Rem-q No. 01-2008 Mid Exam

download Rem-q No. 01-2008 Mid Exam

of 5

Transcript of Rem-q No. 01-2008 Mid Exam

  • 8/11/2019 Rem-q No. 01-2008 Mid Exam

    1/5

    Mid Semester Group Assignment

    CE74.51 RIVER ENGINEERING AND MODELLING 3,(3-0)

    SEMESTER AUGUST 2014

    ASIAN INSTITUTE OF TECHNOLOGY

    THAILAND

    School of Engineering and Technology

    Water Engineering and Management

    Assignment Topic: Question No.1 of 2008-MID SEMESTER PAPER

    Instructor:

    Prof. Dr. TAWATCHAI TINGSANCHALI

    Submitted by:

    MUHAMMAD ABDUL QAYYUM QADUME (ID#16669)

    MUHAMMAD MOHSIN SHABBIR (ID#116674)

    DATED 25-Sep-2014

  • 8/11/2019 Rem-q No. 01-2008 Mid Exam

    2/5

    Question No.1 2008-MID SEMESTER PAPER

    PROBLEM:A 20m wide channel has a flow velocity of 1.5 m/s, depth of 3mand bed slope 1/10000. The channel carries suspended load with D50=50um.

    The concentration Ca is 0.1 kg/m3 at a distance 0.3m above the bed. Using

    Rouse equation, determine the amount of suspended load for whole cross

    section in Kg/day. Water temperature is 200C.

    Given Data :

    = 1.5 m/s

    Ca = 0.1 kg/m3

    a = 0.3 m

    D50= 50 m =0.050 mm

    i = 1/10000 m

    Suspended Load=? (By using Rouse Equation)

  • 8/11/2019 Rem-q No. 01-2008 Mid Exam

    3/5

    SOLUTION :

    Rouse equation for suspended load

    Cy/Ca = [a/h-a . h-y/y]Z

    As Z = w/ku*

    So, u* =ghi

    u* =9.830.0001 =0.0542 m/s

    Considering Fall velocity (w) graph using D50 and SF 0.07 we have

    w = 1.9 mm/s = 0.0019 m/s

    Now z = w/ku* whereas k=0.4

    z = 0.0019/0.40.0542 = 0.087

    u*/w =0.0542/0.0019 = 28.5

    where z = w/ku*=0.087

    Dividing the whole cross section of channel in strips of 0.3m depth

    each and calculating concentration for various strips

    So, using rouse equation we get

    Cy = Ca x [{(a/(h-a)} . {(h-y)/y}]Z

  • 8/11/2019 Rem-q No. 01-2008 Mid Exam

    4/5

    At y=0.3 Ca=0.1 kg/ m3

    (given in the question)

    At y=0.6 Cb=0.1 x [{0.3/(3-0.3)} {(3-0.6)/0.6}]0.087

    Cb=0.093 kg/m3

    At y=0.9 Cc=0.1 x [{0.3/(3-0.3) } { (3-0.9)/0.9}]0.087

    Cc=0.0889 kg/m3

    At y=1.2 Cd=0.1 x [{0.3/(3-0.3) } { (3-1.2)/1.2}]0.087

    Cd=0.0855 kg/m3

    At y=1.5 Ce =0.1 x [{0.3/(3-0.3)} { (3-1.5)/1.5}]0.087

    Ce=0.0825 kg/m3

    At y=1.8 Cf=0.1 x [{0.3/(3-0.3) } {(3-1.8)/1.8}]0.087

    Cf=0.0797 kg/m

    3

    At y=2.1 Cg=0.1 x [{0.3/(3-0.3)} {(3-2.1)/2.1}]0.087

    Cg=0.0767 kg/m3

    At y=2.4 Ch=0.1 x [{0.3/(3-0.3)} {(3-2.4)/2.4}]0.087

    Ch=0.0732 kg/m3

    At y=2.7 Ci=0.1 x [{0.3/(3-0.3)} {(3-2.7)/2.7}]0.087

    Ci=0.0682 kg/m3

    At y=3.0 Cj=0.1 x [{0.3/(3-0.3)} {(3-3.0)/3.0}]0.087

    Cj=0 kg/m3

    Total Suspended Load=Ss

  • 8/11/2019 Rem-q No. 01-2008 Mid Exam

    5/5

    Ss= x (YaCa+YbCbc+YcCcd+YdCde+YdCde+YeCef+YfCfg+YgCgh+

    YhChi+YiCij)

    Ss= x Y x (Ca+Cbc+Ccd+Cde+Cde+Cef+Cfg+Cgh+Chi+Cij)

    Ss= xY x(.1+.096+.091+.087+.084+.0811+.078+.075+.0707+.034)

    Ss= 1.5 x 0.3 x 1.4334

    Ss= 0.645 Kg/sec/unit width

    For whole cross section width of 20 m

    Ss= 0.645 x 20 Kg/sec

    Ss= 12.9 kg/sec x 24x60x60= 11,14,560 Kg/day Answer.