Professor Sludge Guitar Academy Professor Sludge instruction
Reducing the Amount of Waste Activated Sludge Sara Schmidt CE 479 December 6, 2006.
-
Upload
percival-fox -
Category
Documents
-
view
216 -
download
0
Transcript of Reducing the Amount of Waste Activated Sludge Sara Schmidt CE 479 December 6, 2006.
Overview of Presentation:
Background information Concerns regarding waste activated
sludge What is MicroSludge®? Design comparisons of two digester
systems
Background Information
Primary sludge – produced from the primary settling of untreated wastewater
Waste activated sludge (WAS) – excess sludge produced from activated sludge process
CMAD – Conventional Mesophilic Anaerobic Digester
Mesophilic – operating temperature of 25 - 40°C
Background Information
Thermophilic – operating temperature of 50-60°C
MicroSludge – Sludge pre-treatment that greatly enhances the performance of digesters
Concerns Regarding WAS:
Risks to public health from sludge residuals
High capital and operating costs
Contribute to the public’s growing concerns regarding odors
Negative environmental impacts
How much waste do people really produce?
A typical secondary wastewater treatment plant that serves 1 million people generates 25 football fields (about three feet deep) of biosolids each year.
What is MicroSludge®?
MicroSludge works by destroying microbial cell membranes and enabling anaerobic digesters to achieve significantly greater conversion of WAS to biogas.
www.microsludge.com
MicroSludge and Microbes
The image to the left shows intact microbes (magnified 20,000 times)
The image to the right shows the same microbes after the MicroSludge process
Benefits of MicroSludge
Major reduction in WAS residual biosolids (VSr)
Lowers retention time => additional digester capacity
Increased amount of biogas production
Reduces operating, disposal, & mixing costs
Design Parameters (Design 1)
Q = 2Mgal/d = 7440 m3/d Dry volatile solids = 0.16 kg/m3
Biodegradable COD removed = 0.17 kg/m3 HRT (hydraulic retention time) = 15 days Efficiency of waste utilization, E = overall
VSr = Mass fractionPS x VSrPS + Mass fractionTWAS x VSrTWAS = (0.65 x 0.68) + (0.35 x 0.45) = 0.60 = E
Design Parameters
Y = 0.08kg VSS/kg bCOD utilized Kd = 0.03d-1
Digester gas is 65% methane Sludge contains 94% moisture, 6% solids
= 0.06 = Ps
Sludge has a specific gravity, Ssl = 1.02
Calculations
Sludge volume
= [Ms] ÷ [(Ssl)(ρw)(Ps)]
= [(0.16 kg/m3)(7440 m3/d)] ÷
[1.02(103 kg/m3)(0.06)]
= 19.45 m3/d
Calculations
bCOD loading
= (0.17 kg/m3)(7440 m3/d)
= 1265 kg/d
HRT = V/Q => V = Q * HRT
= (19.45 m3/d)(15 d)
V1 = 292 m3
Calculations
bCOD in inffluent, So
So = 1265 kg/d
bCOD in effluent, S
S = 1265(1 - E)
= 1265(1 – 0.60) = 506 kg/d
Calculations
Quantity of volatile solids produced per day, Px
Px= [Y(So – S)] ÷ [1 + (kd)(HRT)]
= [0.08kg VSS/kg bCOD(759)] ÷
[1 + (0.03d-1)(15 d)]
Px(1) = 41.88 kg/d
Calculations
Volume of methane produced per day @ 35°C, VCH4
VCH4 = (0.40)[(So – S) – 1.42Px]
= (0.40m3/kg)[759 kg/d –
1.42*(41.88 kg/d)]
VCH4 = 280 m3/d
Estimate total gas production
= 280/0.65 = 430 m3/d
Design Parameters (Design 2)
Q = 2Mgal/d = 7440 m3/d Dry volatile solids = 0.16 kg/m3
Biodegradable COD removed = 0.17 kg/m3 HRT (hydraulic retention time) = 15 days Efficiency of waste utilization, E = overall
VSr = Mass fractionPS x VSrPS + Mass fractionTWAS x VSrTWAS = (0.65 x 0.68) + (0.35 x 0.97) = 0.78 = E
Design Parameters
Y = 0.08kg VSS/kg bCOD utilized Kd = 0.03d-1
Digester gas is 65% methane Sludge contains 94% moisture, 6% solids
= 0.06 = Ps
Sludge has a specific gravity, Ssl = 1.02
Calculations
Sludge volume
= [Ms] ÷ [(Ssl)(ρw)(Ps)]
= [(0.16 kg/m3)(7440 m3/d)] ÷
[1.02(103 kg/m3)(0.06)]
= 19.45 m3/d
Calculations
bCOD loading
= (0.17 kg/m3)(7440 m3/d)
= 1265 kg/d
HRT = V/Q => V = Q * HRT
= (19.45 m3/d)(13 d)
V2 = 253 m3
Calculations
bCOD in inffluent, So
So = 1265 kg/d
bCOD in effluent, S
S = 1265(1 - E)
= 1265(1 – 0.78) = 278 kg/d
Calculations
Quantity of volatile solids produced per day, Px
Px= [Y(So – S)] ÷ [1 + (kd)(HRT)]
= [0.08kg VSS/kg bCOD(987)] ÷
[1 + (0.03d-1)(13 d)]
Px(2) = 56.79 kg/d
Calculations
Volume of methane produced per day @ 35°C, VCH4
VCH4 = (0.40)[(So – S) – 1.42Px]
= (0.40m3/kg)[987 kg/d –
1.42*(56.79 kg/d)]
VCH4 = 362 m3/d
Estimate total gas production
= 362/0.65 = 557 m3/d
Comparison of two designs
Without using MicroSludge (Design 1):– V(1) = 292 m3
– Px(1) = 41.88 kg/d
– VCH4 = 280 m3/d
With using MicroSludge (Design 2):– V(2) = 253 m3
– Px(2) = 56.79 kg/d
– VCH4 = 362 m3/d
Cost Comparison
The major difference between these two designs are the volume needed for the digesters, volatile solids production, and methane gas production .
These differences are a major cost reductions for a wastewater treatment plant.