR EQUIPMENT LISTConcord Engineering Group

Cumberland County Technical Education Center

Page 128: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 26 of 34

Domestic Hot Water HeatersTag T-2 - -

Unit Type Tank - -

Qty 1 - -

Location Mechanical Room - -

Area Served Building Domestic Water - -

Manufacturer Quaker City Iron Works - -

Model # R-4569 - -

Serial # Nat'l BD No: 7568 - -

Size (Gallons) 5,680 - -

Input Capacity (MBH/KW)

- - -

Recovery (Gal/Hr) - - -

Efficiency % - - -

Fuel - - -

Approx Age 1971 - -

ASHRAE Service Life 50 - -

Remaining Life 10 - -

Comments Nat'l BD No: 7568, Non-insulated

- -

Page 129: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 27 of 34

Domestic Hot Water HeatersTag WH WH WH

Unit Type Tank Tank Tank

Qty 1 1 1

Location W-13 Plumbing W-13 Plumbing W-13 Plumbing

Area Served Classroom Classroom Classroom

Manufacturer American Water Heater Group

American Water Heater Group Kenmore

Model # PVG52-40T50-3NV E52-40R-045DV Power Miser 9

Serial # 9624109027 9615171435 -

Size (Gallons) 40 40 -

Input Capacity (MBH/KW)

50 MBH 3.38 / 4.5 kW -

Recovery (Gal/Hr) - - -

Efficiency % - - 80%

Fuel Natural Gas 208/1 , 240/1 Natural Gas

Approx Age 2007 2008 -

ASHRAE Service Life 12 12 12

Remaining Life 8 9 -

Comments Classroom Demonstration unit

Classroom Demonstration unit

Classroom Demonstration unit

Page 130: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 28 of 34

Domestic Hot Water HeatersTag WH WH WH

Unit Type Tank Tank Booster

Qty 1 1 1

Location W-13 Plumbing W-13 Plumbing Lg. Kitchen

Area Served Classroom Classroom Dishwasher

Manufacturer Bock Corp. Burnham Hatco

Model # 21E PAL-26 C-12

Serial # 1271834 08011509 1583179611

Size (Gallons) 20 26 6

Input Capacity (MBH/KW)

84000 12 kW

Recovery (Gal/Hr) 88 69 gph @ 70°F

Efficiency % 98%

Fuel Natural Gas 115/1/60 480/3/60

Approx Age 2007 2008 1983

ASHRAE Service Life 12 12 12

Remaining Life 8 9 (16)

Comments Classroom Demonstration unit

Classroom Demonstration unit

Page 131: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix DPage 29 of 34

PumpsTag P-1, P-2 P-3 -

Unit Type Domestic Circulator Domestic Circulator -

Qty 2 1 -

Location Mechanical Room Mechanical Room -

Area Served Domestic Water Boiler Domestic Water Circulator -

Manufacturer TACO Bell & Gossett -

Model # 0012-BF4-1 PL-55B -

Serial # - 1BL068 K30 -

Horse Power 1/8 500 Watt -

Flow - - -

Motor Info - - -

Electrical Power 115/1/60 115/1/60 -

RPM 3250 3250 -

Motor Efficiency % - - -

Approx Age 2003 2003 -

ASHRAE Service Life 10 10 -

Remaining Life 2 2 -

Comments - - -

MAJOR EQUIPMENT LISTConcord Engineering Group

Cumberland County Technical Education Center

Page 132: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Misc. Equipment

Tag VP-1 - -

Unit Type Vacuum Pump Vacuum Tank Air Compressor

Qty 1 1 1

Location Mechanical Room Mechanical Room Mechanical Room

Area Served - - Dental air system

Manufacturer Ramvav Ramvav Air Technologies

Model # 826E.0800.1 575080 AS50

Serial # BN0810120 IT0809108 509748

Horse Power - - -

Flow - - -

Motor Info - - (2) 1-1/2 hp

Electrical Power - - 208-230-1-60

RPM - - 1650

Motor Efficiency % - - -

Approx Age 2008 2008 2008

ASHRAE Service Life 15 15 18

Remaining Life 12 12 15

Comments CCTEC 00920 - motor s/n 850-034109, 850-034110

MAJOR EQUIPMENT LISTConcord Engineering Group

Cumberland County Technical Education Center

Page 133: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Misc. Equipment

Tag -

Unit Type Air Compressor Generator Roll Up Door

Qty 1 1

Location Mechanical Room Mechanical Room Varies

Area Served - Bldg Emergency Power Varies

Manufacturer Ingersol Rand ONAN Lift Master

Model # 2475N7.5 55 0 KB 15R / 1699P MJ-1211

Serial # 0407290050 117.1343221 223-A3-38405

Horse Power 5 - 1/2

Flow 24 cfm - -

Motor Info s/n E0406254638 - AO Smith

Electrical Power 460/3/60 3 ph: 55 kW, 69 KVA 1ph: 37 kW, 46 KVA 115/1/60

RPM 1500 1800 1000

Motor Efficiency % - - -

Approx Age - - -

ASHRAE Service Life 15 - -

Remaining Life - - -

Comments 80 Gallon Tank, NJ 118019-10U

CCVTC 00000133, m/n V401, S/n 124349 -

Page 134: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Misc. Equipment

Tag - - -

Unit Type Dust Collector Air Cleaner UPS

Qty 1 2 1

Location Grade adjacent to W-13 Carpentry W-11 Plumbing -

Area Served W-13 Carpentry W-11 Plumbing -

Manufacturer Donaldson Company Limited Air Specialists, Inc. Unisys

Model # 24 CVC Smokeeter UP1410-0

Serial # LG701535 - 4278 2477 6

Horse Power 7.5 - -

Flow - -

Motor Info - - -

Electrical Power 208-460/60 -

Input: 240v/1/60, PF 0.95 Output:

120/208/240, 10 KVA

RPM 3450 - -

Motor Efficiency % - - -

Approx Age - - -

ASHRAE Service Life 18 15 -

Remaining Life - - -

Comments

Page 135: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Misc. Equipment

Tag - - -

Unit Type Air Compressor Air Cleaner Air Purefier

Qty 1 2 1

Location Shed at end of South Wing E-41 Adult Cosmetology E-41 Adult

Cosmetology

Area Served Automotive Shop Air E-41 Adult Cosmetology E-41 Adult Cosmetology

Manufacturer Ingersol Industrial Compressor Crystal-Aire Com Air

Model # - - Eagle 5000

Serial # - - 65875

Horse Power 25 - -

Flow - -

Motor Info Baldor cat.No. 42531T, 284T Frame - -

Electrical Power 460-3-60 - -

RPM 1750 - -

Motor Efficiency % 88.5% - -

Approx Age 1971 - -

ASHRAE Service Life 20 15 15

Remaining Life (20) - -

Comments NJ118020-IDU, ECM#6 - Ozone Generator

Page 136: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Misc. Equipment

Tag - - -

Unit Type Hair Dryer Paint Booth -

Qty 6 1 -

Location - Auto Collision Repair -

Area Served - Auto Collision Repair -

Manufacturer Pibbs Industries SAIMA of North America -

Model # HM1500 ACCUDRAFT 2001 -

Serial # 16327 A6323 -

Horse Power - 40 -

Flow (CFM) - 20,000 -

Motor Info - - -

Electrical Power - 220/3/60 -

RPM - - -

Motor Efficiency % - 90.2% -

Approx Age - 1991 -

ASHRAE Service Life - 18 -

Remaining Life - (2) -

Comments NJ118020-IDU 750 hrs/yr Ozone Generator

Page 137: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-11 of 9

CEG Job #: 9C10088

Project: Cumberland County Tech Ed Center KWH COST: $0.156

601 Bridgeton Ave.

Bridgeton, NJBldg. Sq. Ft.

ECM #1: Lighting Upgrade - GeneralEXISTING LIGHTING PROPOSED LIGHTING SAVINGS

CEG Fixture Yearly No. No. Fixture Fixt Total kWh/Yr Yearly No. No. Retro-Unit Watts Total kWh/Yr Yearly Unit Cost Total kW kWh/Yr Yearly Yearly SimpleType Location Usage Fixts Lamps Type Watts kW Fixtures $ Cost Fixts Lamps Description Used kW Fixtures $ Cost (INSTALLED) Cost Savings Savings $ Savings Payback

242.21 2600 20 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 2.14 5,564.0 $867.98 20 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 1.96 5096 $794.98 $28.00 $560.00 0.18 468 $73.01 7.67

221.11 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

211.11 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

222.21 2600 24 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.49 3,868.8 $603.53 24 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 1.20 3120 $486.72 $14.00 $336.00 0.29 748.8 $116.81 2.88

221.11 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

211.11 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

242.21 2600 14 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 1.50 3,894.8 $607.59 14 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 1.37 3567.2 $556.48 $28.00 $392.00 0.13 327.6 $51.11 7.67

221.14 2600 1 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.06 150.8 $23.52 1 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.05 130 $20.28 $14.00 $14.00 0.01 20.8 $3.24 4.31

222.21 CST 2600 12 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.74 1,934.4 $301.77 12 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.60 1560 $243.36 $14.00 $168.00 0.14 374.4 $58.41 2.88

221.11 Back Office 2600 4 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.25 644.8 $100.59 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 520 $81.12 $14.00 $56.00 0.05 124.8 $19.47 2.88

232.21 2600 27 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 2.32 6,037.2 $941.80 27 3 Relamp - Sylvania Lamp FO28/841/SS/ECO 72 1.94 5054.4 $788.49 $21.00 $567.00 0.38 982.8 $153.32 3.70

617 2600 3 1 Hood Light w/Globe & Cage, 100w A19 Lamp 100 0.30 780.0 $121.68 3 1 (1) 26w CFL Lamp 26 0.08 202.8 $31.64 $20.00 $60.00 0.22 577.2 $90.04 0.67

221.111 2600 22 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Vapor Tite

62 1.36 3,546.4 $553.24 22 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 1.10 2860 $446.16 $14.00 $308.00 0.26 686.4 $107.08 2.88

221.11 Wash Area 2600 6 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.37 967.2 $150.88 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.07 187.2 $29.20 2.88

E43 Classroom, Closet, Lockers

E45 Classroom, Closet

Food Services Classroom

Cumberland County Tech Ed Center

120,543

E41 Classroom, Closet, Lockers

Page 138: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-12 of 9

221.11 Food Storage 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

242.21 2600 32 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 3.42 8,902.4 $1,388.77 32 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 3.14 8153.6 $1,271.96 $28.00 $896.00 0.29 748.8 $116.81 7.67

221.14 2600 6 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.35 904.8 $141.15 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.05 124.8 $19.47 4.31

211.11 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

227.21 2600 6 22x2, 2 Lamp, 32w 700 series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens65 0.39 1,014.0 $158.18 6 2 Sylvania Lamp

FBO30/841XP/6//SS/ECO 49 0.29 764.4 $119.25 $24.00 $144.00 0.10 249.6 $38.94 3.70

232.21 2600 5 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 0.43 1,118.0 $174.41 5 3 Relamp - Sylvania Lamp FO28/841/SS/ECO 72 0.36 936 $146.02 $21.00 $105.00 0.07 182 $28.39 3.70

222.11 2600 10 22x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.62 1,612.0 $251.47 10 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.50 1300 $202.80 $14.00 $140.00 0.12 312 $48.67 2.88

221.11 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

3520 Restroom 1200 1 2 Ceiling Mount White Globe, (2) 100w A Lamp 200 0.20 240.0 $37.44 1 2 26w CFL Lamp 52 0.05 62.4 $9.73 $30.00 $30.00 0.15 177.6 $27.71 1.08

242.22 Conference Room 2600 8 42x4, 4 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

104 0.83 2,163.2 $337.46 8 4 Relamp - Sylvania Lamp FO28/841/SS/ECO 98 0.78 2038.4 $317.99 $28.00 $224.00 0.05 124.8 $19.47 11.51

222.21 Business Office 2600 14 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.87 2,256.8 $352.06 14 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.70 1820 $283.92 $14.00 $196.00 0.17 436.8 $68.14 2.88

766 2600 12 1 400w MH, Prismatic Lens 465 5.58 14,508.0 $2,263.25 12 4 2x4 54w T5HO 4 Lamp w/Reflective Lens, Wire Cage 236 2.83 7363.2 $1,148.66 $240.00 $2,880.00 2.75 7144.8 $1,114.59 2.58

602 8760 2 2 Incandescent Exit Sign 20 0.04 350.4 $54.66 2 1 LED Exit Sign 2 0.00 35.04 $5.47 $65.00 $130.00 0.04 315.36 $49.20 2.64

221.14 Boy's Locker Room 2600 14 2

1x4, 2 Lamp, 32w T8, Elect. Ballast, Surface Mnt., No

Lens58 0.81 2,111.2 $329.35 14 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.70 1820 $283.92 $14.00 $196.00 0.11 291.2 $45.43 4.31

222.21 Gym Office 2600 4 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.25 644.8 $100.59 4 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.20 520 $81.12 $14.00 $56.00 0.05 124.8 $19.47 2.88

221.14 Custodial Closet 2600 1 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.06 150.8 $23.52 1 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.05 130 $20.28 $14.00 $14.00 0.01 20.8 $3.24 4.31

221.14 Mechanical Room 2600 4 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.23 603.2 $94.10 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 520 $81.12 $14.00 $56.00 0.03 83.2 $12.98 4.31

221.14 Gym Storage 1200 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 139.2 $21.72 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 120 $18.72 $14.00 $28.00 0.02 19.2 $3.00 9.35

222.21 E58 Classroom 2600 6 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.37 967.2 $150.88 6 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.07 187.2 $29.20 2.88

Gym

E51 Dining, Food Prep, Lockers

Superintendents Office

Page 139: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-13 of 9

211.11 4400 32 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 1.06 4,646.4 $724.84 32 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.80 3520 $549.12 $7.00 $224.00 0.26 1126.4 $175.72 1.27

222.21 4400 4 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.25 1,091.2 $170.23 4 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.20 880 $137.28 $14.00 $56.00 0.05 211.2 $32.95 1.70

602 8760 3 2 Incandescent Exit Sign 20 0.06 525.6 $81.99 3 1 LED Exit Sign 2 0.01 52.56 $8.20 $65.00 $195.00 0.05 473.04 $73.79 2.64

221.11 Girl's Locker Room 2600 16 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.99 2,579.2 $402.36 16 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.80 2080 $324.48 $14.00 $224.00 0.19 499.2 $77.88 2.88

222.21 Girl's Office 1200 4 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.25 297.6 $46.43 4 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.20 240 $37.44 $14.00 $56.00 0.05 57.6 $8.99 6.23

221.11 Men's Restroom 2600 4 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.25 644.8 $100.59 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 520 $81.12 $14.00 $56.00 0.05 124.8 $19.47 2.88

221.11 Office 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

221.34 2600 62 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.60 9,349.6 $1,458.54 62 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 3.10 8060 $1,257.36 $14.00 $868.00 0.50 1289.6 $201.18 4.31

221.14 2600 10 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.58 1,508.0 $235.25 10 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.50 1300 $202.80 $14.00 $140.00 0.08 208 $32.45 4.31

221.14 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.34 2600 44 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.55 6,635.2 $1,035.09 44 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.20 5720 $892.32 $14.00 $616.00 0.35 915.2 $142.77 4.31

221.11 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

221.11 2600 5 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.31 806.0 $125.74 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.06 156 $24.34 2.88

221.34 E48 Cafeteria 2600 48 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.78 7,238.4 $1,129.19 48 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.40 6240 $973.44 $14.00 $672.00 0.38 998.4 $155.75 4.31

221.34 Vending 2600 6 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.35 904.8 $141.15 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.05 124.8 $19.47 4.31

222.21 2600 30 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.86 4,836.0 $754.42 30 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 1.50 3900 $608.40 $14.00 $420.00 0.36 936 $146.02 2.88

617 2600 2 1 Hood Light w/Globe & Cage, 100w A19 Lamp 100 0.20 520.0 $81.12 2 1 (1) 26w CFL Lamp 26 0.05 135.2 $21.09 $20.00 $40.00 0.15 384.8 $60.03 0.67

221.34 Kitchen Storage 1200 6 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.35 417.6 $65.15 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 360 $56.16 $14.00 $84.00 0.05 57.6 $8.99 9.35

221.34 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.06 69.6 $10.86 1 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.05 60 $9.36 $14.00 $14.00 0.01 9.6 $1.50 9.35

East Corridor

E52 Classroom, Mezzanine,

Lockers

E50 Classroom, Mezzanine,

Lockers

Kitchen

Page 140: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-14 of 9

221.11 Lockers 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

222.21 E44 Faculty Dining 2600 11 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.68 1,773.2 $276.62 11 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.55 1430 $223.08 $14.00 $154.00 0.13 343.2 $53.54 2.88

221.21 Copy Room 2600 4 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

58 0.23 603.2 $94.10 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 520 $81.12 $14.00 $56.00 0.03 83.2 $12.98 4.31

221.34 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.06 69.6 $10.86 1 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.05 60 $9.36 $14.00 $14.00 0.01 9.6 $1.50 9.35

211.11 Men's Restroom 2600 3 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.10 257.4 $40.15 3 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.08 195 $30.42 $7.00 $21.00 0.02 62.4 $9.73 2.16

211.11 Women's Restroom 2600 3 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.10 257.4 $40.15 3 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.08 195 $30.42 $7.00 $21.00 0.02 62.4 $9.73 2.16

222.21 Computer Lab 2600 15 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.93 2,418.0 $377.21 15 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.75 1950 $304.20 $14.00 $210.00 0.18 468 $73.01 2.88

242.21 Cosmo Classroom 2600 15 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 1.61 4,173.0 $650.99 15 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 1.47 3822 $596.23 $28.00 $420.00 0.14 351 $54.76 7.67

221.11 Storage 1200 4 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.25 297.6 $46.43 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 240 $37.44 $14.00 $56.00 0.05 57.6 $8.99 6.23

221.14 Storage 1200 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 139.2 $21.72 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 120 $18.72 $14.00 $28.00 0.02 19.2 $3.00 9.35

222.21 S21A Classroom 2600 18 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.12 2,901.6 $452.65 18 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.90 2340 $365.04 $14.00 $252.00 0.22 561.6 $87.61 2.88

211.11 Practice Room (2) 1200 4 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.13 158.4 $24.71 4 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.10 120 $18.72 $7.00 $28.00 0.03 38.4 $5.99 4.67

222.21 S21C Nursing 2600 7 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.43 1,128.4 $176.03 7 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.35 910 $141.96 $14.00 $98.00 0.08 218.4 $34.07 2.88

222.21 S21B Classroom 2600 21 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.30 3,385.2 $528.09 21 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 1.05 2730 $425.88 $14.00 $294.00 0.25 655.2 $102.21 2.88

211.11 Lockers 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

221.11 Nurses Office 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

Page 141: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-15 of 9

242.21 S23 Classroom 2600 18 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 1.93 5,007.6 $781.19 18 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 1.76 4586.4 $715.48 $28.00 $504.00 0.16 421.2 $65.71 7.67

221.11 Storage 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

221.14 Nurses Office 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

242.21 S25 Classroom 2600 27 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 2.89 7,511.4 $1,171.78 27 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 2.65 6879.6 $1,073.22 $28.00 $756.00 0.24 631.8 $98.56 7.67

221.34 2600 62 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.60 9,349.6 $1,458.54 62 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 3.10 8060 $1,257.36 $14.00 $868.00 0.50 1289.6 $201.18 4.31

211.11 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

221.14 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.34 2600 56 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.25 8,444.8 $1,317.39 56 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.80 7280 $1,135.68 $14.00 $784.00 0.45 1164.8 $181.71 4.31

211.11 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

221.14 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.34 2600 56 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.25 8,444.8 $1,317.39 56 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.80 7280 $1,135.68 $14.00 $784.00 0.45 1164.8 $181.71 4.31

211.11 2600 3 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.10 257.4 $40.15 3 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.08 195 $30.42 $7.00 $21.00 0.02 62.4 $9.73 2.16

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.34 2600 48 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.78 7,238.4 $1,129.19 48 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.40 6240 $973.44 $14.00 $672.00 0.38 998.4 $155.75 4.31

211.11 2600 6 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.20 514.8 $80.31 6 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.15 390 $60.84 $7.00 $42.00 0.05 124.8 $19.47 2.16

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.34 2600 71 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 4.12 10,706.8 $1,670.26 71 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 3.55 9230 $1,439.88 $14.00 $994.00 0.57 1476.8 $230.38 4.31

211.11 2600 6 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.20 514.8 $80.31 6 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.15 390 $60.84 $7.00 $42.00 0.05 124.8 $19.47 2.16

S27 Classroom, Lockers, Storage

S29 Classroom, Lockers, Storage

Welding, Lockers, Storage

S28 Auto, Lockers, Storage

S26 Auto, Lockers, Storage

Page 142: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-16 of 9

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.34 2600 71 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 4.12 10,706.8 $1,670.26 71 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 3.55 9230 $1,439.88 $14.00 $994.00 0.57 1476.8 $230.38 4.31

211.11 2600 8 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.26 686.4 $107.08 8 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.20 520 $81.12 $7.00 $56.00 0.06 166.4 $25.96 2.16

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.11 Men's Restroom 2600 5 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.31 806.0 $125.74 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.06 156 $24.34 2.88

221.11 Women's Restroom 2600 5 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.31 806.0 $125.74 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.06 156 $24.34 2.88

222.21 Media Center Corridor 2600 5 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.31 806.0 $125.74 5 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.06 156 $24.34 2.88

221.14 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.06 69.6 $10.86 1 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.05 60 $9.36 $14.00 $14.00 0.01 9.6 $1.50 9.35

222.21 S22 Classroom 2600 13 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.81 2,095.6 $326.91 13 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.65 1690 $263.64 $14.00 $182.00 0.16 405.6 $63.27 2.88

211.11 4400 16 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.53 2,323.2 $362.42 16 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.40 1760 $274.56 $7.00 $112.00 0.13 563.2 $87.86 1.27

222.21 4400 10 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.62 2,728.0 $425.57 10 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.50 2200 $343.20 $14.00 $140.00 0.12 528 $82.37 1.70

222.21 2600 15 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.93 2,418.0 $377.21 15 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.75 1950 $304.20 $14.00 $210.00 0.18 468 $73.01 2.88

221.11 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

211.14 2600 2 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.07 171.6 $26.77 2 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.05 130 $20.28 $7.00 $14.00 0.02 41.6 $6.49 2.16

222.21 2600 30 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.86 4,836.0 $754.42 30 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 1.50 3900 $608.40 $14.00 $420.00 0.36 936 $146.02 2.88

221.11 1200 4 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.25 297.6 $46.43 4 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.20 240 $37.44 $14.00 $56.00 0.05 57.6 $8.99 6.23

242.11 Conference Room 2600 4 42x4, 4 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

107 0.43 1,112.8 $173.60 4 4 Relamp - Sylvania Lamp FO28/841/SS/ECO 98 0.39 1019.2 $159.00 $28.00 $112.00 0.04 93.6 $14.60 7.67

South Corridor

W1 Classroom, Lockers, Storage

W3 Classroom

S24 Auto, Lockers, Storage

Page 143: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-17 of 9

222.21 W5 Classroom 2600 30 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 1.86 4,836.0 $754.42 30 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 1.50 3900 $608.40 $14.00 $420.00 0.36 936 $146.02 2.88

221.34 Prep Room 2600 3 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.17 452.4 $70.57 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.02 62.4 $9.73 4.31

242.21 W7 Classroom 2600 20 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 2.14 5,564.0 $867.98 20 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 1.96 5096 $794.98 $28.00 $560.00 0.18 468 $73.01 7.67

221.11 Nurses Office 2600 6 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.37 967.2 $150.88 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.07 187.2 $29.20 2.88

221.34 W9 Maintenance 2600 48 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.78 7,238.4 $1,129.19 48 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.40 6240 $973.44 $14.00 $672.00 0.38 998.4 $155.75 4.31

221.11 Maintenance Office 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface

Mnt., Prismatic Lens62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

221.34 2600 56 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.25 8,444.8 $1,317.39 56 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.80 7280 $1,135.68 $14.00 $784.00 0.45 1164.8 $181.71 4.31

221.34 2600 6 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.35 904.8 $141.15 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.05 124.8 $19.47 4.31

221.11 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

221.34 2600 56 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.25 8,444.8 $1,317.39 56 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.80 7280 $1,135.68 $14.00 $784.00 0.45 1164.8 $181.71 4.31

221.34 2600 6 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.35 904.8 $141.15 6 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.30 780 $121.68 $14.00 $84.00 0.05 124.8 $19.47 4.31

221.11 2600 2 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.12 322.4 $50.29 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 62.4 $9.73 2.88

221.34 2600 56 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 3.25 8,444.8 $1,317.39 56 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.80 7280 $1,135.68 $14.00 $784.00 0.45 1164.8 $181.71 4.31

221.34 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

211.11 4400 30 11x4, 1 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

33 0.99 4,356.0 $679.54 30 1 Relamp - Sylvania Lamp FO28/841/SS/ECO 25 0.75 3300 $514.80 $7.00 $210.00 0.24 1056 $164.74 1.27

602 8760 1 2 Incandescent Exit Sign 20 0.02 175.2 $27.33 1 1 LED Exit Sign 2 0.00 17.52 $2.73 $65.00 $65.00 0.02 157.68 $24.60 2.64

242.21 2600 25 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 2.68 6,955.0 $1,084.98 25 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 2.45 6370 $993.72 $28.00 $700.00 0.23 585 $91.26 7.67

221.34 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

W11 Classroom, Tool Shed, Lockers

W13 Classroom, Storage/Office,

Lockers

W15 Classroom, Storage/Tools,

Lockers

West Corridor

W14 Classroom, Storage

Page 144: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-18 of 9

221.34 2600 35 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.03 5,278.0 $823.37 35 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 1.75 4550 $709.80 $14.00 $490.00 0.28 728 $113.57 4.31

221.34 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.34 2600 40 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.32 6,032.0 $940.99 40 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.00 5200 $811.20 $14.00 $560.00 0.32 832 $129.79 4.31

221.34 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.34 2600 40 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 2.32 6,032.0 $940.99 40 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 2.00 5200 $811.20 $14.00 $560.00 0.32 832 $129.79 4.31

221.34 2600 5 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.29 754.0 $117.62 5 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.25 650 $101.40 $14.00 $70.00 0.04 104 $16.22 4.31

221.14 2600 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Surface Mnt., No Lens

58 0.12 301.6 $47.05 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 260 $40.56 $14.00 $28.00 0.02 41.6 $6.49 4.31

221.11 Men's Restroom 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

221.11 Women's Restroom 2600 3 21x4, 2 Lamp, 32w 700 Series

T8, Elect. Ballast, Surface Mnt., Prismatic Lens

62 0.19 483.6 $75.44 3 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.15 390 $60.84 $14.00 $42.00 0.04 93.6 $14.60 2.88

232.22 2600 15 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

86 1.29 3,354.0 $523.22 15 3 Relamp - Sylvania Lamp FO28/841/SS/ECO 72 1.08 2808 $438.05 $21.00 $315.00 0.21 546 $85.18 3.70

232.21 2600 2 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 0.17 447.2 $69.76 2 3 Relamp - Sylvania Lamp FO28/841/SS/ECO 72 0.14 374.4 $58.41 $21.00 $42.00 0.03 72.8 $11.36 3.70

232.21 2600 2 32x4, 3 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Prismatic Lens

86 0.17 447.2 $69.76 2 3 Relamp - Sylvania Lamp FO28/841/SS/ECO 72 0.14 374.4 $58.41 $21.00 $42.00 0.03 72.8 $11.36 3.70

222.21 2600 8 22x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens62 0.50 1,289.6 $201.18 8 2 Relamp - Sylvania Lamp

FO28/841/SS/ECO 50 0.40 1040 $162.24 $14.00 $112.00 0.10 249.6 $38.94 2.88

222.22 2600 23 22x4, 2 Lamp, 32w T8, Elect.

Ballast, Recessed Mnt., Parabolic Lens

58 1.33 3,468.4 $541.07 23 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 1.15 2990 $466.44 $14.00 $322.00 0.18 478.4 $74.63 4.31

242.21 Tech 2600 6 42x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed

Mnt., Prismatic Lens107 0.64 1,669.2 $260.40 6 4 Relamp - Sylvania Lamp

FO28/841/SS/ECO 98 0.59 1528.8 $238.49 $28.00 $168.00 0.05 140.4 $21.90 7.67

221.34 Phone Room 1200 2 21x4, 2 Lamp, 32w T8, Elect.

Ballast, Pendant Mnt., No Lens

58 0.12 139.2 $21.72 2 2 Relamp - Sylvania Lamp FO28/841/SS/ECO 50 0.10 120 $18.72 $14.00 $28.00 0.02 19.2 $3.00 9.35

560 4400 20 1 Recessed Down Light, 20w CFL Lamp 20 0.40 1,760.0 $274.56 20 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

800 4400 5 4 Pendant Mnt. Globe Fixture, 20w CFL Lamp 100 0.50 2,200.0 $343.20 5 0 No Change 0 0.00 0 $0.00 $0.00 $0.00 0.00 0 $0.00 0.00

738 4400 30 1 175w Mercury Vapor Wall Pack 210 6.30 27,720.0 $4,324.32 30 1 80w Induction Wall Pack 80 2.40 10560 $1,647.36 $340.00 $10,200.00 3.90 17160 $2,676.96 3.81

W12 Classroom, Lockers, Storage

W10 Classroom, Lockers, Storage

Atrium

Principal'sOffice

W8 Classroom, Lockers, Storage

W6 Classroom, Electrical Room,

Storage

Page 145: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Investment Grade Lighting Audit APPENDIX E-19 of 9

767 4400 12 1 400w Mercury Vapor Post Mounted Area Light 460 5.52 24,288.0 $3,788.93 12 1

Venture Lighting Optiwave Ballast V90U7421K and 320w

MH Lamp; retrofit349 4.19 18427.2 $2,874.64 $160.00 $1,920.00 1.33 5860.8 $914.28 2.10

Totals 1,880 294 132.10 370,566 $57,808 1,880 289 106.1 290,530 $45,323 $42,754 25.1 76,077 $11,868 3.60

Exterior

Page 146: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-21 of 8

CEG Job #: 9C10093Project: Cumberland County Tech Ed Center KWH COST: $0.156

Address: 601 Bridgeton Ave.Bridgeton, NJ

Building SF:

ECM #2: Lighting Controls not rebate eligible

EXISTING LIGHTING PROPOSED LIGHTING CONTROLS SAVINGSCEG Fixture Yearly No. No. Fixture Fixt Total kWh/Yr Yearly No. No. Controls Watts Total Reduction kWh/Yr Yearly Unit Cost Total kW kWh/Yr Yearly Yearly Simple

Type Location Usage Fixts Lamps Type Watts kW Fixtures $ Cost Fixts Cont. Description Used kW (%) Fixtures $ Cost (INSTALLED) Cost Savings Savings $ Savings Payback

242.21 2600 20 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 2.14 5564 $867.98 20 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 1.71 20% 4451.2 $694.39 $300.00 $300.00 0.43 1112.8 $173.60 1.73

221.11 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

211.11 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

222.21 2600 24 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.488 3868.8 $603.53 24 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 1.19 20% 3095.04 $482.83 $300.00 $300.00 0.30 773.76 $120.71 2.49

221.11 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

211.11 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

242.21 2600 14 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 1.498 3894.8 $607.59 14 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 1.20 20% 3115.84 $486.07 $300.00 $300.00 0.30 778.96 $121.52 2.47

221.14 2600 1 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.058 150.8 $23.52 1 0 No Change 58 0.06 0% 150.8 $23.52 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 CST 2600 12 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.744 1934.4 $301.77 12 1 Dual Technology OccupancySensor - Remote Mnt. 62 0.60 20% 1547.52 $241.41 $250.00 $250.00 0.15 386.88 $60.35 4.14

221.11 Back Office 2600 4 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.248 644.8 $100.59 4 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.20 20% 515.84 $80.47 $150.00 $150.00 0.05 128.96 $20.12 7.46

232.21 2600 27 32x4, 3 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Prismatic Lens

86 2.322 6037.2 $941.80 27 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 86 1.86 20% 4829.76 $753.44 $300.00 $600.00 0.46 1207.44 $188.36 3.19

617 2600 3 1 Hood Light w/Globe & Cage, 100w A19 Lamp 100 0.3 780 $121.68 3 0 No Change 100 0.30 0% 780 $121.68 $0.00 $0.00 0.00 0 $0.00 0.00

221.111 2600 22 21x4, 2 Lamp, 32w 700

Series T8, Elect. Ballast, Surface Mnt., Vapor Tite

62 1.364 3546.4 $553.24 22 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 1.09 20% 2837.12 $442.59 $300.00 $300.00 0.27 709.28 $110.65 2.71

221.11 Wash Area 2600 6 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.372 967.2 $150.88 6 1 Dual Technology OccupancySensor - Remote Mnt. 62 0.30 20% 773.76 $120.71 $250.00 $250.00 0.07 193.44 $30.18 8.28

221.11 Food Storage 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

Food Services Classroom

E43 Classroom, Closet, Lockers

E41 Classroom, Closet, Lockers

E45 Classroom, Closet

120,543

Cumberland County Tech Ed Center

Page 147: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-22 of 8

242.21 2600 32 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 3.424 8902.4 $1,388.77 32 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 2.74 20% 7121.92 $1,111.02 $300.00 $600.00 0.68 1780.48 $277.75 2.16

221.14 2600 6 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.348 904.8 $141.15 6 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.28 20% 723.84 $112.92 $150.00 $150.00 0.07 180.96 $28.23 5.31

211.11 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

227.21 2600 6 2

2x2, 2 Lamp, 32w 700 series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

65 0.39 1014 $158.18 6 0 No Change 65 0.39 0% 1014 $158.18 $0.00 $0.00 0.00 0 $0.00 0.00

232.21 2600 5 32x4, 3 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Prismatic Lens

86 0.43 1118 $174.41 5 0 No Change 86 0.43 0% 1118 $174.41 $0.00 $0.00 0.00 0 $0.00 0.00

222.11 2600 10 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.62 1612 $251.47 10 0 No Change 62 0.62 0% 1612 $251.47 $0.00 $0.00 0.00 0 $0.00 0.00

221.11 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 0 No Change 62 0.12 0% 322.4 $50.29 $0.00 $0.00 0.00 0 $0.00 0.00

3520 Restroom 1200 1 2 Ceiling Mount White Globe, (2) 100w A Lamp 200 0.2 240 $37.44 1 0 No Change 200 0.20 0% 240 $37.44 $0.00 $0.00 0.00 0 $0.00 0.00

242.22 Conference Room 2600 8 42x4, 4 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Parabolic Lens

104 0.832 2163.2 $337.46 8 1 Dual Technology OccupancySensor - Switch Mnt. 104 0.67 20% 1730.56 $269.97 $150.00 $150.00 0.17 432.64 $67.49 2.22

222.21 Business Office 2600 14 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.868 2256.8 $352.06 14 1 Dual Technology OccupancySensor - Remote Mnt. 62 0.69 20% 1805.44 $281.65 $250.00 $250.00 0.17 451.36 $70.41 3.55

766 2600 12 1 400w MH, Prismatic Lens 465 5.58 14508 $2,263.25 12 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 465 4.46 20% 11606.4 $1,810.60 $300.00 $300.00 1.12 2901.6 $452.65 0.66

602 8760 2 2 Incandescent Exit Sign 20 0.04 350.4 $54.66 2 0 No Change 20 0.04 0% 350.4 $54.66 $0.00 $0.00 0.00 0 $0.00 0.00

221.14 Boy's Locker Room 2600 14 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.812 2111.2 $329.35 14 1 Dual Technology OccupancySensor - Remote Mnt. 58 0.65 20% 1688.96 $263.48 $250.00 $250.00 0.16 422.24 $65.87 3.80

222.21 Gym Office 2600 4 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.248 644.8 $100.59 4 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.20 20% 515.84 $80.47 $150.00 $150.00 0.05 128.96 $20.12 7.46

221.14 Custodial Closet 2600 1 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.058 150.8 $23.52 1 0 No Change 58 0.06 0% 150.8 $23.52 $0.00 $0.00 0.00 0 $0.00 0.00

221.14 Mechanical Room 2600 4 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.232 603.2 $94.10 4 0 No Change 58 0.23 0% 603.2 $94.10 $0.00 $0.00 0.00 0 $0.00 0.00

221.14 Gym Storage 1200 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 139.2 $21.72 2 0 No Change 58 0.12 0% 139.2 $21.72 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 E58 Classroom 2600 6 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.372 967.2 $150.88 6 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.30 20% 773.76 $120.71 $150.00 $150.00 0.07 193.44 $30.18 4.97

211.11 4400 32 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 1.056 4646.4 $724.84 32 0 No Change 33 1.06 0% 4646.4 $724.84 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 4400 4 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.248 1091.2 $170.23 4 0 No Change 62 0.25 0% 1091.2 $170.23 $0.00 $0.00 0.00 0 $0.00 0.00

602 8760 3 2 Incandescent Exit Sign 20 0.06 525.6 $81.99 3 0 No Change 20 0.06 0% 525.6 $81.99 $0.00 $0.00 0.00 0 $0.00 0.00

E51 Dining, Food Prep, Lockers

East Corridor

Gym

Superintendents Office

Page 148: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-23 of 8

221.11 Girl's Locker Room 2600 16 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.992 2579.2 $402.36 16 1 Dual Technology OccupancySensor - Remote Mnt. 62 0.79 20% 2063.36 $321.88 $250.00 $250.00 0.20 515.84 $80.47 3.11

222.21 Girl's Office 1200 4 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.248 297.6 $46.43 4 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.20 20% 238.08 $37.14 $150.00 $150.00 0.05 59.52 $9.29 16.15

221.11 Men's Restroom 2600 4 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.248 644.8 $100.59 4 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.20 20% 515.84 $80.47 $150.00 $150.00 0.05 128.96 $20.12 7.46

221.11 Office 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

221.34 2600 62 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.596 9349.6 $1,458.54 62 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.88 20% 7479.68 $1,166.83 $300.00 $900.00 0.72 1869.92 $291.71 3.09

221.14 2600 10 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.58 1508 $235.25 10 0 No Change 58 0.58 0% 1508 $235.25 $0.00 $0.00 0.00 0 $0.00 0.00

221.14 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.34 2600 44 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.552 6635.2 $1,035.09 44 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.04 20% 5308.16 $828.07 $300.00 $900.00 0.51 1327.04 $207.02 4.35

221.11 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

221.11 2600 5 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.31 806 $125.74 5 0 No Change 62 0.31 0% 806 $125.74 $0.00 $0.00 0.00 0 $0.00 0.00

221.34 E48 Cafeteria 2600 48 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.784 7238.4 $1,129.19 48 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.23 20% 5790.72 $903.35 $300.00 $900.00 0.56 1447.68 $225.84 3.99

221.34 Vending 2600 6 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.348 904.8 $141.15 6 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.28 20% 723.84 $112.92 $150.00 $150.00 0.07 180.96 $28.23 5.31

222.21 2600 30 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.86 4836 $754.42 30 0 No Change 62 1.86 0% 4836 $754.42 $0.00 $0.00 0.00 0 $0.00 0.00

617 2600 2 1 Hood Light w/Globe & Cage, 100w A19 Lamp 100 0.2 520 $81.12 2 0 No Change 100 0.20 0% 520 $81.12 $0.00 $0.00 0.00 0 $0.00 0.00

221.34 Kitchen Storage 1200 6 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.348 417.6 $65.15 6 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.28 20% 334.08 $52.12 $150.00 $150.00 0.07 83.52 $13.03 11.51

221.34 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.058 69.6 $10.86 1 0 No Change 58 0.06 0% 69.6 $10.86 $0.00 $0.00 0.00 0 $0.00 0.00

221.11 Lockers 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

222.21 E44 Faculty Dining 2600 11 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.682 1773.2 $276.62 11 1 Dual Technology OccupancySensor - Remote Mnt. 62 0.55 20% 1418.56 $221.30 $250.00 $250.00 0.14 354.64 $55.32 4.52

221.21 Copy Room 2600 4 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Prismatic Lens

58 0.232 603.2 $94.10 4 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.19 20% 482.56 $75.28 $150.00 $150.00 0.05 120.64 $18.82 7.97

221.34 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.058 69.6 $10.86 1 0 No Change 58 0.06 0% 69.6 $10.86 $0.00 $0.00 0.00 0 $0.00 0.00

Kitchen

E50 Classroom, Mezzanine, Lockers

E52 Classroom, Mezzanine, Lockers

Page 149: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-24 of 8

211.11 Men's Restroom 2600 3 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.099 257.4 $40.15 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.08 20% 205.92 $32.12 $150.00 $150.00 0.02 51.48 $8.03 18.68

211.11 Women's Restroom 2600 3 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.099 257.4 $40.15 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.08 20% 205.92 $32.12 $150.00 $150.00 0.02 51.48 $8.03 18.68

222.21 Computer Lab 2600 15 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.93 2418 $377.21 15 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 0.74 20% 1934.4 $301.77 $300.00 $300.00 0.19 483.6 $75.44 3.98

242.21 Cosmo Classroom 2600 15 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 1.605 4173 $650.99 15 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 1.28 20% 3338.4 $520.79 $300.00 $300.00 0.32 834.6 $130.20 2.30

221.11 Storage 1200 4 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.248 297.6 $46.43 4 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.20 20% 238.08 $37.14 $150.00 $150.00 0.05 59.52 $9.29 16.15

221.14 Storage 1200 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 139.2 $21.72 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 111.36 $17.37 $150.00 $150.00 0.02 27.84 $4.34 34.54

222.21 S21A Classroom 2600 18 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.116 2901.6 $452.65 18 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 0.89 20% 2321.28 $362.12 $300.00 $300.00 0.22 580.32 $90.53 3.31

211.11 Practice Room (2) 1200 4 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.132 158.4 $24.71 4 0 No Change 33 0.13 0% 158.4 $24.71 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 S21C Nursing 2600 7 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.434 1128.4 $176.03 7 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.35 20% 902.72 $140.82 $150.00 $150.00 0.09 225.68 $35.21 4.26

222.21 S21B Classroom 2600 21 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.302 3385.2 $528.09 21 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 1.04 20% 2708.16 $422.47 $300.00 $300.00 0.26 677.04 $105.62 2.84

211.11 Lockers 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

221.11 Nurses Office 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

242.21 S23 Classroom 2600 18 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 1.926 5007.6 $781.19 18 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 1.54 20% 4006.08 $624.95 $300.00 $300.00 0.39 1001.52 $156.24 1.92

221.11 Storage 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

221.14 Nurses Office 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

242.21 S25 Classroom 2600 27 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 2.889 7511.4 $1,171.78 27 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 2.31 20% 6009.12 $937.42 $300.00 $600.00 0.58 1502.28 $234.36 2.56

221.34 2600 62 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.596 9349.6 $1,458.54 62 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.88 20% 7479.68 $1,166.83 $300.00 $1,200.00 0.72 1869.92 $291.71 4.11

Page 150: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-25 of 8

211.11 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

221.14 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.34 2600 56 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.248 8444.8 $1,317.39 56 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.60 20% 6755.84 $1,053.91 $300.00 $1,200.00 0.65 1688.96 $263.48 4.55

211.11 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

221.14 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.34 2600 56 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.248 8444.8 $1,317.39 56 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.60 20% 6755.84 $1,053.91 $300.00 $1,200.00 0.65 1688.96 $263.48 4.55

211.11 2600 3 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.099 257.4 $40.15 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.08 20% 205.92 $32.12 $150.00 $150.00 0.02 51.48 $8.03 18.68

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.34 2600 48 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.784 7238.4 $1,129.19 48 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.23 20% 5790.72 $903.35 $300.00 $1,200.00 0.56 1447.68 $225.84 5.31

211.11 2600 6 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.198 514.8 $80.31 6 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.16 20% 411.84 $64.25 $150.00 $150.00 0.04 102.96 $16.06 9.34

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.34 2600 71 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 4.118 10706.8 $1,670.26 71 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 3.29 20% 8565.44 $1,336.21 $300.00 $1,200.00 0.82 2141.36 $334.05 3.59

211.11 2600 6 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.198 514.8 $80.31 6 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.16 20% 411.84 $64.25 $150.00 $150.00 0.04 102.96 $16.06 9.34

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.34 2600 71 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 4.118 10706.8 $1,670.26 71 4

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 3.29 20% 8565.44 $1,336.21 $300.00 $1,200.00 0.82 2141.36 $334.05 3.59

211.11 2600 8 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.264 686.4 $107.08 8 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.21 20% 549.12 $85.66 $150.00 $150.00 0.05 137.28 $21.42 7.00

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.11 Men's Restroom 2600 5 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.31 806 $125.74 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.25 20% 644.8 $100.59 $150.00 $150.00 0.06 161.2 $25.15 5.96

S27 Classroom, Lockers, Storage

S24 Auto, Lockers, Storage

S26 Auto, Lockers, Storage

S28 Auto, Lockers, Storage

Welding, Lockers, Storage

S29 Classroom, Lockers, Storage

Page 151: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-26 of 8

221.11 Women's Restroom 2600 5 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.31 806 $125.74 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.25 20% 644.8 $100.59 $150.00 $150.00 0.06 161.2 $25.15 5.96

222.21 Media Center Corridor 2600 5 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.31 806 $125.74 5 0 No Change 62 0.31 0% 806 $125.74 $0.00 $0.00 0.00 0 $0.00 0.00

221.14 Custodial Closet 1200 1 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.058 69.6 $10.86 1 0 No Change 58 0.06 0% 69.6 $10.86 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 S22 Classroom 2600 13 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.806 2095.6 $326.91 13 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 0.64 20% 1676.48 $261.53 $300.00 $300.00 0.16 419.12 $65.38 4.59

211.11 4400 16 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.528 2323.2 $362.42 16 0 No Change 33 0.53 0% 2323.2 $362.42 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 4400 10 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.62 2728 $425.57 10 0 No Change 62 0.62 0% 2728 $425.57 $0.00 $0.00 0.00 0 $0.00 0.00

222.21 2600 15 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.93 2418 $377.21 15 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 0.74 20% 1934.4 $301.77 $300.00 $300.00 0.19 483.6 $75.44 3.98

221.11 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

211.14 2600 2 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.066 171.6 $26.77 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

33 0.05 20% 137.28 $21.42 $150.00 $150.00 0.01 34.32 $5.35 28.02

222.21 2600 30 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.86 4836 $754.42 30 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 1.49 20% 3868.8 $603.53 $300.00 $600.00 0.37 967.2 $150.88 3.98

221.11 1200 4 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.248 297.6 $46.43 4 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.20 20% 238.08 $37.14 $150.00 $150.00 0.05 59.52 $9.29 16.15

242.11 Conference Room 2600 4 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

107 0.428 1112.8 $173.60 4 1 Dual Technology OccupancySensor - Switch Mnt. 107 0.34 20% 890.24 $138.88 $150.00 $150.00 0.09 222.56 $34.72 4.32

222.21 W5 Classroom 2600 30 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 1.86 4836 $754.42 30 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 62 1.49 20% 3868.8 $603.53 $300.00 $600.00 0.37 967.2 $150.88 3.98

221.34 Prep Room 2600 3 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.174 452.4 $70.57 3 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.14 20% 361.92 $56.46 $150.00 $150.00 0.03 90.48 $14.11 10.63

242.21 W7 Classroom 2600 20 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 2.14 5564 $867.98 20 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 1.71 20% 4451.2 $694.39 $300.00 $300.00 0.43 1112.8 $173.60 1.73

221.11 Nurses Office 2600 6 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.372 967.2 $150.88 6 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.30 20% 773.76 $120.71 $150.00 $150.00 0.07 193.44 $30.18 4.97

221.34 W9 Maintenance 2600 48 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.784 7238.4 $1,129.19 48 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.23 20% 5790.72 $903.35 $300.00 $900.00 0.56 1447.68 $225.84 3.99

W3 Classroom

W1 Classroom, Lockers, Storage

South Corridor

Page 152: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-27 of 8

221.11 Maintenance Office 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. 62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

221.34 2600 56 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.248 8444.8 $1,317.39 56 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.60 20% 6755.84 $1,053.91 $300.00 $900.00 0.65 1688.96 $263.48 3.42

221.34 2600 6 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.348 904.8 $141.15 6 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.28 20% 723.84 $112.92 $150.00 $150.00 0.07 180.96 $28.23 5.31

221.11 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

221.34 2600 56 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.248 8444.8 $1,317.39 56 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.60 20% 6755.84 $1,053.91 $300.00 $900.00 0.65 1688.96 $263.48 3.42

221.34 2600 6 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.348 904.8 $141.15 6 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.28 20% 723.84 $112.92 $150.00 $150.00 0.07 180.96 $28.23 5.31

221.11 2600 2 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.124 322.4 $50.29 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.10 20% 257.92 $40.24 $150.00 $150.00 0.02 64.48 $10.06 14.91

221.34 2600 56 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 3.248 8444.8 $1,317.39 56 3

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 2.60 20% 6755.84 $1,053.91 $300.00 $900.00 0.65 1688.96 $263.48 3.42

221.34 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. 58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

211.11 4400 30 1

1x4, 1 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

33 0.99 4356 $679.54 30 0 No Change 33 0.99 0% 4356 $679.54 $0.00 $0.00 0.00 0 $0.00 0.00

602 8760 1 2 Incandescent Exit Sign 20 0.02 175.2 $27.33 1 0 No Change 20 0.02 0% 175.2 $27.33 $0.00 $0.00 0.00 0 $0.00 0.00

242.21 2600 25 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 2.675 6955 $1,084.98 25 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 107 2.14 20% 5564 $867.98 $300.00 $600.00 0.54 1391 $217.00 2.77

221.34 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.34 2600 35 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.03 5278 $823.37 35 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 1.62 20% 4222.4 $658.69 $300.00 $600.00 0.41 1055.6 $164.67 3.64

221.34 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.34 2600 40 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.32 6032 $940.99 40 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 1.86 20% 4825.6 $752.79 $300.00 $600.00 0.46 1206.4 $188.20 3.19

221.34 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

W13 Classroom, Storage/Office,

Lockers

W11 Classroom, Tool Shed, Lockers

W10 Classroom, Lockers, Storage

W12 Classroom, Lockers, Storage

W14 Classroom, Storage

West Corridor

W15 Classroom, Storage/Tools,

Lockers

Page 153: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

APPENDIX E-28 of 8

221.34 2600 40 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 2.32 6032 $940.99 40 2

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 58 1.86 20% 4825.6 $752.79 $300.00 $600.00 0.46 1206.4 $188.20 3.19

221.34 2600 5 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.29 754 $117.62 5 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.23 20% 603.2 $94.10 $150.00 $150.00 0.06 150.8 $23.52 6.38

221.14 2600 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Surface Mnt., No Lens

58 0.116 301.6 $47.05 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible58 0.09 20% 241.28 $37.64 $150.00 $150.00 0.02 60.32 $9.41 15.94

221.11 Men's Restroom 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

221.11 Women's Restroom 2600 3 2

1x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Surface Mnt., Prismatic

Lens

62 0.186 483.6 $75.44 3 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible

62 0.15 20% 386.88 $60.35 $150.00 $150.00 0.04 96.72 $15.09 9.94

232.22 2600 15 32x4, 3 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Parabolic Lens

86 1.29 3354 $523.22 15 1

Dual Tech. Occupancy Sensor w/2 Pole Powerpack -

remote mount 86 1.03 20% 2683.2 $418.58 $300.00 $300.00 0.26 670.8 $104.64 2.87

232.21 2600 2 32x4, 3 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Prismatic Lens

86 0.172 447.2 $69.76 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible86 0.14 20% 357.76 $55.81 $150.00 $150.00 0.03 89.44 $13.95 10.75

232.21 2600 2 32x4, 3 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Prismatic Lens

86 0.172 447.2 $69.76 2 1 Dual Technology OccupancySensor - Switch Mnt. not rebate

eligible86 0.14 20% 357.76 $55.81 $150.00 $150.00 0.03 89.44 $13.95 10.75

222.21 2600 8 2

2x4, 2 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

62 0.496 1289.6 $201.18 8 0 No Change 62 0.50 0% 1289.6 $201.18 $0.00 $0.00 0.00 0 $0.00 0.00

222.22 2600 23 22x4, 2 Lamp, 32w T8,

Elect. Ballast, Recessed Mnt., Parabolic Lens

58 1.334 3468.4 $541.07 23 0 No Change 58 1.33 0% 3468.4 $541.07 $0.00 $0.00 0.00 0 $0.00 0.00

242.21 Tech 2600 6 4

2x4, 4 Lamp, 32w 700 Series T8, Elect. Ballast, Recessed Mnt., Prismatic

Lens

107 0.642 1669.2 $260.40 6 1 Dual Technology OccupancySensor - Switch Mnt. 107 0.51 20% 1335.36 $208.32 $150.00 $150.00 0.13 333.84 $52.08 2.88

221.34 Phone Room 1200 2 21x4, 2 Lamp, 32w T8,

Elect. Ballast, Pendant Mnt.,No Lens

58 0.116 139.2 $21.72 2 0 No Change 58 0.12 0% 139.2 $21.72 $0.00 $0.00 0.00 0 $0.00 0.00

560 4400 20 1 Recessed Down Light, 20w CFL Lamp 20 0.4 1760 $274.56 20 0 No Change 20 0.40 0% 1760 $274.56 $0.00 $0.00 0.00 0 $0.00 0.00

800 4400 5 4 Pendant Mnt. Globe Fixture,20w CFL Lamp 100 0.5 2200 $343.20 5 0 No Change 100 0.50 0% 2200 $343.20 $0.00 $0.00 0.00 0 $0.00 0.00

738 4400 30 1 175w Mercury Vapor Wall Pack 210 6.3 27720 $4,324.32 30 0 No Change 210 6.30 0% 27720 $4,324.32 $0.00 $0.00 0.00 0 $0.00 0.00

767 4400 12 1 400w Mercury Vapor Post Mounted Area Light 460 5.52 24288 $3,788.93 12 0 No Change 460 5.52 0% 24288 $3,788.93 $0.00 $0.00 0.00 0 $0.00 0.00

Totals 1,880 294 132.1 370,566.4 $57,808 1,880 151 110.5 314,860.1 $49,118.17 $34,800 21.56 55,706 $8,690 4.00

Exterior

Atrium

Principal'sOffice

W6 Classroom, Electrical Room,

Storage

W8 Classroom, Lockers, Storage

Page 154: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix FPage 1 of 3

Project Name: LGEA Solar PV Project - Cumberland County Technical Education Center

Location: Bridgeton, NJ 08302Description: Photovoltaic System 95% Financing - 25 year

Simple Payback Analysis

Total Construction Cost $2,637,180

Annual kWh Production 357,965

Annual Energy Cost Reduction $55,843

Annual SREC Revenue $125,288

First Cost Premium $2,637,180

Simple Payback: Years

Life Cycle Cost Analysis

Analysis Period (years): 25 Financing %: 95%

Financing Term (mths): 300 Maintenance Escalation Rate: 3.0%

Average Energy Cost ($/kWh) $0.156 Energy Cost Escalation Rate: 3.0%

Financing Rate: 7.00% SREC Value ($/kWh) $0.350

Period Additional Energy kWh Energy Cost Additional SREC Interest Loan Net Cash Cumulative

Cash Outlay Production Savings Maint Costs Revenue Expense Principal Flow Cash Flow

0 $131,859 0 0 0 $0 0 0 (131,859) 0

1 $0 357,965 $55,843 $0 $125,288 $174,158 $38,327 ($31,355) ($163,214)

2 $0 356,175 $57,518 $0 $124,661 $171,388 $41,097 ($30,306) ($193,520)

3 $0 354,394 $59,243 $0 $124,038 $168,417 $44,068 ($29,204) ($222,723)

4 $0 352,622 $61,021 $0 $123,418 $165,231 $47,254 ($28,047) ($250,770)

5 $0 350,859 $62,851 $3,614 $122,801 $161,815 $50,670 ($30,447) ($281,217)

6 $0 349,105 $64,737 $3,596 $122,187 $158,152 $54,333 ($29,157) ($310,374)

7 $0 347,359 $66,679 $3,578 $121,576 $154,224 $58,261 ($27,808) ($338,182)

8 $0 345,623 $68,679 $3,560 $120,968 $150,013 $62,472 ($26,398) ($364,580)

9 $0 343,894 $70,740 $3,542 $120,363 $145,497 $66,988 ($24,924) ($389,505)

10 $0 342,175 $72,862 $3,524 $119,761 $140,654 $71,831 ($23,386) ($412,891)

11 $0 340,464 $75,048 $3,507 $119,162 $135,461 $77,024 ($21,782) ($434,673)

12 $0 338,762 $77,299 $3,489 $118,567 $129,893 $82,592 ($20,109) ($454,781)

13 $0 337,068 $79,618 $3,472 $117,974 $123,923 $88,562 ($18,365) ($473,146)

14 $0 335,383 $82,007 $3,454 $117,384 $117,520 $94,965 ($16,549) ($489,695)

15 $0 333,706 $84,467 $3,437 $116,797 $110,655 $101,830 ($14,658) ($504,353)

16 $0 332,037 $87,001 $3,420 $116,213 $103,294 $109,191 ($12,691) ($517,044)

17 $0 330,377 $89,611 $3,403 $115,632 $95,401 $117,084 ($10,645) ($527,690)

18 $0 328,725 $92,299 $3,386 $115,054 $86,937 $125,548 ($8,518) ($536,207)

19 $0 327,082 $95,068 $3,369 $114,479 $77,861 $134,624 ($6,307) ($542,515)

20 $0 325,446 $97,920 $3,352 $113,906 $68,129 $144,356 ($4,011) ($546,525)

21 $0 323,819 $100,858 $3,335 $113,337 $62,070 $132,708 $16,081 ($530,444)

22 $0 322,200 $103,884 $3,319 $112,770 $50,158 $109,206 $53,971 ($476,473)

23 $0 320,589 $107,000 $3,302 $112,206 $0 $0 $215,904 ($260,569)

24 $0 318,986 $110,210 $3,286 $111,645 $0 $0 $218,570 ($42,000)

25 $0 317,391 $113,516 $3,269 $111,087 $0 $0 $221,334 $179,334

Totals: 8,432,206 $2,035,978 $72,214 $2,951,272 $2,750,851 $1,852,991 $311,193 ($9,083,757)

Net Present Value (NPV)

Internal Rate of Return (IRR)

Photovoltaic System 95% Financing - 25 year

($208,073)

1.6%

14.56

Page 155: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix FPage 2 of 3

Project Name: LGEA Solar PV Project - Cumberland County Technical Education Center

Location: Bridgeton, NJ 08302Description: Photovoltaic System - Direct Purchase

Simple Payback AnalysisPhotovoltaic System - Direct Purchase

Total Construction Cost $2,637,180Annual kWh Production 357,965

Annual Energy Cost Reduction $55,843Annual SREC Revenue $125,288

First Cost Premium

Simple Payback: Years

Life Cycle Cost AnalysisAnalysis Period (years): 25 Financing %: 0%Financing Term (mths): 0 Maintenance Escalation Rate: 3.0%

Average Energy Cost ($/kWh) $0.156 Energy Cost Escalation Rate: 3.0%Financing Rate: 0.00% SREC Value ($/kWh) $0.350

Period Additional Energy kWh Energy Cost Additional SREC Net Cash CumulativeCash Outlay Production Savings Maint Costs Revenue Flow Cash Flow

0 $2,637,180 0 0 0 $0 (2,637,180) 01 $0 357,965 $55,843 $0 $125,288 $181,130 ($2,456,050)2 $0 356,175 $57,518 $0 $124,661 $182,179 ($2,273,871)3 $0 354,394 $59,243 $0 $124,038 $183,281 ($2,090,589)4 $0 352,622 $61,021 $0 $123,418 $184,438 ($1,906,151)5 $0 350,859 $62,851 $3,614 $122,801 $182,038 ($1,724,113)6 $0 349,105 $64,737 $3,596 $122,187 $183,328 ($1,540,785)7 $0 347,359 $66,679 $3,578 $121,576 $184,677 ($1,356,108)8 $0 345,623 $68,679 $3,560 $120,968 $186,087 ($1,170,021)9 $0 343,894 $70,740 $3,542 $120,363 $187,561 ($982,460)

10 $0 342,175 $72,862 $3,524 $119,761 $189,099 ($793,361)11 $0 340,464 $75,048 $3,507 $119,162 $190,703 ($602,658)12 $0 338,762 $77,299 $3,489 $118,567 $192,377 ($410,281)13 $0 337,068 $79,618 $3,472 $117,974 $194,120 ($216,161)14 $0 335,383 $82,007 $3,454 $117,384 $195,936 ($20,225)15 $0 333,706 $84,467 $3,437 $116,797 $197,827 $177,60116 $0 332,037 $87,001 $3,420 $116,213 $199,794 $377,39517 $0 330,377 $89,611 $3,403 $115,632 $201,840 $579,23518 $0 328,725 $92,299 $3,386 $115,054 $203,967 $783,20219 $0 327,082 $95,068 $3,369 $114,479 $206,178 $989,38020 $0 325,446 $97,920 $3,352 $113,906 $208,474 $1,197,85521 $1 323,819 $100,858 $3,335 $113,337 $210,859 $1,408,71422 $2 322,200 $103,884 $3,319 $112,770 $213,335 $1,622,04923 $3 320,589 $107,000 $3,302 $112,206 $215,904 $1,837,95324 $4 318,986 $110,210 $3,286 $111,645 $218,570 $2,056,52225 $5 317,391 $113,516 $3,269 $111,087 $221,334 $2,277,856

Totals: 8,432,206 $2,035,978 $72,214 $2,951,272 $4,915,036 ($4,235,071)Net Present Value (NPV)

Internal Rate of Return (IRR)

14.56

$2,637,180

$2,277,8815.3%

Page 156: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

Appendix FPage 3 of 3

Building Roof Area (sq ft) Panel Qty Panel Sq

Ft

Panel Total Sq

Ft

Total KWDC

Total Annual

kWh

Panel Weight (33

lbs)W/SQFT

CCTEC 20,800 Sunpower SPR230

1274 14.7 18,733 293.02 357,965 42,042 15.64

.= Proposed PV Layout

Notes:1. Estimated kWH based on the National Renewable Energy Laboratory PVWatts Version 1 Calculator Program.

Page 157: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G1 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 16,600 20,000

Occ. O.A. Percentage (%) 52% 35%

Unocc. O.A. Percentage (%) 5% 5%

Occ. Temp Diff (°F) 55 55

Unocc. Temp Diff (°F) 65 65

Heating Degree Days (68°F) 5,959 5,959

Heating Degree Days (60°F) 4,027 4,027

Hours of setback per day (ave) 0 9

Heating System Efficiency (%) 75% 80%

Heating Fuel Value 100,000 100,000

Energy Recovery Sys Efficiency 0% 66.4%

Demand Control Ventilation Savings 0% 10%

Occ O.A. Heating Load (Btu/Hr) 507,885 153,584

Unocc O.A. Heating Load (Btu/Hr) 58,266 19,577

Occ O.A. Heating Energy (Therms) 11,900 2,108

Unocc O.A. Heating Energy (Therms) 0 202

Gas Cost ($/Therm) $1.32 $1.32

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Heating Energy (Therms) 11,900 2,310 9,589

Heating Energy Cost ($) $15,708 $3,050 $12,658

AC-1 ENERGY RECOVERY HEATING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Milville Airport,NJ.

Page 158: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G2 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 9,200 7,800

Occ. O.A. Percentage (%) 46% 27%

Unocc. O.A. Percentage (%) 5% 5%

Occ. Temp Diff (°F) 55 55

Unocc. Temp Diff (°F) 65 65

Heating Degree Days (68°F) 5,959 5,959

Heating Degree Days (60°F) 4,027 4,027

Hours of setback per day (ave) 0 9

Heating System Efficiency (%) 75% 80%

Heating Fuel Value 100,000 100,000

Energy Recovery Sys Efficiency 0% 76.3%

Demand Control Ventilation Savings 0% 10%

Occ O.A. Heating Load (Btu/Hr) 253,942 54,280

Unocc O.A. Heating Load (Btu/Hr) 32,292 7,669

Occ O.A. Heating Energy (Therms) 5,950 745

Unocc O.A. Heating Energy (Therms) 0 79

Gas Cost ($/Therm) $1.32 $1.32

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Heating Energy (Therms) 5,950 824 5,126

Heating Energy Cost ($) $7,854 $1,088 $6,766

AC-2 ENERGY RECOVERY HEATING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Milville Airport,NJ.

Page 159: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G3 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 8,200 7,700

Occ. O.A. Percentage (%) 52% 100%

Unocc. O.A. Percentage (%) 5% 5%

Occ. Temp Diff (°F) 55 55

Unocc. Temp Diff (°F) 65 65

Heating Degree Days (68°F) 5,959 5,959

Heating Degree Days (60°F) 4,027 4,027

Hours of setback per day (ave) 0 9

Heating System Efficiency (%) 75% 80%

Heating Fuel Value 100,000 100,000

Energy Recovery Sys Efficiency 0% 11.9%

Demand Control Ventilation Savings 0% 10%

Occ O.A. Heating Load (Btu/Hr) 253,942 201,351

Unocc O.A. Heating Load (Btu/Hr) 28,782 25,357

Occ O.A. Heating Energy (Therms) 5,950 2,764

Unocc O.A. Heating Energy (Therms) 0 262

Gas Cost ($/Therm) $1.32 $1.32

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Heating Energy (Therms) 5,950 3,026 2,924

Heating Energy Cost ($) $7,854 $3,994 $3,860

AC-3 ENERGY RECOVERY HEATING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Milville Airport,NJ.

Page 160: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G4 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 16,600 20,000

Occ. O.A. Percentage (%) 52% 35%

Occ. Enthalpy Diff (°F) 11 11

Unocc. Enthalpy Diff (°F) 0 0

Full Load Cooling Hrs 900 900

Cooling System Efficiency (EER) 5.1 10.5

Energy Recovery Sys Efficiency 0% 66.4%

O.A. Cooling Load (Btu/Hr) 403,999 135,744

Elec Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Cooling Energy (kWh) 71,294 11,635 59,659

Cooling Energy Cost ($) $11,122 $1,815 $9,307

A-1 ENERGY RECOVERY COOLING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Millville Airport,NJ.

Page 161: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G5 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 9,200 7,800

Occ. O.A. Percentage (%) 46% 27%

Occ. Enthalpy Diff (°F) 11 11

Unocc. Enthalpy Diff (°F) 0 0

Full Load Cooling Hrs 900 900

Cooling System Efficiency (EER) 5.3 10.5

Energy Recovery Sys Efficiency 0% 76.3%

O.A. Cooling Load (Btu/Hr) 202,000 47,955

Elec Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Cooling Energy (kWh) 34,302 4,110 30,191

Cooling Energy Cost ($) $5,351 $641 $4,710

A-2 ENERGY RECOVERY COOLING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Millville Airport,NJ.

Page 162: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G6 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 8,200 7,700

Occ. O.A. Percentage (%) 52% 27%

Occ. Enthalpy Diff (°F) 11 11

Unocc. Enthalpy Diff (°F) 0 0

Full Load Cooling Hrs 900 900

Cooling System Efficiency (EER) 5.3 10.5

Energy Recovery Sys Efficiency 0% 11.9%

O.A. Cooling Load (Btu/Hr) 202,000 177,962

Elec Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

O.A. Cooling Energy (kWh) 34,302 15,254 19,048

Cooling Energy Cost ($) $5,351 $2,380 $2,971

A-3 ENERGY RECOVERY COOLING ENERGY CALCULATIONS

ENERGY SAVINGS CALCULATIONS

COMMENTS: Degree Days based on Millville Airport,NJ.

Page 163: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G7 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTSNo O.A.

Preconditioning

Total O.A. Energy

Recovery Wheel

Total AHU Airflow (CFM) 34,000 35,500

Occ. O.A. Percentage (%) 50% 47%

Unocc. O.A. Percentage (%) 5% 5%

Occ. Temp Diff (°F) 55 55

Unocc. Temp Diff (°F) 65 65

Heating Degree Days (68°F) 5,959 5,959

Heating Degree Days (60°F) 4,027 4,027

Hours of setback per day (ave) 0 9

RTU Heating System Efficiency (%) 75% 80%

Heating Fuel Value 100,000 100,000

Boiler Efficiency (%) N/A 87%

Average Energy Recovery Sys Efficiency 0% 57.8%Demand Control Ventilation Savings (10% of Ventilation) 0% 10%

Occ O.A. Heating Load (Btu/Hr) 1,015,770 409,216

Unocc O.A. Heating Load (Btu/Hr) 119,340 52,604

Occ O.A. Heating Energy (Therms) 23,799 5,618 18,181

Unocc O.A. Heating Energy (Therms) 0 543 (543)Skin_Load (BTU/Hr)= Total_Load-Ventilation_Load 514,230 514,230

DDC Controls - Skin load Savings (Therms) 10,697 8,300 2,398

Additional Equip Load (10.45 kW), kWh 0 46,704 (46,704)Elec Cost ($/kWh) $0.156 $0.156Gas Cost ($/Therm) $1.32 $1.32

ECM RESULTS EXISTING PROPOSED SAVINGS

Total Additional Electric Energy (kWh) 0 46,704 (46,704)

Additional Electric Energy Cost ($) $0.000 $7,286 ($7,286)

Total Heating Energy (Therms) 34,496 14,460 20,037

Heating Energy Cost ($) $45,535 $19,087 $26,448

Total Heating Energy Cost ($) $45,535 $26,373 $19,162

ENERGY RECOVERY HEATING ENERGY SUMMARY

ENERGY SAVINGS SUMMARY

COMMENTS: Degree Days based on Milville Airport,NJ.

Page 164: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G8 of 10

ECM INPUTS EXISTING PROPOSED SAVINGS

ECM INPUTS No O.A. Preconditioning

Total O.A. Energy Recovery

Wheel

Total AHU Airflow (CFM) 34,000 35,500

Occ. O.A. Percentage (%) 50% 47%

Occ. Enthalpy Diff (°F) 11 11

Unocc. Enthalpy Diff (°F) 0 0

Full Load Cooling Hrs 900 900

Cooling System Efficiency (EER) 5.1 10.5

Average Energy Recovery Sys Efficiency 0% 55.2%

O.A. Cooling Load (Btu/Hr) 807,999 361,660 Skin_Load (BTU/Hr) 451,781 451,781 DDC Controls - 10% Savings (kWh) 79,726 34,852 44,874

Additional Equip Load (10.45 kW), kWh 0 9,405 (9,405)

Elec Cost ($/kWh) $0.156 $0.156

ECM RESULTS EXISTING PROPOSED SAVINGS

Total Cooling Energy (kWh) 219,624 75,256 144,368

Cooling Energy Cost ($) $34,261 $11,740 $22,521

ENERGY RECOVERY COOLING ENERGY SUMMARY

ENERGY SAVINGS SUMMARY

COMMENTS: Degree Days based on Millville Airport,NJ. ; Add'l Equip: VAV fan, Boiler, Pump1, Pump2 and DDC controls

Page 165: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G9 of 10

Indoor Outdoor Design Temp Difference

Summer 75 95 20Winter 68 13 -55

R UWall - Insulated Block 8.43 0.12Roof O1 12.33 0.08Roof Metal 11.10 0.09Skylight 3.05Windows 3.01Asbestoes Panel 5.55 0.18

Wall Length Height Wall Area Window Area Cooling Load, BTUH

Heating Load, BTUH

Wall - North 340.0 13 4386.0 4211.1Wall - SE 165.0 13 2128.5 1639.4Wall - SW 145.0 13 1870.5 1200.5

8385.0 7051.0 16728.35113 -46002.9656

Roof Roof Area Skylight Area

A 23005 189 37008.92133 -101774.5337B 1298 0 2105.433901 -5789.943228C 2514 0 4077.858881 -11214.11192D 3983 0 6460.665045 -17766.82887E 2566 0 4162.206002 -11446.0665F 835 200 1144.144144 -4137.387387Total 34201 389 54959.2293 -152128.8716

Skylight Skylight Area

A 189B 0C 0D 0E 0F 200F 200Total 389 23729 -65254.75

Window W H Window Area Less Pnls

B 3 5.83 17.49 0.00 10529.0 -28954.7G 36.5 13.4 489.1 457.6448 29443.8 -80970.5H 31.5 13.4 422.1 390.6448 25410.4 -69878.7J 18.5 13.4 247.9 218.42 14923.6 -41039.8

Panels3 5.83 17.49 630.3 -1733.2

5.48 2.87 15.73 283.4 -779.32.75 5 13.75 49.5 -136.3

Skin Load Main BuildingWall, BTUH 16728.35 -46002.97Window, BTUH 80306.80 -220843.70Panel, BTUH 963.20 -2648.80Roof, BTUH 54959.23 -152128.87Skylight, BTUH 23729.00 -65254.75Total Skin Load, MBH 176.69 -486.88Total Ventilation Load, MBH 808.00 -1135.11Lights 1 w/sqft 116.73Equipment 0.5 w/sqft 58.36People 500 BTUH/sqft 100.00Total Load, MBH 1259.78 -1621.99

Page 166: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

ENERGY CALCULATIONS - ENERGY RECOVERY Concord Engineering Group

Cumberland County Technical Education Center APPENDIX G10 of 10

Existing Heat RMU-1 500RMU-2 540RMU-3 500RMU-4 500Total Heat Input, MBH 2040Heat Load, MBH = Heat input x % Efficiency 1530

Existing Cooling RMU-1 266RMU-2 287RMU-3 268RMU-4 262Total Sensible Cooling, MBH 1083Estimated Total Cooling, MBH 1444

Percent Difference = abs(Unit Capacity - abs(load calc)) / Unit Capacity 12.8% 6.0%

The equipment capacity will be used since the percent difference is more than 5%.

Existing Equipment Capacity

Page 167: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEAAppendix HPage 1 of 6

Roofing Upgrade

R U Indoor Outdoor Design Temp Difference

Roof - Old EPDM 12.33 0.081 Summer 75 95 20Roof Metal 11.10 0.090 Winter 68 13 -55Roof New Type 1 12.61 0.079Roof New Type 2 26.22 0.038Skylight 3.050

Roof Roof Area Skylight Area

Existing Cooling Load,

BTUH

Existing Heating Load,

BTUH

Proposed Cooling Load,

BTUH

Proposed Heating Load,

BTUH

Saved Cooling BTUH

Saved Heating BTUH

A 23005 189 37,008.9 -101,774.5 36,187.2 -99,514.7 821.8 2,259.9B 1298 0 2,105.4 -5,789.9 2,058.7 -5,661.4 46.8 128.6C 2514 0 4,077.9 -11,214.1 1,917.6 -5,273.5 2,160.2 5,940.7D 3983 0 6,460.7 -17,766.8 3,038.1 -8,354.9 3,422.5 9,411.9E 2566 0 4,162.2 -11,446.1 1,957.3 -5,382.5 2,204.9 6,063.5F - Metal Roof Main Bldg 835 200 1,144.1 -3,146.4 1,144.1 -3,146.4 0.0 0.0Total 34201 389 54,959.2 -151,137.9 46,303.0 -127,333.3 8,656.2 23,804.6

Skylight Skylight Area

A 189B 0C 0D 0E 0F 200Total 389 23,729.0 -65,254.8 23,729.0 -65,254.8 0.0 0.0

Total Roof Load Main Bldg., kbtuh 78,688.2 -216,392.6 70,032.0 -192,588.1 8,656.2 23,804.6

Page 168: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEA Appendix HPage 2 of 6

Base Bid

R U Indoor OutdoorDesign Temp

Difference

Asbestoes Panel 0.25 4.00 Summer 75 95 20

1"FRP Panel 5.55 0.18 Winter 68 13 -55

Metal Frame 1.15

Hollow Metal Door 1.67 0.60

Roll Up Door 1.15

FRP Door 0.18

Exist Door Glass 0.21

New Door Glass 0.24

Wall 8.43 0.12

Window 3.01

Frame Quantity Heating

Quantity Cooling

Total Panel Area

(SqFT)

Frame Area

(SqFT)

Net Door Area

(SqFT)

Door Glass Area

(SqFT)

Wall Area

(SqFT)

Window Area

(SqFT)

Existing Cooling Load, BTUH

Existing Heating Load, BTUH

Proposed Cooling Load, BTUH

Proposed Heating Load, BTUH

Saved Cooling BTUH

Saved Heating BTUH

A1 3 2 106.4 36.8 153.0 8.0 0.0 193.7 15,257.9 -62,938.9 8,986.2 -37,067.9 6,271.8 25,871.0A2 6 1 176.5 176.2 146.1 8.0 122.6 841.3 14,270.3 -235,459.9 11,819.1 -195,015.4 2,451.2 40,444.5A3 6 3 359.8 76.9 160.0 8.0 0.0 390.6 28,008.5 -154,046.9 13,596.9 -74,782.9 14,411.6 79,264.0A4 6 2 373.8 88.5 146.1 8.0 0.0 378.8 18,843.0 -155,455.0 8,917.6 -73,569.9 9,925.5 81,885.1A5 1 0 39.5 12.2 24.4 1.3 0.0 88.5 0.0 -28,465.9 0.0 -19,613.9 0.0 8,852.0B 10 10 175.0 43.8 196.7 13.3 0.0 0.0 17,423.0 -47,913.4 2,408.9 -6,624.4 15,014.2 41,289.0C 1 0 0.0 3.0 37.2 9.8 0.0 0.0 0.0 -1,532.0 0.0 -686.7 0.0 845.3D 1 0 0.0 5.3 37.2 9.8 0.0 8.9 0.0 -3,153.2 0.0 -2,307.9 0.0 845.3E 1 0 60.0 10.8 26.7 1.3 0.0 67.1 0.0 -25,880.0 0.0 -12,669.3 0.0 13,210.7F 2 0 0.0 7.0 43.0 0.0 0.0 16.6 0.0 -4,616.7 0.0 -3,623.4 0.0 993.3G 1 1 29.2 33.2 18.7 0.0 32.8 374.9 25,975.2 -71,431.7 23,585.7 -64,860.6 2,389.5 6,571.0H 1 1 29.2 28.8 18.7 0.0 29.5 315.6 22,294.5 -61,309.8 19,905.0 -54,738.8 2,389.5 6,571.0J 1 1 27.8 16.4 18.7 0.0 19.5 138.2 11,191.6 -30,776.9 8,907.7 -24,496.2 2,283.9 6,280.7

Total 153,264.0 -882,980.2 98,127.0 -570,057.2 55,137.0 312,923.0

Page 169: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEAAppendix HPage 3 of 6

Alternate Bid

R U Indoor OutdoorDesign Temp

DifferenceAsbestoes Panel 0.25 4.00 Summer 75 95 201"FRP Panel 5.55 0.18 Winter 68 13 -55Metal Frame 1.15Hollow Metal Door 1.67 0.60Roll Up Door 1.15FRP Door 0.18Exist Door Glass 0.21New Door Glass 0.24Wall 8.43 0.12Window 3.01New Window 0.28

Frame Quantity Heating

Quantity Cooling

Total Panel Area

(SqFT)

Frame Area

(SqFT)

Net Door Area

(SqFT)

Door Glass Area

(SqFT)

Wall Area

(SqFT)

Window Area

(SqFT)

Existing Cooling Load, BTUH

Existing Heating Load, BTUH

Proposed Cooling Load, BTUH

Proposed Heating Load, BTUH

Saved Cooling BTUH

Saved Heating BTUH

A1 1 0 35.5 12.3 51.0 2.7 0.0 64.6 0.0 -20,979.6 0.0 -12,356.0 0.0 8,623.7A2 6 1 176.5 176.2 146.1 8.0 122.6 841.3 14,270.3 -235,459.9 11,819.1 -195,015.4 2,451.2 40,444.5A3 5 2 299.8 64.1 133.3 6.7 0.0 325.5 18,672.4 -128,372.4 9,064.6 -62,319.1 9,607.8 66,053.4A4 1 0 62.3 14.8 24.4 1.3 0.0 63.1 0.0 -25,909.2 0.0 -12,261.6 0.0 13,647.5A5 1 0 39.5 12.2 24.4 1.3 0.0 88.5 0.0 -28,465.9 0.0 -19,613.9 0.0 8,852.0B 8 8 140.0 35.0 157.3 10.7 0.0 0.0 13,938.4 -38,330.7 1,927.1 -5,299.5 12,011.3 33,031.2C 1 0 0.0 3.0 37.2 9.8 0.0 0.0 0.0 -1,532.0 0.0 -686.7 0.0 845.3D 1 0 0.0 5.3 37.2 9.8 0.0 8.9 0.0 -3,153.2 0.0 -2,307.9 0.0 845.3E 1 0 60.0 10.8 26.7 1.3 0.0 67.1 0.0 -25,880.0 0.0 -12,669.3 0.0 13,210.7F 2 0 0.0 7.0 43.0 0.0 0.0 16.6 0.0 -4,616.7 0.0 -3,623.4 0.0 993.3G 0 0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0H 1 1 29.2 28.8 18.7 0.0 29.5 315.6 22,294.5 -61,309.8 19,905.0 -54,738.8 2,389.5 6,571.0J 1 1 27.8 16.4 18.7 0.0 19.5 138.2 11,191.6 -30,776.9 8,907.7 -24,496.2 2,283.9 6,280.7

Alt A1 2 2 70.9 24.5 102.0 5.3 0.0 129.1 15,257.9 -41,959.3 1,935.4 -5,322.2 13,322.6 36,637.0Alt A3 1 1 60.0 12.8 26.7 1.3 0.0 65.1 9,336.2 -25,674.5 977.7 -2,688.6 8,358.5 22,985.9Alt A4 5 2 311.5 73.8 121.8 6.7 0.0 315.7 18,843.0 -129,545.8 2,022.8 -13,906.9 16,820.2 115,638.9Alt B 2 2 35.0 8.8 39.3 2.7 0.0 0.0 3,484.6 -9,582.7 481.8 -1,324.9 3,002.8 8,257.8Alt G 1 1 108.6 33.2 18.7 0.0 32.8 295.6 25,975.2 -71,431.7 2,955.9 -8,128.8 23,019.2 63,302.9Total 153,264.0 -882,980.2 59,997.1 -436,759.1 93,267.0 446,221.0

Page 170: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEAAppendix HPage 4 of 6

Door Glass Glass Glass GlassArea (SqFT) w (inch) h (inch) Qty. Area (SqFT)

1 53.67 32 6 2 2.67 51.002 25.69 32 6 1 1.33 24.363 28 32 6 1 1.33 26.674 21 32 6 1 1.33 19.675 47 32 22 2 9.78 37.226 21.5 0 0.00 21.507 18.69 0 0.00 18.698 106.7 0 0 0 0.00 106.709 56 0 0 0 0.00 56.00

Door Type Net Door Area (SqFT)

Page 171: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEAAppendix HPage 5 of 6

Frame W H Area (SqFT) Type Qty. area Type Qty. area Type Qty. area

A1 12.00 13.83 166.0 1 1 26.83 2 3 8.625 1 0 0.0 35.46 12.26 1 53.67 0 0.00 2.67 51.00 0.00 64.57A2 16.00 15.32 245.1 3 1 29.42 1 0 0.000 1 0 0.0 29.42 29.36 2 25.69 8 106.70 1.33 24.36 20.43 140.22A3 12.00 13.82 165.9 1 1 26.83 2 3 8.625 4 1 24.5 59.96 12.81 3 28.00 0 0.00 1.33 26.67 0.00 65.10A4 12.00 13.82 165.9 1 2 53.67 2 3 8.625 1 0 0.0 62.29 14.75 2 25.69 0 0.00 1.33 24.36 0.00 63.14A5 12.00 13.82 165.9 5 1 22.44 2 3 8.625 6 2 8.4 39.47 12.24 2 25.69 9 56.00 1.33 24.36 0.00 88.48B 3.33 12.83 42.8 7 1 17.50 1 0 0.000 1 0 0.0 17.50 4.38 4 21.00 0 0.00 1.33 19.67 0.00 0.00C 6.31 7.94 50.1 1 0 0.00 1 0 0.000 1 0 0.0 0.00 3.02 5 47.00 0 0.00 9.78 37.22 0.00 0.00D 6.33 9.67 61.2 1 0 0.00 1 0 0.000 1 0 0.0 0.00 5.30 5 47.00 0 0.00 9.78 37.22 0.00 8.92E 12.00 13.82 165.9 2 3 8.63 1 1 26.833 4 1 24.5 59.96 10.81 3 28.00 0 0.00 1.33 26.67 0.00 67.11F 3.33 10.00 33.3 1 0 0.00 1 0 0.000 1 0 0.0 0.00 3.52 6 21.50 0 0.00 0.00 21.50 0.00 8.31G 36.44 13.42 488.9 8 2 29.22 1 0 0.000 1 0 0.0 29.22 33.23 7 18.69 0 0.00 0.00 18.69 32.79 374.93H 31.44 13.42 421.8 8 2 29.22 1 0 0.000 1 0 0.0 29.22 28.80 7 18.69 7 18.69 0.00 18.69 29.46 315.62J 16.44 13.42 220.5 8 1 14.61 9 1 13.229 1 0 0.0 27.84 16.39 7 18.69 0 0.00 0.00 18.69 19.46 138.15

Alt A1 12.00 13.83 166.0 1 1 26.83 2 3 8.625 1 0 0.0 35.46 12.26 1 53.67 0 0.00 2.67 51.00 0.00 64.57Alt A3 12.00 13.82 165.9 1 1 26.83 2 3 8.625 4 1 24.5 59.96 12.81 3 28.00 0 0.00 1.33 26.67 0.00 65.10Alt A4 12.00 13.82 165.9 1 2 53.67 2 3 8.625 1 0 0.0 62.29 14.75 2 25.69 0 0.00 1.33 24.36 0.00 63.14Alt B 3.33 12.83 42.8 7 1 17.50 1 0 0.000 1 0 0.0 17.50 4.38 4 21.00 0 0.00 1.33 19.67 0.00 0.00Alt G 36.44 13.42 488.9 8 2 29.22 10 6 79.375 1 0 0.0 108.60 33.23 7 18.69 7 18.69 0.00 18.69 32.79 295.56

Window Area (Sqft)

Frame Opening Panel Panel PanelDOOR TYPE

DOOR AREA

DOOR TYPE

DOOR AREA

Wall Area

(SqFT)

Net Door Area

(SqFT)

Net Door Glass Area

(SqFT)

Total Panel Area (Sqft)

Frame Area (Sqft)

Page 172: REPARED FOR CUMBERLAND COUNTY T E CEnergy...2011/04/06  · April 6, 2011– FINAL Page 3 of 89 I. EXECUTIVE SUMMARY This report presents the findings of the energy audit conducted

CalculationsECM #8 #8.1 ‐ Building Envelope Upgrade

Energy Calculations - Envelope UpgradeConcord Engineering Group

Cumberland County Technical Education Center LGEAAppendix HPage 6 of 6

Panel Type w h area

1 3.83 7.00 26.83

2 3.83 0.75 2.88

3 4.00 7.35 29.42

4 3.50 7.00 24.50

5 3.83 5.85 22.44

6 1.15 3.67 4.20

7 3.00 5.83 17.50

8 2.67 5.48 14.61

9 2.65 5.00 13.23

10 5.00 2.59 12.97