Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut –...

26
Regionalization, A Dredgers Perspective GREAT LAKES DREDGE & DOCK CO. LLC www.gldd.com

Transcript of Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut –...

Page 1: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization, A Dredgers

Perspective

GREAT LAKES DREDGE & DOCK CO. LLC

www.gldd.com

Page 2: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization – A Dredgers Perspective (not THE)

• Important to engage all dredgers in discussion

• Most entrepreneurial business

• Multiple investments amounting to several $100’s of millions dollars even without a commitment.

Page 3: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization - A Dredger’s Perspective

Foundational Issues (why?)

• Schedule

– Typically time to permit

– Time to contract

• Costs

– Always a question

– Best attitude is what can I do to lower costs?

Page 4: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Has this been done before?

ABSOLUTELY!

Page 5: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Experience

- SANDAG (Non- Corps) - PKS (Non- Corps)

- West Coast Hopper - NC Beaches

Upcoming

- Delaware Beaches - SAD Hopper

- Houston - RSM

Page 6: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Promise - Efficient Execution

- Better management

- Regulatory motivation

- More streamlined schedule - Utilize dredges for their purpose not towing

- More bidders

- BETTER bids

Page 7: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Reality - Efficient Execution

- Better management - Transparency

- Regulatory - Transparency

- More bidders

- BETTER bids

Page 8: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob –

Many moving parts – all expensive

Dredge

Support Equipment

Pipeline

Shore Equipment

Weather

Page 9: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) SAFETY – EVERYONE INVOLVED Crews (Some cases over 100 persons mobilized) • Salaried • Shoreside • Waterside Organization • Mob & Demobs Inherently more dangers/risks • Hand over meeting • Task oriented briefings

Page 10: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob (Shared)

Dredge & Support Equipment

- Prep for tow

- Tow

- Breakdown at Site

Page 11: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob (Partially Shared)

Pipeline (Floating, Submerged, and Shore Line)

- Prep for tow

- Tow

- Truck to Site

Page 12: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob (Partially Shared)

Shore Equipment (Dozers, Pipe Handlers, Fill Office, Light Plant)

- Load out

- Transport

- Unload

Page 13: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment

- Waterside tow to Site - Dredge, Supply Barge, Anchor Barge, Derrick Barge, Float

Hose, Fuel Barge, Air Compressor Barge, Tending Tugs, Rafts of submerged pipeline (approx 5,000’)

- Shoreside (partially shared) - Shore pipeline say 10,000’ beach (42 Trucks) - Dozers & Loader (5-10 Trucks) - CRAB (2 Trucks) - Fill Offices, Light Plants, & Misc Support Equip (10-15

Trucks)

Page 14: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob (Fixed Cost)

- Waterside Preparations

- Stage equipment in closest Inlet/Port

- Unraft, prepare, and lay submerged pipeline

- Prepare dredge for work

- Tow dredge to site

- Connect dredge to floating and submerged pipeline

- All very weather dependant

Page 15: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

The Big Nut – Mob & Demob (Fixed Cost)

- Shoreside (partially shared)

- Land submerged Pipeline

- Setup Staging Area

- Lay initial pipeline

- Accept shipment of trucks

- Perform surveys

Page 16: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Experience

SANDAG (2x)

• 5 counties

• 7 beaches

• 1 owner

Page 17: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Experience

Pine Knoll Shoals (2x)

• 2 Towns

• 2 Beaches

• 1 Bid

• 2 Contracts

Page 18: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Experience

West Coast Hopper Contract

• 3 Districts

• 5 projects

• 1 contract

Page 19: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Experience

North Carolina Beaches (2x)

• 1 District

• 5 projects

• 1 contract

Page 20: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Proposed

Delaware Beaches – Sandy Work

• 1 District

• 3 projects

• 1 contract

Page 21: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Proposed

SAD Hopper Contract

•3 Districts

•5 projects

•1 contract

Page 22: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Proposed

Houston Cutter Suction Contract

• 1 Districts

• 5 projects

• 1 contract

Page 23: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Proposed

Regional Sediment Management

- Combining Authorities to do the right thing!

- Beneficial Use of Dredging Material

Page 24: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Cautions

- Include all projects at bid time, don’t piggyback - Have money and permits in place, options add risk - If non-Corps project, focus on boilerplate contract.

Needs to be adaptive for dredging - Engage dredgers early, industry days work

Draft Plans & Specifications

Page 25: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Cautions

- Be flexible on schedules, lots of scheduling issues for dredgers

- Fix dates and priorities if necessary, but understand cost impact.

- Start date unimportant, finish date is important don’t include unnecessary constraints

Page 26: Regionalization, A Dredgers Perspective · Regionalization A Dredgers Perspective The Big Nut – Mob & Demob (Shared) Summary of Equipment -Waterside tow to Site -Dredge, Supply

Regionalization A Dredgers Perspective

Cautions

- When owner is engaged, prices drop

- There is no way to increase work requirements and lower costs. Help yourself by being flexible where possible.

- Allow and encourage innovation

- Reduce Risk