Renewable energy options for leisure centres

24
Renewable Energy Options for Leisure Centres Michael Bell Tipperary Energy Agency 3rd October 2013

description

 

Transcript of Renewable energy options for leisure centres

Page 1: Renewable energy options for leisure centres

Renewable Energy Options for Leisure Centres

Michael Bell

Tipperary Energy Agency

3rd October 2013

Page 2: Renewable energy options for leisure centres

• Which Renewable Energy Option

• Renewable Energy from Biomass

• Biomass Introduced

• Supply Chain

• Project Management Cycle for Biomass Heat Supply

• Specification of Systems

• Contract Options

• Case Studies of Completed Biomass Project in Leisure Centre

• Key Considerations with Biomass

• Renewable Heat from Heat Pumps

• Other Renewable Energy Options

Introduction

Page 3: Renewable energy options for leisure centres

• Every site is unique, however there are some common energy patterns

Which Renewable Energy Option?

Nenagh Thurles -

500

1,000

1,500

2,000

2,500

Electrical (MWh)

Thermal (MWh)

En

erg

y C

on

sum

pti

on

(M

Wh

)

• 75% Thermal Energy Consumption & 61% cost (Average)

• Therefore target thermal renewable energy 1st (After Energy Efficiency)

Page 4: Renewable energy options for leisure centres

• Thermal Energy from Renewable Energy Sources

• Biomass

• Wood Chip

• Wood Pellet

• Heat Pump

• Solar Thermal

• CHP

• Biomass has been the logical choice in Tipperary (off gas)

• Lowest Cost

• Proven Technology

• Typically the space is available

• Suited to retrofitting to high temperature systems

Which Renewable Energy Option?

Page 5: Renewable energy options for leisure centres
Page 6: Renewable energy options for leisure centres

• Two fuels:• Wood Chip and Wood Pellet

• Common Source

Introduction to Biomass

Renewable Energy from Biomass

Wood Chip Wood Pellet

  Chip (35% MC) Pellet (8%MC)kWh/tonne 3200 4800€/tonne 125 230

Page 7: Renewable energy options for leisure centres

Supply Chain

Page 8: Renewable energy options for leisure centres

Partnerships to Supply Heat

• Local wood energy businesses – adopting partnerships

Page 9: Renewable energy options for leisure centres

• Feasibility Study & Supply Chain evaluation

• Project Specification

• Project Contract Structuring

• Project Procurement

• ITT Documentation

• Tender award criteria

• Evaluation

• Develop & Set Contract

• Project Implementation on site

• QA/QC!

• Contract management until heat supply has finished

• Procure heat supply contract for further period

Project Management Cycle for Biomass Heat Supply

Page 10: Renewable energy options for leisure centres

• Biomass = several interlinked systems in one

• Expert skills required to fully integrate

• Correct structuring of contract is key to success

• Integrate supply of heat where possible to one point of responsibility

• Outline specification required for procurement stage when going for heat supply

• Risk assessment

Specification of Systems

Page 11: Renewable energy options for leisure centres

• Thermal Store Size & Location

Specification of Systems

• Boiler Type Size & Location

• Fuel Delivery size & Type & supply chain evaluation

• Fuel Store & Delivery size & Type

Page 12: Renewable energy options for leisure centres

Biomass Contract Options

• Separate Contracts for

• Design

• Supply

• Install

• Operate & Maintain

• Supply of Fuel

OR

• Contract to Supply, Install and supply all heat for period of 3 to 5 years, with subsequent contract options after initial heat supply contract finishes (Customer pays capital)

OR

• Contract to Supply, Install and supply all heat for period of 3 to 5 years, with subsequent contract options after initial heat supply contract finishes (ESCO pays capital)

OR ….. Etc

• Each situation is unique and should be evaluated on its own merits

Page 13: Renewable energy options for leisure centres

Nenagh Biomass Boiler

Summary

Heat load in kWh 900,000

Biomass cost €42,903

Equivalent oil cost @80c/ litre €91,043

Saving €48,140

Capital Cost €203,165

SERVE EU Grant €80,000

CO2 Saving in Tonnes 207

Page 14: Renewable energy options for leisure centres

Nenagh Biomass Boiler

With SERVE EU Grant AidSimple Payback in Years 2.610 Yr NPV €367,00010 Yr IRR 69% Without Grant AidSimple Payback in Years 4.210 Yr NPV €290,03510 Yr IRR 32%

Key Innovation• Contracts• Design Build Operate Contract• Contractor pays for all oil, maintenance, chip

etc.• Single heat supply contract fixed at 4.2c/kWh

for 3 years• All losses, breakdowns covered by contractor• Chip supplied locally.

Page 15: Renewable energy options for leisure centres

Thurles Biomass Boiler

SummaryHeat load in kWh (Reducing) 1,500,000Biomass cost €47,000Equivalent LPG cost @55c/litre €115,000Saving €68,000Capital Cost €160,000DoTTS Grant €135,000CO2 Saving in Tonnes 400

Page 16: Renewable energy options for leisure centres

Thurles Biomass Boiler

With DoTTS Grant AidSimple Payback in Months 610 Yr NPV €496,00010 Yr IRR 194% Without Grant AidSimple Payback in Months 3010 Yr NPV €377,03510 Yr IRR 59%

Page 17: Renewable energy options for leisure centres

Key Considerations with Biomass

• Boiler integration with existing system

• Boiler, pipework & buffer & fuel store sizing

• Pump Control

• Building Energy Management System

• Operation and Maintenance

• Ensure competent personnel

• Supply of fuel

• Asses availability of fuel and level of competition in local market (Wood chip has a local 50km delivery radius)

• Fuel quality

• Fuel Delivery systems and stores

• Ensure systems can accept deliveries from all suppliers in region

• Contract structuring

• Ensure appropriate clauses are covered and structured in contract to cover all parties and enable a long-term sustainable supply of heat (economically & environmentally)

Proper project scoping, specification, procurement, contract & implementation will ensure success

Page 18: Renewable energy options for leisure centres

Renewable Heat from Heat Pumps

• Heat Pumps (HP) are suited to low thermal differential situations

• EG: Pool water heating 29 Celsius is an ideal temperature for HP to supply at

• Heat Pumps can be either air source or ground source

• Coefficient of Performance (COP) depends on how well sized and integrated the HP is

• Fesible to supply large portion of Leisure Centre heat load with HP

Economics (simplified):

• Unit of Electricity = 0.15 €/kWh

• Seasonal COP = 3 (est) , thus heat price = 0.05 €/kWh

• Unit of Oil = 0.1€/kWh

• Efficiency = 85%, thus heat price = 0.11 €/kWh

• 55% saving heat pump vs oil (conservative)

Page 19: Renewable energy options for leisure centres

Ballina Swimming Pool Case Study

• Open 4 months per annum (summer)

• Outdoor pool, previously unheated & unused

• Solution required to be

• Low maintenance

• Robust

• Suited to leaving switched off over winter

• Low operational cost

• Achieve pool temperature of 24 Celsius

• Options Considered

• Cover

• Solar

• Biomass

• Heat Pump (chosen)

Page 20: Renewable energy options for leisure centres

Ballina Swimming Pool Case Study

• 2 x 22kW heat pumps to heat pool Include heat exchanger

• 1 x 9kW heat pump to heat DHW

• 1 x 500l DHW tank

• Aerated shower heads

• CAPEX = €48,000 ex VAT

• Contract structured at procurement stage to include 5 year maintenance

• Annual maintenance is not onerous

• Payback N/A (70% less than oil as system operated during summer with high air & pool temperature) (COP of 4.5)

Page 21: Renewable energy options for leisure centres

Other Renewable Energy Options

• Thermal

• CHP – (Only in Natural Gas areas)

• Should always be sized to meet les than peak electrical demand & should be controlled to never dump heat.

• Note also maintenance agreements – look for performance & output based contracts – not run hours

• Solar thermal

• Electrical

• Wind

• CHP

• Solar Photovoltaic

Page 22: Renewable energy options for leisure centres

Other Renewable Energy Options

• Wind

• Payback 5 to 20 years (lots of variables)

• Two in operation (at leisure centres)

• Some Considerations• Land Registry & Planning Application

Searches• Local authority zoning & development

plans• Planning & legislative constraints• Wind speed data• Location & selection of wind turbine• Energy & C02 emissions savings• Cost benefit analysis• Site Access• Grid Connection• Social Acceptance

Page 23: Renewable energy options for leisure centres

Other Renewable Energy Options

• Solar Photovoltaic

• Cost

• Becoming feasible

Page 24: Renewable energy options for leisure centres

Contacts

Tipperary Energy AgencyCraft GranaryChurch StCahir, Co. Tipperary

Michael BellSenior Energy EngineerT: 052 74 43090F: 052 74 43012E: [email protected] W: www.tea.ie

Thank you.