Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
Transcript of Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
1/67
I N S T R U C T I O N M A N U A L O F
RELIABILITY & MAINTAINABILITY
FOR TRANSFORMER PRODUCTSI N C L U D I N G P O W E R & A U T O
TRANSFORMERS, REACTORS AND
S P E C I A L T R A N S F O R M E R S .
TBEA SHENYANG TRANSFORMERS GROUP CO. LTD.
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
2/67
TABLE OF CONTENTS
1.0 INTRODUCTION 31.1 The core value 41.2 The Mission 4
1.3 The Purpose 41.4 Management Structure 41.5 ISO Certificates and other approvals . 5
2.0 SCOPE ... 5
2.1 Procurement and purchasing 5
2.2 Design and Development . 6
2.3 Manufacturing Process 6-14
2.4 Inspection and Testing . 14-17
2.5 Coating and Painting Systems . 18-20
2.6 Transportation of products 20
2.7 Acceptance and Storage of products . 20-222.8 Assembly and Installation . 22-26
2.9 Operation and Maintenance .. 26-27
3.0 TRANSFORMER MAINTENANCE RECORD . 27-29
4.0 EXPORT REFERENCE LIST . 29
5.0 CUSTOEMRS ACKNOWLEDGEMENT LETTERS 29
6.0 APPENDICES
1. Appendix 1: ISO certification and other approvals . 30-31
2. Appendix 2: Procurement and Purchasing .. 32-38
3. Appendix 3: Design and Development of Products 39-41
4. Appendix 4: Painting Systems of TBEA Shenyang 42-43
5. Appendix 5: Product Transportation System .. 44-49
6. Appendix 6: Export Reference List 50-61
7. Appendix 7: Customers Acknowledgement Letters . 62-65
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
3/67
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
4/67
1.1 THE CORE VALUE
The core value of TBEA is Always Reliable. With this core value as a flat form, TBEA
Shenyang has been growing from strength to strength to provide reliable and satisfactory
services to customers in countries like Canada, United States, India, Pakistan and Philippines
to name a few. To live up to the core value that TBEA stands on, the employees have beenreminded often of Always Reliable and the entire workmanship is working vigorously to
manufacture transformer products are considered reliable, high quality and of competitive
prices.
TBEA Shenyang makes sure that its core value Always Reliable to be the objective to be
targeted on every transformer product it manufactures. To achieve the reliability of
transformers, TBEA Shenyang seriously considers various programs it utilizes in the process
of manufacturing transformer products and apply Always Reliable motto in the programs
ranging from procurement and purchasing of accessories, welding, painting, testing,
transportation, commissioning, operation and maintainability.
1.2 THE MISSION
The mission of TBEA Shenyang is to provide reliable and satisfying services to its clients by
meeting their requirements to establish a lasting business relationship with them.
1.3 THE PURPOSE
The purpose of TBEA Shenyang is to serve governments, their people and businesses
throughout the countries of the world through technology innovation and committing
enormous effort to provide quality and affordable products that will be operated in power
turn-key and EPC projects to improve peoples life, economically efficient and effective, and
environmental friendly.
2.1 MANAGEMENT STRUCTURE
To achieve and accomplish the core values, mission and purpose it stands for, TBEA Shenyang
Transformer Group Co. Ltd has a well organized and structured management. Figure 2
summarizes the management and organization of the Company.
-4-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
5/67
Fig.2: Management Structure of TBEA Shenyang Transformers Group Co. Ltd
1.5 ISO CERTIFICATES AND OTHER APPROVALS
TBEA Shenyang has been in the power industry for more than 70 years of vast experience.
Appendix 1 shows several ISO certification and other approvals from the well known
inspection and testing team around the globe.
2.0 SCOPE OF WORK
This specification generally applies to all transformer products manufactured by TBEA
Shenyang. This includes power equipment in operation, production and at design stage. The
scope of major work and engineering programs it considers being important to apply
Always Reliable value from the start to the commissioning, operation and maintainability.
2.1 PROCUREMENT AND PURCHASING
Procurement and Purchasing of accessories from sub-suppliers are done accordingly in
orderly manner. Sub-suppliers of accessories are screened carefully and make sure they have
qualification and ISO approvals. All of our sub-suppliers are to go through a process of
TBEA products sub-supplier qualification process. Qualified suppliers like Micafil, MR,
Qualitrol, EMB, Shell and Nynas are some of the accessory suppliers on our suppliers list.
Please see Appendix 2 for further information on Procurement and Purchasing. Chart 1 of
Appendix 2 illustrates the process involve for purchasing assessment for suppliers
qualification. Also of appendix 2, the table 1 illustrates the methods in a table form used for
approval of suppliers including evaluation, suggestions and comments.
-5-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
6/67
2.2 DESIGN AND DEVELOPMENT
Design and Development is the integral part of the operation of TBEA Shenyang. This comes
under Design Department and it basically focuses on research, development and designing of
transformer products. As soon as a client submits his/her transformer technical and design
requirements, the team from International Department Project Management analyses andprepare documents for approval from superiors for book keeping. After the approval, the
technical specifications are passed on the Design Department. The design engineers carefully
study the clients technical specifications. The engineers then put a lot of effort to do research
and proceed with designing of the transformer following the technical specified with the
required Standards. Some of the standards applied in designing according to technical
specification are IEC, IEEE, AS, ANSI, NEMA among others.
The design is done within the time limit the client sets. The design process goes through
stages of being designed by the engineer, checked by senior engineer and then approved chief
engineer. Should there be clarification needed, our technical consultants and experts are
asked to give input to the design. During the design, the design engineers also take intoconsideration the technical specification of suitable transformer accessories. These are then
put forward to the purchasing department to for technical clarification and purchasing process
as outlined in Appendix 2. In the process of designing, the design engineers with the project
management team from the international department also liaise with relevant departments for
R&D and secure relevant information. The appendix 3 gives further information on design
and development procedures.
2.3 MANUFACTURING PROCESS
Manufacturing process involves a lot of effort from not only Manufacturing department but also
required departments like design, purchasing, quality control and technical center. After the
contract agreement is signed between TBEA Shenyang and the client, the production schedule is
sighted upon by both parties. TBEA Shenyang can work vigorously to finish manufacture the
product on time according to the schedule.
The manufacturing department makes sure that it is following strictly the right design patterns,
standards, materials and all available information from relevant departments are being executed
during the manufacturing period. The scopes of work to be done are ranging from determination
of core winding (steel plates and copper) including shape, size and vertical and horizontal
windings. The insulation and assembling of active parts are also important matter to take into
serious consideration. The following pictures summarizes the details of manufacturing process
involve.
2.3.1. Automatic Step-lap stacking
Features:CNC Cut-to-length Line (German made) with automatic step-lap stacking
-6-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
7/67
Step-lap stacking
high dimensional accuracy
automatic step-lap stacking
Precise size insuring close fitting joints
Advantages:
Better distribution of the magnetic field at the joints of core
No load loss can be reduced by up to 6% which compared with alternative lap core
Reduced the noise level up to 5dB
2.3.2. Hydraulic Core Stacking and Erection
Advantage:
Ensuring the quality of core manufacturing
2.3.3. Gap Core of Reactor Step-lap Paramagnetic Core Disc Cutting
r
Features:
Straight Core Lamination, Hydraulic core erection to prevent
fitting joints from displacement
Core lamination station to ensure effective levels of core degree
of stacking
Core rose steadily
Automatic cutting machine
for gapped core of reactor
Three-dimensional map of Reactor
Paramagnetic Core Disc
-7-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
8/67
Features:
Automatic step-lap stacking of silicon steel
The direction of silicon for core disc is as same as the main magnetic flux
Steel Sheet slot can be completely cut in required bevel at once
Advantages:
Improve effectively the magnetic line edge of core disc
Low electromagnetic noise and low overheating
Improve the mechanical strength of core disc
Low core loss
2.3.4. Vacuum-Pressure Resin Impregnated Oven for Core Disc
Functions and Features:
It pumps vacuum from the tank with glue in order to remove air bubbles.
Vacuum-pressure resin impregnated inside the tank.
Advantages:
Ensure mechanical strength of core disc firm
Low noise and low vibration
Passed the 5g core disc vibration test of resonance frequencies successfully
Vacuum-pressure resin impregnatedoven for gapped core
Core Disc
-8-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
9/67
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
10/67
Feature:
Winding coil with pre-set tension devices offering horizontal pre-set tension and axial
pre-set tension
Advantage:
Improve short circuit withstanding.
2.3.8. Hydraulic Transposition
Hydraulic transposition
2.3.9 Winding Block Assembly
Standard transposition shape
Transposition does not damage outsourcing
insulation of conductor
Procedure:
All windings and insulation parts areassembled at required positions
accurately on the platform.
Before the assembling of the windings,each winding is compressed firmly and
after the assembly of the windings, the
overall windings are compressed firmly.
The assembled windings are desiccatedby kerosene vapor and compressed again
the entire winding firmly.
Winding Block Assembly
Advantages:
To ensure accurate axial winding size and accurate distance between thewindings
To improve short circuit withstanding
-10-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
11/67
2.3.10 CNC Plasma Cutting
2.3.11 Plate Bending Forming
Feature:
No welding stress
No potential leak
Increasing the overall structural quality
2.3.12 Surface Sand-blasted
CNC plasma cutting machine
Little distortion during cutting
High dimensional cutting
1000 tons Hydraulic machine Cover bending chart
Sand Blast Room
The grade of removing rust is Sa 2
Ensuring paint adhesion firmly
Improving the corrosion resistance of products
-11-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
12/67
2.3.13 Special Paint Room
2.3.14 Lead Shield and Cold Welding
2.3.15 Vapor Phase Drying
Dry winding, phase assembly and active part.
Below 10Pa, the vacuum heating temperature can reach up to 125. Under this
condition, the vapor inside the insulation are dried thoroughly and heated evenly. Further
more, the insulation parts are not easily aging, and insulation contains water level that
can be controlled under 0.3%, 0.2% and 0.1% respectively as per different voltage
ratings.
Computer automatic controls the whole process.
Large sized paint room
Three-dimensional walking down structure which
ensures all surface spray in place Film uniform and magnificent, well adhered
Environmental Safety and protection
Leads connection adapts to the method of coldwelding and mechanical connections and the active
part tidiness reaches the requirement of high-voltage
and large-capacity.
The wrapping of leads shield insulation and theelectrode shape can meet the requirement of the high
electric field.
Vapor phase drying plant (MICAFIL)
-12-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
13/67
Detecting the water percent of insulation for adjusting the insulation quality by Moisture
Meter.
Reduce dielectric loss, enhance insulation strength and extend the service life.
2.3.16 Oil Processing and Preservation
Vacuum oil system is used for oil purification and storage. After the purification process, the
quality standard of oil can reach with: voltage withstanding >70kV, water content
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
14/67
2.3.18 Active Part Moisture Proof
2.3.19 Air Cushion Vehicle
The maximum load capacity of air cushion vehicle is 350 tons. The maximum load capacity of
560 tons or 630 tons can be loaded while using two air cushion vehicles in parallel.
2.4 INSPECTION AND TESTTING
The transformer products shall be subjected to the following type, routine, and special tests at
TBEA Shenyang Transformers Group Co. Ltd (hereafter TBEA Shenyang). The test shall be
carried out in the presences of the Purchasers representatives and all expenses will be
included in the quotation. If the test methods are not prescribed in IEC 60076 or other
standards, we agree that those test methods shall be subject to the agreement before the
contract between manufacturer and purchaser.
Dry air generator
Strictly control the dew point of compressing airat the outlet.
During assembling, the tank will be filled by dryair to prevent moisture on insulation surface of
active part.
Air cushion vehicle transporting productsAir cushion
1000kV ultra high voltage testing hall Product under test monitoring and control
room
-14-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
15/67
2.4.1 Radiographic Test
TBEA Shenyang can perform radiographic test on welded joints of the transformer according
to ASME Code Section V, clause 2. We are able perform radio graphic inspection for butt
welds joints including horizontal and vertical joints
2.4.2 Type Test
TBEA Shenyang can able to do Type Tests in the areas outlined below. We may not be able
to do the transportation test at acceleration equal to 2g however our design value is greater
than 3g. The following type tests can be done as per standard specified.
a. Temperature Rise Test IEC 60076-2/1993b. Gas in oil analysis (chromatographic analysis) (IEC 60076-2/1993, Gas in Oil
Analysis IEC61181/2007
c. Radio Influence Voltage Measurementd. Checking of the effectiveness of the Control Stray Flux Systeme. External Infrared Thermography of the tank.
2.4.3 Routine Test
TBEA Shenyang can able to perform routine test outlined from below. For PD detection
using UHF technique, we sometimes ask the manufacturers of PD monitoring systems and
UHF sensors to carryout the detection and cost of these are included in quotation if and only
if our client wants PD detection analysis. TBEA Shenyang can also be able to do seismic
withstand test standards like America standard IEEE 693/2005.
a. Core Insulation testb. Measurement of winding resistancec. Measurement of the voltage ratio and check of the voltage vector relationshipd. Measurement of short circuit impedancee. Measurement of load lossesf. Induced voltage test with internal partial discharge measurement
g. Measurement of no load loss and no load current (10 %, 90%110%) of the rated
voltage
h. Oil leak test,
i. Test on OLTC (On-load tap-changers)j. Dielectric testk. Tightness Testl. Insulation oil testm. SFRA Fingerprint testn. Measurement of power taken by fan and oil pump motors
2.4.4 Special Test
TBEA Shenyang can do special tests and some of them are:
a). Measurement of zero-sequence impedance
b). Measurement of no-load losses and exciting current at low voltagec). Measurement of the harmonic of the no load current
-15-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
16/67
d). Measurement of sound pressure, intensity and power level
e). Performance test
2.4.5 TBEA Shenyang can able to perform Insulation levels and Dielectric Tests
a). Applied potential test corresponding to insulation level of neutral
b). Lightening Impulse Test
c). Switching Impulse test for line terminals
d). Long Duration AC voltage test with partial discharge measurement
e). Measurement of the dielectric dissipation factor and the capacitance (at rated
frequency).
f). Measurement of insulation resistance and polarization index of all possible
elementary insulating zones of auto transformer
g). TBEA Shenyang can provide transformer capacitance equivalent circuit including the
capacitance value.
2.4.6 Lightening Impulse Test,
TBEA Shenyang can be able to perform Lightening Impulse test:
a). Rated lightening impulse withstand voltage 1.2/50 /sec.
b). The lightening impulse test, full wave according to IEC 60076-3/2000, clause 13.
c). The test with lightening impulse test chopped on the tail according to IEC 60076-3/2000clause 14.
d). The reduced full wave test for the crest value of the voltage
2.4.7 Rated switching impulse withstand voltage
2.4.8 Applied Potential test according to IEC 60076-3/2000 clause 11
2.4.9 Long Duration Induced AC voltage test with Partial Discharge measurement
a). The partial discharge measurement on maximum voltage which is according to IEC
publication 60270/2000
2.4.10 Test Plan
The table 1 below shows the schedule for test and measurement that can be done is sequential
order.
-16-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
17/67
Sequential
Order
Test Type
1 Radiographic Test
2 Check the effective of Control Stray Flux System
3 Oil Leak test
4 Tightness Test
5 Insulation oil Test
6 Measurement of winding resistance
7 Measurement of voltage ratio and check of voltage vector relationship
8 Measurement of insulation resistance and polarization index for all possible insulating zones of theauto-transformer
9 Core Insulation test
10 Long Duration Induced AC voltage test with partial discharge measurement and measurement ofdielectric dissipation factor and the capacitance
11 Measurement of no-load loss and no-load current
12 Lightening Impulse test
13 Switching Impulse test for the HV (400kV) line terminal
14 Performance Test and Applied Potential test corresponding to insulation level of neutral
15 Induced voltage Test with internal partial discharge measurement and Long Duration induced ACvoltage test with partial discharge measurements.
16 Measurement of no-load loss and no-load current again
17 Measurement of the harmonics of the no-load current
18 Measurement of Short Circuit Impedance
19 Measurement of Load Losses
20 Measurement of Zero-Sequence Impedance
21 Temperature Rise Test
22 Gas in oil analysis
23 Check the External Infrared Thermography of the tank
24 Test on On-Load Tap-Changers
25 Measurement of Sound Pressure/ intensity and power levels
26 Measurement of the radio influence voltage
27 Measurement of power taken by fan and oil pump motors
28 SFRA Fingerprint Test
29 Measurement of No Load Loss and exciting current at low voltage
30 All other Tests and Measurements shall be done as necessary and according to the requirementsand standards
Table 1: Schedule for Tests and Measurements
-17-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
18/67
2.5 COATING AND PAINTING SYSTEMS OF TBEA SHENYANG
Specification for Coating Requirements of Load Transformers. See Appendix 4 for detail
information of the coating and painting system of TBEA Shenyang.
TBEA Shenyang can able to provide the coating system to supply protection against any
atmospheric corrosion however we can not specify how long it can last without need for
maintenance. From our experience, the painting can last for about 4 to 5 years but paint
maintenance can be done when realized that the products need paint maintenance.
TBEA Shenyang can design anti-corrosion coating as per clients requirement according to
the transformer installation site environment. Paints shall be applied in the shop in the frame
of SSPC PA1 and cannot apply field painting. Internal surfaces shall be painted as TBEA
Shenyang applies in some of its products.
TBEA Shenyang makes sure that all external and internal paints of any transformer product
are to be compatible with the transformer oil we supply. TBEA Shenyang has been in the
transformer industry for more than 70 years of experience with proven record to make sure
painting does not affect or deviate the quality of the transformer oil.
The cover painting for the transformer will be thicker and it can include anti skid solution.
Since we have so much experience for coating systems, we are able to do anti skid coating
system on the cover.
The outer top-layer shade shall be by RAL 7038 and internal shade is fair.
TBEA Shenyang will make sure the final product will be good looking, homogeneous, free
from leaks and the product will have a good adhesion to the transformer matrix.
For maintenance for the damages from shipment, it is recommended that the paint can be
taken to the site to repair the damaged part.
2.5.1 Coating Procedure DescriptionThis may include surface preparation and treatment for problematic areas.
2.5.1.1 Preparation before coating
Before the coating of metal surface, it must be thoroughly degreased, remove oxidizing and
other contaminating materials attached on the surface, so that the coating can adhere to stick
cohere reliably on the metal surface.
-18-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
19/67
(a). Removing Oil
Should there be any greasy dirt discovered on the surface before the treatment of steel and
iron along with the painting of the product, we should proceed with oil removing process
immediately by dipping the cleaning rags in the toluene then wipe off thoroughly the greasy
dirt on the surface with the rags.
.
(b). Sand (Dirt) Blasting
(i). The transformer tank with all the accessories are kept in a closed door area and start
blasting the sand/dirt off.
(ii). After the blasting of steel and iron surfaces of the transformer and accessories, the steel
and iron are grayish white color that reaches the level Sa2.5.
(iii). Within 8 hours after the blasting of accessories, the coating process is applied to both
top and below of the surface.
(c). Pre-treatment of steel products
(i). Any product that uses steel should undergo the pretreatment process.
(ii). Pre treatment is applied to the welded parts of the tank that includes the welded joints.
The non homogeneous surfaces of welded joint parts, the greasy parts, and welded dregs are
thoroughly eliminated, thus revealing the true colors of steel and iron.
(d). Treatment of Acidic Phosphorization Cleaning
(i). Small and medium accessories along with long and large components are treated by the
use of acid cleaning Phosphorization process for treatment.
(ii). The coating process is applied to top and bottom surfaces within 48 hours of acidic
treatment on all the accessories (Besides the treatment of spare parts).
(e). The edge of tank and accessories - edge, joints and corners polishing process
(i). The top and bottom sections of the tank along with any elevated enclosure and any
similar surfaces are placed on gas cutting surface process to shear any plane that has exposed
edges and corners. This edging process must be done before the coating. The bevel edge
requirement is R3.
(ii). The top and bottom sections of tank are treated with any material that has not been
treated. After the treatment of the bottom material, there must be an abrade stain removal
processing. After the abrade processing surface condition, the colors of steel and iron
become real grayish white that can reach the Sa2.5 level.
-19-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
20/67
2.5.1.2 Brush Painting
(a). For painting, firstly dip the paint brush in the paint then carry on with brush painting. It
must guarantee the paint film evenly and required thickness.
(b). On every product edge, bend angle, flange and the back of the flange border with otheredge spots on the surface are to be brush painted before the spray painting is applied to all the
surfaces including top, bottom, edges, joints and corners. The required width of the brush
painting is 150mm from edges and corner lines within the scope of the whole surface for
brush painting. The brush paint is not only applied to the flat surfaces but also edges, corner
lines and narrow spot of the scope.
(c). For Anti Corrosion Requirement of paint, the brush painting is applied to the whole
flange surface by using a method called brush coating. This creates the coating corrugation.
(d). After the brush and spray paintings of edges and corners, it is a must that all the sections
are painted thoroughly as line upon line. The spray and brush painting thickness control isapproximately about 40m. This can protect the edges and corners from rust.
2.6 TRANSPORTATION OF PRODUCTS
TBEA Shenyang has well organized and arranged equipment that can able to lift, move, load,
unload and transport transformer products. It makes sure that the products are handled with care
when lifting and loading. After the loading, the products are loaded on carriers according to their
sizes and transported to the port to be exported to the clients destination. Appendix 5 covers theTransportation System in detail from one point to another for delivery.
2.7 ACCEPTANCE AND STORAGE OF PRODUCTS
2.7.1 Acceptance and inspection
When a transformer product arrives at the designated site, immediate inspection and
acceptance are required. Acceptance items are as follows:
(i). Check the position of the main body on transport vehicle and record impact (if any) on
the body. Should a visible displacement or impact is found, record the specified area,
picture shall be taken and contact the concerned transportation company at once. If
necessary, internal inspection shall be carried out by concerned people.
-20-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
21/67
(ii). Check rating plate, drawing of rating plate and some other documents, see whether the
products are in accordance with the contract.
(iii). Check if there is any document absent according to a documentation called List of
Transformer Documents.
(iv). Check if all accessories are at arrival site according to Packing List and inspect damages,
if so record and report accordingly.
2.7.2 Storage
(i). For transformer transported with nitrogen
a). First check the nitrogen pressure. It shall be positive pressure at normal temperature. If the
pressure is zero, the product is probably moistened. Further
inspection shall be made.
b). Test oil residual at the bottom of the tank. If the value of U is according to specific value
given in product instruction manual (generally is about U35 to 40 KV), water content(generally 25 to 30 mg/L) and the nitrogen pressure is positive, the transformer can be storedwith nitrogen for 3 months. Otherwise, the transformer shall be stored with oil and not with
nitrogen.
c). Nitrogen pressure shall be kept at 10-30kPa (refer to product manual for exact value)
during storage with nitrogen. If lower than 10kPa, its necessary to add nitrogen with purity
more than 99.99%, and with dew point lower than -40 C.
d). Checking of nitrogen pressure is done every week. If nitrogen pressure decreases rapidly
(even lower than 10kPa), there is leakage. Find out leakage point and take necessary actions
to fix it.
-21-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
22/67
c). If transformer is to be stored for more than 3 months or residual oil doesnt conform to
requirement of sub clause (b), the transformer shall be filled with oil for storage. In this case
conservator shall be mounted. Open blind flanges on tank cover, fill oil from valve at the
bottom of the tank to let nitrogen escape. Fill in oil to the required level. The oil filling
requirement is as follows:
U50KV, (generally, please refer to the product manual), water content to 20 mg/ L, (referto manual), tg
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
23/67
2.8.1 Check before operation
(i). Check if all the components are mounted according to their instructions. For example,
whether thermometer socket is filled with oil, whether earthing terminals on mounting
flanges of bushings and check whether dehydrating breather and the absorbent are in good
condition.
(ii). Check whether all the butterfly valves are in open condition
(iii). Check the indication and rotation of tap-changer to see if phase contacts are in step and
if oil compartment is filled with oil.
(iv). Check whether the terminals of bushing CT are connected well. The transformer is not
permitted to operate with secondary open-circuited.
(v). Check whether main body and earthing bushing of core are earthed.
(vi). Check if oil in conservator and in bushing is in required level.
(vii). Check the wiring of all kinds of protective, control and measuring devices. Check their
signal and actuation. Check fan-motor and controlling system of cooler (radiator).Check
rotation, oil flow direction of oil pump.
(viii). Check whether oil, water (in case of water cooler ) pipes of cooler are correctly
connected. Check whether they are blocked or whether there is leakage somewhere.
(ix). Check ratios at all tap-positions (pay attention to indicating position of driving units).
(x). Measure DC resistance at each tap position and compare them with the factory routine
test.
(xi). Check polarity of transformer, polarity and current ratio of bushing CT (polarity of CT
can be checked before mounting).
-23-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
24/67
(xii). Test oil according to the requirement (please refer to product manual).
Process of Acceptance to Operation of Product
LIFTING AND TRANSPORTATION
ACCEPTANCENOT MOIST IN TRANSPROTATION MOIST IN TRANSPORTATION
STORE TRANSFORMER WITH OIL
FILL OIL ESCAPE NITROGENSTORAGE WITH NITROGEN
INSPECTION BEFORE ASSEMBLY INNER INSPECTIONAND INSTALL BUSHINGFILL OIL ESCAPE NITROGEN
MAIN BODY DRYING TREATEDTRANSPORTED WITH NITROGEN
FINAL ASSEMBLY
RELEASE VACUUM
VACUUM PUMPING
OIL FILLING UNDER VACUUM
INSTALL CONTROL CIRCUIT
OILNESS DONT ACHIEVE STANDARD OR MOISTENEDHOT OIL CIRCULATION
TIGHTNESS TEST FOR TRANSFORMER
TEST AND INSPECTION BEFORE OPERATION
FILL OIL AND PLACE FOR 48HOURS
OILNESS U50Kv, WATER CONTENT15ppM, GAS CONTENT15%, tg0.5%
OPERATIONDISMANTLE SUPPORT FOR INSTALLATION ETC.
PATCH PAINT ON
SURFACE
Fig. 3 The process of acceptance and operation of products
-24-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
25/67
2.8.2 Test Before Operation
(i). No-load test
Before test, connect the signal contact of Bucholz relay to the trip circuit of transformer.
Over current protection shall react instantaneously. The source side of transformer is
provided with the protecting device. Connect source to that side of Transformer in order to
cut off the source in abnormal condition. Then raise the voltage slowly to the rated voltage.
Remain it for 30 minutes. Measure on-load loss and on-load current and compare them with
factory routine test.
(ii). No-load impulse test
First, reset the over current protection of Buchholz relay. When the protecting breaker is
switched on, phase timing difference is less than 0.01s. Impulse voltage is the rated system
voltage and is applied on HV side. The switching time of the breaker is not more than 5
times, During the impulse, voltage (including the first time impulse) once reaches the peak
value and the test is regarded as passed. If no peak value appears during the 5 impulse tests,
the impulse test is passed too. Neutral point shall be earthed for neutral point earthing
transformer.
(iii). If top oil temperature rise does not exceed 50k when the transformer is operated under
rated voltage for 6 hours at no-load, its not necessary to start coolers.
-25-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
26/67
(iv). On-load tap-changer test shall be done according to its instruction. Cooling system and
control circuit shall be tested.
(v). Do the other routine tests according to requirements.
(vi). After the test, connect the signal contacts of Buchholz relay to the alarm circuit and the
trip contacts to the trip circuit. Set the value of over current protection.
(vii). After the tests, make chromatogram analysis of oil, compare the values with those got
before the tests.
2.9 OPERATION AND MAINTENANCE
2.9.1 First, start cooling system (for OFWF system, start oil pump first and then water pump).
If the coolers operate well (operate for more than 1 hour), put transformer into operation.
2.8.2 If a part of coolers operate, the burden can be calculated according to the following
formula:
KVA,Sp
pnpSn H
k
0
=
Where:
Snburden carried by n coolers, KVA
Pthe heat burden of each cooler under the full burden operation of transformer, KW
P=(P0+Pk)/(N1)KW
Nthe number of the mounted coolers
P0no-load loss under the rated voltage and rated frequency, KW
Pkload loss at appropriate tap at full load, KW
SHrated capacity of transformer, KVA
nthe number of the operated coolers (nN1)
2.9.3 During operation, inspect the core by the core earthing bushing. Connect the meter
before cutting off the earthing bushing. Pay attention to the high voltage caused by
instantaneous open circuit. The earthing bushing shall be reliably earthed again aftermeasurement.
-26-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
27/67
2.9.4 Oil adding during operation
Extended from gas sampling device of conservator are two pipes, one is oil adding pipe with
butterfly valve at end, the other is oil draining valve. Add oil from oil filling pipe, meanwhile
open gas release plug on butterfly valve. Close plug and open butterfly valve (exhaust gasfrom pipe) after oil overflow from plug, and then add oil till normal level, close butterfly
valve and cover plate.
2.9.5 If oil can be seen from the inspection window on gas sampling device, its necessary to
open the valve on gas exhausting pipe to release gas. Close the valve when oil level rises
above inspection window.
2.9.6 In the first operating month of transformer, take oil sample for test and chromatogram
analysis every week.
2.9.7 During operation, transformer oil shall conform to the following requirements at least:
U40KV, water content25mg/L, tg4% (at 90.) Please refer to the product manual.
2.9.8 Maintenance and periodical inspection of components are stated in their instructions.
2.9.9 For OFAF transformer, when the fan of coolers stop, oil pump is still running,
transformer can continue to operate as long as top oil temperature doesnt exceed 53K.
2.9.10 For OFWF transformer, if ambient temperature for cooling system is lower than 0,
cold-proof measures shall be taken. When water-cooled coolers are stopped, water inside the
cooler shall be drained off.
3.0 TRANSFORMER MAINTENANCE RECORD
TBEA Shenyang has been and continues to provide liable service even after sales through our
After Sales Service department. We continue to communicate with our clients on the status ofour products to make sure they are in good operational conditions.
Should there be any failure; the necessary measures are taken immediately to rectify the
failure. TBEA Shenyang is not only reliable in designing, manufacturing and other areas of
concern but also reliable in providing after sale service to the satisfactorily of our valuable
clients. TBEA Shenyang longs to maintain a good and reputable relationship with its clients
even to act swiftly to meet the requirements and urgent needs of its clients. Table 2 and Table
3 show the major test and field failures respectively which have been recorded and rectified
to the satisfactorily.
-27-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
28/67
3.1 Test Failure Rate (69kV and above transformers)
Year 2004 2005 2006 2007 2008 2009 Total
Total
Units
Tested
150 195 204 247 259 201 1256
Major
Test
Failure
0 1 3 1 1 2 8
Test
failure
rate (%)
0.0 0.5 1.5 0.4 0.4 1 0.6
Industry
Standard
Failure
Rate (%)
2.0 2.0 2.0 2.0 2.0 2.0 2.0
Table 2: The major test failure of transformer products from 2004 to 2009.
According to Table 2, the major test failure means any test failure that requires to un-tank the
C&C assembly for repairing. HVDC and Shunt Reactor units are not included on the list.
3.1.1 Major highlights as per table 2.
(i). The products of TBEA Shenyang were in operation performing outstanding performance
(ii). More than 1000 units were tested over the last 6 years with only 8 major failure tests.
(iii). Yearly and total rates are much lower than industry standard failure rate (2%)
(iv). Root causes of failures;
(a). Five failures were related to manufacturing processes
(b). Two due to defective materials
(c). One related to design practices
3.2 Field Failure Rate (69 kV and above Transformers)
3.2.1 Major highlights as per table 3.
(i). The products of TBEA Shenyang were in operation performing outstanding performance
(ii). More than 1200 units were installed over the last 10 years with only 2 major failure.
-28-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
29/67
(iii). Root causes of failures;
(a). One failure was related to defective material (conductor)
(b). Another failure was due to defective accessories (bushing)
Year 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 Total
Units
installedeachyear
83 92 97 78 85 120 135 162 187 221 118 1378
Units
withmajorfailure
during
service
0 0 0 1 0 0 0 0 1 0 0 2
Table 3: The major field failure of transformer products from 1999 to 2009.
(iv). Solution of each failures;
(a). Product was sent back to the factory and replaced the defective material
(b). The product was sent back to the factory and replaced the bushing
(v). Current Status of these products.
(a). They have been installed back on time and are currently operating smoothly.
4.0 EXPORT REFERENCE LIST
TBEA Shenyang has been manufacturing transformer products for over 70 years. With its
corporate vision to expands and provide reliable services at the global stage, TBEA Shenyang
has been working with various clients of the around the world. We have our office for North
American market is located in Pasadena, US. We also have offices in Philippines, Pakistan,
India, and South Africa to name a few. Please refer to Appendix 6to see export references of
TBEA Shenyang since 1987 to North America, Gulf Region and General Reference.
5.0 CUSTOMERS ACKNOWLEDGEMENT LETTERS
During the years of its production, TBEA Shenyang has been working with its clients with
respect and understanding. Many of these have valued the liable service provided by TBEA
Shenyang. Appendix 7 shows acknowledgment letters from various customers to express
their honest view about the products.
-29-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
30/67
APPENDICES
Appendix 1: ISO Certification and other approvals
ISO 9001:2008 FM CertificateISO 14001:2004 Certificate
-30-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
31/67
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
32/67
Appendix 2: Procurement and Purchasing
1. Aim and Scope
This procedure applies to the purchase control of raw materials and parts required by transformers and reactors a
2. Standard cited
GB/T 190002000 Quality Management Systemfoundations and terms
GB/T 190012000 Quality Management Systemrequirements
3 Responsibilities
The Purchasing Department is in charge of applying for investigating supplier. The Management Information D
assessment. The Management Information Department, Quality Control Department, Technological Center, P
Department will participate in the assessment of the supplier. The Technological Center and Process Depa
standard and requirements for process. The Quality Control Department is in charge of inspection.
4. Assessment of the supplier
4.1 Input
4.1.1 Prerequisites for qualified suppliers
a). Products of the supplier must have a Production License (within the term of validity) and observe the prstandard during the production and inspection.
b). Supplier must have the capability of examining and testing its products. Examination and test records as wel
If some particular items can not be examined or tested, the examination and test must be done in a test unit w
qualified report should be offered.
-32-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
33/67
c). Suppliers products must meet our companys requirements for design, process, test and other relevant condit
d). Suppliers products must pass the test of our company with a year of trial use.
e). Its production capability, production conditions, equipment and production process must meet the requiremen
4.1.2 Material Grading
The Purchasing Department classifies the suppliers products into three grades, A, B and C in accordance with
Features of Main Common Materials for Transformers (Q/TT J31.02.2-2005) of TBEA Shenyang Transformer G
4.2 Assessment of the supplier
4.2.1 Evaluation of new suppliers raw materials and parts of A and B grades
According to the prerequisites for designated manufacturers proposed by the Purchasing Department, the Head oDepartment develops the inspection plan, method of investigation and form of evaluation, reports it to the chief e
after obtaining approval. Specific steps are listed as below:
a). If it is necessary to make an inspection of the suppliers factory, the Management Information Depart
supervisor of the Technological Center, Process Department, Quality Control Department and the Purcha
inspection.
b). In accordance with their respective duties and powers, personnel participating in on-site inspection define th
every department participating in the assessment of suppliers must make strict examination and evaluation of
item-by-item inspection according to each departments requirements for products, carefully complete the recsubmit it to the supervisor of the Management Information Department after signing their names;
c). Supervisors of the Management Information Department shall organize relevant personnel to complete the
and Raw Materials of Transformers according to the on-site inspection record. After signed by the inspectors, it
of the company for approval. He/she will decide whether to purchase the products for trial use. If approved, the
-33-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
34/67
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
35/67
5.2 Contract signing
The purchaser will sign a contract or an agreement with the qualified supplier according to the purchase plan. A
approval of the planner, head of the department, supervisor of the company and project manager by signing thei
the company in quadruplicate. The contract will be kept by the supplier and the company.
5.3 Product verification
After the raw materials and parts enter the factory, the purchaser will complete the Material Acceptance List, m
Logistics Center the next day. At the same time, necessary quality certificates of the items sent for verification
who will inform the Quality Control Department to check the materials according to the practice and dispose them
a). If Qualified, the materials will be stored in the warehouse following the Warehouse Management Procedur
b). If Substandard, the materials will be returned or be viewed as inconsistent with the certificate (substitut
Control Procedure. The keeper can also apply for concession.
5.4 Reimbursement
The purchaser goes to the Finance Department with the list of materials received signed by the examiner to r
Finance Department will check if it is the product offered by the Qualified Supplier List. If it is, the payment w
reimbursed only if relevant purchase approval formalities are available.
5.5 Emergency clearance
Follow the Emergency Clearance ProcessQG/SB35.952004.
-35-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
36/67
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
37/67
6.5 The Purchasing Department shall evaluate periodically the quality performance of the supplier and mak
disposal according to its qualifications. If the supplier has many problems with quality or the problem is very
(following Article 4 of this procedure).
6.6 The Management Information Department, Purchasing Department and Quality Control Department
evaluation of the supplier (1-2 years).
7. Supplier Assessing Process Chart
Chart 1: (i). Purchase Control Procedure QG / TB35.38.36 2001
-37-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
38/67
(ii). Form of Investigation on Trial Use of the Transformer Parts and Raw Materials, Form of investigation on the
Approval Form of Suppliers of Parts and Raw Materials of Transformers which is shown in table 1 of this appendix.
Approval Form of Qualified Suppliers of Parts and Raw Materials of Transformers
Serial No.: Date:
1. State of Trial Use
Supplier
Goods supplied
Result of incoming testing
State of in-house trial use
State of installation and trial use
2. State of Production and Ex-factory Inspection
Productivity
Testing equipment
Result of periodic apparatus and instruments testing
Testing standard and relevant systems
Testing record
Result of sample testing
3. State of Raw Materials, Measuring instruments and after sale service
Result of raw materials and parts testingResult of measurement testing
State of after sale service
4. Technical Documents
Process documents and national standard
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
39/67
Product instructions
Ex-factory testing record
Product quality inspection report
5. Suggestions on rectification and reform & assessment conclusion
Quality Control Department Technical Center ProcessDepart
Management Info. System Purchasing Dept
Approved: Date
Table 1: Approval Form for Qualified Suppliers
-38-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
40/67
Appendix 3: Design and Development of Products
Designing process is the integral part of the entire process. TBEA Shenyang invests much effort and time to meet
during the designing process. Chart 2 shows the design & development process.
K
Customers Technical
Specification & Requirement
Consideration & approval by
International Department
Project Management
Design and Development
Planning, R&D, Analyze Technical
Specification Satisfactory
Yes
No
Further information
and/or clarification
Design and Development Process
(application of technical
specification & required
standards) and Design approval
No
Ask for
clarification
Yes
Liaise and agreement with
Purchasing department and
other relevant departments
Review, approval
and comments by
senior/chief
engineers and
consultants
International Department
Project Management
Customers
comments, design
and technical review
A rove
Design and Technical Review
Questions and Answers
Is customer
satisfied?
Quotation Process and
Contract Agreement
ProcessesNo
Yes
Clarification
Char
-39-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
41/67
1. Design and development planning
To meet quality characteristics, statutory and regulatory requirements, contract requirements and to avoid errors
our company controls the processes of design and development strictly.
The Technical or Design Center organizes the design and development planning, reviewing, verification and val
stages to ensure effective communication and clear assignment of responsibility.
2. Design and development inputs
The design and development department determines the inputs relating to products and maintains records
performance requirements of contracts, statutory and regulatory requirements, information derived from previous
essential for design and development. These inputs are reviewed for adequacy.
3 Design and Development Output
The outputs of design and development are in a form suitable for verification against the design and developme
drawings. Design and development outputs shall provide appropriate information for purchasing, production and
product acceptance criteria, and specify the characteristics of the product that are essential for its safe and proper
4 Design and development review
Systematic reviews of design and development shall be performed to evaluate the ability of the results of design
and to identify any problems and propose necessary actions. Records of the results of the reviews and any
Manufacturing Engineering Department approves the drawings or changes drawings and chooses the optimal
quality products with economical and reasonable manufacturing methods. Records of the results of the app
maintained.
-40-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
42/67
5 Design and development verification
Verification is performed by Technical Center in accordance with planned arrangements to ensure that design a
design and development input requirements, the input of design stage includes contract, technical agreement anresults of the reviews and any necessary actions are maintained.
Manufacturing Engineering Department performs the verification to ensure reasonableness and applicability o
manufacturing procedures, materials and equipment, and to ensure the product quality stability, low cost, etc. in
Records of the results of the reviews and any necessary actions shall be maintained.
6 Design and development validation
Validation is performed by Technical Center in accordance with arranged plan to ensure that the resultin
requirements for the specified application or intended use. When required the Service Center asks for a "p
customer. The relevant departments provide verification information. Quality Assurance Department provides
Technical Center conducts the verification for new products. It maintains the records of the validation and verific
7 Control of design and development changes
Design and development changes are identified and records maintained by Technical Center, the changes ar
appropriate, and approved before implementation. Technical Centre and Manufacturing Engineering Departm
development changes and maintain records of the results of the reviews of changes and any necessary actions.
-41-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
43/67
Appendix 4: Painting System of TBEA Shenyang
TBEA Shenyang has a lot of experience with the following painting systems.
A. Epoxy zinc-rich primer + Epoxy micaceous iron oxide primer + Polyurethane
1. The inner surface painting requirement:- Epoxy Primer (white) once- The thickness of the Paint Film is about 40-50m
2. The requirement of the outer surface painting- First painting: Epoxy zinc-rich primer twice. The thickness of the Paint Film is about 40-50m.- Second Painting: Epoxy micaceous iron oxide primer twice. The thickness of the paint film is about 1- Third Painting: Acrylic polyurethane enamel twice. The paint thickness is about 50m
The total thickness of the outer surface paint film is not less than 250m
3. The brush and spray painting of tank cover for Anti skid
The routine process of fully painting the top surface of the tank. Brush painting the top cover of the tank for Anti
tank cover is greater than 350m.
B. Epoxy primer + epoxy paints + Polyurethane series
1. The inner surface painting requirement- Thick epoxy primer (white) once- The thickness of the Paint Film is about 40-50m
2. The requirement of the outer surface paintinga) First painting: Thick Epoxy primer (white) twice. The thickness of the Paint Film is about 60-80m.
-42-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
44/67
b) Second Painting: Epoxy micaceous iron oxide primer once. The thickness of the paint film is about 4c) Third Painting: Thick epoxy intermediate coating twice. The paint thickness is about 160 -200m.d) Acrylic polyurethane enamel twice. The paint thickness is about 50m
The total thickness of the outer surface paint film is not less than 350m
3. The brush and spray painting of tank cover for Anti skid
The routine process of fully painting the top surface of the tank. Brush painting the top cover of the tank for Anti
tank cover is greater than 450m.
-43-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
45/67
Appendix 5: Product Transportation System
The transportation system of TBEA Shenyang to lift, load and transport transformer products at various points.
Starting Point: TBEA Shenyang Transformer Group Co.,Ltd. No. 32 Kaifa Avenue Tiexi District Shenyang 1
Destination: Customers approved port
Transportation MethodIntermodal
1. TBEA Shenyang Transformers Factory Port of China (Dalian or Tianjin, here we choose Dalian Port for ill
2. Port of China Customer Designated Port: By sea
3. Customer Designated Port Transformer installation site : By Truck, Jack and Roll
4. TBEA Shenyang Transformer Factory Dalian, China : By Truck
Routine: From Factory to Port
Distance: 356 Km, Freeway, Bridge, Road available for truck, no obstacle.
5. Options for available trucks
5.1. Heavy Transaction Engine
a. WILLEME TG300
-44-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
46/67
b. Yiweike EZ250
Type EZ250
Rated Power525Horse
c. MAN FE600A
Rated Power600Horse
2350
3350
3740
9270
3500
1625 1625
TypeTG300
Made in: France
Drive Model: 8x 8 Transactions, Hustle
Rated Power: 600 horse
-45-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
47/67
5.2. Heavy Smooth Trailer
Nicolas Heavy Rigger
Made byNicolas, France
Type: NICOLAS STG17.15
Single Axial3 Ton
Max. Loading Weight per Axial29 Ton
Axial Distance1.6M
Width: 3.63M
Trailer Height: 1.080.27M
6. Transportation Arrangement - The following procedures are followed
6.1 Truck Preparation and Coordination
Check details of the truck after Notification of Loading the Goods.
Check Truck as per Operation and Maintenance Manual
Function Test of Trailer on Brake, Transaction for : Emergency &Positive Brake
Trailers Hydraulic Device Leakage Checking
Tyre Pressure Checking
Commissioning of Truck
-46-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
48/67
Hydraulic 300MP Min.
Hydraulic Meter Margin: 20% Max.
6.2 Loading of Transformer
Before Loading: Physical Inspection, Measurement checking will be performed and record measurement
Smoothing Trailer Parked on the dedicated place.
Remark will be taken on the loading position, gasket for increasing the friction.
Gravity Checking
13mm Steel Rope, 5 Tons Steel Ring Rope20mm Screw Device for safety banding the transformer d
Timely inspection for impact recorder and Automatic Nitrogen Filling Device.
6.3 Road Arrangement
Constant Communication Walkie-talkie, Mobile phone, Navigator,
SpeedBend Pass 2Km/h Bridge Pass: 5Km/hMax: 15Km/h
Bridge PassConstant SpeedShift, Brake, Acceleration Not Allowed.
Cross Roads and Other High Obstacle: Min Speed, Person Inspection
Unsmooth Road Pass: Radial and Axial Smoothing Adjustment, Trailer Smooth, 3g Max.
-47-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
49/67
Rest During NightMain Hydraulic to Min, Shut Down All Hydraulic Handle
Check Safe of Goods for Each Parking
6.4 Number of required days: Truck Available = 3 Days, Loading = 1 Day, Road Transportation = 3 Days
7. Port of China - Customer approved destination port: By sea
a) Stowage and Calculation (by loading instrument)
Calibration of initial stability height at ships departure
After correction of free water Gmo=1.69m
Rolling period T=13.9 seconds
Conforming to navigation requirements
b) Dunning of Heavy Lift
To be decided in accordance with the strength surface of bottom of heavy lift. Taking the TURBINE PAC
Cargo given: Dunnaging materials: Log: 10*10*200cm, Dunnaging surface: (4 supporting beams) 49m2
Dunnaging method (See sketch)
-48-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
50/67
Transformer Load below Deck
Transformer Safety Position at Sea
2x300MT MF Crane of Heavy Vessel
-49-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
51/67
Appendix 6: Export Reference List
1. The export reference for North America
Voltage (kV)
Countr
y
Name
of
Client
Client Contact
Name
and Ph #
Qt
y
Capacit
y
(MVA)
No. of
windin
g
Freq
.
(Hz)Primar
y
Secondary
Tertiary
Coolin
USALADW
P
Mr .Bina
Vatanpour
( 213 )3672212
1 900 three 60 235 225 buried OA/FA
USA LADW
P
Mr. BinaVatanpour
( 213 )3672212
1 533 three 60 525 230 13.8 FOA
USALADW
PMr. Bina
Vatanpour( 213 )3672212
4 133 three 60 525/3 230/3 13.8 OA/FA
USALADW
PMr. Bina
Vatanpour 3 16 three 60 34.4 5040V ONAN
USALADW
P
Mr. Bina
Vatanpour( 213 )3672212
8 160 three 60 287.5 138 13.8 OA/FA
USASDG&
EMr. Carlos Cuevas
(626) 79599551 224 three 60 230 69
ONAN/ONAF
Canada
Hydro
NEE
PAWA
Mr. Ross Lowry(204) 4743834
1 95 three 60 230 132.8 66ONAN/ONA
F
USA
AES
Corp.Mr.Vijai
(703) 522 13151
632MVA
three
50 500 15 15 OFA
-50-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
52/67
Voltage (kV)
Country
Name
ofClient
Client Contact
Nameand Ph #
Qt
y
Capacit
y(MVA)
No. of
winding
Freq
.(Hz)
Primary
Secondary
Tertiary
Coolin
USA
AES
Corp.Mr.Vijai
(703) 522 1315 1377MV
A three 50 500 20 ODA
USA
AES
Corp. Mr.Vijai(703) 522 1315
1300MV
Athree 50 220 132 13.2 OFA
2. The export reference list for Gulf Region
No Time CountryProduct
Specification
Quantity
(Set)
Clients Name and
Contact person
1 1992 Turkey 63MVA, 141/11kV 2
2 1994 Syria 125MVA, 242/13.8kV 6
3 1998 Iran 63MVA, 230/6.9kV 63
4 Nov. 1998
United Arab
Emirates
(UAE)
1001000kVA,
11/0.433kV
615
5 1999 Iraq 95kVA, 132/10.5kV 2
6 1999 Iraq 8MVA, 135/6.6kV 2
7 Oct. 1999 UAE 90MVA, 220/132kV 2
-51-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
53/67
No Time CountryProduct
Specification
Quantity
(Set)
Clients Name and
Contact person
8 2000 Syria 20MVA, 66/20kV 2
9 2000 Egypt 125MVA, 220/66kV 3
10 May 2000 UAE 11/0.433kV, 500kVA 20
11/0.433kV, 100KVA 200 11 April 2001 UAE
11/0.433kV, 250KVA 100
12 2001 Iran 125MVA 230/10.5kV 3
13 2001 Iran 125kVA, 132/10.5kV 2
14February,
2002
UAE11-6/0.415kV,
1500kVA
50
2002 Iran50MVA
154/132/20kV1
2002 Iran 50MVA 154/10.5kV 1 15
2003 Iran160MVA
230/154/20kV1
Sep, 2003 UAE 100KVA11/0.433KV 250
16
Sep, 2004 Turkey 160MVA400/36/13.8kV
1
250KVA11/0.433KV 100 17 Nov, 2004 UAE
500KVA11/0.433KV 200
-52-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
54/67
No Time CountryProduct
Specification
Quantity
(Set)
Clients Name and
Contact person
1500KVA11/0.433KV 100
18 Oct, 2005 Iran 75MVA 66/10.5kV 2
2000KVA11/0.433KV 80 19 Oct, 2005
United Arab
Emirates 100KVA11/0.433KV 249
20 Jan, 2005United Arab
Emirates100KVA11/0.433KV 200
5750KVA33/0.415KV 2 21 Dec, 2005 UAE
2000KVA33/0.415KV
160MVA 400/13.8kV 1
22 April, 2008 Turkey 160MVA
400/36/13.8kV
240MVA 400/20kV 4
80MVA 33/20kV 1
40MVA 20/6.3kV 1 23 Dec, 2008 Turkey
25MVA 20/6.3kV 1
240MVA 400/20kV 3
80MVA 33/20kV 1
40MVA 20/6.3kV 1 24 April, 2009 Turkey
25MVA 20/6.3kV 1
-53-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
55/67
No Time CountryProduct
Specification
Quantity
(Set)
Clients Name and
Contact person
25 Feb., 2009Saudi
Arabia
SFZ-133000/115 1
United International Trading C
CrissyRubrico P.O.Box75599AlKhobaKSAT+96638812227 F+966388122www.uitc.com.sa [email protected]
26 June, 2009 Iraq SF-75000/132 2
27 30-Sep-09 Turkey 720MVA 400/20kV 1
28 30-Apr-10 Turkey 720MVA 400/20kV 2
29 August, 2010 Iraq SFF-31500/20 4
30 August, 2010 Iraq SFFZ-50000/110 2
3. General Export Reference List from 1987-2008
The transformers & reactor exported by TBEA Shenyang Transformer Group Co., Ltd (Former: SHENYANG TR1987 are as follows:
Voltage (kV) Capacity(MVA)
Country Qty No. ofwinding
Freq.(Hz)
Primary SecondaryTertiary
Cooling
Si
180 China * 1 three 50 242 121 11 OFAF
250 Pakistan 2 two 50 220 15.75 OFAF
40 China * 2 two 50 110 27.5 ONAN
25 China * 6 two 50 110 27.5 ONAN
25 Pakistan 1 two 50 220 6.9 OFAF
25 Pakistan 1 two 50 130 6.6 ONAF
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
56/67
25 Pakistan 2 two 50 15.75 6.6 ONAN
250 Pakistan 1 two 50 220 15.75 OFAF
167 China * 4 three 50 550 220 34.5 OFAF
52.7 China * 1 two 50 220 22 OFAF
25 Pakistan 1 two 50 15.75 6.6 ONAN
160 Pakistan 6 three 50 220 132 11 OFAF
60 Thailand 2 two 50 112 24 ONAN/ONAF
60 Thailand 2 two 50 112 24 ONAN/ONAF
40 Thailand 2 two 50 67 12-24 ONAN/ONAF
160 Pakistan 4 three 50 220 132 11 OFAF
150 Bengal 2 two 50 242 15.75 OFAF
150 Bengal 2 three 50 230 135 34 OFAF
150 Vietnam 1 two 50 20 11 OFAF
63 Turkey 2 two 50 141 11 OFAF
62.5 Indonesia 1 two 50 150 20 OFAF
60 Thailand 2 two 50 112 24 ONAN/ONAF
60 Thailand 3 two 50 67 12-24 ONAN/ONAF
60 Thailand 9 two 50 67 12-24 ONAN/ONAF
50 Thailand 1 two 50 112 22 ONAN/ONAF
44 Indonesia 5 two 50 20 11 OFAF
37.5 Philippines 1 two 60 115 13.8-13.8 ONAN/ONAF
10.7 Pakistan 1 three 50 132 11.5 3.45 ONAF
10 Indonesia 2 two 50 20 3.45 ONAF
10 Indonesia 5 two 50 11 3.45 ONAF
13 Pakistan 2 two 50 132 11.5 ONAN/ONAF
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
57/67
250 Pakistan 2 two 50 235 15.75 ONAF
160 Pakistan 2 three 50 220 132 11 ONAN/ONAF
90 Malaysia 4 two 50 132 33 ONAN/ONAF
60 Thailand 7 two 50 67 12-24 ONAN/ONAF
45 Malaysia 2 two 50 132 33 ONAN/ONAF
30 Malaysia 10 two 50 132 11 ONAN/ONAF
30 Malaysia 10 three 50 132 11 10 ONAN/ONAF
26 Pakistan 22 two 50 132 11.5 ONAN/ONAF
25 Pakistan 2 two 50 15.75 6.9 ONAN
25 Pakistan 1 two 50 230 69 ONAN/ONAF
15 Malaysia 2 two 50 132 11 ONAN/ONAF
15 Malaysia 7 three 50 132 11 10 ONAN/ONAF
7.5
Malaysia
2
two
50
132
11
ONAN/ONAF
380 Pakistan 1 two 50 235 20 ODAF
300 China 5 two 50 550 15.75 OWAF
125 Syria 6 two 50 242 13.8 OWAF
90 Malaysia 6 two 50 132 33 ONAN/ONAF
60 Malaysia 2 three 50 132 22 10 ONAN/ONAF
45 Malaysia 2 two 50 132 33 ONAN/ONAF
40 Pakistan 2 two 50 20 6.6-6.6 ONAN/ONAF
30 Malaysia 2 three 50 132 11 10 ONAN/ONAF
12.5 Pakistan 2 two 50 132 6.3 ONAN/ONAF
8 Viet Nam 3 two 50 13.8 3.3 ONAN
150 Bangladosh 2 two 50 242 15.75 ODAF
63 Malaysia 2 two 50 132 10.5 ONAN/ONAF
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
58/67
25 Bangladesh 1 two 50 20 6.3-6.3 ONAN/ONAF
15 Antigua 1 two 50 69 11 ONAN
10 Malaysia 1 three 50 132 6.3 ONAN
10 Malaysia 2 two 50 10.5 6.3 ONAN
41.7 Bangladesh 1 two 50 132 34.5 ONAN/ONAF
8 Viet Nam 3 two 50 13.8 3.3 ONAN
150 Bangladosh 2 two 50 242 15.75 ODAF
63 Malaysia 2 two 50 132 10.5 ONAN/ONAF
25 Bangladesh 1 two 50 20 6.3-6.3 ONAN/ONAF
15 Antigua 1 two 50 69 11 ONAN
10 Malaysia 1 three 50 132 6.3 ONAN
10 Malaysia 2 two 50 10.5 6.3 ONAN
41.7
Bangladesh
1
two
50
132
34.5
ONAN/ONAF
40 Vietnam 3 two 50 110 1.5 ONAN/ONAF
50 Philippines 1 two 60 115 34.5 OFAF
50 Thailand 10 two 50 115 23.1 ONAN/ONAF
25 Philippines 2 two 60 34.5 3.45 ONAN/ONAF
4.3 China* 2 two 50 66 6.3 ONAN
2 China* 2 two 50 66 6.3 ONAN
300 Pakistan 1 two 50 230 15 ODAF
190 Pakistan 3 two 50 230 11.5 ODAF
160 Pakistan 2 three 50 220 132 11 ONAN/ONAF
25 Pakistan 2 two 50 11.5 6.3 ONAN/ONAF
50 kVA Indonesia 6252 two 50 20 0.4 ONAN
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
59/67
63 Iran 2 two 50 230 6.9-6.9 ONAN/ONAF
40 Iran 4 two 50 20 6.9-6.9 ONAN/ONAF
15 Malaysia 20 two 50 132 11 ONAN/ONAF
5.2 Vietnam 2 two 50 15 0.38 ONAN
125 Iran 6 two 50 400 10.5 ONAN/ONAF
125 Iran 3 two 50 230 10.5 ONAN/ONAF
125 Iran 2 two 50 132 10.5 ONAN/ONAF
100 Philippines 2 three 60 138 69 13.8 OA/FA/FA
10 Burma 2 two 50 66 11 ONAN
60 Malaysia 6 three 50 132 22 11 ONAN/ONAF
90 Malaysia 50 two 50 132 33 ONAN/ONAF
26 Pakistan 18 two 50 132 11.5 ONAN/ONAF
40 Pakistan 1 two 50 132 12 ONAN/ONAF
20 Syria 2 two 50 66 20 ONAF
125 Egypt 3 three 50 220 66 11 ONAN/ONAF
95 Iraq 2 two 50 132 10.5 ONAN/ONAF
8 Iraq 2 two 50 135 6.6 ONAN
26 Pakistan 3 two 50 132 11.5 ONAN/ONAF
400 Yugoslavia 2 three 50 400 231 10.5 OFAF
40 China 8 two 50 116 10.5 ONAN/ONAF
25 China 2 two 50 116 10.5 ONAN/ONAF
120 China 3 three 50 550/ 3 242/ 3 35 OFAF
720 China 1 two 50 550 20 ODAF
840 China 2 two 50 550 20
250 China 3 three 50 550/ 3 242/ 3 36 ODAF
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
60/67
160 Iran 1 three 50 230 154 20 ONAN/ONAF
50 Iran 1 three 50 154 132 20 ONAN/ONAF
250 China 7 two 50 550/ 3 22 FOA
160 Pakistan 2 three 50 220 132 11 ONAN/ONAF
71 Pakistan 1 two 50 550/ 3 13.2
ODWF
100 China 3 two 50 242 10.5 OFWF
282 China 8 two 50 525/ 3 199/ 3 ODAF
160 Pakistan 4 three 50 220 132 11 ONAN/ONAF
100 China 3 two 50 242 13.8 OFWF
900 America 1 three 60 235 225 buried OA/FA/FA
250 China 6 two 50 500 22 FOA
63 China 2 split 50 22 6.3-6.3 OA/FA1/FA2
150 Pakistan 8 three 50 525/3 231/3 23 ONAN/ONAF1 /ONAF2
370 Indonesia 2 two 50 150 20 OFAF 533 America 1 three 60 525 230 13.8 FOA
10Mvar America 4 one 60 230/3 OA
200 Pakistan 4 three 50 525/V3 231/V3 23 ONAn/ONAF1 /ONAF2
160 Pakistan 6 three 50 220 132 11 ONAN/ONAF
40 Congo 4 two 50 242 10.5 ONAN
133 America 4 three 60 525/V3 230/V3 13.8 OA/FA/FA
200 Pakistan 4 three 50 525/3 231/3 23 ONAN/ONAF1 /ONAF2
300 Philippine 1 three 60 230 115 13.8 ONAN/OFAF/OFAF
167 Tadzhikistan 1 three 50 525/V3 230/V3 11 ONAN/OFAF
120 Vietnam 3 two 50 525/V3 20 ODAF
360 Vietnam 1 two 50 242 20 ODAF
50 Vietnam 1 three 50 115 6.8 ONAN
50 Vietnam 2 three 50 20 6.8 ONAN
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
61/67
71 Pakistan 2 two 50 550/ 3 13.2 ODWF
120 China 5 (Smoothing Reactor) 50
200 Pakistan 4 three 50 500/3 220/ 3 22 ONAN/ONAF1/ONAF2
150 Pakistan 4 three 50 500/3 220/ 3 11 ONAN/ONAF1/ONAF2
250 Pakistan 5 three 50 220 132 11 ONAN/ONAF1/ONAF2
125 Vietnam 5 three 50 225 115 23 ONAN/ONAF1/ONAF2
250 Vietnam 1 three 50 225 115 23 ONAN/ONAF1/ONAF2
16 America 3 three 60 34.4 5040V ONAN
125 Vietnam 5 three 50 215 115 10.5 ONAN/ONAF1/ONAF2
24.65 India 7 seven 50 11 132 3 OFWF
-60-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
62/67
N0TE:
1. Abbreviation for cooling system
ONAN..............Oil-immersed self-cooled ONWF ............. Oil-immersed forced-water cooledONAF ............. Oil-immersed forced-air cooled OFWF.............. Forced-oil
forced-water cooled
OFAF .............. Forced-oil forced-air cooled ODAF...............Forced directed-oil forced-air cooled
* .......... With on-load tap-changer ii.......... Auto-transformer
* ................With international loan
* with Siemens technology
-61-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
63/67
Appendix 7: Customers Acknowledgement Letters
1. Pakistan National Transmission & Dispatch Company
-62-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
64/67
2. Malaysia State Power
-63-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
65/67
3. Serbia Power Transmission Company
-64-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
66/67
4. China Shajiao Electric Power
-65-
-
8/7/2019 Reliability & Maintainability Manual of TBEA Shenyang Transformer Products
67/67
Prepared by:
Jeffers Teargun Heptol
International Business Department