REFURBISHMENT OF MEDIUM HEAD FRANCIS TURBINES -TUNGATINAH ... · •Five vertical shaft Francis...
Transcript of REFURBISHMENT OF MEDIUM HEAD FRANCIS TURBINES -TUNGATINAH ... · •Five vertical shaft Francis...
April 9-10, 2014
REFURBISHMENT OF MEDIUM HEAD FRANCIS TURBINES
-TUNGATINAH CASE STUDY-
Congrès SHF : «Enhancing Hydropowerplant facilities», Grenoble
Joseph VIRONE, Anne CUVILLIER, Celine GARNIER, Nicolas JUHEL Claude BUCHI
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 2
TUNGATINAH CASE STUDY Location : Tasmania, Australia
Site Location
Hobart
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 3
Power station description
• Five vertical shaft Francis turbines, designed for 28 MW limited to 26,1: vibrations.
• Turbine are of Boving design, directly coupled to a GE generator.
• Each turbine has a spherical inlet valve and a relief valve discharging directly from the spiral casing.
• The generating sets were first installed and put in operation between 1953 and 1956.
Design characteristics : • Rated output at 289.56 m net head:
26.100 MW Corresponding flow at rated output:10.36 m3/s
• Maximum output: 28.076 MW (37 650 BHP)
• Rated speed: 600 rpm • Maximum runaway speed: 1050 rpm
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 4
Objectives of the refurbishment- 3 units
• HYDRAULIC
• MECHANICAL
• ENVIRONMENTAL
• SAFETY
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 5
Site measurements - performances
CALCULATED EFFICIENCY CURVE
Efficiency
+1,5/2,5 %
Max output 31
MW
Designed for 28
Limited to 26,1
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 6
TURBINE SECTION Turbine general cross section
Air axial valve
Distributor
New components :
• Spiral case
• Distributor
• Lower guide bearing
• Turbine bearing & Shaft
seal
• Turbine shaft
• New coupling bolts with
Gen shaft
• Runner with coupling
• Air axial valve at the top
• New Servomotor for PRV
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 7
Replacement of spiral case
Existing spiral case Existing spiral case dismantling Existing spiral case evacuation
New spiral case : installation New spiral case : concreting
Exceptionnal replacement
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 8
Pressure relief valve solution
Existing pressure relief valve with mechanical link to the
operating ring
New servomotor for oil transfert
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 9
Distributor – new design for medium head Francis turbines
Distributor before refurbishment
Distributor top view during
installation
One of the servomotors
Distributor with turbine shaft Distributor during trial assembly at
woorkshop
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 10
RUNNER
Runner during dynamic balancing
Runner during dye
penetrant test Runner at workshop
Old runner
Single casted parts:
- 17 blades
- Less than 3 t
- Outlet dia 1135 mm
- Dynamically balanced
Casting advantages :
• Reduced delivery time.
• Solves the welding access problem for
small runners.
• Suppresses the risk of weld defects.
European foundries with :
• High tec process
• Very accurate model 5 axis machining
• Overthicknesses reduced
• Until to 5 m
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 11
AIR AXIAL VALVE
View from the installation bay
Air axial valve : cross section
The air valve is fully integrated in
existing cover.
• aeration through the shaft line • automatic with possibility to be piloted. • This arrangement improves unit stability.
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 12
Hydrostatic water bearing
Compact
stiffen
Maintain the shaft in position: spring effect
Compact
Stiffen
Wearing rings gaps optimized
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 13
Full assembly behavior checked by finite elements calculation
Hydrostatic water bearing deflection
The max allowable deflection transmitted by the structure, through the head cover, to the hydrostatic bearing was calculated using finite elements method.
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 14
Hydrostatic water bearing
Hydrostatic turbine water bearing in reverse position
Turbine shaft & sleeve with ceramic coating
New automatic strainer 50µm
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 15
Lower generator bearing
© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
Presentation title - 29/04/2014 – P 16
CONCLUSIONS
Finally we can retain :
- efficiency & output > increased
- limitation due to vibrations removed
- CFD expectations confirmed
• Major innovation has been used : hydrostatic water bearing
• rare replacement has been performed : embedded spiral case
• Unit instabilities have been suppressed ( new air axial valve )
• Environment has been preserved thanks to the new hydrostatic water bearing.
• Safety of the power plant has been increased
suppressing oil vapour contamination ( lower bearing)
using modern & simplified distributor design and failure detection
Using new oil transfert operating mode for pressure relief valve
www.alstom.com
With Alstom, preserve the environment.
Is printing this presentation really necessary?
THANK YOU FOR YOUR ATTENTION !