Our regional NSW priorities
Roads & Maritime Services 6
Connecting communities
Supporting economic growth
Improving safety on our roads
“We’re delivering the Government’s
$4.2 billion program in
regional NSW in 2018/19.”
Corporate Plan 2018-2021
Roads & Maritime Services 7
Increase customer value
Get more out of the network
Keep safety at the heart
Respect our community & environment
Deliver the Government’s Program
Partner to improve services
1
2
3
4
5
6
Our major project spend has lifted 160% over 4 years
8
$0
$500
$1,000
$1,500
$2,000
$2,500
$3,000
$3,500
$4,000
$4,500
$5,000
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23
WestConnex and Rozelle
F6 Extension Stage 1 (Planning)
Western Harbour Tunnel and Beaches Link (Planningand Preconstruction)Sydney Gateway
Pacific Highway
Roads to Support Western Sydney Airport at BadgerysCreekPrinces Highway
Established Sydney Roads
Easing Sydney's Congestion
Western Sydney Growth Roads
Central Coast Roads
Regional NSW Major Road Upgrades
Hunter Roads
Newell Highway
New England Highway
Excludes NorthConnex and construction funding M4 to M5. Excludes maintenance Capex Roads & Maritime Services
Excluding Sydney motorways, NSW roads regional spend dominates
$0
$500
$1,000
$1,500
$2,000
$2,500
2014/15 2015/16 2016/17 2017/18 2018/19 2019/20 2020/21 2021/22 2022/23
$ m
illio
n
Financial Year
Sydney
Roads & Maritime Services
Regional
9 Excludes Sydney motorways
Our forward work plan • NSW roads infrastructure
spend is reaching ‘peak’ • We have 5+ years of
sustained activity ahead • Together we have achieved
a lot….however industry capacity and capability are a challenge
Roads & Maritime Services
NSW Government – Construction sector 10 point plan
12 Roads & Maritime Services
Released June 2018
• Early contractor engagement • Collaborative procurement • Improve skills and training:
o Work with industry to identify, measure and report on skills gaps
o Mandate application of the Infrastructure Skills Legacy Program (ISLP) in all major Government construction contracts
o Reward contractors who exceed performance KPI’s
Innovation network
Roads & Maritime Services
Partnering to innovate
• We need to challenge ourselves to innovate
• Creating a culture where people feel supported to put ideas up
• Continuous and gradual improvement will drive better outcomes and value for our customers
• We’re trialling five winning innovations in our 2018/19 regional road maintenance program
South West region update
Roads & Maritime Services 14
What we have delivered
About $2 billion invested on roads since 2011: • Around 2000 total projects
delivered • 5 significant projects under way • 4151km of roads and 687
bridges and bridge-sized culverts maintained each year
South West region
Roads & Maritime Services 15
The 18/19 program
• Around 300 projects in planning and delivery
• 40 contracts over $100k awarded this year so far
• $212.8 million maintenance and minor work program
South West region road projects
16
Minor and maintenance projects
• 3.3 million square metres of resealing
• 141,000 square metres of rehabilitation
• $10.5 million plant hire per year • 1 bridge replacement project • $181 million maintenance
program
Roads & Maritime Services
Projects in construction
Gocup Road upgrade – Halfway Hill & Doctors Hill
Gee Gee Bridge replacement
Barton Highway safety upgrades – Package Four: Safety work
Echuca-Moama Bridge – Stage Two: Warren Street upgrade
Bahram Bridge
Roads & Maritime Services
Projects in planning
Roads & Maritime Services
.
Barton Highway – Packages One, Two and Three
Echuca Moama Bridge – Stage Four: Moama intersection treatments
Yoogali intersection treatment
Newell Highway Overtaking Lanes Alliance
Future Transport Strategy 2056
Roads & Maritime Services 19
Regional NSW Services and Infrastructure Plan
• Vision for next 40 years • Guiding investment, policy, reform
and service provision in regional NSW including: o Improving connections to key hubs in
Albury, Griffith & Wagga Wagga • Initiatives to be investigated in the
next 10 years include: o Newell Highway, Sturt Highway and
Kidman Way improvements o Sealing Cobb Highway missing links o Murray River bridges
Murray River crossings
Roads & Maritime Services 20
Investment priority assessment 2018 • Prioritising future investment for 32
Murray River crossings • Short term priorities:
1. Swan Hill Bridge 2. Tooleybuc Bridge 3. Abbotsford Bridge 4. John Foord Bridge 5. Gonn Crossing/Murrabit Bridge 6. Towong Bridge
• Medium term priorities: 1. George Chaffey Bridge 2. Yarrawonga-Mulwala Bridge 3. Bethanga Bridge
21
Safety remains a priority Working with our industry partners
• Multiple trials underway on new safety initiatives
• Pacific Highway ‘Separate yourself’ program
• Successful trials extended across sites and projects
• Industry leaders committed to share WHS lead indicators across projects and organisations
Regional Aboriginal engagement Working with our industry partners
22
• Mandatory APiC targets of 1.5%
• 8.2% of over 200 people in our maintenance program are Aboriginal or Torres Strait Islander
• Supporting industry to meet targets - NSW ICC and Supply Nation
Working with Roads and Maritime
Roads & Maritime Services
Understanding our priorities
• Regular industry communication – pipeline, project specific and initiatives
• Customer • Safety • Innovation • Employment and training • Diversity
Working with Roads and Maritime
Roads & Maritime Services
Our panels and schemes
• Prequalification Schemes
• Roads and Maritime Registration Scheme
• Engineering Services Panels
• Regional Maintenance Panels
Working with Roads and Maritime
Roads & Maritime Services
Our panels and schemes
• Assessments based on: o past performance
o technical capacity
o resources
o financial capacity
o management systems – safety, quality
• Most panels and schemes valid for three years
• Opportunities for small and large contractors
Working with Roads and Maritime
Roads & Maritime Services
Direct and indirect opportunities
• Be aware of NSW Government policies – APiC, Construction apprenticeships, HVCoR
• Register your business for schemes and panels
• Smaller contractors apply for prequalification up to $2M and less complex R1 roadwork and B1 bridgework
• Carry out subcontract work for head contractor
• Enter into Joint Venture with larger contractor
• Apply for Roads and Maritime specialist categories